AD26-7-000 · 2026-07-15 · American Municipal Power Inc

Pre-filed Statement of Steven Lieberman, Vice President of Transmission & Regulatory Affairs for American Municipal Power, Inc., for Panel 2 for the PJM…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Governance and Stakeholder Reforms
)
Docket No. AD26-7-000

PRE-TECHNICAL CONFERENCE STATEMENT OF
STEVEN LIEBERMAN ON BEHALF OF
AMERICAN MUNICIPAL POWER, INC.

I appreciate the opportunity to participate in the upcoming Federal Energy Regulatory Commission (“Commission” or “FERC”) technical conference scheduled for July 23, 2026, as a panelist on Panel 2, titled “PJM Stakeholder Process – Design, Transparency, and Decision-Making.” This pre-technical conference statement, presented on behalf of American Municipal Power, Inc. (“AMP”), focuses on the subject matter of that panel discussion, as described in the Commission’s notice.1 As Vice President of Transmission & Regulatory Affairs, I provide oversight and take responsibility for AMP’s advocacy in the Midcontinent Independent System Operator, Inc. (“MISO”) and PJM Interconnection, L.L.C. (“PJM”) RTO stakeholder processes, along with AMP’s participation in the North American Electric Reliability Corporation (“NERC”) standards development process. I hold a Bachelor of Arts degree in Environmental Science from Boston University.

I. INTRODUCTION
These comments share the perspective of AMP as a non-profit public power wholesale supplier of electricity for 135 public power communities located across nine states, including seven PJM states. AMP’s member systems serve approximately

1  See Second Supplemental Notice of Commission-Led Technical Conference, Docket No. AD26-7-000, at 4-6 (July 2, 2026).

PDF page 2

2
650,000 meters, and while AMP represents many of the larger public power systems in PJM, the average AMP member community is less than 5,000 meters and rural. Our member officials are keenly aware of the impact of PJM policies and governance on their local operations and costs for their customers. But AMP’s advocacy is not biased towards pricing outcomes. Said differently, AMP does not advocate for rules that are motivated to intentionally raise prices or lower prices. Instead, AMP advocates for sustainable, commonsense rules that will protect end-use customers from degraded reliability, while ensuring affordability.

PJM’s existing governance framework generally works well and does not require major structural reform. The current sector-weighted voting process appropriately balances consensus-building with timely decision-making and ensures that significant proposals receive broad stakeholder support before advancing.

AMP’s primary recommendation is to improve coordination and consistency between voting at senior committees and voting at lower-level committees, where voting results often determine which proposals move forward. AMP believes coordination between voting results at lower-level committees and votes taken by senior committees would strengthen stakeholder confidence, improve consensus-building, and make decision-making more efficient.

Stakeholder representation and committee structure are not the source of delays. States and other interested parties appropriately have multiple opportunities to participate in PJM processes, and the speed of decision-making is largely determined by PJM’s prioritization of issues and meeting schedules. Accordingly, better issue prioritization is needed, rather than changes to stakeholder representation or governance.

PDF page 3

3
PJM’s most significant challenge remains resource adequacy and reliability, but the existing governance framework, with the adjustments proposed below, is sufficient to address those concerns and there is no basis for weakening stakeholder processes or reducing stakeholder input. Expanded use of expedited stakeholder procedures may result in compressed timelines that hinder stakeholder collaboration, reduce opportunities to build consensus, and create greater regulatory uncertainty. Better outcomes result when stakeholders have adequate time to develop and refine proposals. Finally, PJM should enhance transparency at the Board level. Adopting practices similar to those used by other regional transmission organizations, such as providing greater public access to Board meetings, agendas, and materials, would improve accountability and stakeholder confidence. Overall, AMP supports targeted transparency improvements while preserving the consensus-based processes that have historically promoted reliable and affordable electric service.

