AD26-7-000 · 2026-07-16 · Constellation Energy Generation, LLC
Pre-filed Statement of Mason Emnett, Senior Vice President for Public Policy for Constellation Energy Generation, LLC, for the PJM Governance and…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Governance and Stakeholder Reforms
)
)
Docket No. AD26-7-000
PRE-CONFERENCE STATEMENT OF MASON EMNETT
ON BEHALF OF CONSTELLATION ENERGY GENERATION, LLC
Pursuant to the Commission’s July 2, 2026 notice in the above-captioned proceeding,1 and on behalf of Constellation Energy Generation, LLC (Constellation), Mason Emnett submits this pre-conference statement addressing potential PJM Interconnection, L.L.C. (PJM) stakeholder and governance reforms in advance of the Commissioner-led technical conference to be held on July 23, 2026.
I. COMMENTS
Policymakers and stakeholders have been discussing potential improvements to PJM’s
stakeholder process and governance structure for years.2 The intensity of this debate has ebbed and flowed over time but appears to be reaching a high point, with particular focus on how states can more effectively participate in PJM’s decision-making and whether PJM is organizationally
1 PJM Governance and Stakeholder Reforms, Second Supplemental Notice of Commission-Led Technical Conference, Docket No. AD26-7-000 (July 2, 2026).2 See, e.g., Members Committee, Stakeholder Process Super Forum, PJM Interconnection, L.L.C. (Aug. 22, 2019), https://www.pjm.com/-/media/DotCom/committees-groups/committees/mc/20190926/20190926-item-01- stakeholder-process-super-forum-presentation.ashx (a concentrated effort to make adjustments to the stakeholder process to help address prioritization and transparency); Stakeholder Process Forum, PJM Interconnection, L.L.C., https://www.pjm.com/committees-and-groups/forums/stakeholder-process-forum (PJM has a regular, monthly “check-in” to address issues that come up in the stakeholder process, the Stakeholder Process Forum, where all stakeholders, including representatives of state commissions and agencies, are welcome to participate); Open Letter to the PJM Board of Managers from Nine Governors re: Board Vacancies (July 16, 2025), https://www.pjm.com/- /media/DotCom/about-pjm/who-we-are/public-disclosures/2025/20250717-nine-governors-letter-regarding-board- vacancies.pdf; ICYMI: In Philadelphia, Governor Shapiro Convenes Historic PJM Summit to Push for Reform, Lower Energy Costs, and Protect Grid Reliability, Commonwealth of Pennsylvania (Sept. 23, 2025), https://www.pa.gov/governor/newsroom/2025-press-releases/icymi--in-philadelphia--governor-shapiro-convenes- historic-pjm-s.
PDF page 2
2
capable of quickly responding to emerging resource adequacy challenges. In response, the Commission initiated this proceeding to “focus on identifying and evaluating actionable reforms to improve PJM’s ability to address system needs in a timely and efficient manner.”3 An effective stakeholder process is critical in PJM and, as elaborated below, changes can and should be made to ensure transparency and an opportunity for all voices to be heard. However, these or any other changes considered must preserve PJM’s independence as a regional transmission organization (RTO) and maintain consistency with the Federal Power Act (FPA).
It is also critical that the Commission, PJM, the states, and stakeholders identify with precision the problems (from their respective perspective) that need to be solved so that we can collectively debate solutions that actually address each issue. For example, some suggest that PJM’s lack of section 205 filing rights results in gridlock when PJM’s Members cannot find consensus on a complicated issue. Yet most of the unrest in PJM over the last decade has involved issues related to resource adequacy, generator retirements and replacements, and capacity market rules changes—matters over which PJM already has section 205 filing rights and is able to take action under section 205 even when the Membership disagrees. When PJM has delayed action, it has been because its leadership has decided not to proceed, not because of any lack of authority. In the same vein, PJM’s lack of section 205 rights over energy market issues has not deterred PJM’s action under section 206 when its leadership decided to proceed without Membership endorsement.4 PJM has sufficient authority under its existing decisional structure to take action when its leadership concludes that action is necessary. Strong and decisive leadership by PJM,
3 PJM Governance and Stakeholder Reforms, Notice of Commission-Led Technical Conference, Docket No. AD26- 7-000 (May 12, 2026).4 See, e.g., Facilitating PJM Independent 205 Filing Rights Over Transmission Planning of PJM Interconnection, L.L.C., Docket No. EL24-119-000, at 9-11 (June 21, 2024) (filing by PJM under section 206 of the FPA); Enhanced Price Formation in Reserve Markets of PJM Interconnection, L.L.C., Docket No. EL19-58-000, at 1 & n.1 (Mar. 29, 2019) (filing by PJM under section 206 of the FPA).
