Order Instituting Proceeding under Section 206 of the Federal Power Act re Southwest Power Pool, Inc. et al
Text extracted from the eLibrary original (SHA-256 5f5ed5d98d46f9ff…). Download the original from the official source.
Contents · 16 sections
- I. Background 6.
- A. Growth of Large and Co-Located Loads and ANOPR 6.
- B. Recent Proceedings Addressing Large and Co-Located Loads 11.
- II. SPP’s Existing Processes 19.
- A. Existing Tariff Processes 19.
- B. Recent Stakeholder Proceedings in SPP 27.
- III. Discussion 29.
- A. Transmission Service to Eligible Customers on Behalf of Large Loads 35.
- B. Cost Shifting Risk Among Transmission Customers 47.
- C. Co-Location Arrangements and Load with Behind the Meter Generation 67.
- D. Extending New Transmission Services to Eligible Customers Taking Service on Behalf of Flexible Large Loads 85.
- E. Informational Report 89.
- IV. Briefing Questions 92.
- Background
- Discussion
- Conclusion
Read topic-matched comments in EL26-68
Topics in the text: Cost allocation · Connecting load and generation · Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
195 FERC ¶ 61,213 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Laura V.Read this passage
I. Background 6.
printed heading
I.Read this passage
A. Growth of Large and Co-Located Loads and ANOPR 6.
printed heading
Growth of Large and Co-Located Loads and ANOPR 6.Read this passage
B. Recent Proceedings Addressing Large and Co-Located Loads 11.
printed heading
Recent Proceedings Addressing Large and Co-Located Loads 11. 1.Read this passage
II. SPP’s Existing Processes 19.
printed heading
II.Read this passage
A. Existing Tariff Processes 19.
printed heading
A.Read this passage
B. Recent Stakeholder Proceedings in SPP 27.
printed heading
B.Read this passage
III. Discussion 29.
printed heading
III.Read this passage
A. Transmission Service to Eligible Customers on Behalf of Large Loads 35.
printed heading
Transmission Service to Eligible Customers on Behalf of Large Loads 35. 1.Read this passage
B. Cost Shifting Risk Among Transmission Customers 47.
printed heading · Topic match: Cost allocation
Cost Shifting Risk Among Transmission Customers 47. 1.Read this passage
C. Co-Location Arrangements and Load with Behind the Meter Generation 67.
printed heading
Co-Location Arrangements and Load with Behind the Meter Generation 67. 1.Read this passage
D. Extending New Transmission Services to Eligible Customers Taking Service on Behalf of Flexible Large Loads 85.
printed heading
Extending New Transmission Services to Eligible Customers Taking Service on Behalf of Flexible Large Loads 85.Read this passage
E. Informational Report 89.
printed heading
E.Read this passage
IV. Briefing Questions 92.
printed heading · Topic match: Cost allocation
Over the past year, the Commission has taken action in numerous dockets[fn:2] to address issues related to (a) unprecedented increases in requests for transmission service to serve large loads[fn:3] and (b) growing interest in the co-location of loads with generating facilities (co-location…Read this passage
Background
printed heading · Topic match: Connecting load and generation
PJM Co-Location Proceedings On February 20, 2025, the Commission initiated a show cause proceeding against PJM and the PJM transmission owners regarding the lack of tariff provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to…Read this passage
Discussion
printed heading · Topic match: Cost allocation
Several commenters discuss the risk of cost shifting among transmission customers that could result from transmission service requests by Eligible Customers on behalf of large loads.[fn:129] Commenters also argue that retail-level large load tariffs do not protect wholesale transmission customers…Read this passage Filed comments: Filing procedure
Conclusion
printed heading · Topic match: Cost allocation
While this is a long journey, even so, we must continue to move at breakneck pace to win the AI race.Read this passage
Footnotes
Word notes · Topic match: Connecting load and generation
See infra P 15. [fn:9] We note that SPP’s Tariff does not have a formal definition of “co-located load” or “co-location arrangement.” As discussed below, for the purposes of HILLGA, the generating facility only must be in close electrical proximity.Read this passage Filed comments: Filing procedure