AD26-7-000 · 2026-07-15 · American Electric Power Company Inc

Pre-filed Statement of Stacey Burbure, Senior Vice President of Transmission Regulatory Engagement & Compliance for American Electric Power Company, Inc.…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Governance and Stakeholder Reforms

Docket No. AD26-7-000
STATEMENT OF STACEY BURBURE
AMERICAN ELECTRIC POWER COMPANY, INC.
PANEL 1

American Electric Power Company, Inc. (“AEP”) appreciates the opportunity to participate on Panel 1 of the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) technical conference on governance and stakeholder reforms in PJM Interconnection, L.L.C. (“PJM”).1 As Senior Vice President of Transmission Regulatory Engagement and Compliance, I support AEP’s operating utilities, including those operating within the PJM region. AEP operates within seven of the thirteen states in PJM’s footprint (Indiana, Kentucky, Michigan, Ohio, Tennessee, Virginia, and West Virginia).

AEP participates in four Regional Transmission Organizations (“RTO”): PJM, the
Midcontinent Independent System Operator (“MISO”), the Southwest Power Pool (“SPP”), and the Electric Reliability Council of Texas (“ERCOT”), providing the company with broad experience across diverse governance models, market structures, and planning frameworks. In addition to my responsibilities supporting AEP’s utilities across these regions, I serve on the SPP Members Committee, providing firsthand experience with RTO stakeholder governance and decision-making.

1 The questions posed by the Commission to Panel 1 and AEP’s answers are set forth in the Appendix to this statement.

PDF page 2

2
I. Introduction and Summary
The United States has before it today one of the greatest requirements for energy development in generations. This required energy development is largely driven by the national interest in being the worldwide leader in artificial intelligence infrastructure and technology. Addressing this national interest is essential to national security and presents a tremendous opportunity to drive economic growth. At its core, AEP’s concern with PJM is that it is dysfunctional, ineffective, and not capable of doing its job of supporting the deployment of massive amounts of needed generation and transmission by its members. In short, PJM is broken and must be immediately fixed.

To avoid the catastrophic effects of jeopardizing our national security and economic growth, PJM must immediately change. PJM must change its operations and governance to allow customers to interconnect load and generation faster. PJM must have a planning process that takes transmission and generation into account together. That planning process must identify and provide sufficient resources to meet the needs of existing and future customers. Finally, PJM governance must change so stakeholders can be heard, innovation can occur, decisions can be made, and PJM can move forward and get out of the deadlock it faces today.

AEP proposes three overarching areas of change for PJM. First, generator interconnection must be reformed in PJM. Under current interconnection rules, a generator cannot reach commercial operation without significant delays and inefficiencies. This discourages generation development. Second, PJM’s approach to ensuring resource adequacy in the region must be updated. PJM’s Reliability Pricing Model has failed to send efficient investment and retirement signals which has distorted price formation. The result is diminished long-term revenue certainty for generation developers which discourages investment in dependable, dispatchable generation and undermines resource adequacy over time. Third, PJM governance and stakeholder processes

PDF page 3

3
must be reformed. PJM is seeking to solve today’s challenges with an outdated Board of Managers (“Board”) governance and stakeholder process where necessary reforms cannot be implemented efficiently and effectively.  Too often, reforms are stymied by a stakeholder process that consistently deadlocks on important issues and a Board governance model lacking clear accountability and the will to drive change.

The need for change in these three areas is urgent. PJM is confronting the most significant reliability, affordability, and infrastructure challenge in its history. Demand from national security needs, advanced manufacturing, data centers, and electrification is accelerating faster than the region is able to plan and build the infrastructure needed to support it through PJM’s current mechanisms. The question before the Commission is whether PJM’s Board governance structure and stakeholder process enable timely, technically sound decisions that maintain reliability, support affordability, and enable economic growth. In AEP’s view, they do not. PJM suffers from a governance mismatch: responsibility for outcomes rests with the Board, but authority over many of the tools needed to achieve those outcomes remains fragmented. PJM’s existing governance framework has not consistently enabled timely action to meet customer needs or address evolving reliability, planning, and market challenges. That is not a sustainable near-term or long-term operating condition for the region. PJM’s governance structure must align responsibility, authority, and accountability so that those charged with ensuring reliability have the ability—and the obligation—to deliver it. PJM states, accountable to their citizens, lack any formal role. While every stakeholder deserves a voice, governance must better reflect who is responsible for planning, financing, operating, and maintaining the infrastructure upon which reliability depends, and solving the urgent generator interconnection and resource adequacy issues.

PDF page 4

4
Effective governance is not measured by the number of committees or the degree of stakeholder participation. It is measured by whether responsibility, authority, and accountability are aligned to produce timely decisions that maintain reliability, support affordability, and enable fast generation interconnection to support national security and economic growth. It is ultimately measured by customer outcomes: Do the lights stay on, is growth supported on the customer’s development timeline, and do planning processes stay ahead of demand so growth can occur and important national interests like security and AI development can move forward unconstrained? Reliable, affordable, and efficient customer service form the foundation of AEP’s recommendations.

