AD26-7-000 · 2026-07-15 · Public Service Enterprise Group Incorporated

Pre-filed Statement of Jodi L. Moskowitz, Vice President Regulatory – Law, Deputy General Counsel and RTO Strategy Officer for Public Service Enterprise…

PDF page 1

1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Governance and Stakeholder Reforms

Docket No. AD26-7-000

PRE-TECHNICAL CONFERENCE COMMENTS OF
THE PSEG COMPANIES

The PSEG Companies1 appreciate the opportunity to submit these comments in advance of the Federal Energy Regulatory Commission’s (“Commission”) 2026 Technical Conference on PJM Governance and Stakeholder Reforms (“Technical Conference”) to be held on July 23, 2026.  These comments address the issues to be discussed during Panel 2: “PJM Stakeholder Process–Design, Transparency, and Decision-Making.” This panel will examine the PJM

stakeholder process, the flaws inherent in this process and ways to fix, or at least mitigate, these challenges. PSEG recognizes the Commission’s leadership in convening this technical

conference.  This timely and needed initiative comes when PJM is at an inflection point in its history, grappling with how to address the region’s profound resource adequacy challenge before it becomes a major reliability crisis for customers across the region. As both a founding member and significant Transmission Owner (“TO”) in PJM, PSEG offers a unique and informed

perspective on PJM’s flawed governance structure. Fixing PJM governance is not optional, and there are a range of potential solutions. Fundamentally, the objective must be to achieve consistently better, durable outcomes at PJM – defined as supporting (i) a system that is reliably planned in the short-term and in the long-term and a well-functioning wholesale electricity market with stable, defensible rules; (ii) efficient and timely decision-making; and (iii) an RTO

1 The PSEG Companies are Public Service and Gas Company (“PSE&G”), PSEG Power LLC and PSEG Energy Resources & Trade LLC, which are each wholly-owned, direct or indirect subsidiaries of Public Service Enterprise Group Incorporated (“PSEG”) (collectively, “PSEG” or the “PSEG Companies”).  PSEG is a diversified energy company based in Newark, New Jersey consisting primarily of a regulated electric and gas utility and a nuclear generation business.  Through its wholly-owned subsidiary PSE&G, PSEG owns over 2,200 circuit miles of electric transmission lines within the PJM region.  PSE&G has 2.4 million electric customers in its franchised service territory and an obligation to reliably serve those customers.  For 24 consecutive years, PSE&G has won reliability awards in the Mid-Atlantic region and has a proven record of providing reliable and affordable service to customers. PSEG also has an ownership interest in approximately 3,800 MW of reliable, baseload nuclear generation.

PDF page 2

2

that is both empowered to make the right decisions and is fully accountable for those decisions. PSEG proposes actionable solutions to deliver these results.

This is not an academic exercise; customer reliability is at risk. Just this year, due to the unsolved supply/demand imbalance, PJM has gone into emergency alert conditions across the region four times, and in the process has sought and obtained multiple emergency authorizations from the Department of Energy (“DOE”) permitting it to run generating units beyond otherwise- applicable permit limitations and to call on large customers to run back-up generation, subject to curtailment if necessary.2 This continual state of operating in “crisis mode” is not sustainable. PSEG has had iron in the ground in PJM for decades. Our core concerns, and stake in the future of PJM, do not – and will not - wax and wane based on individual Regional Transmission Expansion Plan (“RTEP”) cycles or Base Residual Auctions. We have warned of critical flaws in PJM governance for years, and unfortunately those risks have fully materialized. We are deeply committed to continuing to work with PJM to keep the lights on for our customers. Our comments are offered through this lens and with this long-term perspective.

I. Executive Summary
PJM’s governance model is broken. As Chairman Laura Swett stated at the May 2026 PJM Annual Meeting, the “current stakeholder process is slow where it must be fast, opaque where it must be transparent, and vulnerable to vetoes and agenda control exactly when the region needs immediate action.”3  While it may seem counterintuitive to tackle PJM governance while PJM and its stakeholders are simultaneously seeking to solve the substantive issues of large load integration and resource adequacy, the reality is that the flawed governance structure has (i) played a role in causing these problems and (ii) will prevent PJM and its stakeholders from developing effective, long-term solutions. The current process is locked in an endless cycle of finger pointing, lack of defined accountabilities, flawed voting and contentious stakeholder processes -- with no resolution in sight.