PDF page 3
3
whether proceeding under section 205 or section 206, is what matters, and the Commission, states, and stakeholders should be focused on improvements to the stakeholder process or governance mechanics that reinforce (rather than undermine) PJM’s leadership.
A. The Role of States: Existing Participation and Additional Opportunities
Much of the current debate regarding the effectiveness of the PJM stakeholder process and related governance mechanics appears to be driven by concerns from some states that they do not have sufficient opportunity to be heard by PJM or otherwise participate in PJM processes and decision-making. Notwithstanding these concerns, state representatives have a long history of active participation in PJM’s stakeholder processes, both individually and collectively. For example, state representatives can and routinely do:
• Submit issues charges for PJM and its Members to consider;5
• Participate directly in the stakeholder process, such as by submitting proposals and
weighing in on others’ proposals6 (and, in fact, state-supported proposals have been
5 See, e.g., Issue Charge, PJM Interconnection, L.L.C. (July 16, 2025), https://www.pjm.com/- /media/DotCom/committees-groups/committees/mrc/2025/20250723/20250723-item-05---3-revised-sub-annual- auction-issue-charge---clean.pdf (sub-annual issue charge brought by Governor Josh Shapiro, on behalf of the Commonwealth of Pennsylvania, which led to the creation of the Sub-Annual Capacity Market Senior Task Force, https://www.pjm.com/committees-and-groups/task-forces/sacmstf); Clean Attribute Procurement Senior Task Force, PJM Interconnection, L.L.C., https://www.pjm.com/committees-and-groups/closed-groups/capstf (this now-closed group was established by an issue charge to coordinate the PJM markets with state clean energy attributes).6 See, e.g., Appendix 1, attached below (compiling written submissions by PJM state entities in two recent PJM Critical Issues Fast Path stakeholder processes); Letter from Maryland Delegate Lorig Charkoudian on behalf of the National Caucus of Environmental Legislators (NCEL), to President Mills & the PJM Board (June 23, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-written-comments--- maryland-delegate-lorig-charkoudian-on-behalf-of-ncel.pdf; Agenda for Critical Issue Fast Path (CIFP) - Reliability Backstop Procurement (RBP) / Connect & Manage (C&M), PJM Interconnection, L.L.C., (June 30, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-agenda.pdf (Maryland State Senator Katie Fry Hester allotted time for comments).
PDF page 4
4
selected by PJM and its stakeholders—and accepted by the Commission—as the
path forward7);
• Submit letters to the PJM Board expressing their views directly to the PJM Board;8
and
• Participate in state-specific task forces, user groups, and committees.9
States are nevertheless expressing increasing concern that participation has been difficult and ineffective. To enhance the ability of states to participate consistently in PJM processes, OPSI has begun expanding its capabilities so it can more effectively coordinate and represent state interests. The Commission, PJM, and its Members should support this right-sizing of OPSI
resources to ensure that the organization is sufficiently staffed and supported (including by lawyers and consultants) and capable of enabling a robust and effective state/PJM relationship, particularly as states seek to address the resource adequacy challenges that have been the focus of recent state concern.
7 See 2025 Periodic Review of Variable Resource Requirement Curve Shape and Key Parameters of PJM Interconnection, L.L.C., Docket No. ER26-455-000, at 7-8 (Nov. 7, 2025) (describing the Joint PJM/PA Public Utility Commission, Vice Chair Barrow proposal that received super-majority support from stakeholders and was adopted by the PJM Board without modification), accepted by PJM Interconnection, L.L.C., 194 FERC ¶ 61,049, on reh’g, 196 FERC ¶ 61,007 (2026).
