Attachment A_Reply Testimony of Lance Schafer (Final 5.28.2026)
PDF page 1
Attachment APage 1 of 13
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
)
Docket No. EL25-49-001
)
Large Loads Co-Located at Generating Facilities
)
Docket No. AD24-11-000
)
Constellation Energy Generation, LLC
)
Docket No. EL25-20-000
v.
)
PJM Interconnection, L.L.C.
)
(Consolidated)
REPLY TESTIMONY
OF
LANCE SCHAFER
I. INTRODUCTION
1 Q. Please state your name, title, business address, and provide your professional 2 background and relevant experience. 3
A. My name is Lance Schafer, and my business address is 293 Boston Post Road West, 4
Marlborough, MA 01752. I am a Senior Project Manager with Concentric Energy 5
Advisors, Inc. My professional background and relevant experience was provided as 6
Exhibit No. PTO-0002 to the Indicated PJM Transmission Owners’ Initial Brief filed on 7
February 23, 2026 in these proceedings.
8
Q.
Have you previously submitted testimony in these proceedings?
9
A. Yes. I submitted testimony on behalf of the Indicated PJM Transmission Owners (“PJM 10
Transmission Owners”)1 as part of the Direct Joint Testimony filed on February 23, 2026, 11
and as part of the Joint Rebuttal Testimony filed on April 24, 2026 in these proceedings. 12
1 For purposes of this reply testimony and the accompanying answer, the PJM Transmission Owners are: American Electric Power Service Corporation on behalf of its affiliates, Appalachian Power Company, Indiana
PDF page 2
Attachment APage 2 of 13
II. BACKGROUND
1
Q.
What is the background of this proceeding?
2
A. On December 18, 2025, the Commission issued its order in PJM Interconnection. L.L.C., 3
193 FERC ¶ 61,217 (2025) (“Order”). In the Order, the Commission found that PJM
4
Interconnection, L.L.C.’s (“PJM”) Open Access Transmission Tariff (“Tariff”) “is unjust 5
and unreasonable because it does not contain provisions addressing with sufficient clarity 6
or consistency the rates, terms, and conditions of service that apply to generators serving 7
Co-Located Load and Eligible Customers taking transmission service on behalf of Co-
8
Located Load.”2 Specifically, the Commission found PJM’s Tariff “unjust and
9
unreasonable because it does not include types of transmission service that reflect Eligible 10
Customers taking service on behalf of Co-Located Loads that are willing and able to limit 11
their use of the transmission system under certain conditions.”3
12
The Commission ordered PJM to offer three new forms of transmission service
13
under its Tariff, and identified these three new forms of transmission service as: (i) Firm 14
Contract Demand transmission service; (ii) Non-Firm Contract Demand transmission
15
Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc., AEP Indiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and AEP West Virginia Transmission Company, Inc.; The Dayton Power and Light Company d/b/a AES Ohio; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc.; Duquesne Light Company; East Kentucky Power Cooperative, Inc.; Exelon Corporation on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, on behalf of its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, The Potomac Edison Company, Monongahela Power Company, Keystone Appalachian Transmission Company, and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); PPL Electric Utilities Corporation; Public Service Electric and Gas Company; Rockland Electric Company; and the Southern Maryland Electric Cooperative.
2 Order at P 2.3 Id.
PDF page 3
Attachment APage 3 of 13
service; and (iii) interim, non-firm transmission service.4 The Commission also established 1
a paper hearing to determine the just and reasonable rates, terms, and conditions for these 2
new transmission services.5
3
III. PURPOSE OF TESTIMONY
4
Q.
What is the purpose of your testimony?
5
A. The purpose of my testimony is to support the Answer of the PJM Transmission Owners 6
submitted in response to the Motion for Leave and Answer of Constellation Energy 7
Generation, LLC (“Constellation”) filed on May 11, 2026 in these proceedings. In 8
particular, I respond to the Reply Testimony of Zachary Ming, filed on behalf of 9
Constellation on May 11, 2026. Mr. Ming’s testimony replies to the PJM Transmission 10
Owners’ April 24, 2026 Reply Brief, including specifically the Joint Rebuttal Testimony 11
that accompanied that Reply Brief concerning the PJM Transmission Owners’ proposal for 12
calculating a Grid Reliance Charge.
