Vistra Corp. submits Request for Clarification or, in the Alternative, Rehearing of the 06/18/2026 Order
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
Docket Nos. EL25-49-002
EL25-49-000
Docket No. AD24-11-001
Docket No. EL25-20-001
(consolidated)
Docket No. ER26-1479-000
REQUEST FOR CLARIFICATION OR, IN THE ALTERNATIVE, REHEARING
OF VISTRA CORP.
Pursuant to Section 313 of the Federal Power Act (“FPA”)1 and Rules 212 and 713 of the
Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission” or “FERC”),2 Vistra Corp. (“Vistra”) requests clarification, or in the alternative, rehearing, of the order issued by the Commission on June 18, 2026, in the above-captioned dockets (“June 2026 Order”).3 The Commission should clarify one narrow issue: when a secondary generator4 in a Co-Location Arrangement will continue to be available to PJM as a capacity resource and comply with its Day-Ahead Market offer requirement, that unit should not be required to delist its Capacity
1 16 U.S.C. § 825l(a).2 18 C.F.R. §§ 385.212, 385.713.3 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026) (“June 2026 Order”).4 In this context, a “secondary generator” refers to a generation unit that will serve the Co-Located Load only if the unit dedicated to providing primary service to the Co-Located Load is on an outage and only if the secondary generator is not committed in PJM’s energy market. However, Vistra notes that the same principles apply where the service to the Co-Located Load does not come entirely from a single unit, but instead comes from portions of each generation unit with the remaining MW from each unit being offered in PJM’s energy market.
PDF page 2
-2-
Interconnection Rights (“CIRs”). This clarification is necessary because the Commission’s June 2026 Order’s findings on CIR treatment did not address the circumstance in which the secondary generator complies with the Day-Ahead Market offer requirement. To the extent this clarification is denied, we seek rehearing.
SPECIFICATION OF ERRORS & STATEMENT OF ISSUES
1. The PJM tariff is ambiguous as to whether an Interconnection Customer must delist the CIRs of a secondary, interruptible unit that serves a Co-Located Load only when not committed in the PJM market. The Commission should clarify that the PJM tariff does not require an Interconnection Customer to delist the CIRs of a unit of a capacity resource that is capable of meeting both the emergency performance and the Day-Ahead Market must-offer requirements applicable to capacity resources, if the unit provides secondary, interruptible service to a Co- Located Load only when the unit is not committed in PJM’s energy market. Without clarification, the PJM tariff violates the FPA requirement that rates, terms, and conditions of Commission-jurisdictional service be just and reasonable and not unduly discriminatory or preferential. See 16 U.S.C. §§ 824d(a), 824d(b), 824e.
2. If the Commission declines to provide the clarification requested above, the June 2026 Order is arbitrary and capricious, in violation of the Administrative Procedure Act, because the Commission failed to engage in reasoned decisionmaking by failing to respond to Vistra’s objections to PJM’s proposal and failing to consider the important issues that Vistra raised. See 5 U.S.C. § 706(2)(A); Motor Vehicle Mfrs. Ass’n v. State Farm Mutual Automobile Ins. Co., 463 U.S. 29 (1983) (“State Farm”); Michigan v. EPA, 576 U.S. 743 (2015); Del. Div. of Pub. Advoc. v. FERC, 3 F.4th 461 (D.C. Cir. 2021); New England Power Generators Ass’n v. FERC, 881 F.3d 202 (D.C. Cir. 2018); TransCanada Power Mktg. Ltd. v. FERC, 811 F.3d 1 (D.C. Cir. 2015); Pub. Serv. Comm’n of Ky. v. FERC, 397 F.3d 1004 (D.C. Cir. 2005); Canadian Ass’n of Petroleum Producers v. FERC, 254 F.3d 289, 299 (D.C. Cir. 2001).
3. If the Commission declines to provide the clarification requested above, the June 2026 Order is arbitrary and capricious, in violation of the Administrative Procedure Act, because the Commission accepted tariff provisions that did not comply with its directive to clarify its interconnection procedures and agreements to increase certainty and consistency. See 5 U.S.C. § 706(2)(A); State Farm, 463 U.S. 29; FCC v. Fox Television Stations, Inc., 556 U.S. 502 (2009); PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 159 (2025).
