EL25-49-000 · 2026-05-28 · Indicated PJM Transmission Owners

Motion for Leave to Answer and Answer of the Indicated PJM Transmission Owners in response to certain reply briefs filed on 04/24/2026 and the Motion for…

PDF page 1

1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
)
Docket No. EL25-49-001
)
Large Loads Co-Located at Generating Facilities
)
Docket No. AD24-11-000
)
Constellation Energy Generation, LLC
)
v. )
Docket No. EL25-20-000
PJM Interconnection, L.L.C.
)
(Consolidated)
MOTION FOR LEAVE TO ANSWER AND ANSWER
OF
THE INDICATED PJM TRANSMISSION OWNERS
I. INTRODUCTION AND SUMMARY
Pursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”), 18 C.F.R. §§ 385.212 and

385.213 (2025), the Indicated PJM Transmission Owners (the “PJM Transmission Owners”)1 respectfully submit this Motion for Leave to Answer and Answer in response to certain of the

1 For purposes of this answer, the PJM Transmission Owners are:  American Electric Power Service Corporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc., AEP Indiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and AEP West Virginia Transmission Company, Inc.; The Dayton Power and Light Company d/b/a AES Ohio; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc.; Duquesne Light Company; East Kentucky Power Cooperative, Inc.; Exelon Corporation on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, on behalf of its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, The Potomac Edison Company, Monongahela Power Company, Keystone Appalachian Transmission Company, and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); PPL Electric Utilities Corporation; Public Service Electric and Gas Company; Rockland Electric Company; and the Southern Maryland Electric Cooperative.

PDF page 2

2
reply briefs filed on April 24, 20262 and the Motion For Leave and Answer of Constellation filed on May 11, 2026 in these proceedings.  The April 24 reply briefs and Constellation answer were filed in response to the Commission’s December 18, 2025 order in PJM Interconnection. L.L.C., 193 FERC ¶ 61,217, at P 193 (2025) (“Order”).

The Commission should reject Constellation’s attempt to subvert the clear meaning of the Order through its proposal to make protection systems optional for Co-Located Load arrangements.3  Redundant protection systems are necessary for all Co-Located Load taking one of the new transmission services to ensure adherence to relevant contractual limits, as well as to secure system reliability.  The Commission should also deny Constellation’s request to require Transmission Owners to file their load integration studies with FERC.  This requirement would exceed the Commission’s jurisdiction and is unnecessary given the protections afforded by existing transmission planning processes as well as PJM’s proposed Co-Located Load transmission study process.  Finally, the Commission should reject further attempts to shift to other ratepayers the costs associated with the benefits Co-Located Load customers receive through continued interconnection and synchronization to the grid, as reflected in the PJM Transmission Owners’ proposed Grid Reliance Charge.

II. MOTION FOR LEAVE TO FILE ANSWER
Although answers are not expressly permitted under the Order, the Commission has permitted answers when they clarify issues in dispute, provide information to assist in the 2

The PJM Transmission Owners address the reply briefs and responses filed by Constellation Energy Generation, LLC (“Constellation”); Eolian, L.P., Antora Energy, Inc., Calibrant Energy, Mainspring Energy, Inc., U.S. Energy Storage Coalition, and Verrus, LLC (collectively, the “Joint Co-Location Developers”); PJM Industrial Customer Coalition, the Industrial Energy Consumers of America, the American Forest and Paper Association, and the National Railroad Passenger Corporation (collectively, the “PJM Industrial Customer Organizations and Amtrak”); and Old Dominion Electric Cooperative.

3 Capitalized terms that are not otherwise defined shall have the meanings set forth in the PJM Interconnection, L.L.C. (“PJM”) Open Access Transmission Tariff (“Tariff”).

PDF page 3

3
Commission’s decision-making process, or to ensure the record is complete and accurate.4  This answer will provide the Commission with information to ensure the record is complete and accurate because the reply briefs and Constellation’s further pleading either misunderstand or misrepresent the PJM and PJM Transmission Owners’ proposals.  This answer will clarify the record and will aid the Commission in its decision-making process.  For these reasons, the PJM Transmission Owners respectfully request that the Commission accept this answer.

III. ANSWER
A. Protection Systems and Other Reliability Remediation Requirements are
not Optional.
Two reply briefs raise issues concerning PJM’s proposal for protection systems and
other reliability remediation requirements.  They generally argue that reliability protections and remediation should be tailored to actual risk rather than imposed as default requirements.5 These arguments suggest that protection systems and remediation requirements are somehow elective.  For instance, Constellation claims that protection systems are not appropriate for every situation and should not be used to mitigate contractual issues such as unauthorized withdrawals.6  These arguments are inconsistent with the Order as well as fundamental reliability principles.