8 In just the past year-and-a-half, the PJM states, in some capacity, have submitted over fifty letters to the PJM Board on a variety of issues. See Appendix 2, attached below. In addition, the Organization of PJM States, Inc. (OPSI) can meet with the PJM Board multiple times annually.9 See, e.g., Independent State Agencies Committee, PJM Interconnection, L.L.C., https://www.pjm.com/committees- and-groups/state-commissions/isac (focused primarily on transmission matters); Affordability and Reliability for Residential Consumers User Group, PJM Interconnection, L.L.C., https://www.pjm.com/committees-and- groups/user-groups/arrcug (includes state-appointed consumer advocates of several restructured states within the PJM service area); Public Interest & Environmental Organizations User Group, PJM Interconnection, L.L.C., https://www.pjm.com/committees-and-groups/user-groups/pieoug (includes representatives of Consumer Advocates, as well as public interest and environmental organizations, and holds an annual meeting with the PJM Board); Clean Attribute Procurement Senior Task Force, PJM Interconnection, L.L.C., https://www.pjm.com/committees-and- groups/closed-groups/capstf (this now-closed group was set up to “coordinate a comprehensive discussion” between OPSI, PJM stakeholders, and staff “around enhancements to enable states and other willing buyers to procure clean resource attributes, on a voluntary basis, through a regional and centralized procurement or market.”).
PDF page 5
5
PJM also could facilitate more effective engagement by the states by being explicit
regarding the input that it seeks from states and the forum(s) in which that input is to be provided. Whether accurate or not, there is a general perception that PJM leadership does not take input from the states seriously. PJM can correct that perception by identifying in a structured way the specific input that it desires from states, where and when that input is to be provided, and then communicating back to the states how that information was considered by PJM to reach decisions. Constellation recommends that PJM do this for the following topics at a minimum:
• Proposed changes to market rules and planning processes;
• Jurisdictional authority of PJM relative to the states;
• Load forecasting, including obtaining input from state retail regulatory authorities on what large load requests are sufficiently real to be included in PJM’s capacity
procurement and transmission planning;
• Resource adequacy preferences, including whether the state intends to rely on PJM
markets for capacity procurement or to establish its own planning and procurement
mechanism(s) and whether the state prefers certain capacity types and, if so, how
those resources should be procured;10 and
• Views on the relative importance of rule or process changes so PJM can factor that
into its workload prioritization.
10 See Transcript of Technical Video Conference at 225, Technical Conference Regarding Resource Adequacy in the Evolving Electricity Sector, Docket No. AD21-10-000 (Mar. 23, 2021) (Jason Stanek, Chairman, Maryland Public Service Commission: “So [FRR] would allow us to reclaim resource adequacy. But at the same time we’ve been relatively content in the capacity markets up until the Calpine decision, and we’d like to stay if possible.”); Transcript of Technical Conference at 179-247 (Panel 3), Meeting the Challenge of Resource Adequacy in Regional Transmission Organization and Independent System Operator Regions, Docket No. AD25-7-000 (June 4, 2025), (roundtable discussion with state public utility commissioners and other state representatives about the role of states in resource adequacy in PJM).
PDF page 6
6
This increased collaboration also should go both ways. There are a number of market and resource adequacy-related matters governed by state laws and regulations that are impacted by PJM decisions or otherwise interact with the wholesale markets and planning functions overseen by PJM. PJM should work with the states to identify the areas of support they need to fulfill their own duties. This could include matters ranging from the siting and permitting of transmission, generation, and gas pipeline infrastructure necessary to bring PJM-planned resources online, to opportunities to increase the use of bilateral contracting and hedging structures to protect consumers from wholesale market volatility.
As noted above, effective coordination with the states will require both PJM and the states to be specific as to the information or input to be provided and the forum(s) in which that information and input is to be provided. To ensure that OPSI can provide meaningful and coordinated support to the states in meeting those expectations, PJM should:
• Establish protocols and schedules for meeting regularly with state commissions and their staff, both individually and collectively, to seek input regarding important market and transmission issues, rule changes, and other areas of concern, including both staff-to-staff and leadership-to-leadership meetings;
• Establish a process for states, both individually and collectively, to request and receive technical information and support on matters related to wholesale markets and/or infrastructure planning and their interactions with state regulation and retail rates; and
• Develop (with Commission and state guidance) options for additional hedging tools, such as a state purchasing authority (or buyers’ cooperative), to facilitate
PDF page 7
7
bilateral contracting11 and manage consumer risks associated with wholesale price
volatility.12
Finally, PJM also should discuss with OPSI and the PJM Governors Collaborative whether they desire to establish an organization, either separate from or integrated with OPSI, to facilitate participation by state elected officials in PJM processes. Elected officials do not currently have a forum similar to OPSI to support their engagement in PJM matters and may lack the technical resources needed to engage effectively. Additional funding for such an organization, whether separate from or integrated with OPSI, could be provided through the PJM Tariff to ensure sufficient staffing and support (including by lawyers and consultants). This could be accomplished through an amendment to Schedule 9 of the PJM Tariff, which already provides funding for both OPSI as well as the Consumer Advocates of PJM States, Inc. (CAPS).