4. If the Commission declines to provide the clarification requested above, the June 2026 Order is arbitrary and capricious, in violation of the Administrative Procedure Act and the Federal Power Act, to the extent the Commission accepted unjust, unreasonable, and unduly discriminatory tariff provisions that require a secondary, interruptible unit serving Co-Located Load only when not committed in PJM’s market (and only when the primary unit is not serving the Co-Located Load) to delist its CIRs to implement a Co-Location Arrangement. See 5 U.S.C. § 706(2)(A); 16 U.S.C. §§ 824d, 824e; State Farm, 463 U.S. 29.
PDF page 3
-3-
I. Background
Last December, the Commission found that the PJM tariff is unjust and unreasonable because it lacks sufficient clarity and consistency regarding how interconnection customers can serve Co-Located Load using existing generating facilities.5 The Commission directed PJM to propose tariff revisions to clarify that existing generators can use the necessary study process to modify their interconnection to reflect the addition of new Co-Located Loads.6 In connection with the addition of those Co-Located Loads, the Commission explained that “an existing generating facility may not begin serving Co-Located Load that is not Network Load until it has delisted its CIRs for the portion of the generating facility to be designated to serve any Co-Located Load that is not receiving [Network Integration Transmission Service (“NITS”)].”7
PJM proposed, on compliance, to require existing generators that seek to serve Co-Located Load to submit to PJM “the amount of reduction to [CIRs] to facilitate the Co-Located Load configuration.”8 PJM would then “assess the impact of the reduction in [CIRs]” in the necessary study process.9
Vistra filed a protest to PJM’s compliance filing, expressing concern that this tariff language remained ambiguous and therefore did not address the Commission’s directive to “clarify” its interconnection procedures to ensure that it is clear to existing generators how to
5 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 225 (2025) (“December 2025 Order”).6 Id. P 226. 7 Id. P 230 (emphasis added).8 PJM Interconnection, L.L.C., Transmittal Letter, Docket No. ER26-1479-000, at 26 (filed Feb. 23, 2026) (“PJM Transmittal Letter”); PJM, Open Access Transmission Tariff, pt. VIII, subpt. A, § 401 (Applications for Cycle Process Introduction) (5.0.0), § H(3)(b)(i)(c); id., pt. IX, subpt. G (Form of Necessary Studies Agreement) (3.0.0), attach. 1 (Planned Modifications).9 PJM, Open Access Transmission Tariff, pt. VIII, subpt. A, § 401 (5.0.0), § H(3)(b)(ii).
PDF page 4
-4-
interconnect in a Co-Location Arrangement.10 Specifically, Vistra explained, PJM’s proposed tariff language was ambiguous with regards to how a generator should calculate the amount by which its CIRs should be reduced. Vistra expressed concern that the tariff could be read to require generators to delist CIRs associated with any facility that would ever provide power to Co-Located Load, not just the portion of the facility designated to serve the Co-Located Load. Under this broad reading, an existing, two-unit generator with one 50 MW unit serving Co-Located Load on a firm basis and one 50 MW unit serving Co-Located Load on an interruptible, secondary basis only when the unit is not committed in PJM’s energy market would need to delist 100 MWs of CIRs. In other words, the generator would need to delist more CIRs than the portion the facility designated to serve the Co-Located Load on a firm basis.11
Vistra explained that this overly broad reading would be unduly discriminatory. There is no principled basis to treat a secondary unit in a Co-Location Arrangement differently from a generator with a non-firm or recallable commitment to sell power outside of PJM where both types of generators comply with all capacity resource obligations, including the Day-Ahead Market must-offer requirement.12 And as a matter of policy, there is no reason to ignore the valuable contribution secondary units can make to resource adequacy. Doing so would unnecessarily deprive the PJM region of available capacity.1310 Vistra Protest at 9-11.11 Id. at 9-10.12 Id. at 11-12.13 Id. at 10, 12.
