ER26-1479-001 · 2026-07-20 · Exelon Corporation, The FirstEnergy Transmission Companies

Exelon Corporation and FirstEnergy Service Company submit Request for Rehearing of the 06/18/2026 Order

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.

)
Docket No. EL25-49-002
Docket No. EL25-49-000

Large Loads Co-Located at Generating
Facilities
)
Docket No. AD24-11-001
Constellation Energy Generation, LLC

v.

PJM Interconnection, L.L.C.

PJM Interconnection, L.L.C.
)

)

)

)
Docket No. EL25-20-001
(consolidated)

Docket No. ER26-1479-000

REQUEST FOR REHEARING OF EXELON CORPORATION AND
FIRSTENERGY SERVICE COMPANY

Pursuant to Federal Power Act (“FPA”) section 3131 and Rule 7132 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”), Exelon Corporation3 and FirstEnergy Service Company4 (together “Exelon and FirstEnergy”) request rehearing of the Commission’s ruling that extends the new forms of transmission service that were ordered for Co-Located Load to also be made available to load served by Behind-the- Meter Generation (“BTMG”).5 The Commission’s June 18, 2026 Order determination that new

1
16 U.S.C. § 825l(a).
2
See 18 C.F.R. § 385.713.
3 Exelon Corporation submits this rehearing request on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company (“ComEd”), Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company
4 FirstEnergy Service Company submits this rehearing request as agent for its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, Keystone Appalachian Transmission Company, The Potomac Edison Company, Monongahela Power Company and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Transmission Companies”).
5 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026) (“June 18, 2026 Order”).

PDF page 2

2

transmission service options must be provided for load served by BTMG are arbitrary and capricious and not based upon reasoned decision making.

The June 18, 2026 Order addressed rehearing requests relating to the Commission’s December 18, 2025 Order6 in this proceeding, concerning the Commission’s determination that the existing Network Service in the PJM Tariff is unjust and unreasonable for service to Co- Located Load and requiring that three new forms of service be made available for Co-Located Load: Firm Contract Demand Network Service (“FCD”); Non-Firm Contract Demand Network Service (“NFCD”); and Interim Network Service. Exelon and FirstEnergy sought rehearing of that order on January 16, 2026, which rehearing request was denied by operation of law when the Commission did not rule by February 17, 2026. Exelon and FirstEnergy have submitted Petitions for Review in the Third Circuit Court of Appeals on the issues where their rehearing was rejected.7 The June 18, 2026 Order does not alter the Commission’s finding on the issues pending in Exelon and FirstEnergy’s submitted petitions for review; Exelon and FirstEnergy are not addressing those issues further here, and the issues are instead before the Third Circuit.

In addition to rejecting Exelon and FirstEnergy’s rehearings of the December 18, 2025 Order, the June 18, 2026 Order made certain new findings relating to BTMG. In the June 18, 2026 Order, the Commission erroneously extended the availability of its new FCD, NFDC, and Interim Network Service offerings to loads served by BTMG. This rehearing addresses only the extension of the new service options to load served by BTMG.

In addition to addressing rehearings, the June 18, 2026 Order also addressed filings that were made in compliance with the December 18, 2025 Order in order to implement the new forms

6 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18, 2025 Order”).
7 Exelon Corp., Case No. 26-1901 (3rd Cir.); American Transmission Systems, Inc., Case No. 26-2494 (3rd Cir.).

PDF page 3

3

of transmission service. This rehearing does not address the compliance issues in the June 18, 2026 Order which Exelon and FirstEnergy are instead addressing in other pleadings. To be clear, the purported purpose of the Commission’s rulings at issue here is to improve the availability of service to new BTMG-served customers and ensure that service to such customers does not impose unnecessary costs on existing customers. But the creation of these new forms of transmission service will not hasten or improve service and instead merely reduces transmission charges for BTMG-served customers at the expense of other customers. The Commission’s order does not resolve any actual inadequacy in the PJM Tariff and instead is merely an unreasonable and unduly preferential gift to a favored class.

I. Statement of Issues/Specification of Error.
In accordance with 18 C.F.R. § 385.713(c)(1) and (2), Exelon and FirstEnergy provide the following specification of errors and statement of issues, including citations to representative Commission and judicial precedent.

1. The Burden Under FPA Section 206 Has Not Been Met: The Existing Rate Has Not Been Shown to Be Unjust and Unreasonable. See 16 U.S.C. § 824e(a); Pub. Citizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021) (explaining that “[t]he burden of proving” that a rate is unjust or unreasonably is placed on “the party that initiated the proceeding”).

a. There is No Evidence In the Record That Loads Served by BTMG Are
Unable to Obtain Reliable, Timely, and Reasonably Priced Service
Using the Existing Network Service Construct. Therefore, the
Commission
Fails
To
Satisfy
the
Requirement
Under
the
Administrative Procedure Act That Its Decision Be Supported With
Substantial Evidence.
i. The Administrative Procedure Act (“APA”) requires the
Commission to “examine the relevant data and articulate a
satisfactory explanation for its action including a ‘rational
connection between the facts found and the choice made,’” and
to base its decision on substantial evidence; because FERC has
failed to do so, its decision is arbitrary and capricious. Motor

PDF page 4

4

Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co. (“State Farm”), 463 U.S. 29, 43 (1983) (citation omitted); see Fla. Gas Transmission Co. v. FERC (“Florida Gas”), 604 F.3d 636, 639 (D.C. Cir. 2010) (“[T]he Commission ‘must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record.’”) (citation omitted); Consol. Edison Co. of N.Y. v. NLRB, 305 U.S. 197, 229 (1938) (explaining that substantial evidence means “more than a mere scintilla”); see also 5 U.S.C. § 706.

ii. The PJM Tariff provides two transmission service options (Network Integration Transmission Service and Point-to-Point Transmission Service) and includes provisions to explain how those services work and how Network Customers will be Served. See PJM Tariff at §§ 31.1, 31.2, 31.3, 31.6 and 32; see also generally PJM Tariff , OATT Definitions.

iii. To the extent that parties have argued they are unable to interconnect or are experiencing delays, that is false and any delay is of their own making. See, e.g., Exelon Dec. 8, 2025 Comments at 3-4; Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, Docket No. EL25-20, at Ex. 5 Attach 1 (providing Exelon’s Nov. 12, 2024 Letter). FERC arbitrarily and capriciously disregarded evidence in the record that Network Service under the current tariff is feasible and has been used for co-location arrangements. Compare PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024) and PJM Interconnection, L.L.C., Docket No. ER24-2172-000, Application Attach. A, Amended ISA, at Schedule F, Part F.4 (June 1, 2024), with Press Release, Talen Energy, Talen Energy Expands Nuclear Energy

Relationship
with
Amazon
(June
11,
2025),
https://ir.talenenergy.com/news-releases/news-release- details/talen-energy-expands-nuclear-energy-relationship-amazon. See also Exelon Dec. 8, 2025 Comments at 6.

iv. Ignoring data in the record regarding the ability of large loads to interconnect to the transmission system violates the APA and renders FERC’s decision arbitrary and capricious. See State Farm, 463 U.S. at 43.

v. There is no evidence in the record that the cost of Network Service adversely impacts loads served by BTMG. Nor is there evidence to support that existing Network Service imposes unnecessary upgrades on all customers. Nor is there evidence that new forms of transmission service will allow for faster interconnection. See Florida Gas, 604 F.3d at 639 (“[T]he Commission ‘must be able to demonstrate that it has made a

PDF page 5

5

reasoned decision based upon substantial evidence in the record.’”) (citation omitted); Consol. Edison Co. of N.Y., 305 U.S. at 229 (explaining that substantial evidence means “more than a mere scintilla”); see also 5 U.S.C. § 706.

vi. The Commission has not met its burden under FPA section 206 because it acknowledges that the existing transmission services remain just and reasonable options. See June 18, 2026 Order, 195 FERC ¶ 61,209 at P 195 (finding Network Service charged on a gross demand basis to be “one just and reasonable transmission service option”).