4 See, e.g., Transcontinental Gas Pipeline Corp., 119 FERC ¶ 61,039, at P 15 (2007) (accepting an answer because the information assisted the Commission in its decision-making process); Mich. Elec. Transmission Co., 106 FERC ¶ 61,064, at P 3 (2004) (accepting an answer because “it provides information that clarifies the issues and aids us in the decisional process.”); Duke Energy Oakland, LLC, 102 FERC ¶ 61,093, at P 10 (2003) (finding good cause to accept an otherwise impermissible answer because the answer assisted the Commission in understanding and resolving the issues involved in the proceeding); Carolina Power & Light Co., 97 FERC ¶ 61,048 at 61,278 (2001) (finding good cause to waive Rule 213 when the pleading helped to ensure a complete and accurate record); Morgan Stanley Capital Group, Inc. v. N.Y. Indep. Sys. Operator, Inc., 93 FERC ¶ 61,017 at 61,036 (2000) (accepting an answer to an answer that was “helpful in the development of the record.”).
5 Constellation at 13-18, Ex. 1 at 3-8; Joint Co-Location Developers at 5-10, Attachment A at 10-15.
6 Constellation at 16.

PDF page 4

4
In the Order, the Commission made clear that one of the rationales for implementing the three new transmission services specific to Co-Located Load was Co-Located Loads “are willing and able to control their withdrawals from the transmission system” through the use of system protection facilities.7  The Commission was unambiguous on this point, stating that “in these instances where the Co-Location Arrangement includes special protection schemes that limit its energy withdrawals, we find that it is a just and reasonable replacement rate to allow an Eligible Customer taking transmission service on behalf of such load to take and be charged for new types of transmission service that are alternatives, and not equivalent, to [Network Integration Transmission Service].”8  In other words, in order for an Eligible Customer to take one of the new Co-Located Load-specific transmission services it is necessary and thus just and reasonable to require an Eligible Customer to include appropriate protection systems. Therefore, contrary to Constellation’s claim, it is not only appropriate but necessary for PJM to require that any Eligible Customer that wishes to take one of the new transmission services to include protection systems to ensure that those Eligible Customers do not exceed their contractual limitations.

Moreover, the obligations of PJM and Transmission Owners in PJM to safeguard and maintain system reliability are paramount, as the Commission has established on numerous occasions.  Accordingly, the new transmission services required under the Order must be subject to appropriate terms and conditions to ensure that the implementation of these new services does not compromise system reliability.  Co-Located Loads, as well as any on-site generators used to serve those loads, are not islanded.  Rather, they are fully connected and

7 Order at P 204. 8 Id. at P 205 (emphasis added).

PDF page 5

5
synchronized with the transmission system, like all other loads and generators, and thus the total on-site load and generation have the ability to adversely affect the system.  This is especially true given that PJM proposes that it will not identify network upgrades to accommodate transmission service requests for Co-Located Load beyond those amounts that an Eligible Customer designates for Network Integration Transmission Service or Firm Contract Demand Service.9  For Co-Located Loads, maintaining the continued reliability of the system will depend on the utilization of protection schemes and remediation requirements to ensure use of the system by Co-Located Load beyond its reserved use.

Constellation asserts that fully redundant protection systems should not be the default requirement for Co-Located Load arrangements.10  Constellation acknowledges that such protections may be appropriate, but argues that they are only appropriate in limited, higher-risk situations.11  It adds that there is no rational basis to require protection schemes on both the customer’s and the Transmission Owner’s side of the point of interconnection.12  This claim is incorrect.  Special Protection Schemes (“SPS”) on both the Co-Located Load customer’s and the Transmission Owner’s side of the point of interconnection should not be limited to what Constellation claims are higher-risk situations.  Constellation’s suggestion that financial penalties imposed by PJM after the fact are a sufficient deterrent to ensure curtailment in response to a transmission system event or fault within the Eligible Customer’s facility shows a fundamental lack of understanding of power system engineering.  The Eligible Customer

9 See, e.g., PJM February 23 Initial Brief, Illustrative Tariff Sheets at 710.5 (“As set forth in the Service Agreement for Contract Demand Transmission Service, the Eligible Customer may also be responsible for the cost of network upgrades from the Transmission Provider’s Transmission System to the Delivery Point.”).
10 Constellation at 13-18; Ex. 1 at 3-7.
11 Id.
12 Id.

