Order Instituting Proceeding Under Section 206 etc. re PJM Interconnection, L.L.C. et al
Text extracted from the eLibrary original (SHA-256 993af8ee8c539ae9…). Download the original from the official source.
Contents · 16 sections
- I. Background 6.
- A. Growth of Large and Co-Located Loads and ANOPR 6.
- B. Recent Proceedings Addressing Large and Co-Located Loads 11.
- II. PJM’s Existing Processes 19.
- A. Existing Tariff Processes 19.
- B. Recent Stakeholder Proceedings in PJM 31.
- III. Discussion 35.
- A. Transmission Service to Eligible Customers on Behalf of Large Loads 41.
- B. Cost Shifting Risk Among Transmission Customers 66.
- C. Extending New Transmission Services to Eligible Customers Taking Service on Behalf of Flexible Large Loads 85.
- D. Interconnection Customers Serving Electrically Proximate Large Load and Co-Located Load 88.
- E. Informational Report 102.
- IV. Briefing Questions 105.
- Background
- Discussion
- Conclusion
Read topic-matched comments in EL26-67
Topics in the text: Cost allocation · Connecting load and generation · Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
195 FERC ¶ 61,211 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Laura V.Read this passage
I. Background 6.
printed heading
I.Read this passage
A. Growth of Large and Co-Located Loads and ANOPR 6.
printed heading
Growth of Large and Co-Located Loads and ANOPR 6.Read this passage
B. Recent Proceedings Addressing Large and Co-Located Loads 11.
printed heading
Recent Proceedings Addressing Large and Co-Located Loads 11. 1.Read this passage
II. PJM’s Existing Processes 19.
printed heading
II.Read this passage
A. Existing Tariff Processes 19.
printed heading
A.Read this passage
B. Recent Stakeholder Proceedings in PJM 31.
printed heading
B.Read this passage
III. Discussion 35.
printed heading
III.Read this passage
A. Transmission Service to Eligible Customers on Behalf of Large Loads 41.
printed heading
Transmission Service to Eligible Customers on Behalf of Large Loads 41. 1.Read this passage
B. Cost Shifting Risk Among Transmission Customers 66.
printed heading · Topic match: Cost allocation
Cost Shifting Risk Among Transmission Customers 66. 1.Read this passage Filed comments: Cost allocation
C. Extending New Transmission Services to Eligible Customers Taking Service on Behalf of Flexible Large Loads 85.
printed heading
Extending New Transmission Services to Eligible Customers Taking Service on Behalf of Flexible Large Loads 85.Read this passage
D. Interconnection Customers Serving Electrically Proximate Large Load and Co-Located Load 88.
printed heading · Topic match: Connecting load and generation
Interconnection Customers Serving Electrically Proximate Large Load and Co-Located Load 88. 1.Read this passage Filed comments: Connecting load and generation
E. Informational Report 102.
printed heading
E.Read this passage
IV. Briefing Questions 105.
printed heading · Topic match: Connecting load and generation
Over the past year, the Commission has taken action in numerous dockets[fn:2] to address issues related to (a) unprecedented increases in requests for transmission service to serve large loads[fn:3] and (b) growing interest in the co-location of loads with generating facilities (co-location…Read this passage Filed comments: Connecting load and generation
Background
printed heading · Topic match: Connecting load and generation
PJM Co-Location Proceedings On February 20, 2025, the Commission initiated a show cause proceeding against PJM and the PJM Transmission Owners regarding the lack of tariff provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to…Read this passage Filed comments: Connecting load and generation
Discussion
printed heading · Topic match: Cost allocation
Several commenters discuss the risk of cost shifting among transmission customers that could result from transmission service requests by Eligible Customers on behalf of large loads.[fn:169] Commenters also argue that retail-level large load tariffs do not protect wholesale transmission customers…Read this passage Filed comments: Cost allocation
Conclusion
printed heading · Topic match: Cost allocation
While this is a long journey, even so, we must continue to move at breakneck pace to win the AI race.Read this passage Filed comments: Cost allocation
Footnotes
Word notes · Topic match: Cost allocation
C, § 404(A)(5)(c) (Cost Allocation for Network Upgrades) (1.0.0); see PJM Manual 14H: New Service Requests Cycle Process, § 4.2.6 (Sep. 2025), https://www.pjm.com/-/media/DotCom/documents/manuals/m14h.ashx (PJM Manual 14H). [fn:83] PJM Tariff, pt.Read this passage Filed comments: Cost allocation