b. The Commission Did Not Engage in Reasoned Decision Making Because It Did Not Explain its Departure from FERC Precedent Regarding the Reasonableness of the Existing Network Service. See F.C.C. v. Fox Television Stations, Inc., 556 U.S. 502, 515 (2009) (“[T]he requirement that an agency provide reasoned explanation for its action would ordinarily demand that it display awareness that it is changing position. An agency may not, for example, depart from a prior policy sub silentio or simply disregard rules that are still on the books.”); New England Power Generators Ass’n v. FERC, 881 F.3d 202, 211 (D.C. Cir. 2018) (“Although case-by-case adjudication sometimes results in decisions that seem at odds but can be distinguished on their facts, it is the agency’s responsibility to provide a reasoned explanation of why those facts matter.”); W. Deptford Energy, LLC v. FERC, 766 F.3d 10, 20 (D.C. Cir. 2014) (“It is textbook administrative law that an agency must ‘provide[ ] a reasoned explanation for departing from precedent or treating similar situations differently,’ and Commission cases are no exception.”) (citations omitted); Cal. Pub. Utils. Comm’n v. FERC, 879 F.3d 966, 977 (9th Cir. 2018) (“FERC departed from this policy without acknowledgment or explanation. This departure was arbitrary and capricious.”); Sw. Airlines Co. v. FERC, 926 F.3d 851, 856 (D.C. Cir. 2019) (“‘A full and rational explanation’ becomes ‘especially important’ when, as here, an agency elects to ‘shift [its] policy’ or ‘depart[ ] from its typical manner of’ administering a program. . . . [FERC] must at least ‘acknowledge’ its seemingly inconsistent precedents and either offer a reason ‘to distinguish them’ or ‘explain its apparent rejection of their approach’ . . . . But however the agency justifies its new position, what it may not do is ‘gloss[ ] over or swerve[ ] from prior precedents without discussion.’”) (most alterations in original) (citations omitted); see also 16 U.S.C. § 824d(b) (prohibiting a public utility from making or granting an “undue preference or advantage” or from maintaining “any unreasonable difference in rates, charges, service, facilities, or in any other respect, . . . as between classes of service”); TransCanada Power Mktg. Ltd. v. FERC, 811 F.3d 1, 12–13 (D.C. Cir. 2015) (remanding because FERC did not adequately explain its position).

PDF page 6

6

i. The Commission has a long-standing policy of rejecting attempts by network transmission customers to avoid paying their load ratio share of system cost. See, e.g., Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 171 FERC ¶ 61,237 at PP 40–41, denying clarification & addressing arguments raised on reh’g, 173 FERC ¶ 61,043 at PP 13–14 (2020); see Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888- A, FERC Stats. & Regs. ¶ 31,048, 62 Fed. Reg. 12,274, 12,324 (Mar. 14, 1997), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002); see also, e.g., Fla. Mun. Power Auth. v. FERC, 411 F.3d 287 (D.C. Cir. 2005); Fla. Power & Light Co., 113 FERC ¶ 61,290 (2005), aff’d on rehearing, 116 FERC ¶ 61,012 (2006), aff’d on appeal sub nom. Fla. Mun. Power Agency v. FERC, 264 F. App’x 4 (D.C. Cir. 2008) (per curiam); Idaho Power Co., 106 FERC ¶ 61,329 (2004); Ameren Servs. Co. v. Prairieland Energy Inc., 131 FERC ¶ 61,125 (2010); Ariz. Pub. Serv. Co., 151 FERC ¶ 61,191 (2015); Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890, 119 FERC ¶ 61,119 (“Order No. 890”), order on reh’g, Order No. 890-A, 121 FERC ¶ 61,297 (2007), order on reh’g, Order No. 890-B, 123 FERC ¶ 61,299 (2008), order on reh’g, Order No. 890- C, 126 FERC ¶ 61,228, order on clarification, Order No. 890-D, 129 FERC ¶ 61,126 (2009).

c. The Loads Rely Upon the Entire Embedded Transmission System to Serve Their Full Gross Load. Therefore, FERC’s Decision is Arbitrary and Capricious Because the Embedded Transmission System Costs Should Be Charged For Those Transmission Services. See Decl. of David Weaver, PE, Attachment 1 to Exelon Comments, Docket No. EL25- 20 (Dec. 12, 2024); see also PJM Interconnection, L.L.C., Docket No. EL25-20-000, Indicated TOs June 3, 2025 Answer, Declaration of Danielle S. Powers, at P 29.

i. The Commission’s failure to consider the benefits of grid interconnection makes the June 18, 2026 Order arbitrary and capricious. See State Farm, 463 U.S. at 43.

2. The Burden Has Not Been Met Under FPA Section 206: FERC’s Replacement Rate is Not Just and Reasonable. See 16 U.S.C. § 824e(a); Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 663 (D.C. Cir. 2017) (“If the Commission finds that a rate is ‘unjust, unreasonable, unduly discriminatory or preferential, the Commission shall determine the just and reasonable rate ... and shall fix the same

PDF page 7

7

by order,’” and “[i]t is the Commission’s job—not the petitioner’s—to find a just and reasonable rate.”) (alterations in original) (citation omitted); Emera Maine v. FERC, 854 F.3d 9, 21 (D.C. Cir. 2017); Atl. City Elec. Co. v. FERC, 295 F.3d 1, 10 (D.C. Cir. 2002). The June 18, 2026 Order failed to address the fact that reliability is relevant to the inquiry of whether a rate is just and reasonable. See Constellation Mystic Power, LLC v. FERC, 45 F.4th 1028, 1035 (D.C. Cir. 2022) (“The reasonableness of a rate is assessed in light of the FPA’s goals of promoting reliable service at reasonable rates and developing plentiful energy supplies.”); NAACP v. FPC, 425 U.S. 662, 669–70 (1976) (“[T]he principal purpose of [the FPA is] to encourage the orderly development of plentiful supplies of electricity . . . at reasonable prices.”).

a. Allowing Special Treatment For These Loads Violates the FPA’s Requirement That There Be No Undue Preference Or Unreasonable Difference In Rates Between Classes of Service. See 16 U.S.C. § 824d(b).

i. To the extent that the Commission suggests that the
transmission provider may move forward with interconnection before studies are completed, such course of action would

jeopardize reliability and would be in tension with NERC
reliability standards. See, e.g., See NERC, FAC-002-4 – Facility Interconnection

Studies
(2022), https://www.nerc.com/globalassets/standards/reliability- standards/fac/fac-002-4.pdf; NERC, 181 FERC ¶ 61,126 (2022) (approving FAC-002-4).

ii. There is no lawful basis to require tariff changes to impose new forms of service that give certain customers a reduced share of embedded costs compared to all other users when they receive the same benefits. See Coal. of MISO Transmission Customers v. FERC, 45 F.4th 1004, 1009 (D.C. Cir. 2022).

b. The Commission’s Emphasis on Protective Systems Is In Tension With the Commission’s Open Access Policies and Therefore Is Arbitrary and Capricious. The Commission Also Erred In Minimizing the Fact that Protective Systems Can and Have Failed. See NERC, Characteristics and Risks of Emerging Large Loads: Large Loads Task Force White Paper, at 13 (July 2025), https://www.nerc.com/globalassets/who-we-are/standing- committees/rstc/whitepaper-characteristics-and-risks-of-emerging-large- loads.pdf.

i. The Commission erred in adopting a policy in tension with its open access policies. See Promoting Wholesale Competition

Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048, 62 Fed. Reg. 12,274 (Mar. 14, 1997), order on reh’g,

PDF page 8

8

Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).

c. The June 18, 2026 Order is Arbitrary and Capricious in Abandoning the Main Construct of Service to Load, Which is That Customers Share In the Embedded Costs of the System. The Commission Also Erred in Adopting a Generator Funding Model for The Funding of Network Upgrades for Co-Located Load with No Supporting Evidence. See Florida Gas, 604 F.3d at 639 (“[T]he Commission ‘must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record.’”) (citation omitted); Consol. Edison Co. of N.Y., 305 U.S. at 229 (explaining that substantial evidence means “more than a mere scintilla”); see also 5 U.S.C. § 706.