PDF page 5
-5-
In the June 2026 Order, the Commission summarized some of Vistra’s arguments14 but did
not meaningfully respond to them. It simply “disagree[d] with Vistra and Constellation that capacity resources should not have to reduce their CIRs to serve Co-Located Load.”15 Its sole support for this conclusion was a cross-reference to its reasoning in an earlier section of the June 2026 Order, where it had addressed Constellation’s argument—which was distinct from any of Vistra’s arguments in critical ways. Specifically, Constellation argued that a generator serving Co-Located Load should retain its CIRs if “PJM can verify that the Co-Located Load has no
contractual right to energy from the generator during a capacity emergency and that the Co- Located Load has the ability either to curtail or draw on back-up power.”16 In that earlier section of the June 2026 Order, the Commission rejected Constellation’s argument, explaining that under the scenario Constellation laid out, “the Co-Located Generator would not be capable of meeting its entire capacity requirement,” which includes the requirement to offer its energy into the Day- Ahead Market throughout the delivery year. It found that Constellation’s proposal would allow the capacity resource to violate the must-offer requirement and thus provide an inferior capacity product for the same payment.1714 June 2026 Order, 195 FERC ¶ 61,209 at P 278 (“Vistra claims that PJM’s proposal would require existing generators to provide PJM with the amount of reduction to CIRs to facilitate the Co-Located Load configuration, which Vistra argues is vague and potentially overbroad because it could be read to require that generators include in their CIR reduction any portion of a facility that will ever provide power to a Co-Located Load. Vistra and DCC express concern that PJM’s proposal could require generators to delist more CIRs than necessary. Vistra further contends that allowing secondary units to provide occasional, interruptible service to Co-Located Load and to retain their CIRs would be consistent with the Tariff. Vistra and Constellation argue that capacity resources that serve Co- Located Load on an interruptible basis should not be required to delist CIRs.” (internal citations omitted)).15 Id. P 288 (citing id. PP 159-162); see also id. P 279 (accepting PJM’s proposed revisions to its Necessary Study process in part). The Commission rejected PJM’s proposed Form of Necessary Studies Agreement on different grounds. Id. P 288.16 Id. P 157.17 Id. P 161.
PDF page 6
-6-
II. Request for Clarification
Clarification of the June 2026 Order is necessary because it accepted unclear tariff language and failed to explain how that tariff language applies to the issue Vistra raised in its protest. Specifically, the December 2025 Order found that existing generators need only delist CIRs “for the portion of the generating facility to be designated to serve any Co-Located Load that is not receiving NITS.”18 PJM’s compliance filing failed to account for this specific Commission directive, instead generally leaving it to generators to submit “the amount of reduction to [CIRs] to facilitate the Co-Located Load configuration,”19 without specifying how that CIR reduction should be calculated. Rather than direct PJM to remedy that ambiguity in a manner consistent with the December 2025 Order, the Commission accepted PJM’s vague language and did not respond to the nuances of how that language should apply.
PJM’s tariff revisions—and the Commission order accepting them—are ambiguous on the critical point of how customers should calculate the reduction in CIRs. PJM’s tariff language risks being interpreted far too broadly, to require an Interconnection Customer to delist the CIRs for a capacity resource that is capable of meeting both the emergency performance and the Day-Ahead Market must-offer requirements, and that provides secondary, interruptible service to a Co- Located Load only when the unit is not committed in PJM’s energy market. Vistra respectfully requests that the Commission clarify that PJM’s tariff revisions should not be read in that manner. The Commission should clarify that an Interconnection Customer is not required to delist the
18 December 2025 Order, 193 FERC ¶ 61,217 at P 230 (emphasis added). 19 PJM Transmittal Letter at 26; PJM, Open Access Transmission Tariff, pt. VIII, subpt. A, § 401 (5.0.0), § H(3)(b)(i)(c); id. pt. IX, subpt. G, attach. 1.
PDF page 7
-7-
portion of the CIRs that meet the specifications described above when implementing a Co- Location Arrangement.