II. COMMENTS
Question 1: Sector-weighted Voting

Do sector-weighted voting and existing voting thresholds strike the right balance between achieving consensus and taking timely action?

Sector weighted voting (SWV) is used for votes of the Members Committee (MC) and the Markets and Reliability Committee (MRC) (i.e., the Senior Standing Committees). SWV and the related voting thresholds for issues to be deemed approved (or endorsed) achieves a reasonable balance between developing consensus and timely action. The threshold is two-thirds support from the five sectors, in which each sector provides 1.000 votes towards the total. Thus the threshold for an issue to be deemed approved or passed via SWV is 3.334 (rounding up).

PDF page 4

4
PJM facilitates nearly all stakeholder meetings except for the MC and the Liaison Committee (LC). There is no voting at the LC, thus there is only one instance in which a PJM Member facilitates a committee in which voting occurs (the MC). In terms of timely action, the committee or task force facilitator or a stakeholder can “call the question” on an agenda item to ensure timely action.

Achieving consensus does not mean unanimous support. In some instances,
consensus is a simple majority threshold and in others it is a super-majority. While it may seem difficult to achieve a super-majority threshold, particularly on contentious issues, when it is attained, it signals to FERC that the proposal before it is supported by a broad range of PJM Members.

Question 2. Transparency Reforms

What transparency reforms would improve the quality of PJM’s stakeholder
process and increase stakeholder confidence in its decision-making?

Transparency reforms are desperately needed, particularly for matters of
significance that come before the PJM Board following stakeholder consideration and that result in FERC filings. There is substantial opaqueness in the PJM Board’s deliberations on such matters. One aspect that PJM should consider adopting from SPP is that “[a]ll SPP Board meetings that are not in executive session are open to the public. All meeting materials, agendas, and minutes are publicly posted on the SPP website.”2 Transparency is key, recognizing that certain issues necessarily lend themselves to being discussed in executive session.

2  See FERC, An Introductory Guide for Participation in Southwest Power Pool Processes (“Q. How is SPP Governed?”), https://www.ferc.gov/introductory-guide-participation-southwest-power-pool- processes.

PDF page 5

5
MISO’s similarly open approach is also instructive. The MISO Board holds an open meeting each quarter. The committees of the Board hold open meetings at least each quarter. Stakeholders and the public are allowed to listen to these meetings. The Board and its committees cover general materials in open session, but do have executive sessions for material related to confidential business (personnel matters, legal matters, contract issues, etc.).  The committees publish and review a work plan for the year showing when they have open meetings and executive sessions with a general overview of the topics to be covered in the meetings.

At the end of their meetings the MISO Board and its committees allow an opportunity for public comment. During MISO’s Board week, when the Board holds an open meeting, the Board joins the MISO Advisory Committee (AC)—the stakeholder committee with representatives from all of the stakeholder sectors—to hold a discussion on a topic decided prior to the meeting. The discussion for June 2026 was “Maintaining Resource Adequacy in a Time of Transition.” The MISO Board and the AC receive reports from the chairs of various MISO stakeholder groups.  After each report on the topics of interest being discussed at the stakeholder committees, the MISO Board and the AC have an opportunity to ask the chair of each group questions about the work of the committee. Additional opportunities for the PJM Board to interact with stakeholders and for stakeholders to hear PJM Board deliberations and understand the basis for decision- making, more like other RTOs, could increase stakeholder confidence in, or at least understanding of, PJM Board decisions.

PDF page 6

6
Question 3. State Participation

Are there structured opportunities in the stakeholder process for state participation (e.g., defined consultation windows, joint technical sessions) to provide input on topics that are of interest to the states?