13
IV. REBUTTAL TO MR. MING’S REPLY TESTIMONY ON THE GRID RELIANCE
14
CHARGE
15
Q.
What is the Grid Reliance Charge?
16
A. The PJM Transmission Owners are proposing to charge a Grid Reliance Charge to Eligible 17
Customers6 taking the new Contract Demand services based on the difference between the 18
amount of their firm contract demand for Firm Contract Demand Service and their total 19
(gross) on-site load. The proposed Grid Reliance Charge is designed to reflect the costs of 20
using the transmission system to deliver black start and regulation services, as well as 21
4 Id. at P 160.5 Id. at PP 2, 194.6 Capitalized terms that are not otherwise defined shall have the meanings set forth in the PJM Tariff.
PDF page 4
Attachment APage 4 of 13
providing the inherent benefits that all customers, including Contract Demand customers, 1
receive as a result of their synchronization to and reliance on the grid. The Grid Reliance 2
Charge also recognizes the costs associated with the operations, maintenance, and other 3
activities that PJM transmission owners will need to perform for the grid and to 4
accommodate the increased number of protection schemes that will be required for Co- 5
Located Load customers.
6
Q.
How do the PJM Transmission Owners propose to calculate the Grid Reliance 7
Charge?
8
A. The PJM Transmission Owners propose to calculate a Grid Reliance Charge for each PJM 9
zone based on determining an average fixed percentage of the portion of transmission 10
depreciation and operations and maintenance expense associated with providing grid 11
reliance services, and then applying that average fixed percentage to each PJM 12
Transmission Owner’s Attachment H annual transmission revenue requirement. 13
Q.
Mr. Ming claims that the PJM Transmission Owners “fail to address the fundamental 14
shortcoming of their proposal – a transmission system built only to deliver ancillary 15
services would be nowhere near as large or expensive as a transmission system built 16
to serve peak demand.”7 Do you agree?
17
A. No. Mr. Ming’s claim is incorrect. First, Mr. Ming continues to assume, erroneously, that 18
the sole purpose of the Grid Reliance Charge is to recover costs associated with the delivery 19
of ancillary services. As I have explained, the Grid Reliance Charge is not limited to 20
recovering the costs associated with the delivery of ancillary services, but rather is intended 21
to reflect the full suite of benefits that Co-Located Load will receive by virtue of the fact 22
7 Reply Testimony of Zachary Ming at 9:14-16 (“Ming Reply Testimony”).
PDF page 5
Attachment APage 5 of 13
that it will be interconnected to the integrated transmission system, and not islanded. Mr. 1
Ming simply ignores these benefits, which as I discussed in my previous testimony include 2
delivering ancillary services and a suite of essential reliability services, such as frequency 3
support, inertia, voltage stability, fault current capability, ride-through and protection 4
coordination, and providing sufficient short-circuit capability.
5
Mr. Ming’s other conceptual critique regarding the alleged unprecedented nature 6
of the Transmission Owners’ proposal fares no better. The Contract Demand Transmission 7
Services that the Commission has directed here are themselves based on the novel premise 8
that load will connect to the system and take transmission service without the transmission 9
provider identifying and constructing upgrades to facilitate the full amount of load. Thus, 10
the design of the Grid Reliance Charge reflects the unique circumstances of this 11
proceeding, and the transmission services that the Commission has directed here. 12
Finally, Mr. Ming’s attempt to distinguish his proposal from the PJM Transmission 13
Owners’ on the basis that his is somehow more “principled” rather than what he 14
characterizes as an “improvised” approach by the Transmission Owners is spurious.8 As I 15
explained in my previous testimony, and discuss further below, Mr. Ming’s “minimum 16
system” methodology has no relevance here, and even if it did, his proposed application is 17
flawed and superficial. Thus, it is Mr. Ming who is attempting to defend what is clearly a 18
contrived effort by Constellation to attempt to minimize the Grid Reliance Charge in order 19
to reduce their own costs at the expense of other ratepayers.