As discussed below, Vistra’s requested interpretation is consistent with the December 2025 Order. It is also consistent with the rest of the PJM tariff. Moreover, allowing this ambiguity to persist (or adopting a contrary interpretation) would be unjust and unreasonable and unduly discriminatory or preferential.
A. Vistra’s Requested Clarification Is Consistent With the December 2025 Order
and the Reasoning in the June 2026 Order
The Commission’s December 2025 Order set a clear standard: an existing generator must delist CIRs “for the portion of the generating facility to be designated to serve any Co-Located Load that is not receiving NITS.”20 PJM’s compliance proposal did not clearly implement that standard.
To “designate” something is “to indicate and set [it] apart for a specific purpose, office, or duty.”21 In the configuration Vistra described in its protest, a portion of the generating facility is clearly “set apart for [the] specific purpose” of serving the Co-Located Load. The remainder of the facility is not. The facility will continue offering the remaining generation into the Day-Ahead Market and injecting power onto the PJM grid when it receives a Day-Ahead Market award. Accordingly, the remaining capacity is not “designated” to serve the Co-Located Load, which means that under the December 2025 Order, it need not delist its CIRs.
20 December 2025 Order, 193 FERC ¶ 61,217 at P 230 (emphasis added).21 Designate, Merriam-Webster, https://www.merriam-webster.com/dictionary/designate (last visited July 20, 2026); accord Designate, Black’s Law Dictionary (12th ed. 2024) (“To choose (someone or something) for a particular job or purpose.”).
PDF page 8
-8-
The Commission’s June 2026 Order did not address this issue. Rather, it addressed Constellation’s (different) argument that a capacity resource serving Co-Located Load that can supply power to the grid during emergencies should not be required to delist its CIRs. The Commission’s reason for rejecting Constellation’s argument was that such a resource would be incapable of meeting its Day-Ahead Market must-offer obligation.22 That reasoning simply does not apply to the scenario Vistra presented, where the secondary, interruptible unit would meet its Day-Ahead Market must-offer obligation and would only serve Co-Located Load if doing so did not conflict with its commitment in PJM’s market (and would only do so as backup to the primary unit which is designated to serve the Co-Located Load). The Commission should clarify that these types of secondary units—that meet Day-Ahead Market must-offer requirements—should retain their CIRs.
B. Clarification Will Ensure that the PJM Tariff Is Just and Reasonable and Not Unduly Discriminatory or Preferential
Vistra’s requested clarification will ensure compliance with the FPA. As Vistra explained in its protest, requiring a secondary, interruptible unit that serves Co-Located Load only when it is not committed in PJM’s market (and only when the primary unit is not serving the Co-Located Load) to delist its CIRs would be unjust and unreasonable and unduly discriminatory or preferential.23
PJM already permits a class of resources with non-firm, non-network commitments to participate as capacity resources: generators with a non-firm or recallable commitments to external sales of capacity. While the tariff excuses capacity resources with firm commitments to external
22 See June 2026 Order, 195 FERC ¶ 61,209 at P 161.23 16 U.S.C. § 824
PDF page 9
-9-
sales of their capacity from the capacity market must-offer requirement,24 it does not excuse capacity resources with non-firm or recallable commitments to external sales from that requirement.25 The tariff thus recognizes that firm external sales pose unique concerns for meeting capacity market commitments, while non-firm or recallable external sales do not: generators with non-firm or recallable external sale commitments can be expected to perform normally in the capacity market. The same distinction applies here. Primary units that provide firm energy to a Co-Located Load clearly cannot also meet the obligations of PJM capacity resources, but secondary units that provide interruptible, backup energy to a Co-Located Load can. There is no principled basis to treat a secondary, interruptible unit in a Co-Location Arrangement differently from an external resource with a non-firm capacity commitment. Like generators with non-firm or recallable external sale commitments, secondary interruptible units can fulfill capacity resource obligations.26 Accordingly, the two classes of generators are similarly situated with respect to their ability to serve as capacity resources. Subjecting the two categories to different rules—specifically, allowing one to maintain CIRs while requiring the other to delist them—would amount to undue discrimination.