Yes, state participation is possible, and states (some perhaps more than others) do participate in stakeholder meetings, including by presenting proposals for consideration. Per Manual 34, Section 4: Roles and Responsibilities, “[t]here are several types of participants in the PJM stakeholder process, including the Members, PJM (the Office of the Interconnection, or Staff), the Independent Market Monitor (IMM) and the Organization of PJM States, Inc. and its member regulatory agencies. Additionally from time to time other parties may participate in the PJM stakeholder process.”3 Section 4.1 Members and Other Participants, explains that “[i]t is the responsibility of each participant in the PJM stakeholder process to represent its interests in cooperation with all other stakeholders to ensure the reliability of the PJM system and implementation of efficient, fair and transparent markets.” Specifically, participant responsibility includes five stated items:

•
Articulating their interests, concerns, ideas and their basis of support for a particular approach or proposal;

•
Raising objections and concerns, and the responsibility to provide an alternative if they are not able to agree with a proposal or option;

•
Alerting the stakeholder meeting facilitator to specific sensitive concerns related to the process or subject matter;

•
Providing all materials in a timely manner for website posting and notification; and

3  Additional information about the roles and responsibilities of the Organization of PJM States, Inc. (OPSI) and State Regulators is provided in PJM, Manual 34, Section 4.4, at 23, https://www.pjm.com/- /media/DotCom/documents/manuals/m34.pdf.

PDF page 7

7
•
Adhering to the Stakeholder Group’s Charter and work plan, and seeking to complete it in a timely and efficient manner that meets any regulatory or other deadlines.

Moreover, PJM’s stakeholder process allows for the formation of a “user group.” Recently, the consumer advocates created a user group, the Affordability and Reliability for Residential Consumers User Group. The consumer advocates also joined with environmental interests to form the Public Interest & Environmental Organizations User Group. There is also the Independent State Agencies Committee (ISAC), which is a voluntary, stand-alone committee that consists of members from regulatory and other state agencies representing all of the states within the service territory of PJM and the District of Columbia. “The ISAC is an independent committee that shall not be controlled or directed by PJM or the PJM Board of Managers.”4 The ISAC provides “PJM with input to inform the assumptions, scenarios, and studies developed as part of PJM’s Regional Transmission Expansion Planning Protocol as well as to discuss alternative sensitivity studies, modeling assumptions, and scenario analyses.”5 The ISAC may also address “items described in section 1.5 of Schedule 6 of the PJM Operating Agreement,”6 i.e., the procedures for developing the PJM Regional Transmission Expansion Plan. Finally, one of the most direct ways any stakeholder may communicate its position is to send a letter to PJM’s President and CEO, and to PJM’s Board of Managers. States, public utility commissions, concerned citizens, and Members from every sector all avail themselves of this opportunity, which typically results in a timely response from the Board

4  OPSI, ISAC Charter at 1, https://opsi.us/wp-content/uploads/2023/05/ISAC-Charter.pdf.
5  Id. 6  Id.

PDF page 8

8
Chair. A list of communications submitted to PJM and the responses from PJM are publicly posted on PJM.com here.

Question 4. Governing Documents

Do existing governing document provisions (e.g., Operating Agreement, Manuals) impede stakeholder decision-making and what changes could be made to

address them?

Although the current PJM governance framework remains generally sound, there are targeted reforms that could be made to improve the efficiency of the stakeholder process. Existing provisions of Manual 34 (PJM Stakeholder Process) impede stakeholder decision-making and a key example is the impact of voting that occurs at the “lower level” committees in determining which proposals may be voted on in the senior committees. The lower-level committees should play a critical role in screening and developing the proposals that are ultimately considered by the senior committees. For proposals to be viable, their ultimate approval at the Members Committee should be reasonably foreseeable by the lower-level committees. In order to efficiently build proposals that may achieve consensus at the critical Members Committee, it is imperative to ensure that the voting structure at the lower level Standing Committees adequately captures the views of stakeholders represented in MC voting. Under the existing rules, it does not.