2 NERC EEA conditions were announced January 26, 2026; May 17 to 19, 2026; June 30 to July 2, 2026; and July 14 to July 21, 2026.  See Emergency Procedures - Postings.
3 See Chairman Laura Swett's Comments at PJM's Annual Meeting in Baltimore, MD | Federal Energy Regulatory Commission.

PDF page 3

3

PJM is fundamentally different from other RTOs and ISOs. ISO-NE, for example, consists of six states that have relatively homogenous state policies. MISO and SPP, while representing large footprints, consist primarily of vertically integrated states. New York and California are single state ISOs, minimizing regional policy friction that affects multi-state markets. By contrast, PJM is comprised of fourteen jurisdictions with a large range of state policies reflected in the vast membership, and a combination of retail choice and vertically integrated states. PJM’s vast size, broad scope and regional diversity exacerbate its governance challenges. The fundamental flaws in PJM’s governance structure were largely masked over the past two decades because the relevant externalities were significantly different. During most of that time, PJM was in a position of excess supply and demand was manageable and somewhat predictable, with largely flat or declining load growth. Under surplus capacity conditions PJM’s governance was not truly stress-tested. With economics and policy causing the retirement of a significant amount of capacity in the region4 and the recent rapid demand growth driven by the integration of large loads,5 the externalities have now radically changed, and PJM’s governance problems have been fully exposed.

PJM acknowledges this reality in its recently issued whitepaper on market design reforms, “Powering Reliability Through Market Design.”6 As noted by PJM President and CEO David Mills, “the conditions that made the market work for nearly two decades have changed.”7  Mills explains that the problems facing the region are “more fundamental than a design that needs recalibration” and that “the current situation is not tenable.”8 These statements are simultaneously revealing and troubling.

We are not interested in assigning blame as that is neither productive nor fair.  Instead, we seek to be a constructive partner in resolving the governance issues that lie before us. PJM has

4 See Monitoring Analytics, "2023 State of the Market Report for PJM," Section 1 Introduction, page 1. Document file: 2023-som-pjm-sec1.pdf, available at: https://monitoringanalytics.com.
5 See PJM 2026 PJM Load Forecast Report (Jan. 14, 2026) (available at: https://www.pjm.com/- /media/DotCom/library/reports-notices/load-forecast/2026-load-report.pdf).
6 See PJM Whitepaper entitled "Powering Reliability Through Market Design," (May 6, 2026) (“PJM 2026 Whitepaper”) available at: https://www.pjm.com/-/media/DotCom/library/reports-notices/special- reports/2026/20260506-powering-reliability-through-market-design.pdf.
7 PJM 2026 Whitepaper at 3.
8 Id.

PDF page 4

4

vast amounts of expertise, and the organization is capable of remarkable operational performance (e.g., during the recent heat dome in early July). But long-term organizational success is not adequately measured by its ability to manage crisis to crisis, capacity auction to capacity auction, or extreme weather event (summer or winter) to extreme weather event.

 Our goals are straightforward.  We seek to equip PJM with the governance tools to (i) reliably plan the system and run its markets with clear, stable and transparent rules, (ii) improve the effectiveness of the PJM stakeholder process and (iii) strengthen PJM’s accountability to grid asset owners and other PJM stakeholders to restore confidence in its decision-making.

In furtherance of these goals, we propose a targeted framework for the Commission’s consideration:

• First, the Consolidated Transmission Owners Agreement (“CTOA”) and the PJM Operating Agreement (“OA”) must be amended to empower PJM to make effective regional planning decisions while increasing its accountability to grid asset owners.