i. FERC’s order is arbitrary and capricious in abandoning the main construct of service to load, which is that customers share in the embedded costs of the system. See State Farm, 463 U.S. at 43; Coal. of MISO Transmission Customers, 45 F.4th at 1009 (quoting S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 53 (D.C. Cir. 2014) (per curiam)).

ii. The Commission’s proposal that such load must self-fund any needed transmission upgrades is arbitrary and capricious because FERC has not explained its decision to depart from prior precedent. See F.C.C. v. Fox Television Stations, Inc., 556 U.S. at 515 (“[T]he requirement that an agency provide reasoned explanation for its action would ordinarily demand that it display awareness that it is changing position. An agency may not, for example, depart from a prior policy sub silentio or simply disregard rules that are still on the books.”); New England Power Generators Ass’n, 881 F.3d at 211 (“Although case-by-case adjudication sometimes results in decisions that seem at odds but can be distinguished on their facts, it is the agency’s responsibility to provide a reasoned explanation of why those facts matter.”); W. Deptford Energy, LLC, 766 F.3d at 20 (“It is textbook administrative law that an agency must ‘provide[ ] a reasoned explanation for departing from precedent or treating similar situations differently,’ and Commission cases are no exception.”) (citations omitted); Cal. Pub. Utils. Comm’n, 879 F.3d at 977 (“FERC departed from this policy without acknowledgment or explanation. This departure was arbitrary and capricious.”); Sw. Airlines Co., 926 F.3d at 856 (“‘A full and rational explanation’ becomes ‘especially important’ when, as here, an agency elects to ‘shift [its] policy’ or ‘depart[ ] from its typical manner of’ administering a program. . . . [FERC] must at

PDF page 9

9

least ‘acknowledge’ its seemingly inconsistent precedents and either offer a reason ‘to distinguish them’ or ‘explain its apparent rejection of their approach’ . . . . But however the agency justifies its new position, what it may not do is ‘gloss[ ] over or swerve[ ] from prior precedents without discussion.’”) (most alterations in original) (citations omitted); see also 16 U.S.C. § 824d(b) (prohibiting a public utility from making or granting an “undue preference or advantage” or from maintaining “any unreasonable difference in rates, charges, service, facilities, or in any other respect, . . . as between classes of service”); TransCanada Power Mktg. Ltd., 811 F.3d at 12–13 (remanding because FERC did not adequately explain its position).

iii. The June 18, 2026 Order departs from traditional cost causation principles and fails to explain or justify its departure. See, e.g., Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 173 FERC ¶ 61,043, at PP 13–14 (2020); see also Fox Television Stations, Inc., 556 U.S. at 515 (“[T]he requirement that an agency provide reasoned explanation for its action would ordinarily demand that it display awareness that it is changing position. An agency may not, for example, depart from a prior policy sub silentio or simply disregard rules that are still on the books.”) (citation omitted).

iv. The Commission provides no record evidence nor a reasoned explanation for why this load should not be charged like other load, i.e., with the upgrade cost recovered as part of the transmission rates charged to all customers. Transmission owners are permitted to earn a reasonable return on the investments necessary to construct, operate, and maintain transmission facilities, including those network upgrades required to serve co-located load. See, e.g., Fed. Power Comm’n

v. Hope Nat. Gas Co., 320 U.S. 591 (1944); Bluefield Water Works & Improvement Co. v. Pub. Service Comm’n of W. Va., 262 U.S. 679 (1923).

d. The Commission is Wrong in Suggesting That the New Service Will Promote Efficiency or Change Siting.

i. The Commission’s decision to require options for CD Service does not change how the study process or the regional planning process should work. See PJM Tariff §§ 31.1-31.3, 31.6, 32. e. The

Commission’s
Disregard
of
Reliability
Considerations
Underscores that the Replacement Rate is Not Just and Reasonable. See Constellation Mystic Power, LLC, 45 F.4th at 1035 (“The reasonableness of a rate is assessed in light of the FPA’s goals of promoting reliable service at reasonable rates and developing plentiful energy supplies.”); NAACP v.

PDF page 10

10

FPC, 425 U.S. at 669–70 (“[T]he principal purpose of [the FPA is] to encourage the orderly development of plentiful supplies of electricity . . . at reasonable prices.”).

3. FERC Exceeded Its Jurisdiction. See 16 U.S.C. § 824(b).
a. FERC’s Replacement Rate Violates the Major Questions Doctrine. See West Virginia v. EPA, 597 U.S. 697, 723 (2022); Whitman v. Am. Trucking Ass’ns, 531 U.S. 457, 468 (2001) (“Congress, we have held, does not alter the fundamental details of a regulatory scheme in vague terms or ancillary provisions—it does not, one might say, hide elephants in mouseholes.”); see also Midship Pipeline Co., v. FERC, 45 F.4th 867, 877 (5th Cir. 2022) (vacating part of the Commission’s order and remanding the remainder because “[t]he FERC’s interpretation of the NGA to give the agency power to determine ‘the reasonable cost’ of remediation efforts ‘change[d] the plot line’ of its enabling legislation, and was therefore erroneous” and “[t]he FERC lacks such authority under the NGA, and it likewise lacked authority to order an ALJ to make such a determination indirectly”) (quoting West Virginia v. EPA, 597 U.S. at 723); see Atl. City Elec. Co. v. FERC, 295 F.3d 1, 8 (D.C. Cir. 2002) (As a federal agency, “FERC is a ‘creature of statute,’ having ‘no constitutional or common law existence or authority, but only those authorities conferred upon it by Congress. Thus, if there is no statute conferring authority, FERC has none.”) (citation omitted).’

b. The Commission’s New Approach Infringes on State Retail Authority.
i. The Commission’s new approach infringes on state jurisdiction and is distinguishable from wholesale demand response

programs. See 16 U.S.C. § 824(b); see also FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 270, 278–79 (2016); FERC, Energy Primer: A Handbook for Energy Market Basics, at 41 (Jan. 17, 2024),

https://www.ferc.gov/news-events/news/ferc-staff-issues-
2024-energy-primer-handbook-energy-market-basics.
ii. The Commission is unable to do indirectly what it cannot do directly. Cf. Nat’l Fuel Gas Supply Corp. v. FERC, 909

F.2d 1519, 1522 (D.C. Cir. 1990) (“once want of power to do this directly were established, the existence of power to achieve the same end indirectly through the conditioning power might well be doubted” (quoting Sunray Mid-Continent Oil Co. v. FPC, 364

U.S. 137, 152 (1960) and citing Richmond Power & Light v.
FERC, 574 F.2d 610, 620 (D.C. Cir. 1978) (the Commission may not achieve indirectly through conditioning power of Federal Power Act what it is otherwise prohibited from achieving directly)); Am. Gas Ass’n v. FERC, 912 F.2d 1496, 1510 (D.C. Cir. 1990) (“[T]he Commission may not use its § 7 conditioning power to do

indirectly . . . things that it cannot do at all.”); see also FERC v. Elec.

PDF page 11

11

Power Supply Ass’n, 577 U.S. at 288 (“The FPA ‘leaves no room
either for direct state regulation of the prices of interstate
wholesales’ or for regulation that ‘would indirectly achieve the same
result.’”) (citation omitted).
II. The Burden Under FPA Section 206 Has Not Been Met: The Existing Rate
Has Not Been Shown To Be Unjust And Unreasonable.

The FPA requires that the rates and charges of a public utility “in connection with the transmission or sale of electric energy subject to the jurisdiction of the Commission, and all rules and regulations affecting or pertaining to such rates or charges shall be just and reasonable.”8 “[A]ny such rate or charge that is not just and reasonable is . . . unlawful.”9 Under FPA section 206, the Commission may, by its own motion or upon complaint from a third party, remedy any “rate [or] charge” or “any rule, regulation, practice, or contract affecting such rate [or] charge” found to be “unjust [or] unreasonable.”10 “The burden of proving an unjust or unreasonable rate rests with the party that initiated the proceeding—that is, the Commission or the third-party complainant.”11 In other words, a respondent to a FPA section 206 complaint is not required to make an affirmative showing that its existing rate is still just and reasonable. For the reasons below, neither the complainants in the above-captioned dockets nor any other party have met their burden of demonstrating that PJM’s current rate is unjust and unreasonable so as to require new forms of transmission service for load served by BTMG.

