Pre-filed Statement of Jodi L. Moskowitz, Vice President Regulatory – Law, Deputy General Counsel and RTO Strategy Officer for Public Service Enterprise…
Text extracted from the eLibrary original (SHA-256 4f6d733eac07c7ef…). Download the original from the official source.
Contents · 6 sections
- I. Executive Summary
- II. The CTOA and the OA must be amended to empower PJM’s regional transmission
- III. PJM’s voting framework must be fundamentally overhauled.
- IV. The PJM stakeholder process should be reformed to accelerate the speed of decision-
- V. Reforms are critical to enhance PJM’s accountability and ensure defensible, durable
- VI. Conclusion
Read topic-matched comments in AD26-7
Topics in the text: Reliability and curtailment · Cost allocation · Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
Fundamentally, the objective must be to achieve consistently better, durable outcomes at PJM – defined as supporting (i) a system that is reliably planned in the short-term and in the long-term and a well-functioning wholesale electricity market with stable, defensible rules; (ii) efficient and…Read this passage Filed comments: Reliability and curtailment
I. Executive Summary
printed heading · Topic match: Reliability and curtailment
As Chairman Laura Swett stated at the May 2026 PJM Annual Meeting, the “current stakeholder process is slow where it must be fast, opaque where it must be transparent, and vulnerable to vetoes and agenda control exactly when the region needs immediate action.”3 While it may seem counterintuitive to…Read this passage Filed comments: Reliability and curtailment
II. The CTOA and the OA must be amended to empower PJM’s regional transmission
printed heading · Topic match: Cost allocation
The CTOA and the OA must be amended to empower PJM’s regional transmission planning and enhance its accountability to asset owners. 1.Read this passage Filed comments: Cost allocation
III. PJM’s voting framework must be fundamentally overhauled.
printed heading · Topic match: Cost allocation
PJM’s voting framework must be fundamentally overhauled. 1.Read this passage Filed comments: Cost allocation
IV. The PJM stakeholder process should be reformed to accelerate the speed of decision-
printed heading
The PJM stakeholder process should be reformed to accelerate the speed of decision- making.Read this passage
V. Reforms are critical to enhance PJM’s accountability and ensure defensible, durable
printed heading · Topic match: Reliability and curtailment
ER09-1063-000, at 56 (filed Apr. 29, 2009). 35 See PJM Interconnection, LLC, "PJM Governance & Stakeholder Process," Stakeholder Process "Super Forum" (July 25, 2018), file name: 20180725-item-01-introduction.pdf, available at: https://pjm.com. 36 See PJM Manual 34. 37 See PJM Operating Agreement…Read this passage Filed comments: Reliability and curtailment
VI. Conclusion
printed heading
Reforms must be focused on changing and improving PJM’s decision-making and providing PJM with the tools to effectuate sustainable outcomes that will ensure long-term system reliability.Read this passage