ER26-1479-000 · 2026-05-12 · Eastman Chemical Company
Motion for Leave to Answer and Answer of Eastman Chemical Company in response to the Indicated PJM Transmission Owners' 04/24/2026 Answer
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, LLC
)
Docket No. ER26-1479-000
MOTION FOR LEAVE TO ANSWER AND ANSWER OF
EASTMAN CHEMICAL COMPANY
Pursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (FERC or Commission), 18 C.F.R. §§ 385.212 and 385.213 (2026), Eastman Chemical Company (Eastman) seeks leave to answer and submits this answer to the “Motion for Leave to Answer and Answer of the Indicated PJM Transmission Owners [(PJM TOs)]” submitted in the above-referenced docket on April 24, 2026 (PJM TOs Answer).1 The Commission should deny the PJM TOs Answer because it will not assist the Commission in its decision-making, nor does it clarify the record for the Commission. There is good cause to accept this answer to the PJM TOs Answer because the PJM TOs Answer fails to address the specific behind the meter generation (BTMG) issues that Eastman raised in its protest,2 as set forth in further detail below.
1 The Indicated PJM Transmission Owners are the American Electric Power Service Corporation on behalf of its affiliates, which includes Kingsport Power Company. Eastman Chemical Company connects to the grid through Kingsport Power Company.2 18 C.F.R. § 385.213(a)(2) (2026). The Commission will allow answers to answer where there is good cause and where the answer will assist the Commission in its decision-making. See PJM Interconnection, LLC, 185 FERC 61,025 at P 24 (2023) (accepting answers because they provided information to assist in decision making); Pub. Serv. Comm’n of W. Va. v. PJM Interconnection, 186 FERC 61,163 at P 69 (2024); Midcontinent Indep. Sys. Operator, Inc., 191 FERC 61,154 at P 42 (2025).
PDF page 2
2
A. PJM TOs Ignore Operational Realities of Industrial BTMG Facilities
First, the PJM TOs Answer inappropriately lumps together all industrial BTMG facilities, ignoring explicit statement that not all loads using BTMG create the reliability and resource adequacy risks.3 The blanket endorsement of a 50 MW threshold4 does not provide consideration for the realities of individual facilities, including the Eastman facility which, despite the 194 MW BTMG capacity of its facilities, could not operate solely on electrical power delivered from the grid.5
Nameplate capacity is not inherently indicative of the actual capability of BTMG at a facility. As Eastman explained in its Protest, the Kingsport facility is a co- generation facility, and its electric generation is coupled with steam production which is necessary for Eastman’s industrial processes.6 When the facility's generators are constrained, both electricity output and steam production fall, reducing the facility's own industrial load and with it, demand on the grid.7 The facility naturally reduces grid demand precisely when its generation output is limited, the opposite dynamic from the large loads that motivated the Commission's concern.83 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 at P 107 (2025) (Order).4 PJM TOs’ Answer at 3.5 Protest of Eastman Chemical Company, Docket No. ER26-1479-000, at 6 (filed Mar. 16, 2026) (Protest).6 Id. at 5.7 Id.8 Id.; Order at P 83.
PDF page 3
3
The Commission directed PJM to propose a threshold that would “reduce the reliability and resource adequacy risks that large or increasing BTMG may pose,” while allowing Network Customers to continue netting “in a transparent, not unduly discriminatory fashion.”9 PJM has proposed an arbitrarily low threshold that will detrimentally impact facilities that poses no such reliability or resource adequacy risks, without taking into account the facility’s actual use of the transmission system. Additionally, it is at odds with the established principle of cost causation, which has been raised and affirmed by the Commission in previous PJM tariff filings.10 The Commission should reject the PJM TOs' position and recognize that BTMG facilities warrant treatment that reflects their operational realities. Eastman recommends a minimum threshold of 200 MW.
B. PJM TOs Fail to Defend the PJM All-or-Nothing Netting Structure
Second, the Commission directed PJM to establish a threshold for the load that Network Customers may net using BTMG.11 However, PJM has created a standard that eliminates all netting for any facility that exceeds the 50 MW threshold by a single
9 Order at P 83.10 See Occidental Chemical Corp. v. PJM Interconnection, L.L.C., 102 FERC ¶ 61,275 (2003)(finding that “charges for the use of PJM’s transmission system should be allocated to network customers based on a network customer’s actual use of PJM’s system, consistent with the principle of cost causation.”); see also PJM Interconnection, L.L.C., 107 FERC 61,113 at PP 27-28 (2004)(finding that the BTMG tariff provisions would “charges for use of PJM’s transmission system should be allocated to network customers based on a network customer’s actual use of PJM’s system, consistent with the principle of cost causation.”).11 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 at P 221 (2025) (Show Cause Order).