A. There is No Evidence In The Record That Loads Served by BTMG Are
Unable to Obtain Reliable, Timely, And Reasonably Priced Service Using
The Existing Network Service Construct. Therefore, the Commission Fails To
Satisfy The Requirement Under The APA That Its Decision Be Supported
With Substantial Evidence.

8 16 U.S.C. § 824d(a).
9 Id.
10  Id. § 824e(a).
11  Pub. Citizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021).

PDF page 12

12

Under the APA, the Commission “must examine the relevant data and articulate a satisfactory explanation for its action including a ‘rational connection between the facts found and the choice made’”12 and must base its decision on substantial evidence in the record.13 Substantial evidence means “more than a mere scintilla,” that is, “such relevant evidence as a reasonable mind might accept as adequate to support a conclusion.”14 The Commission’s June 18, 2026 Order does not satisfy this requirement.

The totality of the Commission’s reasoning for requiring that new forms of transmission service be offered to loads served by BTMG is in Paragraph 91 of the Order, which states: the Tariff is unjust and unreasonable because it does not

include transmission services that reflect that Eligible
Customers taking transmission service on behalf of load with
BTMG are willing and able to limit their energy withdrawals
from the transmission system under certain conditions.
Requiring Eligible Customers taking transmission service on
behalf of load with BTMG to take NITS, without the option to
instead take such alternative transmission services that reflect
their willingness and ability to limit their energy withdrawals,
would be unjust and unreasonable for the same reasons we
made the same finding with respect to Eligible Customers
taking transmission service on behalf of Co-Located Load.15

This finding with respect to load served by BTMG is unsupported by evidence that the current tariff service options are inadequate. Under the current PJM Tariff, there are two transmission service options: (1) Network Integration Transmission Service (“NITS” or “Network

12  State Farm, 463 U.S. at 43 (citation omitted).
13  See, e.g., Fla. Gas Transmission Co. v. FERC, 604 F.3d 636, 639 (D.C. Cir. 2010) (“[T]he Commission ‘must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record.’” (quoting Pac. Gas & Elec. Co. v. FERC, 373 F.3d 1315, 1319 (D.C. Cir. 2004))); see also 5 U.S.C. § 706.
14  Consol. Edison Co. of N.Y., 305 U.S. at 229.
15  June 18, 2026 Order at P 91.

PDF page 13

13

Service”);16 and (2) Point-to-Point Transmission Service.17 There is no inability to determine how to serve load in PJM; the PJM Tariff already has provisions explaining how Network Service works and how loads of Network Customers will be served. The starting point is Section 31.1 of the PJM Tariff, which (mirroring the Commission’s own pro forma Open Access Transmission Tariff (“OATT”)) requires that Network Loads are to be specified in the Service Agreement. The PJM Tariff sets forth in Sections 31.2 and 31.3 the procedures for identifying new Network Loads that will be served by the Network Customer. If, and to the extent that, study is required of the request, the requirements of that study are spelled out in Section 32 of the PJM Tariff. And, in recognition of the fact that loads change after commencement of service, Section 31.6 provides the process by which to report on changing loads. Further, there are application procedures for studying any new service in Section 29 of the PJM Tariff, which require specification of all aspects of the requested service, including capabilities and operating restrictions on all proposed network resources. These tariff provisions have been in place for decades, and already require that service requests should be assessed and analyzed based on their particular features; thus they already provide mechanisms for factoring in and assessing the individualized characteristics of the proposed service. The June 18, 2026 Order does not even begin to explain how the existing Network Service construct and existing PJM Tariff rules and precedent fail to provide a mechanism for loads of all sorts, including loads served by BTMG with specific resource limitations and restrictions.

16  Under the PJM Tariff, “Network Transmission Service” “mean[s] transmission service provided pursuant to the rates, terms and conditions set forth in Tariff, Part III, or transmission service comparable to such service that is provided to a Load Serving Entity that is also a Transmission Owner.”  PJM Tariff, OATT Definitions – L – M – N, at 13-14.  The PJM Tariff defines “Network Integration Transmission Service” as “the transmission service provided under Tariff, Part III.  There are two types of firm Network Integration Transmission Service:  Regional Network Integration Transmission Service and firm Cross-Border Network Integration Transmission Service. Non-firm Network Integration Transmission Service includes Secondary Service.”  Id. at 12–13.
17  Under the PJM Tariff, “Point-To-Point Transmission Service” “mean[s] the reservation and transmission of capacity and energy on either a firm or non-firm basis from the Point(s) of Receipt to the Point(s) of Delivery under Tariff, Part II.”  Id., OATT Definitions – O – P – Q, at 10.

PDF page 14

14

The Commission’s reasoning on load served by BTMG relies on its analysis with respect to Co-Located Load, but there too there is no evidence that the existing rules are inadequate. There are certainly statements that there is a lack of “clarity”, such as in Paragraph 56-58 of the June 18, 2026 Order, but there is no evidence to back that up. For example, the Commission states in Paragraph 58 that there is no clarity that an Eligible Customer must be designated to take transmission service, but the existing PJM Tariff already defines “Transmission Customer” and specifies that it must be an “Eligible Customer”.18 While it is certainly true that certain parties in these proceedings, such as Constellation, have sought transmission service without designation of an Eligible Customer, 19 there has never been a credible case that there is a lack of clarity on the issue. The Commission continues to use the Constellation example as a demonstration that there is a lack of “clarity” requiring new forms of transmission service,20 but this is a logical tautology. That is, the fact that Constellation attempted to circumvent the rules, causing delays in its service request, does not prove that the existing rules were inadequate.

At Para 65 of the June 18, 2026 Order, the Commission cites to the Susquehanna ISA Proceeding, in fn. 136, as evidence that there is continued reason for concern.  In Docket Nos. ER24-2172-000 and ER24-2172-001 (“Susquehanna ISA Proceeding”),21 there was a proposal to allow co-located load to avoid purchasing Network Service through the use of a behind-the-meter

18  PJM Tariff, Definition of Transmission Customer, Section 1.
19  See Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, at Ex. 5 Attach. 1, Declaration of James R. McCoskey (filed Nov. 22, 2024).   That attachment is a November 12, 2024, letter from ComEd to Constellation concerning interconnection requests at the LaSalle and Byron nuclear facilities.  In that letter, ComEd details certain design issues with Constellation’s proposal and then explains that the “end use load is retail load under both Illinois and federal law and cannot be interconnected solely through amendments to the LaSalle or Byron [interconnection service agreements].”  In other words, Constellation was seeking transmission service without an Eligible Customer.

20  See June 18, 2026 Order at fn. 114, citing the Constellation situation.
21  See Susquehanna ISA Order, 189 FERC ¶ 61,078.

PDF page 15

15

arrangement.22 The Commission correctly rejected the proposed interconnection service agreement (“ISA”) in the Susquehanna ISA Proceeding. 23 Talen subsequently announced that “[t]he existing Susquehanna co-located load arrangement between Talen and Amazon will transition to a ‘front-of-the-meter’ arrangement after the completion of transmission reconfigurations expected in the Spring of 2026, concurrent with Susquehanna’s refueling outage.”24 Talen effectively conceded that PJM Network Service works, which is to say that Network Service under the existing PJM Tariff provides for timely service, and is a service upon which all customers may rely. There is simply no evidence suggesting otherwise. The Commission’s findings relating to the existing tariff promoting “economic

inefficiency”25 are likewise devoid of evidence. That is, the existing PJM Tariff provides for a fulsome study process based on the proposed operating characteristics of the loads and resources. See PJM Tariff at Sections 29 and 31. No evidence is offered in the order of any circumstance in which the current transmission rate service offerings in the PJM Tariff impacted study results. To the contrary, study results are based on the physics and engineering of the system – not on whether the rates are based on the customer’s gross load or net load. Customers with BTMG have been served under open access tariffs for decades and there is simply no evidence offered in the order that such customers are forced to operate inefficiently on account of the existing OATT transmission service offerings.  Indeed, as discussed below, the Commission has consistently

22  See PJM Interconnection, L.L.C., Docket No. ER24-2172-000, Application Attach. A, Amended ISA, at Schedule F, Part F.4 (June 3, 2024). 23  Susquehanna ISA Order, 189 FERC ¶ 61,078.
24  Press Release, Talen Energy, Talen Energy Expands Nuclear Energy Relationship with Amazon (June 11, 2025), https://ir.talenenergy.com/news-releases/news-release-details/talen-energy-expands-nuclear-energy- relationship-amazon.
25  June 18, 2026 Order at P 65.