PDF page 6

6
might not be a NERC-registered entity subject to its oversight.  Additionally, it is overly optimistic to believe that penalties alone will ensure that Eligible Customers, who have a financial interest in minimizing the costs associated with protection systems, always will install, operate, and maintain their SPS and Remedial Action Schemes (“RAS”) correctly over time if the only consequence they may face are possible fines after an event.

On every other element of the bulk electric system in PJM, there is an expectation for redundancy for protection systems that are primarily responsible for fault clearing.  In the case of Co-Located Load, the failure to curtail load or generation adequately can adversely impact the transmission system just as significantly as a fault, especially if there are no limitations on the size of the load and generation connected in one facility.  Without protection system redundancy, the transmission system and the millions of customers that rely on it are at risk. Accordingly, it is not accurate to claim that lower-risk configurations can be addressed effectively through operating procedures, relaying, and remote tripping capability, as Constellation contends.13

Constellation’s assertions that PJM should use a PJM-driven study process to determine whether SPS or other types of remediation are needed, and that any remediation should be commensurate with actual reliability risk rather than imposed by default,14 ignore the fact that PJM is not equipped to perform these studies.  Currently, PJM does not possess the relay settings for Co-Located Load interconnections.  Nor is it likely that PJM could obtain the relay settings or perform any meaningful analysis even if it did obtain them.  Studying the need for SPS and RAS is within the purview of the PJM Transmission Owners because they have the

13 Constellation at 13-18; Ex. 1 at 3-7.
14 Id. at 12-18; Ex. 1 at 6-8.

PDF page 7

7
knowledge and insight with respect to the local protection systems and operational constraints that may occur due to equipment outages for routine maintenance or equipment failure. Also, the cost to implement protection systems should not be a deterrent.  The overall cost to implement protection systems at a given facility comes primarily from the personnel hours during engineering and construction, then later maintenance.  But in any event, the cost of protection system equipment is extremely low when compared to other costs associated with the development and interconnection of Co-Located Load.  Similarly, such installations are best performed when the Co-Located Load first comes on-line as it is relatively inexpensive to install protection systems as part of initial construction.  It is, on the other hand, much more expensive and time-consuming to retrofit a Co-Located Load facility after initial construction, given that it likely would require a generation facility outage.

Finally, Constellation continues to offer unsupported accusations concerning
Transmission Owner discrimination, asserting that the Commission should guard against Transmission Owner discretion that could enable discrimination or delay.15  As the PJM Transmission Owners discussed in their April 24 Reply Brief,16 claims that the PJM Transmission Owners will use their role in the study process to delay and deny co-location arrangements or otherwise discriminate against Co-Located Load are baseless and speculative.  There simply is no reason to assume that any PJM Transmission Owner will seek to frustrate the intent of Commission-accepted tariff provisions.  Likewise, it is illogical to assume that any PJM Transmission Owners will have an incentive to discriminate against Co-Located Loads in studying

15 Constellation at 9-12.  Constellation’s list of concerns includes rejecting the proposed use of “Point of Change in Ownership” in the definition of Co-Located Load, imposing deadlines for studies and approvals, and requiring co-location standards, requirements, guidance, and practices to be filed with the Commission or placed in the tariff.  Id.
16 Indicated PJM Transmission Owners April 24 Reply Brief at 11.

PDF page 8

8
such arrangements.  As noted above, the primary concern for Transmission Owners in PJM is system reliability.  To the extent Co-Located Load arrangements present no reliability issues, there is no reason or evidence to suggest that the PJM Transmission Owners will not accommodate their interconnections.

B. Transmission Owner Load Integration Studies Should not be Subject to
FERC Filing.
Constellation claims that the Commission should exercise jurisdiction over load
integration studies conducted by Transmission Owners and direct those load integration studies to be filed with the Commission.17  This suggestion is meritless.  As PJM correctly pointed out in its April 24 reply brief, the Transmission Owners’ processes for studying the integration of new retail loads, and identifying associated upgrades, do not inherently implicate the Commission’s jurisdiction.18  To the contrary, retail load studies have always been subject to state jurisdiction, and the fact that such studies will be used as one of the inputs into PJM’s process for studying applications for one of the new transmission services does not provide a sufficient basis for the Commission to assert jurisdiction over those studies.  There is a fundamental distinction between studying load for purposes of providing retail distribution and energy delivery services, and the implementation of FERC-jurisdictional interconnection and transmission services, a jurisdictional line that has long been respected by the Commission.19  Under PJM’s proposed Co-Located Load