II. How Process Thwarts Substance in PJM—An Illustration
Today’s stakeholder process makes it nearly impossible to evaluate integrated solutions that span the two areas most critically in need of change—generation interconnection and resource adequacy—as well as related areas of load interconnection and market design. A reformed process must enable stakeholders to bring creative proposals designed to solve PJM’s biggest problems to the table for serious review by other stakeholders, PJM management, and the Board. The current PJM stakeholder process does not encourage new innovative ideas and the structure of the committee system complicates needed market reforms that hope to solve some of today’s greatest challenges. As far back as December of 2024, the PJM Board publicly acknowledged that they foresaw immediate capacity shortage conditions in the 2026/27 Delivery Year forecast. With an unprecedented challenge that should have prompted bold action, PJM proposed only minor changes.  This was, in part, due to the byzantine nature of the stakeholder process and an inability to bring about consensus from its membership. When faced with today’s unprecedented challenges, AEP believes that instead of minor tweaks, PJM should be empowered

PDF page 5

5
to move forward boldly with solutions which may not gain the support of entrenched market participants who benefit from the status quo.

One such proposal that helps to demonstrate this archaic stakeholder misalignment within the PJM governance process is AEP’s Accelerated Load, Infrastructure, Generation and Network Planning (“ALIGN”) concept. AEP’s ALIGN concept is for PJM to consolidate planning so that committed load, generation resources, and transmission facilities would be planned and evaluated as a coordinated portfolio rather than through separate and sequential processes. Eligibility would be limited to projects supported by executed agreements, financial security, and other enforceable commitments, thereby helping distinguish executable projects from speculative queue activity. ALIGN would also augment PJM’s existing planning and interconnection processes, not replace them. By concentrating planning studies on committed demand, the framework is intended to improve queue integrity, increase planning certainty, and better align infrastructure investment with actual customer need.

AEP’s ALIGN proposal illustrates why governance reform matters: today’s stakeholder process could require the proposal to be fragmented across multiple committees and multiple filing authorities before its merits could even be evaluated. Despite working as an integrated framework, the proposal could be broken up among stakeholder groups focusing on generator interconnection, load interconnection, transmission planning, and others where aspects would be debated in isolation. Then, if the proposal advanced, because it would require both Tariff and Operating Agreement revisions, a two-sector Members Committee veto could block the whole concept. A well-formed stakeholder process must not stifle big, innovative ideas; it must facilitate their consideration on the merits.

PDF page 6

6
AEP’s ALIGN concept is not without precedent. Other RTOs have been able to
successfully incorporate and demonstrate the value of integrated planning processes that evaluate multiple infrastructure needs together rather than through disconnected stakeholder processes. SPP was able to incorporate its Integrated Transmission Planning process which evaluates reliability, economic, and public policy needs within a single coordinated planning framework. ALIGN applies that same planning philosophy to today’s emerging challenges and takes it one step further. Rather than evaluating committed load, generation, and transmission through separate interconnection queues, planning processes, and stakeholder committees, ALIGN would enable PJM to evaluate these interdependent facilities as a coordinated infrastructure portfolio. The lesson is not that PJM should replicate another RTO’s planning process. Rather, it is that governance must enable planners and stakeholders to evaluate comprehensive infrastructure solutions that reflect how the electric system actually functions. As load growth accelerates and infrastructure development becomes increasingly complex, PJM’s governance structure must evolve to support the innovation that will be required to meet the needs of today and the next century. The purpose of governance reform is to enable technically superior solutions by aligning responsibility, authority, and accountability.

III. PJM And Its Stakeholders: Reform Is Needed To Facilitate Action
PJM’s immediate market and planning issues must be addressed through the most effective near-term mechanisms available, but the underlying governance deficiencies also must be addressed to place PJM, its members, and its states on a more durable path. A stakeholder framework that clearly allocates responsibility, facilitates the Board’s work, and enables timely Commission review will better support the Board’s independence, responsiveness, and ability to act—producing better results for reliability, infrastructure development, and market reforms over the long term.

PDF page 7

7
Specifically, AEP recommends PJM create an advisory stakeholder structure aligning the advisory function with an appropriate process to enable stakeholders to provide better, actionable advice to the Board. This will restore balance to PJM’s governance structure and unlock the Board’s ability to make decisions and address the most important issues proactively, nimbly, and decisively.

