ER26-1479-001 · 2026-07-20 · Vistra Corp.

Vistra Corp. submits Request for Clarification or, in the Alternative, Rehearing of the 06/18/2026 Order

Text extracted from the eLibrary original (SHA-256 0e013dcedf25ea1e…). Download the original from the official source.

Contents · 9 sections
  1. I. Background p. 3
  2. II. Request for Clarification p. 6
  3. A. Vistra’s Requested Clarification Is Consistent With the December 2025 Order p. 7
  4. B. Clarification Will Ensure that the PJM Tariff Is Just and Reasonable and Not p. 8
  5. III. Alternative Request for Rehearing p. 11
  6. A. The Commission’s Failure to Respond to Vistra’s Objections Was Arbitrary and p. 12
  7. B. PJM’s Tariff Revisions Do Not Satisfy the Directive to “Clarify” its p. 14
  8. C. It Is Unjust and Unreasonable and Unduly Discriminatory to Require a p. 16
  9. IV. Conclusion p. 17

Read topic-matched comments in ER26-1479

Topics in the text: Connecting load and generation · Filing procedure · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

The PJM tariff is ambiguous as to whether an Interconnection Customer must delist the CIRs of a secondary, interruptible unit that serves a Co-Located Load only when not committed in the PJM market.
Read this passage Filed comments: Connecting load and generation

I. Background

printed heading · Topic match: Connecting load and generation

It found that Constellation’s proposal would allow the capacity resource to violate the must-offer requirement and thus provide an inferior capacity product for the same payment.17 14 June 2026 Order, 195 FERC ¶ 61,209 at P 278 (“Vistra claims that PJM’s proposal would require existing generators…
Read this passage Filed comments: Connecting load and generation

II. Request for Clarification

printed heading · Topic match: Connecting load and generation

PJM’s tariff language risks being interpreted far too broadly, to require an Interconnection Customer to delist the CIRs for a capacity resource that is capable of meeting both the emergency performance and the Day-Ahead Market must-offer requirements, and that provides secondary, interruptible…
Read this passage Filed comments: Connecting load and generation

A. Vistra’s Requested Clarification Is Consistent With the December 2025 Order

printed heading · Topic match: Connecting load and generation

The Commission’s reason for rejecting Constellation’s argument was that such a resource would be incapable of meeting its Day-Ahead Market must-offer obligation.22 That reasoning simply does not apply to the scenario Vistra presented, where the secondary, interruptible unit would meet its Day-Ahead…
Read this passage Filed comments: Connecting load and generation

B. Clarification Will Ensure that the PJM Tariff Is Just and Reasonable and Not

printed heading · Topic match: Connecting load and generation

Because the Co-Located Load would have to pay for the secondary unit’s capacity, there would be no reason for the Co-Located Load to choose to switch to its own back-up generator and make the secondary unit’s capacity available to the grid. * * * 27 See PJM Interconnection, L.L.C., 190 FERC ¶…
Read this passage Filed comments: Connecting load and generation

III. Alternative Request for Rehearing

printed heading · Topic match: Filing procedure

Alternative Request for Rehearing To the extent the Commission denies the clarification Vistra seeks above, Vistra requests rehearing of the June 2026 Order.
Read this passage Filed comments: Filing procedure

A. The Commission’s Failure to Respond to Vistra’s Objections Was Arbitrary and

printed heading · Topic match: Connecting load and generation

The Commission’s Failure to Respond to Vistra’s Objections Was Arbitrary and Capricious The June 2026 Order does not reflect the type of reasoned decisionmaking required by the Administrative Procedure Act.30 “It is well established” that the Administrative Procedure Act’s reasoned decisionmaking…
Read this passage Filed comments: Connecting load and generation

B. PJM’s Tariff Revisions Do Not Satisfy the Directive to “Clarify” its

printed heading · Topic match: Connecting load and generation

The Commission must acknowledge and provide a reasoned explanation for a change in position.45 Because the Commission failed to do so here, it erred in accepting PJM’s proposal.
Read this passage Filed comments: Connecting load and generation

C. It Is Unjust and Unreasonable and Unduly Discriminatory to Require a

printed heading · Topic match: Connecting load and generation

EL25-49-000, at 6 (filed Mar. 9, 2026)). 55 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,088 at P 47 (accepting PJM proposal to account for reliability must-run resources as capacity resources because they “can reasonably be expected to perform, similar to capacity resources”). -17- Second, as…
Read this passage Filed comments: Connecting load and generation

IV. Conclusion

printed heading · Topic match: Connecting load and generation

Conclusion At a time when PJM’s capacity market is increasingly tight on supply, demand is rising rapidly, and PJM and the Commission face an affordability imperative, there is no reason to ignore the valuable contributions that secondary, interruptible units can make to resource adequacy and to…
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

printed heading

Dated: July 20, 2026 Washington, D.C. /s/ Rachel Neuburger Wilson Sonsini Goodrich & Rosati 1700 K Street NW Fifth Floor Washington, DC 20006