PDF page 16

16

rejected arguments that different ratemaking should be applied even where there are limits to the amount of transmission system use.26

Further, the Commission’s December 18, 2025 Order held that Network Service remains just and reasonable. The Commission states that,

it continues to be just and reasonable for an Eligible Customer
taking transmission service on behalf of Co-Located Load to elect,
as one of the required transmission services from which the Eligible
Customer must choose, to take NITS. . . . NITS provides significant
benefits because a NITS customer gains the right to be served from
the transmission system at any time, and PJM and the transmission
owners incorporate NITS load into their transmission planning.27

In the June 18, 2026 Order, the Commission holds fast to that determination but holds that certain customers (which now includes load served by BTMG) are entitled to more new options.28 The Commission (in fn 156) then cites back to the December 18, 2025 Order and its finding without evidence that inefficiencies result if new options are not available. In total, there are assertions of inefficiency, but no evidence to support the conclusion that the existing service options fail to address the needs of any loads, including loads served by BTMG. That is not a permissible basis to take action under FPA section 206.

B. The Commission Did Not Engage in Reasoned Decision Making Because It
Did Not Explain its Departure from FERC Precedent or Refute that, Because
the Existing PJM Tariff Provides Service on the Same Basis for All
Customers, the Existing PJM Tariff Does Not Grant an Undue Preference.

As an initial matter, picking and choosing customers to receive preferential rate treatment runs contrary to the FPA’s requirement that “[n]o public utility shall, with respect to any

26  See Fla. Power & Light Co., 113 FERC ¶ 61,290 (2005), aff’d on rehearing, 116 FERC ¶ 61,012 (2006), aff’d on appeal sub nom. Fla. Mun. Power Agency v. FERC, 264 F. App’x 4 (D.C. Cir. 2008) (per curiam).
27  December 18, 2025 Order, at  P 195 (footnote omitted).
28  June 18, 2026 Order at P 68.

PDF page 17

17

transmission or sale subject to [FERC’s] jurisdiction . . . (1) make or grant any undue preference or advantage to any person or subject any person to any undue prejudice or disadvantage, or (2) maintain any unreasonable difference in rates, charges, service, facilities, or in any other respect, either as between localities or as between classes of service.”29

The Commission has a long-standing policy of rejecting attempts by network transmission customers to avoid paying their load ratio share of system cost. As the Commission recognized in the June 18, 2025 Order, citing the Amtrak case, the Commission “has rejected cost causation arguments made by network customers that sought to lower their load ratio share based on actual use of the transmission system.”30 This policy has long persisted for very good reason. The “assessment of [Network Integration Transmission Service] is not based on actual use over a particular transmission path, but rather based on the network customer’s right to use the entire system” and its effects on that system.31

The Amtrak case, which rejected an attempt by a network customer in PJM to pay for less than its full gross load, was not an outlier, but instead reflected decades of Commission precedent, rejecting challenges to uniform application of the rule that Network Service would be based on the entire gross load of the network customer, regardless of arguments (such as those advanced by Amtrak) that the customer could purportedly limit use of the system. For example, this exact issue was addressed in Order No. 888-A and resulting appeals. In Order No. 888-A, the Commission

29  16 U.S.C. § 824d(b).
30  June 18, 2026 Order, 193 FERC ¶ 61,217 at P 196 & n.412 (citing Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp, 171 FERC ¶ 61,237, at P 41 (2020), denying clarification and addressing reh’g, Nat’l R.R. Passenger Corp.
v. PPL Elec. Utils. Corp., 173 FERC ¶ 61,043 (2020) (“Amtrak”); PJM Interconnection, L.L.C., 169 FERC ¶ 61,041, at P 60 (2019)).

31  Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 173 FERC ¶ 61,043, at PP 13–14 (2020).

PDF page 18

18

held that customers cannot “split” their load at a delivery point—if some of the load takes Network Service, all of the load must be designated for Network Service:

The concept of allowing a “split system” or splitting a discrete load
is antithetical to the concept of network service. A request for
network service is a request for the integration of a customer’s
resources and loads. Quite simply, a load at a discrete point of
delivery cannot be partially integrated—it is either fully integrated
or not integrated. Furthermore, such a split system creates the
potential for a customer to “game the system” thereby evading some
or all of its load-ratio cost responsibility for network services.32
That ruling was expressly upheld on appeal by the U.S Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”), which accepted the Commission’s reasoning, finding that objections were “not well-taken.”33

In the June 18, 2026 Order, the Commission argues that it is not violating Order No. 888- A, because the load is not “split” but is instead limited by contract demand.34 This is sophistry – charging network service for a portion of the load, and not for other portions of the load at the same delivery point, is the exact type of load-splitting proposal that the Commission rejected in Order No. 888-A. Further, because the Commission has recognized that these customers use the transmission system for some services for their whole load (such as load following and black start), the notion that the customer can use the system for those services but not others, again reflects a splitting of responsibility for the load that flies in the face of the Commission’s Order 888-A ruling. The Commission suggests that specification of a fixed contract demand avoids opportunities for

32  Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888-A, 78 FERC ¶ 61,220 (1997), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).
33  Transmission Access Pol’y Study Grp., 225 F.3d at 726.
34  June 18, 2026 Order at P 112.

PDF page 19

19

“gaming” eliminating at least one of the concerns of Order No. 888-A,35 but the gaming
opportunity here is in the designation of contract demand, which pretends that the load is only partially using the transmission system, even though the transmission system is following the entirety of the load.

The issue was likewise addressed in a long series of cases involving Florida Municipal
Power Agency (“FMPA”) and transmission service it was taking from Florida Power and Light.
As recounted by the D.C. Circuit in 2005, years of litigation in that case involved the attempt by FMPA to avoid paying for Network Service based on its overall gross load, with the Commission consistently rejecting all arguments by FMPA against such load splitting.36 In the 2005 decision, the court remanded one argument by FMPA, which is that physical constraints on the transmission system made it physically impossible for its entire load to be served by the FPL system.37 On remand, the Commission found that even in the case of physical impossibility of serving the entire load, the gross load construct was most appropriate, rejecting arguments that a network customer should pay for any less than its entire system load.38

The Commission has consistently followed this precedent.39 For example, in Idaho Power,
the Commission rejected Bonneville Power Administration’s (“BPA”) attempt to remove certain

35  Id.
36  Fla. Mun. Power Auth. v. FERC, 411 F.3d 287 (D.C. Cir. 2005) (describing history of case back to 1993).
37  Id. at 292 (remanding because “FERC . . . failed to explain why network customers should be charged by the transmission provider for network service that the provider is physically constrained from offering and, relatedly, why physical impossibility should not be recognized as an exception to the general rule against permitting partial load ratio pricing for network customers”).
38  Fla. Power & Light, 113 FERC  ¶ 61,290 (2005), aff’d on rehearing, 116 FERC ¶ 61,012 (2006), aff’d on appeal, 264 F. App’x 4 (D.C. Cir. 2008).
39  See, e.g., Idaho Power Co., 106 FERC ¶ 61,329 (2004) (“Idaho Power”); Ameren Servs. Co. v. Prairieland Energy Inc., 131 FERC ¶ 61,125 (2010) (finding that network customer failed to comply with the tariff by not designating its total load as network load); Ariz. Pub. Serv. Co., 151 FERC ¶ 61,191 (2015) (finding that a network customer's request to designate less than its entire load as network load violated both the transmission provider’s OATT and (cont'd)