The current process impedes stakeholder decision-making because at the lower- level committees, all PJM Members receive one vote, including Affiliates, but at the senior committees, each corporate family receives only one vote.  As a result, Members with more Affiliates control the flow of proposals from the lower-level committees to the senior committees, meaning that proposals that are not viable at the senior-level committees

PDF page 9

9
because there was not buy-in across the stakeholder sectors in the lower-level committees are sometimes moved forward, and potentially viable proposals are left behind.

In this regard, the code of conduct included in Manual 34 explains that: the stakeholder process has been designed intentionally so

that the decision-making authority is exclusively vested with
the Senior Standing Committees consistent with Operating
Agreement, section 8.4. Votes at the "lower" Standing
Committees (e.g. the Operating Committee, Planning
Committee, Market Implementation Committee, and Risk
Management
Committee)
and
their
subordinate
subcommittees and task forces have no such weight or finality
in their votes. Votes at the lower level Standing Committees
merely set the order of voting on various proposals that were
considered in the lower Committee for consideration at the
Senior Standing Committees and afford Members an
opportunity to understand general stakeholder sentiment
helpful in fostering further consensus building activities. See generally, Section 3: Purpose of the Stakeholder Process as

well as Section 8: Consensus Based Issue Resolution at the
Standing Committee Level. A PJM Members Committee vote
is singularly the vote that fulfills their Operating Agreement
responsibilities. All other Member votes and stakeholder polls
are only indicative of a Members' preference or interest as
solutions are explored.7
At the two senior committees, the MRC and the MC, only Members are able to vote (i.e., no Affiliates and no non-Members). For all other committees and senior task forces, each Member gets one vote. The standard process for a Member seeking action on an item by the MRC and MC requires that the proposal first receive simple majority support at the subordinate, lower level committees and task forces. If multiple proposals achieve simple majority support, the proposal with the greatest level of support is deemed

7  PJM, Manual 34, Section 4.5, at 23.

PDF page 10

10
the “main motion” and the others are “alternates.” If the main motion passes at the MRC and MC, there is no vote on the alternates.

Thus the disparity in voting participants at the lower level compared to the senior level committees may and often does greatly impact the voting outcome at the MRC and MC. This is because a Member with multiple Affiliates has an outsized opportunity to influence the order of voting, and therefore the proposals that are voted on, at the senior level. The largest numbers of Affiliates belong to Members in the Generation Owner (260), Other Supplier (228), and Transmission Owner (39) sectors.8 Members in sectors typically viewed as aligned with consumer interests have few, if any, Affiliates; sector totals are: Electric Distributors (9); End Use Customers (4).

Manual 34 explains that voting at the Standing Committees includes both Members and Affiliates, and that if a simple majority prefers a proposal over the status quo the proposal with the greatest level of support will become the Main Motion for consideration at the MRC, while other proposals will be Alternate Motions. If the Main Motion passes, no vote is taken on Alternate Motions.

The status quo voting paradigm that allows Affiliates to vote at Standing Committees favors Members with registered Affiliates. The more Affiliates a Member has, and the more Affiliates a sector has, the greater the influence that Member and that sector have on Senior Standing Committees such as the MRC and MC, where voting is Members-only. Members who have substantial numbers of Affiliates are positioned to act as a veto on proposals that would otherwise be brought to the MRC for a vote by only Members (i.e., no Affiliates) since there are more Affiliate members in PJM (540) than

8  PJM, Member List (July 10, 2026), https://www.pjm.com/about-pjm/member-services/member-list.

PDF page 11

11
voting Members (517).9 Due to their combined size, Members with their Affiliates may have a voting block with substantial sway over the voting results at the lower committees and, by implication, at the Senior Standing Committee level. As noted above, there are three sectors that have the overwhelming majority of total Affiliates in PJM and these three sectors, or a combination of any two of the three sectors, are able to determine which, if any, proposals may be voted on at the MRC by all five sectors. One simple way to fix this would be to modify the lower-level committee voting structure to match the senior committees. This would allow voting Members to better understand whether a proposal that is supported at a lower-level committee has sufficient sector weighted support to potentially pass an MC vote, and if not, to identify the sticking points so they can be addressed.

