Attachment A_Reply Testimony of Lance Schafer (Final 5.28.2026)
Text extracted from the eLibrary original (SHA-256 dbab9783e83bbad8…). Download the original from the official source.
Contents · 37 sections
- Attachment A
- I. INTRODUCTION
- A. My name is Lance Schafer, and my business address is 293 Boston Post Road West,
- A. Yes. I submitted testimony on behalf of the Indicated PJM Transmission Owners (“PJM
- Attachment A
- II. BACKGROUND
- A. On December 18, 2025, the Commission issued its order in PJM Interconnection. L.L.C.,
- Attachment A
- III. PURPOSE OF TESTIMONY
- A. The purpose of my testimony is to support the Answer of the PJM Transmission Owners
- IV. REBUTTAL TO MR. MING’S REPLY TESTIMONY ON THE GRID RELIANCE
- A. The PJM Transmission Owners are proposing to charge a Grid Reliance Charge to Eligible
- Attachment A
- A. The PJM Transmission Owners propose to calculate a Grid Reliance Charge for each PJM
- A. No. Mr. Ming’s claim is incorrect. First, Mr. Ming continues to assume, erroneously, that
- Attachment A
- Attachment A
- A. Yes. Although Mr. Ming supports the application of a Grid Reliance Charge, he continues
- A. Mr. Ming is incorrect. Mr. Ming’s statement is in reaction to my criticism that his
- Attachment A
- A. Mr. Ming incorrectly believes that the purpose of a minimum system study is to produce a
- A. Plant balances developed either on a book-cost or replacement-cost basis are used to
- Attachment A
- A. No. The NARUC Manual clearly explains that the minimum system method’s purpose is
- Attachment A
- A. Yes. Lawrence J. Vogt’s commonly referenced book Electricity Pricing, Engineering
- A. It does not. In his minimum system study, Mr. Ming determined that 6.2% of the plant in
- Attachment A
- A. Yes. Moving beyond the misapplication of the minimum system study approach, in
- Attachment A
- A. Mr. Ming claims that his “theoretical” minimum system, based on the use of distribution
- A. No. On the one hand, Mr. Ming justifies the use of distribution equipment in his minimum
- Attachment A
- A. No. Mr. Ming states that his recommendation to employ the minimum system method in
- A. Mr. Ming’s proposal to employ the minimum system method in calculating the Grid
- Attachment A
- A. Yes.
Read topic-matched comments in EL25-49
Topics in the text: Cost allocation · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword. Pages with no text layer: 14.
Attachment A
printed heading
Attachment A Page 1 of 13 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al. ) Docket No.Read this passage
I. INTRODUCTION
printed heading
Please state your name, title, business address, and provide your professional 2 background and relevant experience. 3Read this passage
A. My name is Lance Schafer, and my business address is 293 Boston Post Road West,
printed heading
My name is Lance Schafer, and my business address is 293 Boston Post Road West, 4 Marlborough, MA 01752.Read this passage
A. Yes. I submitted testimony on behalf of the Indicated PJM Transmission Owners (“PJM
printed heading
I submitted testimony on behalf of the Indicated PJM Transmission Owners (“PJM 10 Transmission Owners”)1 as part of the Direct Joint Testimony filed on February 23, 2026, 11 and as part of the Joint Rebuttal Testimony filed on April 24, 2026 in these proceedings. 12 1 For purposes of this reply…Read this passage
Attachment A
printed heading
Attachment A Page 2 of 13Read this passage
II. BACKGROUND
printed heading
II.Read this passage
A. On December 18, 2025, the Commission issued its order in PJM Interconnection. L.L.C.,
printed heading · Topic match: Connecting load and generation
On December 18, 2025, the Commission issued its order in PJM Interconnection.Read this passage Filed comments: Connecting load and generation
Attachment A
printed heading
Attachment A Page 3 of 13 service; and (iii) interim, non-firm transmission service.4 The Commission also established 1 a paper hearing to determine the just and reasonable rates, terms, and conditions for these 2 new transmission services.5 3Read this passage
III. PURPOSE OF TESTIMONY
printed heading
III.Read this passage