20
21
22
8 Ming Reply Testimony at 10:16-21, 12:11-12, 18:1-3.
PDF page 6
Attachment APage 6 of 13
Q.
Does Mr. Ming offer an alternative to the PJM Transmission Owners’ method for 1
calculating the Grid Reliance Charge?
2
A. Yes. Although Mr. Ming supports the application of a Grid Reliance Charge, he continues 3
to argue that the Commission should reject the PJM Transmission Owners’ Grid Reliance 4
Charge and adopt a charge based on the “minimum system method.”
5
Q.
Mr. Ming states that your April 24, 2026 Joint Rebuttal Testimony reflects a 6
misunderstanding of the minimum system method and how its results should be 7
used.9 How do you respond?
8
A. Mr. Ming is incorrect. Mr. Ming’s statement is in reaction to my criticism that his 9
recommended 6.2% minimum system percentage only includes certain plant balances and 10
does not include any other element typically included in a transmission revenue 11
requirement, such as rate of return, taxes, depreciation, and operation and maintenance 12
expense.10 I pointed this out in response to Mr. Ming’s argument that the PJM Transmission 13
Owners’ proposal was deficient because it excluded certain cost of service components, 14
such as rate of return and taxes.
15
Mr. Ming’s result is the ratio of his calculated minimum system plant amount to 16
the total plant amount for the accounts he included in his study. A plant ratio is indeed 17
consistent with the expected output of a distribution minimum system study. However, Mr. 18
Ming then takes this plant ratio, whose purpose is only to identify the minimum-system- 19
related portions of certain plant accounts, and applies it to the entire transmission revenue 20
9 Ming Reply Testimony at 17:3-12.10 See Joint Rebuttal Testimony of Peter Blazunas, Lance Schafer, and Hanhan Hammer, Exhibit No. PTO- 0005 at 26.
PDF page 7
Attachment APage 7 of 13
requirement. This is methodologically unsound because the results of a minimum-system 1
study are not intended to be applied to a revenue requirement.
2
Q.
If the result of a minimum system study is not intended to be applied to a revenue 3
requirement, why does Mr. Ming use the result for this purpose?
4
A. Mr. Ming incorrectly believes that the purpose of a minimum system study is to produce a 5
result that can be applied to a revenue requirement. He states that “[t]he minimum system 6
uses the ratio of replacement costs for both the minimum system and actual system to 7
identify what portion of the entire revenue requirement is attributable to the minimum 8
system. It does not omit any element of the revenue requirement.”11 However, as noted just 9
above, Mr. Ming’s recommended 6.2% minimum system percentage was calculated by 10
comparing gross plant amounts in certain plant accounts. Mr. Ming is therefore taking a 11
ratio that he developed from studying certain gross-plant account balances and applying 12
that ratio to the entire revenue requirement. But a gross-plant ratio is not directly applicable 13
to the entire revenue requirement.
14
Q.
Does the minimum system method use either book cost or replacement cost to 15
determine the minimum system portion of the accounts included in the minimum 16
system study?
17
A. Plant balances developed either on a book-cost or replacement-cost basis are used to 18
compare the “minimum system” plant balances with the total plant balances for the 19
accounts included in the study. This is done to determine the percentage of plant in those 20
specific accounts associated with the minimum system. However, contrary to Mr. Ming’s 21
11 Ming Reply Testimony at 17:5-9 (emphasis added).
PDF page 8
Attachment APage 8 of 13
assertions, the minimum system study does not develop a result that appropriately describes 1
the minimum-system portion of the entire revenue requirement.
2
Q.