While an advisory stakeholder process and an empowered board are ideas borrowed from some other RTOs’ approaches, PJM’s size, diversity of states, and range of regulatory paradigms distinguish it. The Commission’s mantra—that one-size-fits-all approaches do not work—rings true here. AEP’s goal is not for PJM to adopt any particular structure for its own sake, but to achieve a balance that is fair and sensible for all stakeholders, including by appropriately reflecting the interests of parties with responsibility for, and exposure to, reliability and cost impacts in the region. And critically, PJM needs a structure that enables the Board to make timely decisions in support of national security, reliability, affordability, and economic development.

IV. The Role of the States
States must have a voice in PJM’s stakeholder process and revised governance structure. As to the role of states in PJM processes, AEP is steadfastly supportive of proposals that result in a governance framework that is balanced and appropriately reflects the interests of parties with responsibility for—and exposure to—reliability and cost impacts in the region. The central objective of this and other governance reforms must be ensuring that PJM is able to achieve the core goals of regional coordination: transmission system reliability and “an abundant supply of electric energy … with the greatest possible economy.”2  AEP supports providing states with

2 16 U.S.C. § 824a(a); see Federal Power Act; Delegation of Authority to the Federal Energy Regulatory Commission, 63 Fed. Reg. 53889-01 (Oct. 7, 1998) (delegating Section 202(a) authority to FERC and noting that such authority “could aid in … addressing reliability-related issues, thereby increasing the reliability of the transmission system”).

PDF page 8

8
defined authority under Section 205 of the Federal Power Act to cause filings to be made before the Commission on matters within their collective jurisdiction, recognizing that states have a direct responsibility for protecting consumers and advancing resource adequacy, affordability, and public policy objectives.

Today, there is a mismatch between which entities have responsibility for reliability, resource adequacy, and cost impacts, and which are able to control or influence PJM decisions that directly affect those outcomes. Governance reform efforts—including rethinking the role of states in PJM—must seek to bridge this gap.

V. The Role of the Board
AEP recommends targeted modifications to PJM’s governance rules that would strengthen the PJM Board’s effectiveness while preserving its independence and responsiveness.

• PJM must adopt a preference for Board candidates who reside within the PJM footprint and have significant professional experience with the region’s electric system.

• PJM’s Operating Agreement must be revised to make the President and CEO a
voting member of the Board. Under current rules, PJM’s President and CEO sits on the Board ex officio, but does not have a vote.3

• PJM’s ex parte rules must be amended to eliminate or significantly reduce limits on communications between the Board and stakeholders. Reforming PJM’s ex

parte rules would improve governance by enabling Board members to receive
timely, balanced, and informed perspectives on complex national security,
reliability, market, and transmission planning issues.

3 PJM Operating Agreement § 7.1.

PDF page 9

9
VI. Conclusion
PJM stakeholders—from transmission owners and generators to states and consumer advocates—are committed to serving customers across the region reliably, at least cost. But too often, PJM’s governance structure has inhibited, rather than facilitated, this essential work. Action takes too long, even as problems proliferate, and the solutions adopted do not meet the moment. PJM’s structure handcuffs the Board from leading from the front and mires stakeholders with process over substance. “[T]he status quo,” as Chairman Swett has put it, “is unacceptable and has been for some time.”4  To secure the greatest benefits for the 67 million customers who rely on PJM, the Board must be able to act proactively, nimbly, and decisively with useful input from stakeholders to solve the region’s challenges.

PJM’s governance structure was developed for a different era—one characterized by slower load growth, excess generation, and incremental infrastructure needs. Today’s environment is fundamentally different. Meeting the nation’s growing demand for electricity will require an RTO capable of making timely, informed, and accountable decisions. Governance reform must not seek to diminish stakeholder participation, but rather ensure that stakeholder engagement produces actionable advice, that the Board possesses the authority necessary to fulfill its statutory responsibilities, and that states have a meaningful voice in the process. The next generation of grid challenges will not be solved by incremental procedural reforms. They will require governance capable of evaluating integrated technical solutions such as ALIGN, empowering the Board to act, incorporating meaningful stakeholder and state input, and aligning responsibility, authority and accountability.

4  FERC, Chairman Laura Swett’s Comments at PJM’s Annual Meeting in Baltimore, Md. (May 12, 2026), https://www.ferc.gov/news-events/news/chairman-laura-swetts-comments-pjms-annual-meeting-baltimore-md-0.

PDF page 10

10
In summary, PJM is broken and must be fixed one way or the other. Our national security and ability to satisfy customer requirements are at risk. The current precarious state of affairs must be addressed immediately.

Respectfully,

/s/ Stacey Burbure
Stacey Burbure
SVP, Transmission Regulatory Engagement and Compliance
American Electric Power
8500 Smith’s Mill Road
New Albany, OH 43054

PDF page 11

1

APPENDIX
PANEL 1 QUESTIONS
1. What is the PJM Board’s role in ensuring that PJM is sufficiently tackling the region’s operational and market challenges? How does the Board evaluate its effectiveness in that role? How often, and under what circumstances, does the Board act unilaterally, and should this change?