PDF page 20

20

of its load from its load ratio share.40 The Commission explained that, contrary to Order No. 888, “BPA’s proposal would essentially leave the behind the meter loads . . . as part of BPA’s network load served by Idaho Power’s transmission service, but eliminate the requirement that such loads be metered, i.e., included in BPA’s load ratio share, because Idaho Power’s transmission service may only be needed in rare instances.”41 Similarly, in Order No. 890,42 commenters complained that assigning transmission-related costs to customers that reduce their use of the transmission provider’s system to serve load is inconsistent with the Commission’s cost-causation principles. The Commission rejected such arguments, stating that its existing policy already provides customers with the opportunity to reduce network service costs to the extent a customer is not relying on the transmission system to meet its energy needs (i.e., by taking point-to-point transmission service instead of network service).43

In the June 18, 2026 Order, the Commission in its ruling on BTMG now has departed from
these decades of precedent and, contrary to the APA, has failed adequately to explain its departure.44 The Commission’s prior determinations of the fairness of load ratio allocation (based

long standing Commission policy, which require network customers to designate their entire load as network load to receive network service).

40  Idaho Power, 106 FERC ¶ 61,329 at P 14.
41  Id. 42  Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890, 119 FERC ¶ 61,119 (“Order No. 890”), order on reh'g, Order No. 890-A, 121 FERC ¶ 61,297 (2007), order on reh'g, Order No. 890- B, 123 FERC ¶ 61,299 (2008), order on reh'g, Order No. 890-C, 126 FERC ¶ 61,228, order on clarification, Order No. 890-D, 129 FERC ¶ 61,126 (2009).
43  See Order No. 890, 119 FERC ¶ 61,119..
44  See  Fox Television Stations, Inc., 556 U.S. at 515 (“the requirement that an agency provide reasoned explanation for its action would ordinarily demand that it display awareness that it is changing position. An agency may not, for example, depart from a prior policy sub silentio or simply disregard rules that are still on the books.”).  At paragraph 211 of the June 18, 2026 Order, the Commission says that the current load-splitting proposal is different from prior situations because PJM need only plan for the specified contract demand rather than the full load, but this argument is not a difference from prior cases at all, such as the FPL case where there was no contention that (cont'd)

PDF page 21

21

on gross load—even in the case of purported physical impossibility of service to full load) of embedded costs hold true. There is no reasoned basis for these distinctions.

The Declaration of Danielle S. Powers (“Powers Declaration”), submitted by Exelon and FirstEnergy, explains why the assessment of Network Service is not based on actual use over specific transmission paths.45 All customers have different usage of the grid. Many customers’ reliance upon the grid varies during different times of the year and can be distinguished from other customers’ uses. These customers may have distinct load shapes or load factors, but they pay the same rate for Network Service as do high load factor customers. Such customers pay the full Network Service rate, but because Network Service charges are allocated based on contribution to the system coincident peak, some customer charges may be lower on average than others if their operations occur disproportionately outside of the peak hours. No additional rate discount is necessary or given. Up until now, the Commission has consistently applied this approach of not carving out special rates for different customer classes for good reason—every customer can attempt to make arguments why their usage should result in a decrease of their share of the embedded costs of the transmission system. Utilities have an obligation to serve load and that load needs to be able to call on service regardless of whether they actually utilize the system to the maximum allowable extent since weather and other factors are unpredictable. Hence, actual usage does not reflect the benefit. Entertaining such arguments would frustrate the rate design that the Commission has applied across the board and that was put in place following Order No. 888.46

FPL was redesigning its system to serve the full load of FMPA, or the Amtrak case where the entire premise of the argument was that Amtrak made only rare and limited use of the system.

45  See PJM Interconnection, L.L.C., Docket No. EL25-20-000, Indicated TOs June 3, 2025 Answer, Declaration of Danielle S. Powers at P 29. 46  See, e.g., Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., Order No. 888, 75 FERC ¶ 61,080 (1996), order on reh’g, Order No. 888-A, 78 FERC ¶ 61,220, order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (cont'd)

PDF page 22

22

The existing PJM Tariff effectuates the principle that those that benefit from the
transmission system should contribute on a load ratio basis to the embedded costs of the system and is consistent with the pro forma OATT in providing for Network Service and Point-to-Point Service, an important component of Order No. 888.47 Under the APA, the Commission must

explain why circumstances have changed such that this proceeding requires departure from past efforts by customers to pay for less than gross load.48 The Commission made no serious attempt to do so. Nor has the Commission distinguished why other existing customers will not qualify for discounts—many of whom can argue that they impose lesser demand on the grid by some measure. That failure to provide explanation renders FERC’s decision arbitrary and capricious and violates the APA.49 Ultimately, this is not reasoned decision making and will create a nightmare as other customers in PJM and beyond raise a host of similar arguments that their transmission rates should

(1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000) (TAPS), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).

47  See, e.g., id.
48  See Fox Television Stations, Inc., 556 U.S. at 515 (“the requirement that an agency provide reasoned explanation for its action would ordinarily demand that it display awareness that it is changing position.  An agency may not, for example, depart from a prior policy sub silentio or simply disregard rules that are still on the books.”); see also Constellation Mystic Power, LLC 45 F.4th at 1057 (finding the Commission’s decision to be arbitrary and capricious and that “the Commission’s ‘failure to provide an intelligible explanation . . . amounts to a failure to engage in reasoned decisionmaking’”) (citation omitted); New England Power Generators Ass’n, Inc. v. FERC, 881 F.3d 202, 211 (D.C. Cir. 2018) (“Although case-by-case adjudication sometimes results in decisions that seem at odds but can be distinguished on their facts, it is the agency’s responsibility to provide a reasoned explanation of why those facts matter.” (citing BP Energy Co. v. FERC, 828 F.3d 959, 968 (D.C. Cir. 2016) (vacating finding of no undue discrimination where Commission identified differences between two natural-gas companies but failed to adequately explain why they provide a rational basis for the difference in treatment))); W. Deptford Energy, LLC v. FERC, 766 F.3d 10, 20 (D.C. Cir. 2014) (“It is textbook administrative law that an agency must ‘provide[ ] a reasoned explanation for departing from precedent or treating similar situations differently,’ . . . and Commission cases are no exception . . . .”) (alteration in original) (citations omitted).
49  See, e.g., Cal. Pub. Utils. Comm’n, 879 F.3d at 977 (“FERC departed from this policy without acknowledgment or explanation. This departure was arbitrary and capricious.”); Sw. Airlines Co., 926 F.3d at 856 (“‘A full and rational explanation’ becomes ‘especially important’ when, as here, an agency elects to ‘shift [its] policy’ or ‘depart[ ] from its typical manner of’ administering a program. . . .  [FERC] must at least ‘acknowledge’ its seemingly inconsistent precedents and either offer a reason ‘to distinguish them’ or ‘explain its apparent rejection of their approach’ . . . But however the agency justifies its new position, what it may not do is ‘gloss[ ] over or swerve[ ] from prior precedents without discussion.’”) (alterations in original) (citation omitted).

PDF page 23

23

be modified based on their allegedly different use of the system, which is a reason why the Commission never mandated this in the past.

C. The Loads Rely Upon The Entire Embedded Transmission System To Serve
Their Full Gross Load. Therefore, FERC’s Decision is Arbitrary and
Capricious Because The Embedded Transmission System Costs Should Be
Charged For Those Transmission Services.
Notwithstanding well-established Commission policy and judicial precedent to the contrary, the June 18, 2026 Order establishes a new preferential transmission rate available for loads served by BTMG. Not only is this new rate unduly discriminatory (as discussed herein), but it is based on a false premise that the combination of transmission system burdens and user benefits to loads served by BTMG are so insignificant as to justify the establishment of a lower, preferential rate. The Commission is wrong, with respect to both the actual burdens on the system and the benefits to load served by BTMG of being interconnected to the grid.