B. The Commission’s Role: Ensuring PJM Processes Are Effective
In situations where the Commission desires to see prompt action on a particular matter, or the Commission is concerned that a lack of stakeholder consensus is leading to inaction by PJM, the Commission can spur action by using its convening authority, both informal and formal. For example, the Commission could hold conferences/workshops on enhancing bilateral transactions or other steps that PJM could take in coordination with states to protect consumers from price volatility in the wholesale market. Despite the best efforts of PJM and its stakeholders,
11 Bilateral contracting is generally beneficial as it supports competitive investment to meet resource adequacy goals and provides risk mitigation for supply and demand-side market participants. See Meeting the Challenge of Resource Adequacy in Regional Transmission Organization and Independent System Operator Regions, Post-Technical Conference Comments of Constellation Energy Generation, LLC, Docket No. AD25-7-000, at 5-9 (July 7, 2025).12 In its recent whitepaper on the future of its markets, PJM stressed the importance of bilateral contracting for retail ratepayer loads through their Load Serving Entities (LSEs) and Electric Distribution Companies (EDCs). PJM suggested this could be done either through an individual LSE hedging requirement or through a PJM-administered, long-term procurement, such as a tiered, multi-year capacity market. See Powering Reliability Through Market Design, PJM Interconnection, L.L.C. (May 6, 2026), https://www.pjm.com/-/media/DotCom/library/reports- notices/special-reports/2026/20260506-powering-reliability-through-market-design.pdf.
PDF page 8
8
complicated matters sometimes cannot be resolved and formal proceedings are initiated at the Commission. In addition to working through these disputes itself, based on the record submitted by the parties (as it typically does), the Commission should be more expansive in its use of settlement proceedings, providing guidance as to what it would find (un)acceptable, imposing tight deadlines on discussions (which can motivate parties to compromise), and encouraging settlement judges to actively engage in the process and discussions.13 This has worked well in the past. The original Reliability Pricing Model mechanism was developed as part of a Commission settlement process that was initiated and shaped by a prior Commission “guidance” order.14 Cost allocation issues in the wake of the GreenHat default also were resolved by settlement,15 and numerous PJM- related complaints filed in the wake of Winter Storm Elliott were resolved through a Commission- ordered expedited settlement process.16
The Commission also should consider more frequent use of designating non-decisional Commission staff on contentious policy matters. Non-decisional Commission staff can help PJM, the states and stakeholders to better understand Commission policy guidance and increase the likelihood that the resolution of conflicts or rule changes are ultimately found by the Commission to be just and reasonable. For instance, non-decisional staff played a key role in supporting PJM stakeholders when responding to Commission directed changes to PJM’s capacity market (i.e., Minimum Offer Price Rule).1713 A Commission Policy Statement could lay out how the Commission will make use of such mechanism, including if requested by the parties.14 See PJM Interconnection, L.L.C., 115 FERC ¶ 61,079, at P 176 (2006) (Initial Order on Reliability Pricing Model).15 See PJM Interconnection, L.L.C., 167 FERC ¶ 61,209, at PP 28-29 (2019).16 See Essential Power OPP, LLC, 183 FERC ¶ 61,163, at P 17 (2023).17 See Calpine Corp. v. PJM Interconnection, L.L.C., Notice of Designation of Commission Staff as Non-Decisional, Docket Nos. EL16-49-000, et al. (July 17, 2018); Calpine Corp. v. PJM Interconnection, L.L.C., 163 FERC ¶ 61,236 (2018).
PDF page 9
9
C. PJM’s Role: Using its Stakeholder Processes and Governance Mechanisms to
Address System Needs in a Timely and Efficient Manner
In Constellation’s experience, many of the complaints about PJM’s stakeholder process and its governance mechanisms are, in actuality, disagreements with PJM about its decisions to take, defer, or decline a particular action combined with a perception that competing views have not been adequately considered. The Commission’s goal cannot be for PJM to always agree or take unwavering direction from a particular entity or group of entities. That would be inconsistent with the core independence principle of Order No. 2000, which the Commission enforces in order to ensure that each RTO has “a decisionmaking process that is independent of control by any market participant or class of participants.”18 The same is true of states, which should participate extensively in RTO processes and, as discussed above, have the resources and organizational structures to do so. While improvements are needed in PJM to ensure that the views of states (as well as other stakeholders) are fully considered, it does not follow that states need or should be given filing rights under section 205 of the FPA or decisional control over PJM leadership.