The resource adequacy challenges facing PJM are existential. Its fundamental charge is to serve customers reliably. Despite a half-decade of lead time, the issue is still not under control. This struggle has revealed that the Board lacks a consistent ability to take timely action to meet customer needs or address evolving national security matters, reliability, planning, and market challenges. The Board has been forced to be reactive and defensive rather than nimble and decisive, preventing timely action. AEP believes the cause is an imbalance among the core goals that RTOs under Order No. 2000 must pursue: independence, responsiveness, and action.

Independence. Independence is the “bedrock upon which [PJM] must be built,”5 requiring the RTO to maintain “a decision making process that is independent of control by any market participant or class of participants.” 6  PJM’s Board is structurally independent, but it lacks functional independence, impeding decision making.7  A well-functioning Board must have the expertise, confidence and backbone to make hard decisions that will have significant impacts and draw opposition. Those decisions, however, need not and must not be made in isolation; they must be made based on experience, a robust understanding of the substance, and full consideration of diverse stakeholders’ needs. This can only be achieved when Board members can engage on the

5 Reg’l Transmission Orgs., Order No. 2000, FERC Stats. & Regs. ¶ 31,089 at 31,046 (1999), order on reh’g, Order No. 2000-A, FERC Stats. & Regs. ¶ 31,092 (2000) (cleaned up).

6 Order No. 2000, FERC Stats. & Regs. ¶ 31,089 at 31,060.
7 See PJM Interconnection, L.L.C., 96 FERC ¶ 61,061 at 8 (2001).

PDF page 12

2

ground through committees where the work of the RTO is done, and through formal and informal discussions with stakeholders. PJM’s structure, however, limits these opportunities. Responsiveness. PJM must be “responsive[] to the needs of customers and other stakeholders,” providing “avenue[s] for customers and other stakeholders to present their views on RTO and ISO decision-making, and to have those views considered.” 8  Although PJM’s stakeholder process attempts to fulfill this requirement, 9  structural flaws in the Members Committee create gridlock and stalemate rather than useful input for the Board. As PJM’s most senior committee, the Members Committee reviews recommendations from all other committees and approves actions or recommendations with a two-thirds sector-weighted vote.10  The two- thirds requirement is not just limited to amending the Operating Agreement, over which the Members Committee maintains Section 205 filing rights, but extends to any recommendations to the Board. But because there are five sectors, any two sectors can combine to veto an action. As recent history has shown,11 the Members Committee’s advice to the Board is far too often no advice at all. Moreover, because the stakeholder process is split across numerous committees, subcommittees, task forces, and other groups, stakeholders struggle to bring broad proposals to address cross-cutting issues.

This leads to a situation where transmission owners and other entities which serve load are unable to be responsive to customer needs, such as by fostering processes that allow new load and generation to get connected in the time the customer needs, not an RTO-mandated timeline built

8 Wholesale Competition in Regions with Organized Elec. Mkts., Order No. 719, FERC Stats. & Regs. ¶ 31,281 at PP 502-03 (2008), order on reh’g, Order No. 719-A, FERC Stats. & Regs. ¶ 31,292 (2009). 9 PJM Interconnection, L.L.C., 133 FERC ¶ 61,071 at PP 1-2 (2010).

10 PJM Operating Agreement § 8.4.
11 See, e.g., PJM Interconnection, L.L.C., Docket No. ER24-98-000, Transmittal Letter. at 5, 63-64 (filed Oct. 13, 2023).

PDF page 13

3

for another era. A case in point is the process for interconnecting generation to serve new loads. It is slow and iterative with long study timelines and repeated restudies. While action is being taken to improve this issue, those measures are only now being studied and do not mean that PJM has fully addressed the core governance issues causing its lack of responsiveness overall.

Action. The Board’s “primary responsibility” under the Operating Agreement is to take
action to ensure PJM is run in a manner “consistent with . . . the safe and reliable operation of the [] Region” and with a “robust, competitive, and non-discriminatory electric power market . . . .”12 As the Commission has emphasized, RTO governance must facilitate effective action, so that the RTO can “ensure that [it] formulates policies, operates the system, and resolves disputes in a fair and non-discriminatory manner.” 13   And the Commission has stressed the need for RTO

governance to be “workable.”14  But when the stakeholder process becomes a bottleneck, and the Board lacks the necessary authority, it becomes difficult for the Board to take action when needed. Exacerbating the challenges, the Members Committee holds Section 205 filing rights under the Operating Agreement not just for corporate issues of the RTO, but core functions like energy markets and regional transmission planning. Thus in many cases, the Board lacks the power to act on holistic solutions to the most pressing challenges outside of filing a Section 206 complaint. When issues were slow-moving and the region had surplus capacity, these challenges may

have slipped under the radar—but this decade’s challenges have proved the status quo inadequate.