• Second, changes to voting rules are desperately needed. Change could take one of two forms – either aligning voting rules with members’ actual and measurable stake in PJM outcomes or full advisory voting, which, when coupled with increased PJM

accountability, may allow PJM to leverage its knowledge of the system and the markets to make independent, timely and bold decisions and stick with them.

• Third, in light of the fundamental changes happening in the industry, PJM’s stakeholder process needs to accelerate to meet this moment.

• Fourth, there should be enhanced accountability for PJM, including regular third-party evaluations of the PJM Board’s and PJM senior management performance.

Finally, we support a revised role for the PJM states, reflecting their role in resource adequacy and their desire to better understand and positively impact the stakeholder process. At the same time, any such change must be linked to effectuating improved outcomes in PJM, as measured by the above-listed objectives of achieving reliable system planning and stable, well- functioning markets, an effective stakeholder process and measurable PJM accountability. Comments

PDF page 5

5

II. The CTOA and the OA must be amended to empower PJM’s regional transmission planning and enhance its accountability to asset owners.

1. What is the status quo under the current CTOA paradigm?
The CTOA is the foundational agreement by which the TOs collectively contracted with PJM to transfer control of over $80 billion of transmission assets to PJM. Under the CTOA, PJM is responsible for: (1) providing open-access transmission service, including processing transmission service and interconnection requests; (2) directing the operation of the TOs’ transmission facilities and monitoring/operating the bulk power system; (3) preparing the RTEP and the load forecast used as an input to the RTEP; and (4) conducting all planning of “expansions” and “enhancements” to the regional transmission grid.9 The TOs retain responsibility to: (1) build, finance, own, acquire, sell, or otherwise transfer assets, including terminating the member’s relationship with PJM; (2) maintain, repair and replace transmission assets; (3) identify and plan supplemental projects to address local reliability needs; and (4) seek FERC approval for new rules or changes to existing rules regarding the recovery of transmission revenue requirements, rate design and cost allocation.10

The CTOA is unique among the PJM governing documents in establishing a demarcated and fundamental split of responsibilities between PJM and its TOs. Yet, the agreement is often ignored in discussions about PJM governance. The legal and practical reality is that it cannot be ignored. From the TO perspective, discussions about the future of PJM governance must start with the CTOA.

 One fundamental flaw with the CTOA is that it memorializes a structure whereby the regional planning protocol establishing rules for regional transmission planning resides in the PJM OA instead of the Tariff. Pursuant to the CTOA, “Each party shall transfer to PJM, pursuant to this Agreement and in accordance with the Operating Agreement, the responsibility to prepare a Regional Transmission Expansion Plan and to provide information reasonably requested by PJM to prepare the Regional Transmission Expansion Plan...”11 And under the OA, PJM is required to obtain the approval of the PJM Members Committee prior to

9See CTOA, Sections 4.1 and 6.3.
10 CTOA, Sections 5 and 7.
11 Id. section 4.1.4 (emphasis added).

PDF page 6

6

filing any change in its planning rules under Section 205 of the Federal Power Act (absent such approval, PJM is required to file under Federal Power Act Section 206 to effectuate the change).12 PJM has itself explained, “In the absence of such Members Committee approval, PJM may only propose a change to its planning rules for the Commission’s consideration using FPA section 206, thereby: (i) requiring PJM to first meet the higher statutory burden of demonstrating that an existing provision (or absence of a provision) is ‘unjust and unreasonable,’ prior to actually proposing the rule change for consideration; and (ii) creating an indeterminate period of time for Commission action on PJM’s proposed rule change.”13 This allows members to make decisions about RTEP rules through the OA when the underlying responsibility to plan the regional transmission system clearly resides with PJM under the CTOA.