A. The purpose of my testimony is to support the Answer of the PJM Transmission Owners
printed heading
The purpose of my testimony is to support the Answer of the PJM Transmission Owners 6 submitted in response to the Motion for Leave and Answer of Constellation Energy 7 Generation, LLC (“Constellation”) filed on May 11, 2026 in these proceedings.Read this passage
IV. REBUTTAL TO MR. MING’S REPLY TESTIMONY ON THE GRID RELIANCE
printed heading
MING’S REPLY TESTIMONY ON THE GRID RELIANCE 14 CHARGE 15 Q.Read this passage
A. The PJM Transmission Owners are proposing to charge a Grid Reliance Charge to Eligible
printed heading
The proposed Grid Reliance Charge is designed to reflect the costs of 20 using the transmission system to deliver black start and regulation services, as well as 21 4 Id. at P 160. 5 Id. at PP 2, 194. 6 Capitalized terms that are not otherwise defined shall have the meanings set forth in the PJM…Read this passage
Attachment A
printed heading
Attachment A Page 4 of 13 providing the inherent benefits that all customers, including Contract Demand customers, 1 receive as a result of their synchronization to and reliance on the grid.Read this passage
A. The PJM Transmission Owners propose to calculate a Grid Reliance Charge for each PJM
printed heading
The PJM Transmission Owners propose to calculate a Grid Reliance Charge for each PJM 9 zone based on determining an average fixed percentage of the portion of transmission 10 depreciation and operations and maintenance expense associated with providing grid 11 reliance services, and then applying…Read this passage
A. No. Mr. Ming’s claim is incorrect. First, Mr. Ming continues to assume, erroneously, that
printed heading · Topic match: Connecting load and generation
As I have explained, the Grid Reliance Charge is not limited to 20 recovering the costs associated with the delivery of ancillary services, but rather is intended 21 to reflect the full suite of benefits that Co-Located Load will receive by virtue of the fact 22 7 Reply Testimony of Zachary Ming at…Read this passage Filed comments: Connecting load and generation
Attachment A
printed heading · Topic match: Cost allocation
Ming who is attempting to defend what is clearly a 18 contrived effort by Constellation to attempt to minimize the Grid Reliance Charge in order 19 to reduce their own costs at the expense of other ratepayers. 20 21 22 8 Ming Reply Testimony at 10:16-21, 12:11-12, 18:1-3.Read this passage Filed comments: Cost allocation
Attachment A
printed heading
Ming offer an alternative to the PJM Transmission Owners’ method for 1 calculating the Grid Reliance Charge? 2Read this passage
A. Yes. Although Mr. Ming supports the application of a Grid Reliance Charge, he continues
printed heading
Ming supports the application of a Grid Reliance Charge, he continues 3 to argue that the Commission should reject the PJM Transmission Owners’ Grid Reliance 4 Charge and adopt a charge based on the “minimum system method.” 5 Q.Read this passage
A. Mr. Ming is incorrect. Mr. Ming’s statement is in reaction to my criticism that his
printed heading
Ming’s statement is in reaction to my criticism that his 9 recommended 6.2% minimum system percentage only includes certain plant balances and 10 does not include any other element typically included in a transmission revenue 11 requirement, such as rate of return, taxes, depreciation, and…Read this passage
Attachment A
printed heading
This is methodologically unsound because the results of a minimum-system 1 study are not intended to be applied to a revenue requirement. 2 Q.Read this passage
A. Mr. Ming incorrectly believes that the purpose of a minimum system study is to produce a
printed heading
Ming incorrectly believes that the purpose of a minimum system study is to produce a 5 result that can be applied to a revenue requirement.Read this passage
A. Plant balances developed either on a book-cost or replacement-cost basis are used to
printed heading
Plant balances developed either on a book-cost or replacement-cost basis are used to 18 compare the “minimum system” plant balances with the total plant balances for the 19 accounts included in the study.Read this passage