17 Constellation May 11 Answer at 6-7.
18 PJM April 24 Reply Brief at 34.
19 See Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036 (1996) (cross-referenced at 75 FERC ¶ 61,080), on reh’g, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 (cross-referenced at 78 FERC ¶ 61,220), on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom., Transmission Access Policy Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom., N.Y. v. FERC, 535 U.S. 1 (2002); Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, 104 FERC ¶ 61,103 (2003), order on reh’g, Order No. 2003-A, 106 FERC ¶ 61,220, order on reh’g, Order No. 2003-B, 109 FERC ¶ 61,287 (2004),

PDF page 9

9
tariff provisions, it is PJM as the Transmission Provider that will make determinations about whether and to what extent one of the new transmission services can be provided to an applicant.20 These determinations will be transparent, as PJM is required to provide a written explanation with respect to any denial of service.21

Moreover, any FERC-jurisdictional transmission facilities needed to accommodate a load interconnection, be it a Co-Located Load or otherwise, will continue to be subject to the planning procedures, including the associated stakeholder review and input processes, set forth in PJM’s Tariff and Operating Agreement, either through the Regional Transmission Expansion Planning protocols, or the local planning provisions set forth in Attachment M-3.  Finally, even with respect to studies performed with respect to FERC-jurisdictional services, such as generator interconnection and transmission services, the Commission does not require transmission providers to file studies, as they are neither service agreements nor rate schedules.  To the extent that a customer has a dispute with the outcome of a particular study, the customer may challenge that outcome in the context of the Interconnection Agreement or Transmission Service Agreement process.  Similarly, if an Eligible Customer seeking to procure one or more of the new Co-Located Load transmission services believes that the outcome of PJM’s study process is flawed, the customer can seek redress through the Commission.

order on reh’g, Order No. 2003-C, 111 FERC ¶ 61,401 (2005), aff’d sub nom. Nat’l Ass’n of Regul. Util. Comm’rs
v. FERC, 475 F.3d 1277 (D.C. Cir. 2007).
20 PJM February 23 Initial Brief, Illustrative Tariff Sheets at 710.3 (“Following completion of all studies, Transmission Provider will make the determination, in consultation with the affected PJM Transmission Owner(s), about whether (and to what level as applicable) Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Services can be reliably provided for an Application, and if so, what level of service may be provided.”).
21 See id. at 710.3 (“If the Transmission Provider determines that only a portion of the Non-Firm Contract Demand Transmission Service requested by Eligible Customer can be provided reliably, the Transmission Provider will provide a written explanation of its reasons for partial denial of service.”).

PDF page 10

10
For these reasons, there is no need or legal basis for FERC to assert jurisdiction over and require the filing of Transmission Owner load integration studies.

C. Objections to the Proposed Grid Reliance Charge are Meritless.
A few reply briefs take issue with the PJM Transmission Owners’ Grid Reliance Charge proposal.  In general, these briefs claim that the proposed Grid Reliance Charge is unprecedented and inconsistent with principles of cost causation.22  These objections are misplaced for a number of reasons.

The PJM Transmission Owners developed the Grid Reliance Charge partially in response to Commissioner Chang’s guidance that a just and reasonable replacement rate for the new transmission services should reflect “some form of minimum transmission service charge, which would protect other customers against cost shifts resulting from Co-Located Loads that rely upon the transmission system but do not directly or meaningfully contribute to its costs via transmission service payments.”23  The PJM Transmission Owners’ proposed Grid Reliance Charge achieves this goal.  As the PJM Transmission Owners explained in their April 24 Reply Brief, the proposed Grid Reliance Charge is designed to reflect the costs of using the transmission system to deliver black start and regulation services, as well as the costs of providing the inherent benefits that all customers, including Contract Demand customers, receive as a result of their synchronization to and reliance on the grid.24

22 See, e.g., Constellation at 8; PJM Industrial Customer Organizations and Amtrak at 11-14; Joint Co- Location Developers at 3-4.
23 Order, Chang Concurrence at P 9.
24 Indicated PJM Transmission Owners April 24 Reply Brief at 21.