1. PJM Leadership Matters Most
Whether an issue is raised for consideration by a stakeholder or PJM, PJM sets the agenda for its standing committees and task forces, where most of the substantive work is done. It is PJM’s responsibility, then, to use its stakeholder process to drive to decisions instead of delay. Stakeholders look to PJM to determine when an issue has been fully vetted, opportunities for collaboration or compromise have been exhausted, and it is time for PJM or stakeholders to move
18 Regional Transmission Organizations, Order No. 2000, 89 FERC ¶ 61,285, at slip op. 194 (1999), order on reh’g, Order No. 2000-A, 90 FERC ¶ 61,201 (2000), petitions for review dismissed sub nom. Pub. Util. Dist. No. 1 v. FERC, 272 F.3d 607 (D.C. Cir. 2001); see Duquesne Light Co., 189 FERC ¶ 61,181, at PP 24-25, 43-47 (2024), order on reh’g, 192 FERC ¶ 61,051, at PP 36-40 (2025) (Commission reiterating the importance of PJM independence), aff’d sub nom. PJM Transmission Owners v. FERC, Nos. 25-1064, 25-1100, 2026 U.S. App. LEXIS 16255 (D.C. Cir. June 5, 2026).
PDF page 10
10
forward with a decision. Undoubtedly, PJM has a difficult job balancing competing interests with respect to prioritization, timing, information, transparency, and direction, and there will always be stakeholders who would like additional time to discuss an issue or additional information before making a decision, sometimes with the intent of delaying a resolution of an issue rather than reaching consensus. PJM’s leadership can reduce gridlock by making decisions on a timely basis, communicating its decisions clearly, explaining its views of alternative positions, and sticking with its decisions through execution and over time.
When PJM strikes the balance right, working collaboratively with stakeholders, it can successfully and timely address some of the system’s most pressing needs. For example, the Interconnection Process Reform Task Force was able, in the span of roughly one year, to develop both significant reforms to the PJM interconnection process and a transition mechanism to address the backlog of existing interconnection requests. Guided by clear goals and timeframes from PJM, stakeholders were able to consider a range of PJM and stakeholder proposed solutions, agree on a package of reforms, and file that package at the Commission.19 This is how the stakeholder process should work.
Without clear guidance from PJM, the stakeholder process can instead flounder. For example, the Reserve Certainty Senior Task Force began its work in 2023 with a dauntingly long project plan timeline, has had numerous restarts as PJM has revised its deliverables, has failed to file one set of reforms that PJM deemed necessary, and is stumbling toward the finish line where it is unclear that any proposal will receive sector-weighted majority support. Even initiatives designed to be accelerated can, without PJM leadership, fail to meet their intended goals. Such
19 See Tariff Revisions for Interconnection Process Reform of PJM Interconnection, L.L.C., Docket No. ER22-2110- 000, at 2, 13 (June 14, 2022), accepted by PJM Interconnection, L.L.C., 181 FERC ¶ 61,162 (2022), order on reh’g, 184 FERC ¶ 61,006 (2023), aff’d sub nom. Hecate Energy LLC v. FERC, 126 F.4th 660 (2025).
PDF page 11
11
was the case with last year’s Critical Issue Fast Path (CIFP)-Large Load Addition stakeholder process which, after months of deliberation, led to a second CIFP process instead of a decision on issues that had been vetted fully.
2. Who Has Section 205 Filing Rights Is a Red Herring
Some nevertheless argue that PJM’s section 205 rights should be expanded, pointing to a lack of Member endorsement leading to gridlock. As discussed above, PJM already has section 205 filing rights over resource adequacy, generator retirements and replacements, and capacity market rule changes which have been the most contentious issues in PJM particularly for the states. Dissatisfaction over PJM’s actions and inactions on these issues has more to do with how PJM is addressing (or not) feedback received than who has the right to propose a rule change under section 205. And while it is true that PJM needs Member endorsement to file an energy market rule change under section 205, the lack of stakeholder approval has not stopped PJM in the past from proceeding with filings under section 206 when its leadership concluded that a change was necessary despite stakeholders not reaching the consensus necessary for PJM to file under section 205.20
Others argue that states should be given section 205 filing rights, but that would be inconsistent with the very structure of the Federal Power Act. Utilities providing jurisdictional service have filing rights, and the Commission reviews proposed changes to ensure they are just and reasonable. The same is true for state regulation of utilities. If either the Commission or a state commission desires to change a tariff or market rule, it can initiate its own proceeding to investigate if that change is needed. It would be unreasonable to give states more authority over