12 PJM Operating Agreement § 7.7(i). 13 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. & Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036 at 31,731 (1996), order on reh’g, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048, order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).
14 See, e.g., Order No. 719, FERC Stats. & Regs. ¶ 31,281 at P 546; Order No. 2000, FERC Stats. & Regs. ¶ 31,089 at 31,065, 31,069, 31,076.

PDF page 14

4

A well-functioning Board, that is independent, responsive, willing to take action, and focused on the core RTO mission of maintaining reliability, supporting affordability, and enabling economic growth, would be better equipped to swiftly consider innovative approaches like AEP’s ALIGN concept than the current fragmented governance structure where passage requires that integrated ideas are rung through a time consuming gauntlet of lower level stakeholder committees.

2. How should states, through the Organization of PJM States, Inc. (OPSI) or other structures, interface with the Board to enable the region to meet operational and market challenges while respecting PJM’s independence?

States must have an expanded and more formal role in PJM’s governance process—
whether through state representation on the Board, creation of a state committee, or another structure—that provides states a meaningful voice while preserving PJM’s independence and fairly balancing the interests of parties with responsibility for grid reliability and cost impacts.  In Order No. 2000, the Commission recognized that “states have important roles to play in RTO matters,” but concluded that imposing “specific requirements on the role of state agencies in RTOs … would be counterproductive in light of the variation in the legal responsibilities of state commissions and RTO design across regions.”15  States have a key interest in reliable and affordable electric service for their citizens. These issues have become critically important challenges within the PJM region and are directly impacted by PJM decisions and policies. Yet states do not have any formal role in PJM governance, either individually or via the Organization of PJM States, Inc. (“OPSI”). States should be able to act as a key voice in promoting innovative, integrated solutions that they see as valuable for addressing today’s issues. With a more direct role in the stakeholder process, states could provide needed clarity to drive solutions—like ALIGN and similar integrated solutions that

15 Order No. 2000, FERC Stats. & Regs. ¶ 31,089 at 31,212, 31,073.

PDF page 15

5

we have seen in other RTOs—that span multiple stakeholder groups in transmission planning, generation interconnection, load interconnection, and market design.

A variety of reform options could help right-size the role of states in PJM’s governance process. AEP offers two ideas. For example, the advisory stakeholder model discussed above would give states the opportunity to directly contribute to PJM policymaking processes. Indeed, one of the main benefits of the advisory process approach is that it would give a meaningful voice to states and other stakeholders who lack voting rights on the Members Committee. An expanded state role must be accompanied by stakeholder process reforms aimed at the core goals of enabling timely, technically sound decisions that drive dramatically improved national security, maintain reliability, support affordability, and enable economic growth. OPSI commissioners have acknowledged to FERC that the PJM states have diverse regulatory environments and policy interests.16 Without additional stakeholder reforms, an expanded state role could lead to further gridlock, indecision, and regulatory uncertainty.

3. What governance reforms would best improve accountability and responsiveness? An advisory stakeholder model would best improve accountability and responsiveness. A well-functioning and vibrant stakeholder process will support the Board in achieving the best outcomes. The stakeholder process, however, has become an end unto itself, becoming a forum for gridlock, not advice. AEP recommends that PJM employ an advisory model that provides stakeholders a meaningful opportunity to explore options, find consensus, and advise the Board without the risk of obstruction and stalemate.

16 Fed. & State Current Issues Collaborative, Docket No. AD24-7-000, Transcript of the 7/27/2025 Meeting on RTO Governance/Resource Adequacy (posted Aug. 25, 2025).

PDF page 16

6

A key flaw today is misalignment between stakeholders’ advisory role (on the one hand) and the process (on the other). Stakeholders wear many hats, from advising the Board to exercising Section 205 rights over the Operating Agreement. But the Members Committee has (with limited exceptions) a single process for approving matters: a two-thirds sector-weighted vote.17  Changing PJM’s decision-making rules, and recommending tweaks to the capacity market, are governed by the same rules. Moreover, because there are five sectors, it just takes two to band together to veto action. And with no de minimis threshold for participation, small groups can form minority coalitions to defeat proposals supported by majorities of the stakeholders with core interests in reliability and affordability. Moreover, the current sectors do not accurately reflect accountability. For example, PJM states have no formal role, yet they are accountable to their citizens, all of whom are electric customers reliant on the PJM grid. Further, AEP owns over 20% of the assets in PJM and controls less than 2% of the vote in the stakeholder process. Both of these examples show the disconnect that exists in the current system.