Does the National Association of Regulatory Utility Commissioner’s Electric Cost 3
Allocation Manual (“NARUC Manual”) state that the purpose of the minimum 4
system method is to develop a result that can be applied to a revenue requirement? 5
A. No. The NARUC Manual clearly explains that the minimum system method’s purpose is 6
to classify distribution plant. The NARUC Manual states the following: 7
Classifying distribution plant with the minimum-size method assumes that a 8
minimum size distribution system can be built to serve the minimum loading 9
requirements of the customer. The minimum-size method involves determining the 10
minimum size pole, conductor, cable, transformer, and service that is currently 11
installed by the utility. Normally, the average book cost for each piece of equipment 12
determines the price of all installed units. Once determined for each primary plant 13
account, the minimum size distribution system is classified as customer-related 14
costs. The demand-related costs for each account are the difference between the 15
total investment in the account and customer-related costs.12
16
17
The minimum system study, as explained above, serves to classify portions of certain 18
accounts as either customer (i.e., pertaining to the minimum distribution system) or demand 19
related. Mr. Ming’s result of 6.2% merely means that, of the plant accounts included in his 20
study, he determined that 6.2% of the balances are related to a hypothetical minimum 21
system. Therefore, Mr. Ming’s calculation does not represent true revenue requirement for 22
the minimum system represented by that 6.2%.
23
24
25
12 National Association of Regulatory Utility Commissioners, Electric Cost Allocation Manual (Jan. 1992), at 90-91.
PDF page 9
Attachment APage 9 of 13
Q.
In addition to the NARUC Manual, do any other commonly referenced works of cost 1
allocation describe the purpose of the minimum system study?
2
A. Yes. Lawrence J. Vogt’s commonly referenced book Electricity Pricing, Engineering 3
Principles and Methodologies also describes that the purpose of the minimum system study 4
is to classify certain plant as either demand or customer related. It adds: 5
[O]n the principle of cost causation, some distribution facilities can be classified as 6
purely demand related, while other distribution facilities can be classified as purely 7
customer related. A substantial amount of distribution plant investment has cost 8
causation attributes of both demand and customer cost components. For instance, a 9
line transformer is both customer related and demand related as it provides both a 10
load and a no-load function. This distinction is derived through a minimum 11
distribution system analysis of poles, conductors and a variety of line equipment . . 12
. .”13
13
14
Neither Mr. Vogt’s book nor the NARUC Manual, nor any other industry manual on cost 15
allocation that I am aware of, supports the notion that the purpose of the minimum system 16
study is to produce a ratio that can be applied to a revenue requirement. 17
Q.
Mr. Ming states that the minimum system uses “the ratio of replacement costs for 18
both the minimum system and actual system to identify what portion of the entire 19
revenue requirement is attributable to the minimum system.”14 How does the 6.2% 20
represent the minimum system portion of the entire revenue requirement? 21
A. It does not. In his minimum system study, Mr. Ming determined that 6.2% of the plant in 22
the following accounts were related to a transmission minimum system: overhead 23
conductors, poles, towers, and substations.15 He uses plant balances—not a revenue 24
requirement—to derive the 6.2%. To be clear, plant balances are exactly what an analyst 25
13 Lawrence H. Vogt, P.E., Electricity Pricing, Engineering Principles and Methodologies (2009), at 495.14 See Ming Reply Testimony at 17:5-8.15 See Constellation March 25, 2026 Reply Brief, Testimony of Zachary Ming at 20:1.
PDF page 10
Attachment APage 10 of 13
should use in a minimum system study—because the object of the study is classification, 1
not the determination of a minimum system revenue requirement. Mr. Ming then applies 2
his 6.2% result to the entire transmission revenue requirement. This is a methodological 3
leap that is not in any way a component of a distribution minimum system study. In short, 4
Mr. Ming is comparing apples to oranges in an attempt to arrive at a result that has a veneer 5
of principled objectivity. But Mr. Ming’s flawed application of the minimum system 6
methodology underscores the inappropriateness of his recommendation to use the 7
minimum system study for purposes of establishing the Grid Reliance Charge. 8
Q.