20 See supra note 4.
PDF page 12
12
filings made by Commission-jurisdictional RTOs than the Commission itself has, or more than states have over their own utilities.21
If the Commission nonetheless believes that something has changed that now renders
PJM’s existing filing rights over market rules unjust, unreasonable and unduly preferential, then it is generators who should receive additional authority to expedite section 205 filings proposing changes to those rules. Generators are the only entities providing capacity, energy, and related jurisdictional services under the FPA. To the extent generators ceded any of their rights under section 205 in agreeing to participate in PJM, they cannot be forced to further cede those rights through other changes to the filing rights structure in PJM.22
3. Board Member Selection Must Remain Independent
Finally, it is essential that PJM’s Board member selection process remain independent of
undue influence from any particular interest.23 PJM’s existing selection process is consistent with Commission precedent and welcomes input, including potential nominees, from all interested parties.24 This is a healthy process that is fair to all Members and is consistent with approaches used in other regions.
21 Some incorrectly point to “jump ball” rights in New England as an example of states having section 205 filing rights. In reality, those “jump ball” rights are held by the New England Power Pool, which is an association of representatives from six sectors of the electricity industry: generators, suppliers, transmission owners or utilities, end users, publicly owned entities, and alternative resources. See Corporate Governance, ISO New England Inc., https://www.iso-ne.com/about/corporate-governance. In MISO and SPP, states have limited rights to require or otherwise request the RTO to submit section 205 filings addressing resource adequacy and transmission cost allocation. That authority is tailored to the particular regulatory structures of those regions, which are dominated by vertically integrated utilities with states engaging regularly in integrated resource planning.22 With respect to substantive capacity market matters, PJM only has authority to make filings under section 205 to the extent such authority has been contracted to it. But as noted, PJM cannot force those providing jurisdictional services to provide PJM with even more of their section 205 rights.23 See supra note 19.24 PJM Nominating Committee offers the opportunity for any interested person to submit candidates directly to an independent consultant (currently, Korn Ferry International). See Nominating Committee, PJM Interconnection, L.L.C., https://www.pjm.com/committees-and-groups/committees/nc; Operating Agreement §§ 7.1-7.2.
PDF page 13
13
Some states in PJM have requested a more formal role in Board member selections. Giving any group, whether states or anyone else, an outsized role in Board member selection could undermine the independence of the Board and PJM as an organization. Instead, states can and should make their views known about potential Board members by taking advantage of existing opportunities to engage. This could include coordinating efforts by developing a list of suggested nominees, perhaps through OPSI or through the formation of nomination advisory group consisting of state-designated representatives.
Relatedly, it is important that the Board is immune from political pressure and has all the information it needs in making decisions. To ensure Board independence is maintained, PJM stakeholders and the Commission should evaluate whether Board terms should be lengthened, and whether substantive criteria should be adopted for removing Board members, to promote well- informed Board decisions that are immune from political influence. In addition, to support the Board’s consideration of complicated policy decisions, the Board should be given access to input from third-party market experts when complex technical matters are being considered.25
II. CONCLUSION
Thank you for the opportunity to address the Commission regarding potential PJM governance reforms. Constellation looks forward to working with the Commission, PJM, its stakeholders, and that states as we evaluate and implement improvements to existing processes to make participation more effective while supporting PJM’s leadership and independence.
July 14, 2026
25 Improvements could also include returning the Liaison Committee meetings to being entirely in-person and separate from the Annual Meeting and/or adding networking receptions at each Board meeting where there isn’t a Liaison Committee meeting.
PDF page 14
APPENDIX 1
State Entity Involvement in a Sampling of Recent CIFP Proceedings
Critical Issue Fast Path - Reliability Backstop Procurement / Connect & Manage
1
Written Comments - Delaware Public Service Commission
7.2.2026
2
Written Comments - VA SCC and Data Center Coalition
6.30.2026
3
Written Comments - West Virginia Public Service Commission 6.30.2026
4
Written Comments - Virginia Chief Energy Officer
6.30.2026
5
Written Comments - DC DOEE
6.30.2026
6
Written Comments - PJM Governors Collaborative
6.25.2026
7
Written Comments - Maryland Delegate Lorig Charkoudian on behalf of NCEL
6.23.2026
8
Item 02C - Joint Consumer Advocates - C&M and RBP - Executive Summary 6.23.2026
9
Item 03I - Joint Consumer Advocates Presentation
6.5.2026
11
Item 02K - Joint Consumer Advocates Presentation
5.1.2026
12
OPSI Reliability Backstop Procurement Feedback
4.27.2026
Critical Issue Fast Path - Reliability Backstop Procurement / Connect & Manage, PJM Interconnection, L.L.C., https://www.pjm.com/committees-and-groups/cifp-rbp (last visited July 13, 2026).