Attachment A
printed heading
Attachment A Page 8 of 13 assertions, the minimum system study does not develop a result that appropriately describes 1 the minimum-system portion of the entire revenue requirement. 2 Q.Read this passage
A. No. The NARUC Manual clearly explains that the minimum system method’s purpose is
printed heading · Topic match: Cost allocation
Ming’s calculation does not represent true revenue requirement for 22 the minimum system represented by that 6.2%. 23 24 25 12 National Association of Regulatory Utility Commissioners, Electric Cost Allocation Manual (Jan. 1992), at 90-91.Read this passage Filed comments: Cost allocation
Attachment A
printed heading
In addition to the NARUC Manual, do any other commonly referenced works of cost 1 allocation describe the purpose of the minimum system study? 2Read this passage
A. Yes. Lawrence J. Vogt’s commonly referenced book Electricity Pricing, Engineering
printed heading · Topic match: Cost allocation
It adds: 5 [O]n the principle of cost causation, some distribution facilities can be classified as 6 purely demand related, while other distribution facilities can be classified as purely 7 customer related.Read this passage Filed comments: Cost allocation
A. It does not. In his minimum system study, Mr. Ming determined that 6.2% of the plant in
printed heading
Ming determined that 6.2% of the plant in 22 the following accounts were related to a transmission minimum system: overhead 23 conductors, poles, towers, and substations.15 He uses plant balances—not a revenue 24 requirement—to derive the 6.2%.Read this passage
Attachment A
printed heading
Attachment A Page 10 of 13 should use in a minimum system study—because the object of the study is classification, 1 not the determination of a minimum system revenue requirement.Read this passage
A. Yes. Moving beyond the misapplication of the minimum system study approach, in
printed heading
Moving beyond the misapplication of the minimum system study approach, in 11 conducting his minimum system study, Mr.Read this passage
Attachment A
printed heading
Attachment A Page 11 of 13 service that is currently installed by the utility.”17 I am not aware of any instance where a 1 transmission owner has installed wood distribution poles for the purposes of providing 2 transmission service. 3 Q.Read this passage
A. Mr. Ming claims that his “theoretical” minimum system, based on the use of distribution
printed heading
Ming claims that his “theoretical” minimum system, based on the use of distribution 6 equipment, is justified because it represents the “cost-causation basis for determining the 7 portion of the system that is necessary to provide ancillary services.”18 8 Q.Read this passage
A. No. On the one hand, Mr. Ming justifies the use of distribution equipment in his minimum
printed heading · Topic match: Cost allocation
Also, I am not aware of any industry manual on cost allocation that supports 15 Mr.Read this passage Filed comments: Cost allocation
Attachment A
printed heading · Topic match: Cost allocation
Ming’s recommendation to employ the minimum system method in calculating 1 the Grid Reliance Charge consistent with cost causation principles? 2Read this passage Filed comments: Cost allocation
A. No. Mr. Ming states that his recommendation to employ the minimum system method in
printed heading · Topic match: Cost allocation
Ming states that his recommendation to employ the minimum system method in 3 calculating the Grid Reliance Charge is based on principles of cost causation.19 This is 4 simply not the case because the minimum system method is only appropriate for and 5 applicable to distribution level service.Read this passage Filed comments: Cost allocation
A. Mr. Ming’s proposal to employ the minimum system method in calculating the Grid
printed heading
Ming’s proposal to employ the minimum system method in calculating the Grid 12 Reliance Charge is fundamentally flawed.Read this passage
Attachment A
printed heading
Does this complete your testimony at this time? 1Read this passage
A. Yes.
printed heading
A.Read this passage