Pre-filed Statement of Stacey Burbure, Senior Vice President of Transmission Regulatory Engagement & Compliance for American Electric Power Company, Inc.…
Text extracted from the eLibrary original (SHA-256 51a8beb7a1c0ba13…). Download the original from the official source.
Contents · 6 sections
Read topic-matched comments in AD26-7
Topics in the text: Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Governance and Stakeholder Reforms Docket No.Read this passage
I. Introduction and Summary
printed heading · Topic match: Reliability and curtailment
Second, PJM’s approach to ensuring resource adequacy in the region must be updated.Read this passage Filed comments: Reliability and curtailment
II. How Process Thwarts Substance in PJM—An Illustration
printed heading · Topic match: Reliability and curtailment
A reformed process must enable stakeholders to bring creative proposals designed to solve PJM’s biggest problems to the table for serious review by other stakeholders, PJM management, and the Board.Read this passage Filed comments: Reliability and curtailment
III. PJM And Its Stakeholders: Reform Is Needed To Facilitate Action
printed heading
PJM And Its Stakeholders: Reform Is Needed To Facilitate Action PJM’s immediate market and planning issues must be addressed through the most effective near-term mechanisms available, but the underlying governance deficiencies also must be addressed to place PJM, its members, and its states on a…Read this passage
IV. The Role of the States
printed heading · Topic match: Reliability and curtailment
The Role of the States States must have a voice in PJM’s stakeholder process and revised governance structure.Read this passage Filed comments: Reliability and curtailment
V. The Role of the Board
printed heading
The Role of the Board AEP recommends targeted modifications to PJM’s governance rules that would strengthen the PJM Board’s effectiveness while preserving its independence and responsiveness. • PJM must adopt a preference for Board candidates who reside within the PJM footprint and have significant…Read this passage
VI. Conclusion
printed heading · Topic match: Reliability and curtailment
“[T]he status quo,” as Chairman Swett has put it, “is unacceptable and has been for some time.”4 To secure the greatest benefits for the 67 million customers who rely on PJM, the Board must be able to act proactively, nimbly, and decisively with useful input from stakeholders to solve the region’s…Read this passage Filed comments: Reliability and curtailment