Further, it would be unjust and unreasonable to require a secondary, interruptible unit serving Co-Located Load only when not committed in PJM’s market (and only when the primary unit is not serving the Co-Located Load) to delist its CIRs to implement a Co-Location
24 See Vistra Protest at 10 (citing PJM, Open Access Transmission Tariff, attach. DD.6, § 6.6 (Offer Requirement for Capacity Resources) (3.0.0), §§ 6.6(a), (g); PJM Interconnection L.L.C., Constellation Request for Clarification or, in the Alternative, Rehearing, Docket Nos. EL25-49-000, et al., at 4 (filed Jan. 20, 2026)).25 See id. at 10-11 (citing PJM Interconnection, L.L.C., Mot. for Leave to Answer & Answer of PJM, Docket No. EL25-49-000, at 6 (filed Mar. 9, 2026)).26 See also PJM Interconnection, L.L.C., 190 FERC ¶ 61,088, at P 47 (2025) (accepting PJM proposal to account for reliability must-run resources as capacity resources because they “can reasonably be expected to perform, similar to capacity resources”).
PDF page 10
-10-
Arrangement. Just like resources with non-firm external capacity commitments, this type of secondary unit would be fully capable of meeting PJM’s capacity commitment requirements— including both the emergency performance requirement and the Day-Ahead Market must-offer obligation.
Requiring that secondary, interruptible unit to delist its CIRs would deprive the PJM capacity market of available capacity for no conceivable reason.27 For the vast majority of hours, the secondary, interruptible unit could offer into the Day-Ahead Market and provide energy when economic. In the remaining hours, the secondary, interruptible unit could offer into the Day-Ahead Market with an offer that reasonably reflects its non-firm commitment to the Co-Located Load such that the unit would be available to the system during emergencies. Such a resource has all the hallmarks of a capacity resource. It is patently unjust and unreasonable to deprive the capacity market of such a resource at a time when capacity market supply is tight, demand is rising, and PJM and the Commission face unprecedented pressure to address rising prices.28
In addition, forcing the secondary unit to delist its CIRs would disincentivize the Co- Located Load from providing demand response to the grid. Because the Co-Located Load would have to pay for the secondary unit’s capacity, there would be no reason for the Co-Located Load to choose to switch to its own back-up generator and make the secondary unit’s capacity available to the grid.
* * *
27 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,088 at P 47 (finding that including reliability must-run resources in the capacity market supply stack would “reflect the actual availability of resources in the PJM Region”).28 See id.
PDF page 11
-11-
The Commission should grant clarification that secondary, interruptible units in the scenario Vistra has outlined are not required to delist their CIRs. This clarification would comport with the December 2025 Order, and it would ensure that the PJM tariff remains just and reasonable and not unduly discriminatory or preferential.
III. Alternative Request for Rehearing
To the extent the Commission denies the clarification Vistra seeks above, Vistra requests rehearing of the June 2026 Order. In the absence of Vistra’s requested clarification, the Commission’s decision in the June 2026 Order was arbitrary, capricious, and otherwise not in accordance with law for three reasons.29 First, the Commission failed to respond to any of the objections Vistra raised on this issue in its protest. Second, the Commission erred in accepting a proposal that failed to comply with the Commission’s directive to “clarify” procedures for entering Co-Location Arrangements. Third, the Commission erred in accepting PJM’s proposal because it is unjust and unreasonable and unduly discriminatory or preferential in violation of the Federal Power Act to the extent it requires secondary, interruptible units to delist their CIRs. For those reasons, the Commission’s acceptance of PJM’s proposal violated its obligation to engage in reasoned decisionmaking and its duty under the FPA to ensure that the rates, terms, and conditions of transmission service are just and reasonable and not unduly discriminatory. To remedy these flaws, the Commission should grant rehearing and direct PJM to revise its tariff to specify that a secondary, interruptible unit serving a Co-Located Load only when not committed in PJM’s markets is not required to delist its CIRs to implement a Co-Location Arrangement.
29 5 U.S.C. § 706(2)(A).