PDF page 4
4
megawatt.12 Under PJM's proposed structure, a facility with 50 MW of nameplate capacity retains full netting rights, while a facility with 51 MW loses all netting rights.13 This binary result is not a reasonable application of the Commission’s Order. The Commission's Order directed PJM to allow Network Customers to net “up to” a threshold level, preserving some benefit for all BTMG facilities while limiting the scale of large or increasing BTMG.14 Further, the Commission Show Cause Order states that BTMG netting is just and reasonable because it encourages load response when generation or transmission are in short supply and prices are rising15 and that charges to the PJM customer should be based on actual use of the system.16 PJM's proposal distorts the Commission’s directive by using the 50 MW threshold not to cap netting, but to eliminate it for any facility that exceeds the cap.
Neither the PJM TOs nor PJM offer a just and reasonable basis for this structure. A threshold that draws no distinction between a 51 MW passive load and a 194 MW industrial cogeneration facility that actively supports the grid is neither consistent with the Commission's directive nor just and reasonable.17 The Commission should reject PJM's all-or-nothing approach and require PJM to submit a revised compliance filing that permits all BTMG facilities to net load up to the threshold level, regardless of total nameplate capacity.
12 PJM TOs’ Answer at 3; Protest at 7.13 Compliance Filing at 7-8.14 Show Cause Order at P 221; Order at P 100.15 Show Cause Order at P 7.16 PJM, 107 FERC 61,113 at PP 27-28.17 Order at P 100; Protest at 6-7.
PDF page 5
5
C. The PJM TOs Justification of 50 MW Threshold is Arbitrary
Third, the PJM TOs provide no operational justification for the 50 MW threshold. The PJM TOs sole justification for the 50 MW threshold is a definition developed in an entirely different regulatory context, which was not intended to address the reliability or resource adequacy risks that the Commission raised in relation to BTMG netting.18 The PJM TOs provide no evidence that BTMG facilities at or above 50 MW have historically caused the resource adequacy or reliability problems the Commission identified as a concern.19
Additionally, PJM TOs administrability argument is unpersuasive. While a static nameplate-based threshold may be easy to administer, administrative convenience does not establish that a proposal is just and reasonable, particularly where the result is the arbitrary elimination of netting rights for facilities that pose no grid reliability or resources adequacy risk. Nameplate capacity measures the maximum potential output of a generator, not the actual impact that a BTMG facility has on the grid. For industrial co-generation facilities like the Kingsport facility, the relevant metric is not how much electricity the facility could generate, but how that generation interacts with the facility's load under real operating conditions. Further, the
18 Compliance Filing, Transmittal Letter at Part III.A.2 and Attachment A (The PJM Large Load Additions definition was developed in order to address the reliability and resource adequacy challenges posed by unprecedented demand growth from data centers and other large new loads connecting to the grid and it does not address BTMG at any point or any considerations related to how the definition would impact BTMG).19 Order at P 83.
PDF page 6
6
Commission directed PJM to establish a threshold for load that customers may net using BTMG.20 The Commission's goal was not to eliminate BTMG netting but to address the specific risks posed by large or increasing BTMG.21 An administrable threshold that captures facilities posing no such risk is not a solution, it is an over-simplified standard that mischaracterizes the Commission's objective while imposing real harm on facilities.
For the foregoing reasons, Eastman requests that the Commission accept this answer and grant the relief requested in the Protest or establish an evidentiary hearing with full rights of discovery to explore the issues of material fact that are in dispute. Respectfully submitted,
By:
/s/ Emma M. Ross
Emma M. Ross
(571) 842-8187
emr@floomenergylaw.com
John Paul Floom
(571) 842-8185
jpf@floomenergylaw.com
Kaci W. Poor
(571) 842-8189
kwp@floomenergylaw.com
Floom Energy Law PLLC
3100 Clarendon Blvd., Suite 920
Arlington, VA 22201
Attorneys for
Eastman Chemical Company
Date: May 12, 2026
20 Show Cause Order at P 221.21 Order at P 83.
PDF page 7
CERTIFICATE OF SERVICE
Pursuant to Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2026), I hereby certify that I have this day served a copy of the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Arlington, Virginia, this 12th day of May 2026.
By: /s/ Emma M. Ross
Emma M. Ross
Floom Energy Law PLLC
3100 Clarendon Blvd., Suite 920
Arlington, VA 22201
(571) 842-8185