PJM is the only RTO that does not have independent Section 205 filing rights over transmission planning. 14 This paradigm undermines PJM’s independence to plan the grid and potentially hamstrings PJM from being able to pursue transmission grid initiatives due to stakeholder voting factions and dysfunction. Another challenge with the CTOA is that the TOs have no audit rights of PJM and therefore no way under the agreement to hold PJM accountable for its performance under the agreement. Other RTOs, including SPP and MISO, provide such rights to their TO members. In SPP, transmission owners have audit rights to “verify compliance by SPP with [the Membership] Agreement, to audit and verify transactions … and to assist Member[s] in complying with[]statutory and regulatory requirements” under the Membership Agreement.15 MISO TOs have nearly identical provisions in their Transmission Owners Agreement, which state that “MISO shall grant each Member, its employees or agents, external auditors, and federal and state regulatory authorities having jurisdiction over MISO or an Owner,

12 See Operating Agreement, Section 18.6(a) (as amended).
13 Duquesne Light Co., PJM Transmittal Letter, Docket Nos. ER24-2336-000, et al., at 2 (Jun. 21, 2024). 14 In 2024, the Commission rejected proposed changes to the CTOA and OA that would have provided PJM independent planning rights and addressed identified gaps and problems with the CTOA. The Commission did not disagree with the underlying premise that PJM should have filing rights with respect to its RTEP rules.  See Duquesne Light Co., Order Rejecting Consolidated Transmission Owners Agreement Amendments and Denying Complaint, Docket Nos. ER24-2336-000, et al.,189 FERC ¶ 61,181 (Dec. 6, 2024).  On rehearing of that decision, the Commission emphasized that the “dismissal of the PJM Complaint here does not preclude a future filing proposing to move the RTEP Protocol from the OA to the Tariff.  The PJM Board has the authority to petition the Commission under FPA section 206 to modify any provision or schedule of the OA that the PJM Board believes to be unjust, unreasonable, or unduly discriminatory.” Duquesne Light Co., 192 FERC ¶ 61,051 at P 105 (July 14, 2025) (emphasis added).
15 See Southwest Power Pool, Inc., "Membership Agreement," Section 2.4 (May 1, 2004), available at: https://spp.org.

PDF page 7

7

such access to MISO's books and records as is necessary to verify compliance by MISO with the MISO Agreement and to audit and verify transactions under the MISO Agreement.”16 Nothing comparable exists in either the CTOA or the PJM OA, but such rights should exist.

2. What changes should be made to the CTOA and related governing documents and how can they be effectuated?

Specific changes to the CTOA and related governing documents are needed to address these flaws, including:

a. Amending the CTOA to effectuate the transfer of the planning protocols from the OA to the PJM Tariff so that PJM has independent Section 205 filing rights with respect to its RTEP rules; and

b. Incorporating audit provisions in both the CTOA and OA to monitor PJM’s
performance and ensure compliance with its responsibilities.
These changes would require a FERC filing and approval as part of either a Section 205 or Section 206-initiated proceeding.

III. PJM’s voting framework must be fundamentally overhauled.
1. What is the status quo under current PJM voting rules?
As illustrated in the table below, the PJM of the late 1990s is radically different from the PJM of 2026.17  At its inception as an ISO in 1997, PJM was composed of only 10 TO members located in 5 states and the District of Columbia.18 Approximately thirty years later, PJM’s membership has risen to over 1,100 total members and 532 voting members in 13 states and the District of Columbia.19 The original limited membership of similar companies varied only by geography, and issues were largely considered from similar points of view. PJM in 2026 reflects states with different policy priorities and different degrees of reliance on the capacity market.

16 See Midcontinent Independent System Operator, Inc., "Agreement of Transmission Facilities Owners to Organize the Midcontinent Independent System Operator, Inc.," Section 10.2 (as amended), available at: https://cdn.misoenergy.org/MISO%20TOA%20(for%20posting)47071.pdf. 17 PJM 2025 Annual Report, Meeting Each Moment (available at Welcome - PJM Annual Report 2025).
18 PJM Operating Agreement, Resolution and Certification page: OA, OA Resolution and Certification Page-
19 See PJM Member List (as of July 9, 2026).