PDF page 15
2
Critical Issue Fast Path - Large Load Additions
1
Item 02E - PJM Legislators and NRDC Package - Executive Summary 11.18.2025
2
Item 02F - Joint Consumer Advocates Package - Executive Summary 11.17.2025
3
Item 02D - Data Center Coalition Governors Exelon and PPL Package
- Executive Summary
11.14.2025
4
Item 03A - Pennsylvania OCA Proposal
11.7.2025
5
Item 03B - State Legislators Collaborative Proposal - Updated 11.7.2025
6
Item 04H - Joint DCC Governors and Exelon Proposal - Updated 11.6.2025
7
Item 04H - Joint DCC and Governors Proposal
11.3.2025
8
Item 04D - Maryland OPC Proposal
11.3.2025
9
Item 03B - State Legislators Collaborative Proposal 11.3.2025
10
Item 03H - Maryland Office of Peoples Counsel Proposed Options 10.13.2025
11
PA, NJ, MD, & IL Governors Letter
8.29.2025
12
Pennsylvania Office of Consumer Advocate Comments
8.29.2025
13
Delaware Public Service Commission Comments
8.29.2025
14
New Jersey Division of Rate Counsel Comments
8.29.2025
15
Maryland Office of People’s Counsel Comments
8.29.2025
16
Illinois Office of the Attorney General Comments
8.29.2025
17
Pennsylvania Public Utility Commission Comments
8.29.2025
18
Delaware Division of the Public Advocate Comments
8.29.2025
Critical Issue Fast Path - Large Load Additions, PJM Interconnection, L.L.C., https://www.pjm.com/committees-and-groups/cifp-lla (last visited July 13, 2026).
PDF page 16
APPENDIX 2
State Entities Letters to the PJM Board from 2025 and 2026
2026
Date
1
Public Utilities Commission of Ohio Letter Regarding CIFP Stage 4 Connect and Manage PDF
7.8.2026
2
VA SCC and Data Center Coalition Letter Regarding CIFP – Connect & Manage / Reliability Backstop Procurement PDF
6.30.2026
3
WV PSC Letter Regarding Connect & Manage Proposal PDF 6.30.2026
4
DC Department of Energy and Environment Letter Regarding PJM’s CIFP-C&M / RBP Proposal PDF
6.25.2026
5
PJM ICC, PA OCA, IL CUB Letter Regarding Positioning States for Success in Retail Cost Allocation PDF
6.23.2026
6
Virginia Chamber of Commerce Letter Regarding Valley Link Project PDF
6.19.2026
7
PJM Legislators’ Collaborative Letter Regarding Reliability Backstop Procurement and Connect & Manage Proposals PDF
6.15.2026
8
PA State Senator Yaw Letter Regarding PJM’s Powering Reliability Through Market Design Paper PDF
5.26.2026
9
PJM Governors’ Collaborative Letter Regarding Reliability Backstop Procurement Objectives PDF
4.14.2026
10
WV State Senator Rose Letter Regarding Reliability Backstop Procurement PDF
4.14.2026
11
WV Delegate Bell Letter Regarding Reliability Backstop Procurement PDF
4.7.2026
12
NJBPU Letter Regarding Connect and Manage Issue Charge PDF 4.1.2026
13
IN Governor Letter Regarding Fixed Resource Requirement PDF 3.20.2026
14
PJM State Legislators Collaborative Letter Regarding Reliability Backstop Procurement PDF
3.19.2026
15
KY Governor Letter Regarding PJM Governance and Fixed Resource Requirement PDF
3.17.2026
16
OH Governor Letter Regarding Ensuring an Abundant, Affordable, and Reliable Energy Supply PDF
2.18.2026
17
IL, NJ Governors’ Letter Regarding the Expedited Interconnection Track Proposal PDF
2.17.2026
18
PA Governor Shapiro Letter Regarding BRA Price Collar Extension PDF
2.11.2026
PDF page 17
219
NECL Letter Regarding Prioritization of Issues in the PJM Board’s Decisional Letter on Critical Issue Fast Path (CIFP) - Large Load Additions PDF
2.11.2026
20
Letters Regarding the Price Collar: OPSI PDF
2.3.2026
21