Meanwhile, because the Members Committee is responsible for deciding core corporate governance issues, it does not provide voting rights to some stakeholders with important voices, including states—even when the Members Committee is serving purely in an advisory function.18 States have important interests, but they lack full representation in the stakeholder process. As a result, States have resorted to extraordinary means to ensure their interests are heard.19 PJM must create an advisory stakeholder process aligning role and function. Such a process would provide stakeholders a robust and meaningful opportunity to review proposals, develop

17 PJM Operating Agreement ¶ 8.4.
18 See Memorandum of Understanding Between PJM Interconnection, L.L.C. and the Organization of PJM States, Inc. (June 8, 2005), https://www.pjm.com/-/media/DotCom/documents/agreements/opsi-pjm-memorandum.ashx.
19 See, e.g., Commonwealth of Penn. v. PJM Interconnection, L.L.C., 191 FERC ¶ 61,066 at PP 1-2 (2025) (describing the complaint filed against PJM by Pennsylvania Governor Josh Shapiro and subsequent settlement).

PDF page 17

7

alternatives, test ideas, and achieve consensus where it can be found. The structure would be flexible, ensuring matters can be carefully scrutinized by committees of stakeholders with particular interests or expertise, but enabling broader, integrated proposals to be reviewed as a whole. Stakeholder voting would not follow a formal voting procedure that controls outcomes. PJM management, instead, would develop proposals after stakeholder engagement, and the Board would determine whether to proceed, weighing stakeholder input and exercising accountability for the final decision. This approach would enhance stakeholder participation while enabling more timely decision-making and clearer accountability. Such a structure would also enable PJM to give a full voice to more stakeholders, including states, which have strong interests in PJM’s success but currently lack a voice on the Members Committee. It could also be flexible, enabling stakeholders to propose big ideas, such as AEP’s ALIGN concept, to address cross-cutting issues that today may be split up across numerous balkanized committees, subcommittees, task forces, and other groups.

4. How does the division of Federal Power Act section 20520 filing rights among PJM, Transmission Owners, and the Members Committee affect PJM’s ability to act

effectively and quickly, when warranted, to address operational and market needs?

PJM’s Board holds Section 205 filing rights over the majority of PJM’s operational functions, including those in the Tariff21 and Reliability Assurance Agreement.22 But the Members Committee retains Section 205 authority over some of these issues that are addressed in the Operating Agreement, including energy markets and the Regional Transmission Expansion Planning Protocol.23 Here, gridlock in the Members Committee is a binding constraint and limits

20 16 U.S.C. § 824d.
21 PJM Open Access Transmission Tariff § 9.2(a); PJM Interconnection, L.L.C., PJM Manual 34: PJM Stakeholder Process 19 (effective Sep. 25, 2025), https://www.pjm.com/-/media/DotCom/documents/manuals/m34.pdf.
22 See PJM Reliability Assurance Agreement § 16.4.
23 See PJM Operating Agreement Sched. 1 (Energy Markets) and Sched. 6 (RTEP).

PDF page 18

8

PJM from solving important problems. This is especially troubling for energy market provisions, which are included verbatim in both the Tariff and Operating Agreement, requiring alignment across the Board and Members Committee. 24  With respect to market design, AEP supports providing states with defined authority under Section 205 to cause filings to be made before the Commission on matters within their collective jurisdiction, recognizing that states have a direct responsibility for protecting consumers and advancing resource adequacy, affordability, and public policy objectives.

PJM’s current stakeholder sector composition no longer reflects the responsibilities of today’s electric system, as it assigns equal voting weight regardless of an entity’s accountability for reliability, investment obligations, or operational responsibility, resulting in governance outcomes that are disconnected from those most responsible for maintaining a reliable grid. Equal voting power, however, is not the same as balanced governance. Effective governance recognizes that parties bearing the greatest responsibility for maintaining reliable electric service should have a commensurate role in shaping the decisions for which they ultimately remain accountable. States are accountable to their citizens for affordability, reliability, economic development, and resource adequacy.  A governance structure that excludes them from meaningful participation ignores one of the principal governmental entities responsible for electric service.

It is time to reexamine whether it is appropriate for the Members Committee to retain Section 205 authority over core functional matters. The practical effect of the current system is that a single integrated solution, like AEP’s ALIGN concept, can require approvals under multiple governing documents with different filing priorities. Process therefore becomes a barrier to technical innovation.

24 Compare PJM Open Access Transmission Tariff Attach. K-Appendix with PJM Operating Agreement Sched. 1.

PDF page 19

9

5. To what extent do provisions in PJM’s Operating Agreement, Transmission Owner Agreement, Open Access Transmission Tariff, Reliability Assurance Agreement, or Manuals impede timely decision-making by PJM?

The stakeholder process, which is subject to deadlock and delay, is the core issue impeding timely decision-making by PJM. As noted above, the Members Committee must not retain Section 205 authority over core functional matters.

6. Recognizing regional differences, are there lessons from other regional transmission organization/independent system operator (RTO/ISO) governance structures that PJM could reasonably adopt to improve its responsiveness to the region’s operational and market challenges?