PDF page 8

8

PJM Facts
Late 1990s
2026
Number of Members
10
1,145
Number of Voting Members
10
517
Transmission Owner
10
12
Generation Owner
0
110
End Use Customer
0
24
Electric Distributor
0
45
Other Supplier
0
326
Customers Served
~25M
>67M
States Served
5 + DC
13 + DC
Peak Load (MW)
>48,000
>165,000
Transmission Lines (Miles)
~6,300
>88,000
Generating Capacity (MW)
>57,000
>185,000

PJM’s senior standing committees – the Markets and Reliability Committee and the Members Committee - use sector-weighted voting, with members categorized into one of five sectors with equal voting strength. Each of the five sectors has 20% of the vote and a proposal must achieve 2/3 approval from the sectors to pass.  PJM’s sector voting structure was designed to ensure that no one group could “disproportionately dominate” the stakeholder decision-making and voting processes. Yet the PJM voting structure when applied to today’s membership composition no longer works to produce effective outcomes.

Below are two real-world examples of anomalies and inefficiencies in the PJM voting process that impede resolution of critical issues:

• Critical Issue Fast Path (“CIFP”) process for Large Loads: This stakeholder process was initiated by PJM to develop rules around the important issue of the integration of large loads. Yet, when votes on proposals were taken in November 2025, only 118 of 520 eligible Members participated, reflecting 24% of PJM’s total voting population. The Generation Owner and Other Supplier sectors had less than half of their membership in attendance (29% and 7% respectively), but those two sectors combined for 40% of the sector-weighting under PJM’s voting protocol.20 The ability of two sectors to join together to “sector block” a proposal from being endorsed is magnified with limited

20 PJM Operating Agreement 8.4.

PDF page 9

9

voting participation and represents a meaningful flaw in the voting process. In the case of the CIFP vote, no proposal was ultimately endorsed on this key substantive matter.

• End of Life Transmission Planning: In 2019, PJM initiated a stakeholder process to establish criteria that would apply to all transmission projects seeking to resolve “end of life” drivers on PJM Tariff transmission assets.21 The process culminated in a vote at the Members Committee where a proposal seeking to transfer responsibility for “end of life” decision-making away from the TOs and to PJM received a 69% sector-weighted supermajority vote. This proposal was brought by a coalition of “joint stakeholders” that do not have any responsibility for the ownership, operation or planning of transmission facilities. Ultimately, the member-endorsed proposal was filed at FERC and was opposed by PJM itself, who explained to FERC that the members filing conflicted with the rights of the Transmission Owners under the CTOA.22 This is a perfect example of a misaligned stakeholder process that wasted resources and produced a poor (and ultimately FERC- rejected) outcome.

2. What changes should be made to PJM’s current voting rules and how can these changes be effectuated?

We present two types of potential solutions to revise the current PJM voting structure. The first category would involve implementing a different weighting so that votes are based on a member’s actual level of interest in PJM and its stake in PJM outcomes. The second category would simply make all voting advisory. In PSEG’s view, this second approach will not be as effective if pursued in isolation and, given the increased authority accorded to PJM under this scenario, should be accompanied by meaningful changes to enhance PJM’s accountability and clearly delineate responsibilities.

a. Changes to the voting structure to reflect members’ actual economic and operational stake in PJM outcomes

21 See PJM Interconnection, LLC, "Issue Details: Transparency and End of Life Planning," PJM Issue Tracking ID: 23b82425-6796-4b0c-8c4a-5ff9b6b5f061, available at: https://www.pjm.com/committees-and-groups/issue- tracking/issue-tracking-details.aspx?Issue=23b82425-6796-4b0c-8c4a-5ff9b6b5f061.
22 PJM Interconnection L.L.C., 176 FERC ¶ 61,053 (2021).