Are there any other problems with the manner in which Mr. Ming conducted his 9
minimum system study?
10
A. Yes. Moving beyond the misapplication of the minimum system study approach, in 11
conducting his minimum system study, Mr. Ming uses wood distribution poles as a 12
substitute for transmission poles.
13
Q.
How does Mr. Ming defend his decision to use wood distribution poles as a substitute 14
for transmission poles?
15
Mr. Ming justifies his use of wood poles by stating he did so “because a minimum system 16
is a theoretical system designed to deliver a de minimis amount of electricity as opposed 17
to a system designed to serve peak demand.”16 However, Mr. Ming’s proposal to substitute 18
wood distribution poles for transmission poles is inappropriate and not supported in 19
industry literature. For example, the NARUC Manual states that “the minimum-size 20
method involves determining the minimum size pole, conductor, cable, transformer, and 21
16 Ming Reply Testimony at 15:13-15.
PDF page 11
Attachment APage 11 of 13
service that is currently installed by the utility.”17 I am not aware of any instance where a 1
transmission owner has installed wood distribution poles for the purposes of providing 2
transmission service.
3
Q.
How does Mr. Ming attempt to justify his minimum system study based on the use of 4
distribution equipment?
5
A. Mr. Ming claims that his “theoretical” minimum system, based on the use of distribution 6
equipment, is justified because it represents the “cost-causation basis for determining the 7
portion of the system that is necessary to provide ancillary services.”18 8
Q.
Do you agree with this claim?
9
A. No. On the one hand, Mr. Ming justifies the use of distribution equipment in his minimum 10
system calculation as being acceptable because his minimum system is only “theoretical” 11
(i.e., it doesn’t exist). On the other hand, he says this theoretical minimum system 12
composed of distribution equipment represents the very system necessary to deliver 13
ancillary services to real-world transmission customers. These two statements are 14
contradictory. Also, I am not aware of any industry manual on cost allocation that supports 15
Mr. Ming’s claim that the minimum system method results in a system that is the 16
appropriate size to supply ancillary services.
17
18
19
20
17 National Association of Regulatory Utility Commissioners, Electric Cost Allocation Manual (Jan. 1992), at 90 (emphasis added).18 Ming Reply Testimony at 8:12-16.
PDF page 12
Attachment APage 12 of 13
Q.
Is Mr. Ming’s recommendation to employ the minimum system method in calculating 1
the Grid Reliance Charge consistent with cost causation principles?
2
A. No. Mr. Ming states that his recommendation to employ the minimum system method in 3
calculating the Grid Reliance Charge is based on principles of cost causation.19 This is 4
simply not the case because the minimum system method is only appropriate for and 5
applicable to distribution level service. Mr. Ming ignores the very purpose of the minimum 6
system study, and inappropriately and inaccurately attempts to translate the methodology 7
to calculate a transmission service rate. By then misinterpreting the results as being 8
applicable to the entire transmission revenue requirement, Mr. Ming abandons all cost- 9
causation principles that exist in a minimum-system study approach.
10
Q.
Please summarize your recommendation regarding Mr. Ming’s testimony?
11
A. Mr. Ming’s proposal to employ the minimum system method in calculating the Grid 12
Reliance Charge is fundamentally flawed. First, Mr. Ming did not conduct his minimum 13
system study correctly because he included distribution equipment not installed for 14
transmission service. Second, Mr. Ming applies the result of his minimum-system study to 15
the entire transmission revenue requirement, which is contrary to the purpose of the study. 16
Third, the minimum system method only is appropriate for and applicable to distribution- 17
level service. It is entirely inappropriate to apply the minimum system method to calculate 18
a transmission service rate. The Commission should reject Mr. Ming’s proposal and accept 19
the PJM Transmission Owners’ just and reasonable mechanism for determining the Grid 20
Reliance Charge.
21
22
19 Id.
PDF page 13
Attachment APage 13 of 13
Q.
Does this complete your testimony at this time? 1
A. Yes.
2