AEP recommends five targeted modifications to PJM’s governance rules that would strengthen the PJM Board’s effectiveness while preserving its independence and responsiveness. These recommendations—which draw on approaches adopted by other RTOs and ISOs to improve governance—are discussed in greater detail below. Collectively, these reforms would modernize PJM governance by strengthening the connection between Board oversight and operational execution, improving the Board’s understanding of the unique and varied conditions within the PJM region, expanding the pool of qualified Board candidates, protecting against entrenchment and status quo bias in the Board nomination process, and allowing the Board to engage productively with stakeholders to effectively guide PJM and confront the complex challenges facing the region’s electric industry today. The common lesson across other RTOs is not identical governance structures, but rather that governance must align responsibility, authority, and accountability while enabling innovation.

Voting rights for PJM’s President and CEO. PJM’s Operating Agreement must be revised to make the President and CEO a voting member of the Board. Under current rules, PJM’s

PDF page 20

10

President and CEO sits on the Board ex officio, but does not have a vote.25  As the executive responsible for implementing Board decisions and managing the nation’s largest wholesale electricity market, PJM’s President and CEO offers unique operational expertise and accountability—and must be fully involved in Board decision-making.

Indeed, the CEOs of MISO, SPP, and NYISO are voting members of their respective RTO/ISOs’ boards (subject to certain recusal limits).26 Giving PJM’s President and CEO a vote on the Board would make PJM more dynamic by improving information flow, enhancing Board debate, and making the President/CEO a decision-making partner.

In-region preference for Board candidates. PJM must adopt a preference for Board candidates who reside within the PJM footprint or have significant professional experience with the region’s electric system. Although PJM’s Operating Agreement imposes certain minimum expertise requirements that the Board collectively must meet, it does not require or prioritize familiarity with the PJM region.27 Accordingly, few current Board members had ties to the PJM region before joining the Board. Because Board decisions directly affect national security, electric reliability, affordability, and economic development across the PJM footprint, regional knowledge must be recognized as an important qualification for Board members. Notably, both ISO-NE and NYISO currently have preferences for in-region directors.28 Regional knowledge is particularly important in PJM, which has a uniquely large and diverse footprint that includes both vertically integrated and restructured states with significant variation in local supply and demand dynamics. As PJM itself recognized in a 2011 filing, adding Board members “from the PJM region who are

25 PJM Operating Agreement § 7.1.
26 See MISO Transmission Owner Agreement, App’x F (“MISO Bylaws”), Art. IV § 4.1; MISO Bylaws Art. V § 5.4; SPP Bylaws § 4.2.1; NYISO Bylaws, Art. III § 3(a).
27 PJM Operating Agreement § 7.2.
28 See ISO-NE Participants Agreement § 9.2.2; NYISO Bylaws, Art. III § 2.

PDF page 21

11

familiar with the current practices and operations of PJM” “is beneficial and crucial to PJM’s continued success.”29

Shorter cooling-off period for prospective Board members. Limiting PJM’s “cooling-off”
period for prospective Board members to one year also would improve PJM’s ability to attract qualified Board candidates with relevant experience and local knowledge. PJM’s rules require at least a two-year gap between service as a director, officer, or employee of a PJM member (or an affiliate or related party) and election to the PJM Board.30  This restriction unnecessarily limits the pool of qualified candidates with recent industry experience. A one-year period would maintain Board independence31 while improving PJM’s ability to recruit members with current expertise. This adjustment would more closely align PJM’s governance rules with those of other RTOs. MISO in 2017 reduced its cooling-off period from two years to one, explaining that the longer restriction had “affected MISO’s ability to recruit Board candidates” as it could “often times create conflicts that … disqualify an individual from consideration.”32 ISO-NE and SPP have no cooling- off periods for board members.33

29 PJM Interconnection, L.L.C., Docket No. ER11-630-000, Transmittal Letter at 2 (filed Sep. 23, 2011) (explaining that “electing members to the Board from the PJM footprint” will allow PJM to “maximize local input” and avoid “expend[ing] time and resources seeking and training candidates who lack the PJM-specific expertise that adds significant value to the PJM Board”).
30 PJM Operating Agreement § 7.2.
31 See Order No. 2000, FERC Stats. & Regs. ¶ 31,089 at 31,062 (explaining that FERC’s “focus” in evaluating financial independence “will be on current financial interests” (emphasis added)).
32 Midcontinent Indep. Sys. Operator, Inc., Docket No. ER17-686-000, Transmittal Letter at 8-9 (filed Dec. 28, 2016); see Midcontinent Indep. Sys. Operator, Inc., Docket No. ER17-686-000, Letter Order (issued Feb. 23, 2017). PJM reduced its cooling-off period from five years to two years in 2011, due to the challenges the protracted cooling-off period created in finding qualified Board candidates from the PJM region. PJM Interconnection, L.L.C., Docket No. ER11-630-000, Transmittal Letter at 2 (filed Sep. 23, 2011); PJM Interconnection, L.L.C., Docket No. ER11-630-000, Letter Order (Nov. 1, 2011).
33 Instead, both ISO-NE and SPP impose restrictions on board members’ current relationships with and financial interest in market participants. See ISO-NE Participants Agreement § 9.3.1; ISO-NE Code of Conduct § 2.2; SPP Bylaws § 4.2.3.