PDF page 10

10

PJM’s current voting rules mean that asset owners with responsibility for customer reliability and long-lived assets in the ground have a significantly diluted vote.23 Yet, several states have implicitly recognized the importance of their utilities’ role in the PJM voting process. For example, last year, New Jersey enacted a law that requires the four electric utilities in the state that “transmit and distribute electricity to end users within the State” to submit an annual voting report to the New Jersey Board of Public Utilities that lists all recorded votes cast by the utilities, describes the context of the votes and explains how each vote “furthers the State’s goals of promoting affordability, reliability and sustainability of electricity production, consumption and conservation ….”24 No other PJM voting member with interests in New Jersey (including generators located in the state, retail default service providers, municipal electric utilities or the New Jersey Division of Rate Counsel) is required to report their votes to the Board of Public Utilities. This requirement, which has been adopted by New Jersey, Maryland and Virginia and is under consideration by Illinois and Pennsylvania, underscores the unique role of the utility in PJM voting and only underscores the mismatch between the nature of the utility interest and the actual ability to influence a PJM vote.25

There are several different voting changes that could be pursued, all of which would involve modification of the PJM OA, to align voting weight with “skin in the game.” One such option would be to match voting interest with member responsibilities under the default cost allocation methodology contained in Section 15.2.2 of the OA. These rules assign a share of member default costs to market participants based on their respective market activity (gross billings).26 Under these rules, PSEG and other larger market participants face the potential for significant default allocations and must account for such risk in their risk management plans. Yet, our vote in the stakeholder process is disconnected from these risks that we bear. Another option would be to weigh TO votes more heavily for votes involving transmission planning rules. A final option is a bicameral voting structure that would count a member’s vote on both a per capita basis and an

23 Despite being a major asset owner with an obligation under state law to provide safe, adequate, and proper service and an obligation under the PJM governing documents to maintain, repair, and replace transmission assets for reliability, PSEG’s vote constitutes about 1.5% of the total vote in PJM senior standing committees and only 0.4% of the vote in the lower committees. 24  N.J.S.A. 48:2-16.5.
25 See Maryland House Bill 121 and Senate Bill 37; Virginia House Bill 84; New Jersey Assembly Bill 5463; IL House Bill 1802; Pennsylvania House Bill 1599.
26 See Section 15.2.2 of the PJM Operating Agreement.

PDF page 11

11

asset ownership basis. Under this approach, the asset ownership component of the vote would reflect MWs of generation capacity, ownership of transmission assets and/or MWs of load owned or controlled by members. This structure would appropriately recognize the operational and financial stake of the members in PJM’s voting process but would at the same time be balanced by a per capita allocation.27

b.  Alternatively, PJM could consider adopting advisory stakeholder voting

We recognize that other RTOs/ISOs employ full stakeholder advisory voting and that PJM already uses it for certain matters falling within the PJM Tariff such as RPM capacity market rules. For example, MISO operates under an advisory stakeholder process “that provides input to MISO on the regional system plan and a range of market- and tariff-related issues and policy initiatives.”28 Similarly, voting in the New England Power Pool (“NEPOOL”) stakeholder process for ISO New England (“ISO-NE”) is advisory; however, if an alternative NEPOOL proposal meets a particular voting threshold, “then ISO-NE must include in its Section 205 filing a description of the alternative proposal” under the “jump ball” provision.29 If advisory voting were to be implemented in PJM, it would shift the ultimate responsibility for decision-making onto PJM and create a structure whereby PJM could independently design and propose Tariff revisions to the FERC on all issues under its purview. While one may legitimately question whether this type of voting has worked with respect to the RPM capacity market rules, we understand that, at least in theory, full advisory voting could help to embolden PJM to act independently and more decisively. Because this approach would provide more authority to PJM it must be accompanied by enhanced accountability, including for the PJM Board, so that members have confidence in the decisions PJM is making.

27  Comments of the PSEG Companies on PJM’s Order No. 719 Compliance filing in ER09-1063 at 11 (June 26, 2009).
28 NESCOE February 19, 2021White Paper on “Governance Structure and Practices in the FERC Jurisdictional ISOs/RTOs” prepared by Exeter at Section 4.3. available at Governance Structure and Practices in the FERC Jurisdictional ISOs/RTOs | NESCOE
29 Id. at Section 3.4.

