Order on Rehearing, Clarification, Compliance Filing, and Paper Hearing re PJM Interconnection, L.L.C. et al
Text extracted from the eLibrary original (SHA-256 3fd02baaa90e7070…). Download the original from the official source.
Contents · 31 sections
- I. Background - 13 -
- A. February Order - 13 -
- B. December Order - 15 -
- II. Notice of Filings and Responsive Pleadings - 17 -
- A. PJM’s Compliance Filing - 17 -
- B. Paper Hearing on New Transmission Services - 18 -
- III. Procedural Matters - 19 -
- IV. Requests for Rehearing and/or Clarification - 21 -
- A. Jurisdiction - 23 -
- B. Show Cause Findings - 29 -
- C. Replacement Rate - 56 -
- D. Informational Report - 102 -
- V. Compliance - 104 -
- A. BTMG Rules - 104 -
- B. Transmission Service - 133 -
- C. Necessary Studies - 141 -
- D. Other - 150 -
- E. Effective Date - 161 -
- VI. Paper Hearing - 162 -
- A. Rates, Terms, and Conditions for Firm and Non-Firm Contract Demand Transmission Service - 163 -
- B. Additional Charge for Eligible Customers Taking FCD and/or NFCD Transmission Service - 207 -
- C. Interconnection Requirements and Operational Practices for Necessary Control Technologies and/or Protection Systems - 221 -
- D. Penalty Charge or Other Remedial Action for New Transmission Services - 232 -
- E. Anti-Toggling Mechanisms for Firm Contract Demand Transmission Service - 251 -
- F. Communications, Alarm, SCADA, or Other Requirements - 254 -
- G. Curtailment Procedures for Interim NITS and Non-Firm Contract Demand Transmission Service - 255 -
- H. Rates, Terms, and Conditions for Interim NITS - 261 -
- I. Annual Report on New Transmission Services - 271 -
- Background
- ATTACHMENT F-3A, OATT ATTACHMENT F-3A (0.0.0)
- ATTACHMENT F-4, OATT ATTACHMENT F-4 (0.0.0)
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Reliability and curtailment · Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
EL25-49-000, et al., pursuant to section 206 of the Federal Power Act (FPA),[fn:2] finding PJM Interconnection, L.L.C.’s (PJM) Tariff unjust and unreasonable because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that…Read this passage Filed comments: Filing procedure
I. Background - 13 -
printed heading
I.Read this passage
A. February Order - 13 -
printed heading
A.Read this passage
B. December Order - 15 -
printed heading
B.Read this passage
II. Notice of Filings and Responsive Pleadings - 17 -
printed heading
Notice of Filings and Responsive Pleadings - 17 -Read this passage
A. PJM’s Compliance Filing - 17 -
printed heading
A.Read this passage
B. Paper Hearing on New Transmission Services - 18 -
printed heading
Paper Hearing on New Transmission Services - 18 -Read this passage
III. Procedural Matters - 19 -
printed heading
III.Read this passage
IV. Requests for Rehearing and/or Clarification - 21 -
printed heading · Topic match: Filing procedure
Requests for Rehearing and/or Clarification - 21 -Read this passage Filed comments: Filing procedure
A. Jurisdiction - 23 -
printed heading
Sales for Resale in Interstate Commerce - 23 - 2.Read this passage
B. Show Cause Findings - 29 -
printed heading
Overview, Transmission Service, Regulation and Black Start - 29 - 2.Read this passage
C. Replacement Rate - 56 -
printed heading · Topic match: Connecting load and generation
Necessary Study Process for Existing Interconnection Customers - 91 - 3.Read this passage Filed comments: Connecting load and generation
D. Informational Report - 102 -
printed heading
D.Read this passage
V. Compliance - 104 -
printed heading
V.Read this passage
A. BTMG Rules - 104 -
printed heading
A.Read this passage
B. Transmission Service - 133 -
printed heading
B.Read this passage
C. Necessary Studies - 141 -
printed heading
C.Read this passage
D. Other - 150 -
printed heading
D.Read this passage
E. Effective Date - 161 -
printed heading
E.Read this passage
VI. Paper Hearing - 162 -
printed heading
VI.Read this passage
A. Rates, Terms, and Conditions for Firm and Non-Firm Contract Demand Transmission Service - 163 -
printed heading
Rates, Terms, and Conditions for Firm and Non-Firm Contract Demand Transmission Service - 163 - 1.Read this passage
B. Additional Charge for Eligible Customers Taking FCD and/or NFCD Transmission Service - 207 -
printed heading
Additional Charge for Eligible Customers Taking FCD and/or NFCD Transmission Service - 207 - 1.Read this passage
C. Interconnection Requirements and Operational Practices for Necessary Control Technologies and/or Protection Systems - 221 -
printed heading
Interconnection Requirements and Operational Practices for Necessary Control Technologies and/or Protection Systems - 221 - 1.Read this passage
D. Penalty Charge or Other Remedial Action for New Transmission Services - 232 -
printed heading
Penalty Charge or Other Remedial Action for New Transmission Services - 232 - 1.Read this passage
E. Anti-Toggling Mechanisms for Firm Contract Demand Transmission Service - 251 -
printed heading
Anti-Toggling Mechanisms for Firm Contract Demand Transmission Service - 251 - 1.Read this passage
F. Communications, Alarm, SCADA, or Other Requirements - 254 -
printed heading
Communications, Alarm, SCADA, or Other Requirements - 254 - 1.Read this passage
G. Curtailment Procedures for Interim NITS and Non-Firm Contract Demand Transmission Service - 255 -
printed heading · Topic match: Reliability and curtailment
Curtailment Procedures for Interim NITS and Non-Firm Contract Demand Transmission Service - 255 - 1.Read this passage Filed comments: Reliability and curtailment
H. Rates, Terms, and Conditions for Interim NITS - 261 -
printed heading
Rates, Terms, and Conditions for Interim NITS - 261 - 1.Read this passage
I. Annual Report on New Transmission Services - 271 -
printed heading
Annual Report on New Transmission Services - 271 - J.Read this passage
Background
printed heading · Topic match: Connecting load and generation
Generation Interconnection Procedures, pro forma GIA, and Common Service Provisions We accept the following of PJM’s proposed revisions to establish rules for Interconnection Customers serving Co-Located Load as complying with the December Order: (1) adding to the list of requirements for a New…Read this passage Filed comments: Connecting load and generation
ATTACHMENT F-3A, OATT ATTACHMENT F-3A (0.0.0)
printed heading
ATTACHMENT F-3A, OATT ATTACHMENT F-3A (0.0.0)Read this passage
ATTACHMENT F-4, OATT ATTACHMENT F-4 (0.0.0)
printed heading · Topic match: Cost allocation
EL25-49-002 EL25-49-000 AD24-11-001 EL25-20-001 (consolidated) ER26-1479-000 (Issued June 18, 2026) CHANG, Commissioner, concurring: In today’s order, the Commission addresses rehearing requests and the paper hearing and compliance record regarding the rates, terms, and conditions through which…Read this passage Filed comments: Cost allocation
Footnotes
Word notes · Topic match: Filing procedure
Co., 100 FERC ¶ 61,097, at P 5 (2002). [fn:41] Pennsylvania Office of Consumer Advocate is not a party to this proceeding with respect to rehearing or clarification of the December Order and therefore may not file an answer to a request for rehearing or clarification. [fn:42] 18 C.F.R. §…Read this passage Filed comments: Filing procedure