EL25-49-000 · 2026-05-11 · Constellation Energy Generation, LLC

Motion for Leave to Answer and Answer of Constellation Energy Generation, LLC in response to PJM Interconnection, LLC's 04/24/2026 Reply Brief

Text extracted from the eLibrary original (SHA-256 05c08452d157c1d8…). Download the original from the official source.

Contents · 13 sections
  1. I. Three Years Is Not “Required” to Replace an Unlawful Rate p. 2
  2. II. Study Procedures and Deadlines Must Be in the Tariff p. 3
  3. A. The Commission Should Require Clear and Detailed Study Requirements to p. 4
  4. B. Transmission Owner Load Integration Study Requirements are Unwritten p. 6
  5. III. The Commission Should Reject Certain Proposed Strictures on the New Transmission p. 7
  6. A. PJM’s Proposed Disqualification and Suspension Scheme is Not a Just, p. 8
  7. B. Limiting Non-Firm Contract Demand Service to Temporary Derates or p. 10
  8. IV. The Transmission Owners’ Grid Reliance Charge is Based Neither on Principle Nor p. 11
  9. V. Requested Clarifications of PJM’s Response Brief and Modifications to Revised p. 13
  10. CONCLUSION p. 16
  11. Introduction p. 21
  12. Background p. 24
  13. Summary p. 37

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Filing procedure · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

Third, draconian rules imposing disqualifications, suspensions and other unnecessary restrictions on the Commission’s new transmission services do not address any genuine “risks to reliability and resource adequacy”4 but instead merely limit access to, frustrate, and otherwise discriminate against…
Read this passage Filed comments: Reliability and curtailment

I. Three Years Is Not “Required” to Replace an Unlawful Rate

printed heading · Topic match: Filing procedure

It is simply not credible that PJM will take more than three years to implement Interim NITS allegedly due to “significant changes to PJM’s core Markets and Operations systems”8 but less than one year to commence Connect and Manage, a framework not clearly defined let alone demonstrated to be just…
Read this passage Filed comments: Filing procedure

II. Study Procedures and Deadlines Must Be in the Tariff

printed heading

Study Procedures and Deadlines Must Be in the Tariff The study procedures for the new transmission services must be identified clearly and spelled out in the tariff.
Read this passage

A. The Commission Should Require Clear and Detailed Study Requirements to

printed heading · Topic match: Retail and wholesale authority

Contrary to PJM’s assertions, these vague statements do not come close to “appropriately detail[ing] PJM’s process, role, and standards for studying requests for these new transmission services.”16 Indeed, the only “detail” that can be gleaned from the Illustrative Tariff is that studies may be…
Read this passage Filed comments: Retail and wholesale authority

B. Transmission Owner Load Integration Study Requirements are Unwritten

printed heading · Topic match: Connecting load and generation

PJM is wrong to assert that “any ‘lack of detail’” regarding those studies is justified for jurisdictional reasons.23 The Commission has jurisdiction over all transmissions, including transmissions to end users.24 The courts have long held the Commission can regulate practices affecting rates…
Read this passage Filed comments: Connecting load and generation

III. The Commission Should Reject Certain Proposed Strictures on the New Transmission

printed heading · Topic match: Filing procedure

Cir. 1978) (finding the Commission’s capacity deficiency charge does not encroach on state jurisdiction, even though it may “motivate [utilities] to develop sufficient capacity to meet their load requirements”). 26 Illustrative Tariff, Part XI, § 710.3 (“Transmission Provider will coordinate with…
Read this passage Filed comments: Filing procedure

A. PJM’s Proposed Disqualification and Suspension Scheme is Not a Just,

printed heading · Topic match: Reliability and curtailment

PJM’s Proposed Disqualification and Suspension Scheme is Not a Just, Reasonable and Non-Discriminatory Replacement Rate PJM fails to demonstrate that “unique reliability and resource adequacy risks” justify the extreme and unprecedented penalties PJM proposes with respect to the Commission’s new…
Read this passage Filed comments: Reliability and curtailment

B. Limiting Non-Firm Contract Demand Service to Temporary Derates or

printed heading

Limiting Non-Firm Contract Demand Service to Temporary Derates or Outages Is Non-Compliant and Unreasonable PJM claims it must limit Non-Firm Contract Demand Service to temporary derates or outages because of “the inherent risks to the Transmission System and operational complexities associated…
Read this passage

IV. The Transmission Owners’ Grid Reliance Charge is Based Neither on Principle Nor

printed heading · Topic match: Cost allocation

The Transmission Owners’ Grid Reliance Charge is Based Neither on Principle Nor Precedent The Commission should reject the Transmission Owners’ Grid Reliance Charge and adopt the minimum system method as recommended by electricity market expert Zachary Ming.47 The Transmission Owners’ Grid Reliance…
Read this passage Filed comments: Cost allocation

V. Requested Clarifications of PJM’s Response Brief and Modifications to Revised

printed heading · Topic match: Connecting load and generation

For Eligible Customers taking service on behalf of Co-Located Load: (1) a demonstration that the Co-Located Load on behalf of which the Eligible Customer is seeking taking to obtain service and the Co-Located Generating Facility are located on the same side of the Delivery Point to the Transmission…
Read this passage Filed comments: Connecting load and generation

CONCLUSION

printed heading

CONCLUSION For the reasons stated above, Constellation respectfully requests that the Commission accept this Answer and promptly approve the terms for Interim NITS, with Constellation’s focused modifications, effective October 1, 2026, with customers commencing service by June 1, 2027.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Large Loads Co-Located at Generating Facilities Constellation Energy Generation, LLC v.
Read this passage

Table of Contents

printed heading · Topic match: Connecting load and generation

Table of Contents 1 Introduction .............................................................................................. 3 2 Background ............................................................................................... 6 3 Evaluation of Transmission Owners’ New Claims…
Read this passage Filed comments: Connecting load and generation

Introduction

printed heading · Topic match: Connecting load and generation

I previously submitted testimony in this docket regarding the appropriate rate 21 designs that should be applied to different configurations of Co-Located Load.1 I 22 1 Testimony of Zachary Ming, on behalf of Constellation Energy Generation, LLC, Docket Nos.
Read this passage Filed comments: Connecting load and generation

Background

printed heading · Topic match: Connecting load and generation

Instead, it would 1 be correct to say that the Transmission Owners’ proposal would shift costs to Co- 2 Located Load customers by forcing Co-Located Load customers to pay costs 3 associated with sizing up the grid to deliver energy, when Co-Located Load 4 customers do not cause those costs at all.…
Read this passage Filed comments: Connecting load and generation

Summary

printed heading · Topic match: Cost allocation

Yes 2 VERIFICATION I declare under penalty of perjury that the foregoing Reply Testimony is true and correct to the best of my knowledge, information, and belief.
Read this passage Filed comments: Cost allocation