PDF page 12

12

IV. The PJM stakeholder process should be reformed to accelerate the speed of decision- making.

We agree with FERC that the current PJM stakeholder process is too slow and subject to the obstructive agendas of various stakeholders. The inability to coalesce on issues in the PJM stakeholder process has resulted in tremendous inefficiencies and in some cases a complete failure to act at all. One such example, referenced above, is the CIFP process to develop large load integration rules, which occurred between August 2025 and November 2025. Despite 11 stakeholder meetings, no proposal was endorsed by the members for consideration by the PJM Board. This lack of action in turn resulted in direct federal and state intervention in PJM decision-making, specifically the January 2026 National Energy Dominance Council and the thirteen PJM state agreement memorializing the “Statement of Principles Regarding PJM.30 Modest changes can be implemented in the short term that will expedite decision-making in the stakeholder process, and we offer a few for consideration:

• Upfront identification of purpose and system benefits of all stakeholder proposals (would require revisions to PJM Manual 34): Solution proposals offered by stakeholders should contain a clear purpose - tied to the defined scope of the stakeholder process at issue - and should explain the measurable benefits that will result if the proposal is endorsed. If the proposal is lacking in any of these respects, PJM should require that the proposal, either be removed from consideration or changed to satisfy these criteria before a vote is taken.

• Member-only proposal submissions (would require revisions to PJM Manual 34): PJM should strongly consider limiting stakeholder proposal submission to members or requiring that at least one member be a co-sponsor to a proposal. Non-member stakeholders may continue to participate and be heard in stakeholder meetings - and can seek to influence the content of proposals - but should not be permitted to sponsor proposals without at least one member also attached to the proposal. Otherwise, non- member stakeholders are allowed a significant benefit of membership without bearing

30 See Statement of Principles signed by the NEDC and the PJM Governors (available at statement-principles- regarding-pjm.pdf)

PDF page 13

13

any of the responsibilities that come along with membership. That asymmetry produces poor outcomes and is also highly inefficient.

• More frequent use of the CIFP process:
PJM crafted the CIFP mechanism for use on substantive issues that are “...extremely difficult to resolve, within the normal CBIR Stakeholder process...in extraordinary circumstances (broad impact to markets or significant reliability issue).”31 If accompanied by PJM adoption of new rules that better vet the content and sponsorship of proposals, more frequent use of the CIFP process could facilitate efficient and effective engagement on critical issues in a structured and time-bounded manner.

V. Reforms are critical to enhance PJM’s accountability and ensure defensible, durable outcomes.  Specific to resource adequacy, additional clarity is needed to delineate responsibilities.

Accountability
PJM’s 2026 Whitepaper on potential market design reforms captures the gravity of the resource adequacy problem at hand. At the same time, the whitepaper fails to identify concrete, timely and actionable solutions. Rather, the white paper merely notes that relevant decisions on future market design “belong to the people and institutions with democratic accountability for their consequences – to state regulators and legislatures, to FERC, to consumers and the advocates who represent them.”32 Given PJM’s status as the independent FERC-approved entity responsible for the reliability of a grid that serves over 65 million customers, its choice to refrain from making a recommendation on a path forward feels inadequate.

Order No. 719 requires each RTO or ISO to demonstrate “that it has in place, or will adopt, practices and procedures to ensure that its board of directors is responsive to customers and other stakeholders.”33 In compliance with this requirement, PJM must make difficult, and at times unpopular, decisions and then explain those decisions to its stakeholders and stand by those decisions.

31 See PJM Manual 34: PJM Stakeholder Process (Sept. 25, 2025).
32 See PJM 2026 Whitepaper at 3.
33 See Order 719 at P 477.

PDF page 14

14

There are corporate governance principles that PJM could adopt to promote accountability and responsiveness from its leadership to its stakeholders. For example, PJM should utilize a third party to regularly evaluate the performance of its Board and its executive leadership team, and its Board should in turn regularly evaluate the performance and effectiveness of its senior leadership. There are several questions that will need to be answered to effectively evaluate PJM’s performance, including: (1) what are the appropriate metrics to be used to measure accountability and responsiveness; (2) which entity is responsible for conducting that measurement; (3) where should those requirements be documented; and (4) what are the repercussions for failing to meet those performance metrics. However, the answers to these questions are secondary to beginning in earnest an effort to increase organizational accountability.