PDF page 12
-12-
A. The Commission’s Failure to Respond to Vistra’s Objections Was Arbitrary and
Capricious
The June 2026 Order does not reflect the type of reasoned decisionmaking required by the Administrative Procedure Act.30 “It is well established” that the Administrative Procedure Act’s reasoned decisionmaking standard means that the “Commission must respond meaningfully to the arguments raised before it.”31 In responding to those arguments, the Commission may not “fail[] to consider an important aspect of the problem” it addresses.32 The June 2026 Order summarily dismissed Vistra’s arguments, without responding to them, by citing an inapposite discussion about an entirely distinct argument. That is squarely in the zone of arbitrary and capricious action.33
As detailed above,34 Vistra’s protest raised four distinct arguments about PJM’s proposal regarding reduction of CIRs. First, Vistra argued that PJM’s vague tariff language did not meet the directive in the December 2025 Order to “clarify” its interconnection procedures and agreements to ensure that existing generators know how to enter a Co-Location Arrangement.35 Rather than provide clarity, PJM’s proposal introduced ambiguity as to how CIR reductions should
30 See Motor Vehicle Mfrs. Ass’n v. State Farm Mutual Automobile Ins. Co., 463 U.S. 29, 43-44 (1983) (“State Farm”); Michigan v. EPA, 576 U.S. 743, 750 (2015).31 New England Power Generators Ass’n v. FERC, 881 F.3d 202, 210 (D.C. Cir. 2018) (cleaned up) (citing TransCanada Power Mktg. Ltd. v. FERC, 811 F.3d 1, 12 (D.C. Cir. 2015); Pub. Serv. Comm’n of Ky. v. FERC, 397 F.3d 1004, 1008 (D.C. Cir. 2005)); Canadian Ass’n of Petroleum Producers v. FERC, 254 F.3d 289, 299 (D.C. Cir. 2001) (“Unless the Commission answers objections that on their face seem legitimate, its decision can hardly be classified as reasoned.”).32 Del. Div. of Pub. Advoc. v. FERC, 3 F.4th 461, 469 (D.C. Cir. 2021) (citing State Farm, 463 U.S. at 43).33 See New England Power Generators Ass’n, 881 F.3d at 211 (“FERC’s responses to Petitioners' arguments below amounted to conclusory statements that dismissed Petitioners’ concerns without providing reasoned analysis.”); TransCanada Power Mktg., 811 F.3d at 12 (finding that Commission order that “simply never addressed the matter” raised by a party, and instead provided a “perplexing response” that did not actually address the party’s concern, was arbitrary and capricious).34 See supra Part I.35 Vistra Protest at 9-11.
PDF page 13
-13-
be calculated. Second, Vistra argued that requiring secondary, interruptible units that can meet the Day-Ahead Market must-offer requirement to delist their CIRs would be unduly discriminatory, treating those units differently from similarly situated capacity resources with non-firm or recallable commitments to sell power outside of PJM.36 Third, Vistra argued that allowing such secondary, interruptible units to maintain their CIRs is consistent with provisions of the PJM tariff distinguishing between generators with firm versus non-firm external capacity commitments for purposes of capacity market must-offer obligations.37 Fourth, Vistra argued that requiring secondary, interruptible units that can meet the Day-Ahead Market must-offer requirement to delist their CIRs would deprive ratepayers of generation that is generally available and could increase capacity prices.38
The Commission did not respond to a single one of these objections. It simply stated that it “disagree[d] with Vistra and Constellation that capacity resources should not have to reduce their CIRs to serve Co-Located Load.”39 As a threshold matter, Vistra did not argue in its protest that capacity resources, writ large, should not have to reduce their CIRs to serve Co-Located Load.40 The Commission’s only support for this “conclusory statement”41 was its cross-reference to an irrelevant discussion addressing Constellation’s request for rehearing of the December 2025 Order. In that irrelevant discussion, the Commission found that a resource that “would not be capable of meeting its entire capacity requirement,” including both its emergency performance
36 Vistra Protest at 11-12.37 Id. at 10-11.38 Id. at 10, 12.39 June 2026 Order, 195 FERC ¶ 61,209 at P 288.40 See TransCanada Power Mktg., 811 F.3d at 12 (finding that a Commission order was arbitrary and capricious where it did not actually address the concern raised in a comment it claimed to address).41 New England Power Generators Ass’n, 881 F.3d at 211.