PDF page 11

11
In its May 11, 2026 Answer, Constellation presents a handful of criticisms of the PJM Transmission Owners’ Grid Reliance Charge proposal.25  For example, Constellation’s witness, Zachary Ming, asserts that the PJM Transmission Owners “fail to address the fundamental shortcoming of their proposal – a transmission system built only to deliver ancillary services would be nowhere near as large or expensive as a transmission system built to serve peak demand.”26 Mr. Ming continues to miss the point.  The purpose of the Grid Reliance Charge is not merely to recover the costs of a fictional transmission system built only to deliver ancillary services, but rather to ensure that Co-Located Load customers pay their fair share of the transmission system as it exists and the associated benefits that it provides to all interconnected customers, including essential reliability services, such as frequency support, inertia, voltage stability, fault current capability, ride-through and protection coordination, and sufficient short-circuit capability.27  The PJM Transmission Owners’ proposed Grid Reliance Charge does so by calculating the portions of annual depreciation and operations and maintenance expenses that constitute a reasonable proxy for the costs of providing those benefits.  The Grid Reliance Charge is therefore just and reasonable.

In contrast, Constellation’s proposed minimum system replacement proposal28 is not just and reasonable.  The minimum system method is only appropriate for and applicable to distribution level service.  It is entirely inappropriate to apply the minimum system method to

25 Constellation May 11 Answer at 2 (“The Transmission Owners’ excessive Grid Reliance Charge has no basis in principle or precedent, while Constellation has proposed a just and reasonable replacement rate the Commission can readily adopt.”); Id. at 11 (The “Grid Reliance Charge is arbitrary and unmoored from cost causation principles.”).
26 Reply Testimony of Zachary Ming at 9:14-16 (“Ming Reply Testimony”).
27 Indicated PJM Transmission Owners April 24 Reply Brief, Exh. PTO-0005 at 31.
28 Constellation March 25, 2026 Reply Brief at Attachment 1; Constellation May 11 Answer at 11-13; Ming Reply Testimony at 11-18.

PDF page 12

12
calculate a transmission service rate.  As Mr. Schafer explains in his further testimony included as Attachment A to this answer, Mr. Ming continues to fail to account for the fact that the minimum system approach is only designed as a mechanism to classify portions of certain distribution plant accounts as either customer- or demand-related.29  It is not, however, used to determine a revenue requirement, and therefore Mr. Ming’s proposed 6.2% “minimum system” allocation factor is inappropriate in the context of calculating a transmission service rate.30  Mr. Ming also continues to base his minimum system analysis on equipment, such as distribution wood poles, that would not be used for transmission assets, even a hypothetical “minimum” transmission system that was designed solely to deliver ancillary services.31

D. ODEC’s Requests for Clarification are Addressed in PJM’s and the PJM
Transmission Owners’ Paper Hearing Briefs.
In its April 24 reply brief, Old Dominion Electric Cooperative (“ODEC”) indicates its general agreement with the proposals submitted by PJM and the PJM Transmission Owners, but requests clarification on several items.  With respect to the PJM Transmission Owners’ proposal to provide billing credits for revenues associated with the Grid Reliance Charge and Non-Firm Contract Demand Transmission Service, ODEC requests that the Transmission Owners confirm the mechanism for providing these credits to customers.32  This issue is addressed in further detail in the PJM Transmission Owners’ April 24 reply brief, which includes illustrative tariff language that provides for direct bill credits to customers from PJM for such revenues.33  ODEC also requests clarification on how regulation and black start service

29 Reply Testimony of Lance Schafer, Attachment A at 8 (“Schafer Reply Testimony”).
30 Schafer Reply Testimony at 8-10.
31 Id. at 10-11.
32 ODEC at 3.
33 April 24 Reply Brief, Exh. No. PTO-0006.

PDF page 13

13
will be charged to Eligible Customers taking service on behalf of Co-Located Load.  Based on PJM’s proposal, the PJM Transmission Owners understand that those charges will be assessed directly to load-serving entities, in the same manner as they are currently for NITS customers.34

IV. CONCLUSION
For the reasons set forth herein, the PJM Transmission Owners respectfully request that the Commission accept this answer and rule in a manner consistent with the discussion above. In particular, the Commission should reject attempts to water down requirements to install sufficient protection systems to ensure Co-Located Load customers do exceed their contractual commitments.  The Commission should also reject arguments to shift costs of Co-Located Load customers to other ratepayers and accept the PJM Transmission Owners’ proposed Grid Reliance Charge.

Respectfully submitted,
/s/ Michael Kunselman
Michael Kunselman
Richard P. Sparling

Nicholas J. Cicale
Jonathan A. Namazi
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, DC 20005
Counsel for the FirstEnergy
  Companies
On behalf of the Indicated PJM
  Transmission Owners
Dated:  May 28, 2026
34 See PJM February 23 Initial Brief at Attachment A.

PDF page 14

CERTIFICATE OF SERVICE
Under Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2025), I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary in these proceedings. Dated at Washington, D.C. this 28th day of May, 2026.

/s/ Daniel Klein
Daniel Klein
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, DC 20005