Pre-filed Statement of Mason Emnett, Senior Vice President for Public Policy for Constellation Energy Generation, LLC, for the PJM Governance and…
Text extracted from the eLibrary original (SHA-256 d34367bddc12d45c…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in AD26-7
Topics in the text: Reliability and curtailment · Registry access · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) PJM Governance and Stakeholder Reforms ) ) Docket No.Read this passage
I. COMMENTS
printed heading · Topic match: Reliability and curtailment
However, these or any other changes considered must preserve PJM’s independence as a regional transmission organization (RTO) and maintain consistency with the Federal Power Act (FPA).Read this passage Filed comments: Reliability and curtailment
A. The Role of States: Existing Participation and Additional Opportunities
printed heading · Topic match: Reliability and curtailment
Constellation recommends that PJM do this for the following topics at a minimum: • Proposed changes to market rules and planning processes; • Jurisdictional authority of PJM relative to the states; • Load forecasting, including obtaining input from state retail regulatory authorities on what large…Read this passage Filed comments: Reliability and curtailment
B. The Commission’s Role: Ensuring PJM Processes Are Effective
printed heading · Topic match: Cost allocation
Despite the best efforts of PJM and its stakeholders, 11 Bilateral contracting is generally beneficial as it supports competitive investment to meet resource adequacy goals and provides risk mitigation for supply and demand-side market participants.Read this passage Filed comments: Cost allocation
C. PJM’s Role: Using its Stakeholder Processes and Governance Mechanisms to
printed heading · Topic match: Reliability and curtailment
For example, the Interconnection Process Reform Task Force was able, in the span of roughly one year, to develop both significant reforms to the PJM interconnection process and a transition mechanism to address the backlog of existing interconnection requests.Read this passage Filed comments: Reliability and curtailment
II. CONCLUSION
printed heading · Topic match: Registry access
APPENDIX 1 State Entity Involvement in a Sampling of Recent CIFP Proceedings Critical Issue Fast Path - Reliability Backstop Procurement / Connect & Manage 1 Written Comments - Delaware Public Service Commission 7.2.2026 2 Written Comments - VA SCC and Data Center Coalition 6.30.2026 3 Written…Read this passage Filed comments: Registry access