Alternatively, in order to ensure that all Members of the MRC have the ability to act on any proposal voted on at the Standing Committee in an equal manner to the Main Motion, not just those preferred by two or three sectors with the vast majority of Affiliates, PJM should analyze the voting results of the Standing Committee. If a proposal has received support from at least one voting Member from four of the five sectors it should be viewed as a potentially viable proposal for consideration by the MRC. Voting on this additional proposal along with the proposal that received the greatest level of support above the simple-majority threshold would occur in a non-truncated manner, allowing both proposals to be voted on at the MRC simultaneously. If multiple proposals receive support from at least four of the five sectors, the proposal with the greatest number of

9  Id.

PDF page 12

12
combined votes would be moved for consideration to the MRC along with the status quo “Main Motion” proposal.

A proposal that receives support from at least one Member in four sectors would be deemed a viable proposal for the MRC to consider as it could pass the MRC even if one entire sector opposes it. This sensible change to the voting methodology for proposals considered by the MRC would mitigate any perceived veto power at either the Standing Committee level or the Senior Standing Committee level.

Question 5. Stakeholder Process Reforms

What reforms to the stakeholder process could ensure PJM can meet the region’s challenges?

The single biggest challenge PJM continually faces is how to conduct a capacity auction to ensure sufficient quantities of capacity are available to meet anticipated demand plus adequate reserves to maintain a 1-in-10 level of reliability, consistent with the FERC-approved Reliability Pricing Model (RPM) capacity construct rules. RPM’s structure is contained within PJM’s Open Access Transmission Tariff (OATT or Tariff). PJM has Federal Power Act section 205 filing rights over the OATT.10 No changes are needed to the stakeholder process to ensure PJM can meet the region’s resource adequacy challenges, given the section 205 filing rights that PJM currently enjoys over the terms and conditions of RPM. Rather than reforming the stakeholder process, significant reforms to how PJM prioritizes and schedules meetings to address the challenges should be made.  PJM already has the ability to do so but has not.

10  With the exception of certain rights reserved by the Transmission Owners.

PDF page 13

13
PJM’s Manual 34 offers a useful high-level description of the interplay between the PJM stakeholder process and filing rights under Federal Power Act sections 205 and 206, as follows:

Sections 205 and 206 of the Federal Power Act set forth the requirements that must be met to obtain FERC approval of a proposed revision to a governing document and are germane to the governing documents of PJM (the Operating Agreement, the Open Access Transmission Tariff (Tariff) and the Reliability Assurance Agreements (RAA)), and to the operation of the PJM stakeholder process. Sections 205 and 206 establish the standards for demonstrating why a proposed revision to a governing document should be approved by the FERC. Section 205 requires that the proposer of a revision demonstrate the proposed revision is “just and reasonable.” Section 206 requires a potentially higher hurdle in that the proposer of a revision to the governing documents must demonstrate that the then current provisions are “unjust and unreasonable,” and that the proposed revisions are “just and reasonable.” Within the PJM stakeholder process it is recognized that the Members Committee maintains Section 205 authority over the Operating Agreement, and that the Board of Managers maintains Section 205 authority over the Open Access Transmission Tariff (Tariff) (with the exception of certain Tariff provisions that are under the exclusive control of the Transmission Owners) and the Reliability Assurance Agreements. Any party not possessing 205 authority over one of the governing documents may propose a revision to the document to the FERC under Section 206. It is also recognized that the Members provide input into the Regional Transmission Expansion Plan (“Plan”), and that the Plan is approved by the Board.11

Manual 34 also describes the consultation process that PJM uses when making FPA section 205 filings. PJM is required under the Tariff to consult with the Transmission Owners and the MC at least seven days prior to filing. However, “neither the Transmission Owners, except as provided for in [Tariff] section 9.3, nor the PJM Members Committee

11  PJM, Manual 34, Section 3, at 18.

PDF page 14

14
shall have any right to veto or delay any such Section 205 filing.”12 Further, “PJM may file with less than a full 7 day advance consultation in circumstances where imminent harm to system reliability or imminent severe economic harm to electric consumers requires a prompt Section 205 filing . . . .”13

Question 6. Near-term Reforms

What near-term reforms to stakeholder representation could PJM and its Members take to improve speed in decision-making while preserving stakeholder input?