PAPUC Letter Regarding 2025 RTEP Window 1 MAAC Regional Cluster Competitive Solution 2025-W1-237 PDF
1.27.2026
22
PA OCA Letter Regarding RTEP Project 237 PDF
1.21.2026
23
IL, NJ Governors’ Letter Regarding National Energy Dominance Council and 13 Governors’ Statement of Principles PDF
1.21.2026
24
CAPS Letter Regarding Consumer Advocate Voting on the SMECO proposal in CIFP-Large Load Addition PDF
1.5.2026
2025
25
Several Governors' Letter Regarding Critical Issue Fast Path – Large Load Additions PDF
12.3.2025
26
Illinois Governor Pritzker Letter Regarding Critical Issue Fast Path – Large Load Additions PDF
11.19.2025
27
PJM Legislators’ Collaborative Letter Regarding Critical Issue Fast Path – Large Load Additions PDF
11.18.2025
28
NJBPU Staff Regarding Critical Issue Fast Path – Large Load Additions PDF
11.18.2025
29
Congressional Letter Regarding Critical Issue Fast Path – Large Load Additions PDF
11.6.2025
30
IL Legislative Letter Regarding Critical Issue Fast Path – Large Load Additions PDF
11.6.2025
31
VA Delegate Sullivan Letter Regarding Data Center Heat Re- Use PDF
10.31.2025
32
Select PA Senate Members Letter Regarding Supporting Resource Adequacy and Affordability in the PJM Region PDF
10.15.2025
33
MD Office of Peoples’ Counsel Regarding Large Load Adjustments for the 2026 Load Forecast PDF
10.15.2025
34
Senator Fetterman Letter Regarding the Large Load Addition Critical Issues Fast Path (CIFP) Process PDF
10.13.2025
35
PJM Governors’ Collaborative Joint Statement of Intent PDF 9.25.2025
36
Governors of PJM Member States Letter to the PJM Board Related to the Nomination Committees Decision Regarding Open Seats on the Board of Managers PDF
9.11.2025
PDF page 18
337
OPSI Letter to the Board Regarding FPR and IRM Values PDF 9.8.2025
38
OPSI Letter Regarding Consultant Review of ELCC
Methodology PDF
8.28.2025
39
OH Stakeholders’ Letter Regarding Board Vacancies PDF 8.15.2025
40
PA, VA Governors’ Letter Regarding Board Candidates PDF 8.11.2025
41
Multiple Parties’ Letter Regarding Future Priorities PDF 7.24.2025
42
Consumer Advocates’ Letter Regarding Board Elections PDF 7.23.2025
43
OH Governor DeWine Letter Regarding Board Vacancies PDF 7.21.2025
44
Nine Governors’ Letter Regarding Board Vacancies PDF 7.17.2025
45
PA, VA Governors’ Letter to the Nominating Committee Regarding PJM Board Nominations PDF
6.25.2025
46
Five Governors’ Letter Regarding FERC Order 1920 PDF 5.28.2025
47
NJ Congressional Delegation Letter Regarding Electricity Prices in New Jersey PDF
5.5.2025
48
NJ Legislature Senate Select and Assembly Telecommunications and Utilities Committees’ Letter Regarding PJM’s March 28, 2025 Testimony PDF
4.22.2025
49
NJBPU President Guhl-Sadovy Letter Regarding Capacity Market Adjustments PDF
3.26.2025
50
MD OPC Letter Regarding Request for FPA 202(c) Order for Continued Operation of Brandon Shores and Wagner PDF 2.28.2025
51
NJ Division of Rate Counsel Letter Regarding NJ Basic Generation Service (BGS) Auction PDF
2.13.2025
52
PA Representative Kauffman Letter Regarding the Transource Project 9-A PDF
1.29.2025
53
MD Governor Moore Letter Regarding Capacity Market Price Cap PDF
1.21.2025
54
NJ Governor Murphy Letter Regarding Capacity Market Price Cap PDF
1.21.2025
55
CAPS Letter Regarding IMM Contract Renewal PDF
1.15.2025
56
PA Governor Shapiro Letter Regarding Capacity Market Price Cap PDF
1.13.2025
Board Communications, PJM Interconnection, L.L.C., https://www.pjm.com/about-pjm/who-we- are/pjm-board/public-disclosures (last visited July 13, 2026).