PDF page 22

12

Reduce Board control over nomination process. PJM must limit the role incumbent Board
members play in the Board nomination process. Under current rules, PJM’s Nominating
Committee—which nominates Board candidates to be elected by the Members Committee—
includes three incumbent Board members (one of whom must not vote on the Nominating
Committee) and five sectoral representatives. 34  This structure gives substantial influence to incumbent Board members and creates—even if unintentionally—a thumb on the scale favoring

the status quo. Corporate governance scholars have long recognized that self-perpetuating board nomination processes can lead to detrimental entrenchment and insulation.35 Allowing only one incumbent Board member to serve on the Nominating Committee in a non-voting role would

preserve information flows and representation of the current Board’s perspective in the nomination process while promoting true independence, responsiveness to PJM members, and bolder, more

effective leadership. Notably, two ISOs—CAISO and ERCOT—have board nomination processes
that provide no formal role for incumbent directors.36
Ease restrictions on ex parte communications. Today, PJM’s Code of Conduct for its
Board includes restrictive ex parte rules that limit the Board’s ability to communicate on important issues.37  These restrictions prevent the Board from effectively engaging with members and other

34 PJM Operating Agreement § 7.1.
35 See, e.g., Adolf A. Berle & Gardiner C. Means, The Modern Corporation and Private Property 88 (1932) (“[C]ontrol will tend to be in the hands of those who select the [nominating] committee by whom, in turn, the election of directors for the ensuing period may be made. Since the [nominating] committee is appointed by existing management, the latter can virtually dictate their own successors. Where ownership is sufficiently sub-divided, the management can thus become a self-perpetuating body even though its share in the ownership is negligible.”); Lucian A. Bebchuk, The Myth that Insulating Boards Serves Long-Term Value, 113 Colum. L. Rev. 1637, 1644 (2013) (“[A]rrangements that insulate boards from shareholders and shareholder pressure have been consistently associated with lower firm value and worse operating performance.”); Bo Becker & Guhan Subramanian, Improving Director Elections, 3 Harv. Bus. L. Rev. 1, 1 (2013) (“It is well known that U.S. director elections are largely a formality: incumbents typically nominate themselves, for elections that are almost always uncontested, and are re-elected with virtual certainty. The result … is what one might expect: directors who are elected not for their qualifications but rather because shareholders simply have no other choice.”).
36 See CAISO Board Selection Policy § 4.2; Tex. Utils. Code § 39.1513(a), (d).
37 PJM Board of Managers Code of Conduct at 3 (updated Nov. 2025).

PDF page 23

13

stakeholders on important issues. Nor are these counterproductive restrictions needed to protect the Board’s independence: No other RTO or ISO imposes such severe restrictions,38 and they do not fit the Board’s role: PJM under the Federal Power Act is a public utility, not a regulator, and we must not foster the misimpression that the Board is akin to another layer of regulation. PJM’s ex parte rules thus must be amended to eliminate or significantly reduce limits on communications between the Board and stakeholders. Reforming PJM’s ex parte rules would improve governance by enabling Board members to receive timely, balanced, and informed perspectives on complex reliability, market, and transmission planning issues. This reform, in particular, would assist the Board in considering innovative reforms necessary to move the grid forward. It will allow a freer exchange of new, innovative ideas from stakeholders—like AEP’s ALIGN concept—and from

other RTOs who are also using integrated system planning and other techniques to cut through today’s load, transmission planning, and generator interconnection issues to provide solutions that more nimbly meet the needs of todays’ grid.

38 See generally Christopher A. Parent et al., Exeter Assocs., Inc. Governance Structure and Practices in the FERC- Jurisdictional ISOs/RTOs, Exeter Assocs., Inc. (Feb. 2021) (discussing PJM’s ex parte restrictions and not identifying any ex parte restrictions for other RTOs or ISOs), https://nescoe.com/wp-content/uploads/2021/02/ISO- RTOGovernanceStructureandPractices_19Feb2021.pdf; see also MISO, Principles of Corporate Governance § V.E (Dec. 7, 2023) (providing that if “a third party [initiates] a communication directly with a Director on Board or Company business without notice to the other Directors,” the Director involved in the communication “shall promptly report the substance of the discussion to the CEO and to the full Board no later than its next regularly scheduled meeting.”).