In its compliance filing in response to Order No. 719, PJM pointed to the existence of the Governance Assessment Special Team (“GAST”) stakeholder forum as a demonstration of PJM’s commitment to considering further enhancements (beyond the requirements of Order No. 719) to its stakeholder and governance processes.34 The GAST was used to examine the concerns of PJM membership regarding governance and stakeholder processes and to develop solutions. Under that process, PJM implemented both the Consensus-Based Issue Resolution (“CBIR”) process and the Stakeholder Process Forum to more efficiently engage stakeholders.35 GAST also implemented the Enhanced Liaison Committee to address important and divisive issues.36  PJM should employ a forum comparable to GAST to work with its stakeholders to develop accountability metrics. That forum could also be used to examine whether the existing requirements for PJM Board participation remain appropriate, including the two-year cooling-off period on material affiliation with a market participant and the lack of a residency or regional connection requirement, or whether they should instead be modified or strengthened.37

34 See PJM Interconnection, L.L.C., PJM’s Compliance Filing, FERC Docket No. ER09-1063-000, at 56 (filed Apr. 29, 2009).
35 See PJM Interconnection, LLC, "PJM Governance & Stakeholder Process," Stakeholder Process "Super Forum" (July 25, 2018), file name: 20180725-item-01-introduction.pdf, available at: https://pjm.com.
36 See PJM Manual 34.
37 See PJM Operating Agreement Section 7.2.

PDF page 15

15

Defined Roles for Resource Adequacy

Enhancing PJM’s accountability will restore confidence in its decision-making at this critical time where it must work with its stakeholders and the PJM states to tackle resource adequacy and the rapid integration of large load customers. PJM has indirect responsibility for resource adequacy through its use of market pricing signals to incent the addition of new generation and to retain existing resources. However, PJM is not an integrated resource planner and therefore does not plan generation.

By contrast, the PJM states do have authority to address resource adequacy through the planning of generation and a vested interest in ensuring that, to the extent they continue to rely on PJM’s markets, rules for those markets are transparent and will procure sufficient supply to maintain reliability. There is a pressing need for clarity on the respective responsibilities between PJM and the states on resource adequacy, and discussions should occur as to how PJM and the states – with support from asset owners with responsibility for reliability - will work together to obtain this clarity. Those discussions need to happen now.

PJM, its states and the TOs have recently collaborated on load forecasting improvements, which will involve, among other things, use of a third party consultant to verify large load forecast data, review by the states of such data and formalized involvement by the states in the overall load forecasting process to ensure state policies are accurately reflected in the forecast.38 Appropriately involving the states in a fulsome way in load forecasting will help to ensure a more accurate and defensible work product. PJM and its states could adopt a similarly productive approach to resource adequacy, and one way to advance progress would be through the use of a properly-bounded state advisory committee, such as exists in SPP and the ISO-NE, with clearly- defined roles and responsibilities.

38 See PJM Interconnection, LLC, "Manual 19: Load Forecasting and Analysis," Attachment B: Load Forecast Adjustment Guidelines, Revision 39 (June 30, 2026), file name: m19.pdf, available at: https://www.pjm.com/- /media/DotCom/documents/manuals/m19.pdf.

PDF page 16

16

VI. Conclusion
Getting the rules right on PJM governance is critical and the time for action is now. Reforms must be focused on changing and improving PJM’s decision-making and providing PJM with the tools to effectuate sustainable outcomes that will ensure long-term system reliability. PSEG’s proposed solutions – providing PJM with filing rights over transmission planning rules, changing voting in a meaningful way, making stakeholder processes more efficient and enhancing PJM accountability for its decisions – are intended to satisfy these objectives. Respectfully submitted,

Jodi L. Moskowitz
Jodi L. Moskowitz
Vice-President and
Deputy General Counsel & RTO Strategy Officer
PSEG Services Corporation
80 Park Plaza, T20
Newark, NJ 07102
(973) 985-7958
Jodi.Moskowitz@PSEG.com
On behalf of the PSEG Companies

Dated:  July 14, 2026
Newark, New Jersey