PDF page 14
-14-
requirement and its Day-Ahead Market must-offer requirement, must delist its CIRs to serve Co- Located Load.42 The Commission’s reasoning there does not address Vistra’s protest because Vistra raised the issue with regards to a capacity resource that can meet both the emergency and its Day-Ahead Market obligations.
By declining to engage with or respond to Vistra’s objections, and by instead citing reasoning addressing a distinct issue, the Commission failed to “respond meaningfully to the arguments raised before it.”43 And in doing so, the Commission also entirely failed to consider several important aspects of the issues the June 2026 Order addressed.44
B. PJM’s Tariff Revisions Do Not Satisfy the Directive to “Clarify” its
Interconnection Procedures
In accepting PJM’s tariff revisions, the Commission departed from its directive in the December 2025 Order to “clarify” its interconnection procedures. The Commission must acknowledge and provide a reasoned explanation for a change in position.45 Because the Commission failed to do so here, it erred in accepting PJM’s proposal.
The fundamental problem that the Commission ordered PJM to remedy in the December 2025 Order was the tariff’s failure to address “with sufficient clarity or consistency” the rates, terms, and conditions of service applicable to interconnection customers serving Co-Located Load. These defects left customers “unable to determine what steps they must take to effectuate Co- Location Arrangements,” leading to “uncertainty,” “disparate treatment,” and “no consistent
42 June 2026 Order, 195 FERC ¶ 61,209 at P 161.43 New England Power Generators Ass’n, 881 F.3d at 210.44 See State Farm, 463 U.S. at 43.45 See FCC v. Fox Television Stations, Inc., 556 U.S. 502, 515-16 (2009).
PDF page 15
-15-
understanding” of customers’ responsibilities.46 The Commission thus directed PJM to “clarify its interconnection procedures and agreements to ensure that it is clear to both new and existing Interconnection Customers how to interconnect in a Co-Location Arrangement.”47 As discussed above, PJM’s tariff language governing reduction of CIRs does not satisfy this directive.48 It continues to leave customers in the dark about how to calculate the CIR reduction necessary to effectuate Co-Location Arrangements. Indeed, this vague language risks being read far too broadly, to require generators to include in their CIR reduction calculation even the CIRs associated with a secondary, interruptible unit, an unjust and unreasonable and unduly discriminatory result.49 In other words, the lack of clarity in the tariff will lead to precisely the types of problems the December 2025 Order told PJM to fix: uncertainty, disparate treatment, and inconsistent understandings of customers’ responsibilities.
Elsewhere in the June 2026 Order, the Commission rejected PJM’s proposed tariff provisions when they contained insufficient detail to provide clarity to customers to ensure that rates would be just and reasonable and not unduly discriminatory or preferential.50 But PJM’s tariff provisions addressing CIR reductions suffer from the same defect. The Commission therefore erred in not directing PJM to address that defect with respect to CIRs.51
46 December 2025 Order, 193 FERC ¶ 61,217 at P 159.47 December 2025 Order, 193 FERC ¶ 61,217 at P 161.48 See supra section II.A.49 See supra section II.50 See June 2026 Order, 195 FERC ¶ 61,209 at PP 283, 370; cf. id. P 280. 51 See Fox Television Stations, 556 U.S. at 515-16.
PDF page 16
-16-
C. It Is Unjust and Unreasonable and Unduly Discriminatory to Require a
Secondary, Interruptible Unit to Delist its CIRs
The FPA requires the Commission to ensure that rates, terms, and conditions for
jurisdictional services are just and reasonable and not unduly discriminatory or preferential.52 The Commission erred when it accepted PJM’s proposed tariff provisions because they violate that foundational standard.