PJM needs to focus on issues related to reliability and resource adequacy above other issues. Stakeholders work on issues that require rapid development based on PJM’s meeting schedules. PJM sets the cadence for the stakeholder process through the calendar. PJM sets the priority of issues when it develops the calendar. If there is a concern about the speed of decision-making, that is not cause for reforming stakeholder representation. Instead, it only requires PJM to prioritize and schedule stakeholder meetings so key discussions can occur more quickly.

Question 7. Committee Structure

Are there elements of PJM’s committee structure that routinely contribute to delays?  Are there stakeholder processes or issues that could be expedited or changed to provide greater focus on key issues and allow faster or more unilateral action on others?

As noted above, PJM controls the calendar, which sets the pace and prioritizes the issues; the committee structure is not the concern. Significantly, per Manual 34, “[t]he Secretary of the Members Committee has ultimate meeting prioritization decision.”14

12  Id., Section 11.14, at 87.
13  Id.
14  Id., Section 11.4, at 80.

PDF page 15

15
Moreover, while the MC chair and vice chair are representatives of Members, the MC Secretary is a PJM staff member15 “appointed by the President of PJM,” who administers the stakeholder process procedures.16 The current MC Secretary is PJM’s Senior Director of Stakeholder Affairs.17

Question 8. Expedited Action

Should PJM increase the use of fast-path or time-bound review procedures to expedite committee action on high-importance topics?

Simply scheduling additional meetings closer together to address mission-critical topics may be more effective than invoking truncated procedures. As we saw in the just completed CIFP-RBP/Connect & Manage process, when PJM attempts to use fast-path or time-bound review procedures to expedite action, PJM may trip itself up, resulting in wholesale changes to its own proposal. Similarly, stakeholders do not have sufficient time to work amongst themselves to consolidate their approaches, resulting in an unwieldy number of alternative proposals that often fail to consolidate into a clear consensus position. Further, expediting discussions in Valley Forge at the expense of consensus in the stakeholder process only serves to increase regulatory uncertainty. Question 9. Regional Differences

Recognizing regional differences, are there lessons from other RTO/ISO
stakeholder processes that PJM could reasonably adopt to improve speed in voting processes and stakeholder representation?

When PJM’s stakeholders have time to thoroughly discuss an issue, understand one another’s opinions, and develop proposals that align with the theory of mutual gains

15  See PJM, Members Committee, https://www.pjm.com/committees-and-groups/committees/mc.
16  PJM, Manual 34, Definitions (Secretary), at 16.
17  See PJM, Members Committee, https://www.pjm.com/committees-and-groups/committees/mc.

PDF page 16

16
(the backbone of PJM’s Consensus Based Issues Resolution structure), the volume of proposals presented to the Members Committee is often greatly reduced, which in turn improves the speed at which the stakeholder process proceeds to a vote. While PJM’s stakeholder process is open to all interested parties, PJM’s stakeholders, including its Members, have very limited access to the PJM Board and essentially no insight into Board decisions on matters passed on by the Board that lead to a FERC filing (FPA sections 205 or 206) until that decision is finalized, filed, and communicated via email to the stakeholders. The transparency improvements discussed supra in response to Question 2 draw on MISO and SPP governance examples that suggest the PJM Board should provide more transparency regarding these matters.

Dated: July 14, 2026