EL25-49-000 · 2026-05-28 · Indicated PJM Transmission Owners

Motion for Leave to Answer and Answer of the Indicated PJM Transmission Owners in response to certain reply briefs filed on 04/24/2026 and the Motion for…

Text extracted from the eLibrary original (SHA-256 ed16a8787c258f4a…). Download the original from the official source.

Contents · 8 sections
  1. I. INTRODUCTION AND SUMMARY p. 1
  2. II. MOTION FOR LEAVE TO FILE ANSWER p. 2
  3. III. ANSWER p. 3
  4. A. Protection Systems and Other Reliability Remediation Requirements are p. 3
  5. B. Transmission Owner Load Integration Studies Should not be Subject to p. 8
  6. C. Objections to the Proposed Grid Reliance Charge are Meritless. p. 10
  7. D. ODEC’s Requests for Clarification are Addressed in PJM’s and the PJM p. 12
  8. IV. CONCLUSION p. 13

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al. ) Docket No.
Read this passage

I. INTRODUCTION AND SUMMARY

printed heading · Topic match: Connecting load and generation

The Commission should reject Constellation’s attempt to subvert the clear meaning of the Order through its proposal to make protection systems optional for Co-Located Load arrangements.3 Redundant protection systems are necessary for all Co-Located Load taking one of the new transmission services…
Read this passage Filed comments: Connecting load and generation

II. MOTION FOR LEAVE TO FILE ANSWER

printed heading

Energy Storage Coalition, and Verrus, LLC (collectively, the “Joint Co-Location Developers”); PJM Industrial Customer Coalition, the Industrial Energy Consumers of America, the American Forest and Paper Association, and the National Railroad Passenger Corporation (collectively, the “PJM Industrial…
Read this passage

III. ANSWER

printed heading

III.
Read this passage

A. Protection Systems and Other Reliability Remediation Requirements are

printed heading · Topic match: Connecting load and generation

This is especially true given that PJM proposes that it will not identify network upgrades to accommodate transmission service requests for Co-Located Load beyond those amounts that an Eligible Customer designates for Network Integration Transmission Service or Firm Contract Demand Service.9 For…
Read this passage Filed comments: Connecting load and generation

B. Transmission Owner Load Integration Studies Should not be Subject to

printed heading · Topic match: Connecting load and generation

As PJM correctly pointed out in its April 24 reply brief, the Transmission Owners’ processes for studying the integration of new retail loads, and identifying associated upgrades, do not inherently implicate the Commission’s jurisdiction.18 To the contrary, retail load studies have always been…
Read this passage Filed comments: Connecting load and generation

C. Objections to the Proposed Grid Reliance Charge are Meritless.

printed heading · Topic match: Cost allocation

In general, these briefs claim that the proposed Grid Reliance Charge is unprecedented and inconsistent with principles of cost causation.22 These objections are misplaced for a number of reasons.
Read this passage Filed comments: Cost allocation

D. ODEC’s Requests for Clarification are Addressed in PJM’s and the PJM

printed heading · Topic match: Connecting load and generation

ODEC’s Requests for Clarification are Addressed in PJM’s and the PJM Transmission Owners’ Paper Hearing Briefs.
Read this passage Filed comments: Connecting load and generation

IV. CONCLUSION

printed heading · Topic match: Connecting load and generation

In particular, the Commission should reject attempts to water down requirements to install sufficient protection systems to ensure Co-Located Load customers do exceed their contractual commitments.
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C. this 28th day of May, 2026. /s/ Daniel Klein Daniel Klein Davis Wright Tremaine LLP 1301 K Street NW Suite 500 East Washington, DC 20005