As Vistra has explained, requiring a secondary, interruptible unit serving Co-Located Load only when not committed in PJM’s market (and only when the primary unit is not serving the Co- Located Load) to delist its CIRs to implement a Co-Location Arrangement is unjust and unreasonable and unduly discriminatory or preferential, in violation of the FPA.
First, as explained above,53 it is unduly discriminatory for PJM to require secondary, interruptible units to delist their CIRs. The PJM tariff permits generators with non-firm, recallable external sale commitments to serve as capacity resources.54 There is no principled distinction between those resources and secondary, interruptible units that would justify prohibiting secondary, interruptible units from also serving as capacity resources. Both types of generators are similarly situated with respect to their ability to fulfill all capacity resource obligations and their ability to perform when needed.55 Subjecting them to different rules—specifically, allowing one to maintain CIRs but requiring the other to delist them—is impermissible undue discrimination.
52 16 U.S.C. §§ 824d(a), 824d(b), 824e(a).53 See supra section II.B.54 See Vistra Protest at 10-11 (citing PJM Interconnection, L.L.C., Mot. for Leave to Answer & Answer of PJM, Docket No. EL25-49-000, at 6 (filed Mar. 9, 2026)).55 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,088 at P 47 (accepting PJM proposal to account for reliability must-run resources as capacity resources because they “can reasonably be expected to perform, similar to capacity resources”).
PDF page 17
-17-
Second, as explained above,56 it is unjust and unreasonable to require a secondary, interruptible unit serving Co-Located Load only when not committed in PJM’s market (and only when the primary unit is not serving the Co-Located Load) to delist its CIRs to implement a Co- Location Arrangement. This unit would be fully capable of meeting all of the performance requirements applicable to a capacity resource—including both the emergency performance requirement and the Day-Ahead Market must-offer obligation. Requiring it to delist its CIRs would deprive the PJM capacity market of available capacity at a time when PJM has no capacity to spare. Doing so would deprive the generation resource owner of its ability to provide capacity to PJM—and harm resource adequacy in PJM—for no conceivable reason, resulting in unjust and unreasonable rates.
IV. Conclusion
At a time when PJM’s capacity market is increasingly tight on supply, demand is rising rapidly, and PJM and the Commission face an affordability imperative, there is no reason to ignore the valuable contributions that secondary, interruptible units can make to resource adequacy and to affordability. Prohibiting these resources from supplying capacity to the PJM grid, when there is no technical or commercial limit on their ability to do so, will force PJM to procure unnecessary capacity.
The Commission can readily prevent that outcome by granting clarification on the narrow issue Vistra presents. Thus, the Commission can and should grant clarification that PJM’s tariff should not be read to require an Interconnection Customer to delist the CIRs of a unit that provides
56 See supra section II.B.
PDF page 18
-18-
secondary, interruptible service to a Co-Located Load only when it is not committed in PJM’s energy market.
In the alternative, the Commission should grant rehearing of its acceptance of PJM’s tariff revisions regarding CIR reductions in the June 2026 Order. For the reasons discussed above, requiring such a unit to delist its CIRs would be unjust and unreasonable and unduly discriminatory. Accordingly, the Commission should grant rehearing and direct PJM to revise its tariff to specify that a secondary, interruptible unit serving a Co-Located Load only when not committed in PJM’s markets is not required to delist its CIRs to implement a Co-Location Arrangement.
Respectfully submitted,
/s/ J. Arnold Quinn
J. Arnold Quinn
SVP of Regulatory Policy
Andrew Weinstein
Vice President, FERC Market Policy
Vistra Corp.
325 7th Street NW
Suite 520
Washington, DC 20004
arnie.quinn@vistracorp.com
andrew.weinstein@vistracorp.com
________________
Nicholas M. Gladd
Sarah Greenberg
Rachel Neuburger
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006
(617) 598-7871
ngladd@wsgr.com
sgreenberg@wsgr.com
rneuburger@wsgr.com
Counsel for Vistra Corp.
Dated: July 20, 2026
PDF page 19
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary of the Commission in these proceedings.
Dated: July 20, 2026
Washington, D.C.
/s/ Rachel Neuburger
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006