As for benefits, the Commission has recognized that co-located loads benefit from black start and load following service,50 and that such service properly should be charged based on gross load. The Commission did not discuss the issue for load served by BTMG, but such load likewise is reliant on black start and load following. Load following services are supplied from a diverse range of the interconnected generation facilities located throughout the system. These services cannot be provided without use of all the transmission system’s resources and personnel. Moreover, because it is a universal rule that generators cannot operate every hour of every year and that unexpected outages can and do occur, transmission interconnections provide an avenue for such loads to readily acquire back-up power when co-located generation facilities are not available.

50  See June 18, 2026 OrderJune 18, 2026 Order, 193 FERC ¶ 61,217 at PP 209, 219 (3), (4).

PDF page 24

24

In addition, in assessing load served by BTMG, the Commission fails to consider the many advantages to such loads when they connect to the transmission system. These advantages become apparent when one compares islanded projects to similar projects that are interconnected to the transmission grid. Islanded projects require extensive back-up generation to assure reliable sources of power. It is very difficult and expensive to supply islanded generation with black start capabilities or instantaneous load following. All back-up generation on an islanded project will sit idle when not needed to serve the islanded load, thereby forgoing significant revenues from selling the surplus power into the wholesale market. These lost opportunity sales revenues alone could likely cover the fully embedded costs of Network Service. Ultimately, islanded generation projects are more risky and therefore more difficult to finance. Grid interconnection is valuable, which is why the BTMG-served customers do not just create isolated islands. In determining that traditional Network Service without the option of additional services is unjust and unreasonable for load served by BTMG, the Commission considered none of these benefits of grid interconnection to such loads. Failure to consider the benefits of grid interconnection makes the June 18, 2026 Order arbitrary and capricious and unreasoned.51

III. The Burden Has Not Been Met Under FPA Section 206: FERC’S Replacement
Rate is Not Just and Reasonable.

Under FPA section 206,52 there are two steps: only after the Commission finds a rate to be unjust and unreasonable, may it set a replacement rate.53 No one has met the burden at either step in ordering that new forms of transmission service be provided to load served by BTMG.

51  See State Farm, 463 U.S. at 43. 52  16 U.S.C. § 824e(a).
53  See id; see also Advanced Energy Mgmt. All., 860 F.3d at 663 (“If the Commission finds that a rate is ‘unjust, unreasonable, unduly discriminatory or preferential, the Commission shall determine the just and reasonable rate … and shall fix the same by order,’” and “[i]t is the Commission’s job—not the petitioner’s—to find a just (cont'd)

PDF page 25

25

A. Allowing Special Treatment For Load Served by BTMG Violates The FPA’s
Requirement That There Be No Undue Preference Or Unreasonable
Difference In Rates Between Classes Of Service.
As explained above, FPA section 205 prohibits any public utility charging transmission rates from “mak[ing] or grant[ing] any undue preference or advantage to any person or subject any person to any undue prejudice or disadvantage” or “maintain[ing] any unreasonable difference in rates, charges, service, facilities, or in any other respect, either as between localities or as between classes of service.”54 The Commission, by requiring new forms of service for load served by BTMG, would establish rates that grant an undue preference or advantage to such loads. There already exist mechanisms (such as demand response at the state and federal levels) to address when customers can scale back their load or bring other generation to bear in order to reduce their withdrawals when called upon. If loads served by BTMG would like to be compensated for being interruptible, then they should rely upon PJM’s demand response rules, or retail rules in the various states, and the June 18, 2026 Order fails to explain why those rules are inadequate here. The point of FPA section 206 is not for the Commission to declare what it thinks would be better tariff options—it is to ensure that the tariff on file is just and reasonable. Similarly, the PJM Tariff already has in place provisions to provide compensation to those that can ease transmission congestion – to the extent that a basis for the Commission’s orders is that some uses of the system reduce grid usage thus easing congestion, the mechanisms are already there.  The Commission does not consider those existing tariff provisions, and thus fails to develop just and reasonable rate mechanisms.

and reasonable rate.”) (alterations in original) (citation omitted); Emera Maine, 854 F.3d at 21; Atl. City Elec. Co., 295 F.3d at 10.

54  16 U.S.C. § 824d(b).

PDF page 26

26

For the new Interim Service, there is no basis for the Commission to require this new form of service prior to the completion of necessary network upgrades and studies to ensure reliability of the system. The Commission has effectively conceded it has not yet done adequate analysis on this point – ruling in Paragraphs 125 and 131 of the June 18, 2026 Order that it is “premature” to determine the extent, if any, that the new forms of service promote efficiency or impact reliability. The Commission cannot have it both ways – if it is premature to consider if the new services promote efficiency, or adequately protect reliability, the Commission cannot rely on purported efficiency gains, to justify imposition of the new services, and cannot claim to have done so in a way that is protective of reliability.

Second, the only issue that CD Services resolve is ratel levels for embedded costs allocated to these load. The form of service does not dictate what studies should be conducted, or what upgrades might be necessary for the system. Whether or not a customer seeks CD Service, studies should consider the actual circumstances of the proposed interconnection, which will be dictated by engineering and physics, and not by the rate level charged to the customer. The notion that CD Service impacts issues such as where a customer interconnects depend on a fallacy that system studies consider rate levels rather than the details of the proposed interconnection. Interconnecting to the grid burdens the system by adding new loads and operating contingencies that must be addressed by system operators. Grid interconnections also bring significant project benefits such as the ability to sell on-site back-up generation into the wholesale markets when it otherwise would sit idle, and the ability to receive load following service from off-site generation. The totality of these burdens and benefits—benefits which no doubt exceed the cost of Network Service based on gross load—easily justify charging these loads the same rate as all other transmission customers. To allow for preferential rate treatment would allow those

PDF page 27

27

customers to rely upon the grid and its benefits at a price that is subsidized by all other customers. That cannot be said to be just and or reasonable.55 Such a decision is not grounded in reasoned decision making and is not supported by substantial evidence.56

B. The Commission’s Emphasis On Protective Systems Is In Tension With The
Commission’s Open Access Policies And Therefore Is Arbitrary And
Capricious. The Commission Also Erred In Minimizing The Fact That
Protective Systems Can And Have Failed.

As Exelon and FirstEnergy have explained, protective systems can provide value, but they are no panacea. They can protect against net withdrawals from the grid (where the load exceeds the co-located generation), but do not protect the grid from real impacts that occur even when there is consumption by a co-located customer but no net withdrawal, such as the impacts of load and voltage spikes and oscillations.57 Further, the emphasis on protective systems to prevent backflows ignores an important issue: other providers may want to compete to serve these customers. The generators have an interest in designing captive arrangements where the customers cannot access alternative supply, but that is not something the Commission should endorse. To the contrary, it flouts the core proposition behind Order No. 888,58 where the Commission established its open

55  See Coal. of MISO Transmission Customers, 45 F.4th at, 1009 (alterations in original) (quoting S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 53 (D.C. Cir. 2014) (per curiam)) (“The cost-causation principle requires that ‘[t]he cost of transmission facilities . . . be allocated to those within the transmission planning region that benefit from those facilities in a manner that is at least roughly commensurate with estimated benefits.’”).
56  See Florida Gas, 604 F.3d at 639 (“[T]he Commission ‘must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record.’”) (citation omitted); Consol. Edison Co. of N.Y., 305 U.S. at 229 (explaining that substantial evidence means “more than a mere scintilla”); see also 5 U.S.C. § 706.
57  This follows directly from the Commission’s acknowledgement that these arrangements need load following for the entire gross load, regardless of the absence of net withdrawals. 58  See Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048, 62 Fed. Reg. 12,274, 12,323 (Mar. 14, 1997), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).

PDF page 28

28

access policies. Transmission asset owners cannot create barriers that inhibit the ability of other generation on the grid to compete to serve load. As the Supreme Court recognized, a key motivation behind the open access requirements is that owners’ “control of transmission facilities gives them the power either to refuse to deliver energy produced by competitors or to deliver competitors’ power on terms and conditions less favorable than those they apply to their own transmissions.”59 But that is exactly what generators propose and the Commission now endorses. By design, the protective systems are intended to prevent ready access to competing suppliers. In addition to its other flaws, that proposal should be rejected because it is an illegal effort to stifle competition.

Moreover, the Commission puts too much faith in protective systems operating
instantaneously and without failure. BTMG loads are like co-located loads which “can pose reliability risks if their generation unexpectedly trips off-line and appropriate protection or ride- through systems are not in place [because] [t]he operational visibility and controllability of [behind-the-meter] loads are limited, making it more challenging to predict system impacts, especially during uncontrolled transitions between on-site generation and grid supply that may arise due to protection system failures.”60 If, after BTMG generation fails, the load unexpectedly shifts to drawing supply from the grid, for even a moment, the transmission system sees a rapid demand spike, which may stress and harm the system.61 Moreover, as the Commission acknowledged, “PJM maintains that it is always possible that any protection system in an isolated

59  New York v. FERC, 535 U.S. 1, 8–9 (2002).
60  NERC, Characteristics and Risks of Emerging Large Loads: Large Loads Task Force White Paper, at 13 (July 2025), https://www.nerc.com/globalassets/who-we-are/standing-committees/rstc/whitepaper-characteristics- and-risks-of-emerging-large-loads.pdf.
61  Id.

PDF page 29

29

(but not islanded) Co-Location Arrangement could mis-operate, be disabled, or degrade, and that, in the few instances where such schemes exist on the PJM system, PJM has observed these schemes fail, and the load has taken grid service.”62

As the Commission recognizes from PJM’s comments, “if the protection system fails, the large load would instantly take significant energy from the system” and “though a few such configurations may seem tolerable, the risk increases with large quantities of such configurations.”63 To address this risk, the Commission “direct[s] PJM to apply a penalty rate.”64 Assessing penalties, however, only addresses the issue after the fact and does not remediate the reliability implications of faulty protective systems.

As previously discussed, because the Commission has not addressed these issues, it has not engaged in reasoned decision making and fails to satisfy the APA requirements.

C. The June 18, 2026 Order is Arbitrary And Capricious To the Extent it Adopts a Generator Funding Model for Network Upgrades Required for Service to

Loads Served by BTMG

In the December 18, 2025 Order, as upheld in the June 18, 2026 Order, FERC adopted a policy that Network Upgrades associated with the new forms of transmission service would be paid for using the Generator Funding Model, in which Generators are responsible for the Upgrade Costs.65 We presume that this ruling now extends to loads served by BTMG. This is a departure from the existing model for transmission service charges – in which loads simply pay a load ratio share of the entire transmission system. 66 To be clear, the Commission has a different model for

62  December 18, 2025 Order, 193 FERC ¶ 61,217 at P 44.
63  Id. P 17.
64  Id. P 212.
65  June 18, 2026 Order at P 166. 66  See, e.g. PJM Tariff P 34.1.

PDF page 30

30

upgrade costs required to interconnect a generator – in which the generator may be required to pay those costs – but that is a different situation because the generator is not a load, and absent those payments does not pay for transmission system costs at all.  The June 18, 2026 order conflates the funding model applicable to upgrades required to serve load and the funding model applicable to upgrades required for generation. In the long run the Commission’s approach that has some categories of load paying only incremental costs will lead to one set of loads paying far less than other loads for use of the same transmission system – that is, in the long run, payment of embedded cost rates on a load ratio basis will generally exceed a one-time assessment of incremental costs. (Again, the situation is just different for generation – which does not owe anything in the long run under load ratio mechanisms.) The Commission has not provided reasoned findings that the existing approach for charging load leads to unreasonable results, nor has it provided reasoned analysis in support of the new model.

As explained above, the Commission’s policy for decades has been that the embedded costs of the transmission system are shared by all customers. To that end the costs of network upgrades are shared by all customers. This makes sense because “[t]he cost-causation principle requires that ‘[t]he cost of transmission facilities . . . be allocated to those within the transmission planning region that benefit from those facilities in a manner that is at least roughly commensurate with estimated benefits.’”67

Again, under the PJM Tariff, as provided in Section 34.1, load pays all transmission costs. The only exception is when the transmission system requires upgrades to accommodate requests by generators (not load) to interconnect. Charging load for the embedded costs of the system,

67  Coal. of MISO Transmission Customers, 45 F.4th at 1009 (second and third alterations in original) (quoting S.C. Pub. Serv. Auth., 762 F.3d at 53).

PDF page 31

31

including upgrades, makes sense because all loads benefit from the transmission network. The Commission provides no record evidence nor a reasoned explanation for why load served by BTMG should not be charged like other load, i.e., with the upgrade cost recovered as part of the transmission rates charged to all customers.68

The new approach to incremental costs – using a Generation Funding model that has not
previously been used for charges to load -- differs from the approach taken in the PJM Tariff, and the Commission’s own OATT, which assign cost responsibility among all load by charging all network customers (based on their respective load ratio shares) for incremental investments needed to reliably serve load expansion (in addition to making all network loads responsible for their share of pre-existing embedded system costs).69 The June 18, 2026 Order’s shifting of cost responsibility from the Load Model to the Generation Funding Model departs from traditional cost causation principles and is randomly applied only to certain cases where the added load is purportedly served through an existing generator interconnection facility. The simultaneous existence of conflicting funding models is discriminatory, internally inconsistent with the June 18, 2026 Order’s retention of Network Service, and contrary to FERC’s cost-causation principles. The June 18, 2026 Order

68  See State Farm, 463 U.S. at 43.  Of course, transmission owners are permitted to earn a reasonable return on the investments necessary to construct, operate, and maintain transmission facilities, including those network upgrades required to serve co-located load.  See, e.g., Fed. Power Comm’n., 320 U.S. 591; Bluefield Water Works & Improvement Co., 262 U.S. 679.  For decades, the Commission has recognized this principle by rolling the costs of load-driven network upgrades into transmission rates.  The June 18, 2026 OrderJune 18, 2026 Order, however, departs from this longstanding approach without substantial record evidence or justification. Eliminating this opportunity for capital recovery with a reasonable rate of return not only creates regulatory uncertainty that undermines investor confidence, but further discourages investment in the transmission system at a time when such investment is critical.  Since the 2003 blackout, the electric industry has faced persistent challenges in attracting private capital.  Abrupt policy shifts—such as narrowing rolled-in rate treatment— exacerbate these challenges, weaken financial performance, and deter investors who rely on stable, predictable returns.

69  See generally PJM Tariff Section 34.1.

PDF page 32

32

fails to explain or justify this departure and therefore is arbitrary and capricious and not the product of reasoned decision making.70

The Commission has failed to consider numerous issues arising from this disparate treatment:

First, in some (if not most) cases, it will be a benefit to other customers to include new loads in the pool of payers for the existing transmission network rather than setting them apart and assigning them only the incremental cost for specific upgrades. By spreading the revenue requirement for the transmission system generally over an increasing number of billing units— a.k.a. “increasing the denominator”—it reduces what other customers pay for transmission. The

undeniable fact is that large loads—not only because of their size, but also their high load factors, impose significantly upon the overall transmission (and distribution) revenue requirement needs now, and new co-located loads would do the same. By contributing to paying the cost of overall system on which they depend, these customers, like other customers, equitably, could help address overall concerns about affordability as the national energy grid transforms. But, if they are required to pay only for incremental investment, they avoid paying for the broader system upon which they depend and that public benefit is lost. The more some loads are carved out to pay separately for certain transmission infrastructure, the less they will pay for the overall grid and the more other customers will pay as a forced subsidy.

Over the long term the calculus of requiring some loads to fund upgrades but not pay otherwise for their use of the existing system, can play out in just one way: it is worse for other customers while it significantly and unduly benefits the select customers who get to enjoy the incremental-only pricing model. Once a load has fulfilled its responsibility (whether immediately

70  See New England Power Generators Ass’n, Inc., 881 F.3d at 211.

PDF page 33

33

or over time) for funding certain upgrades, such customers taking minimalistic contract demand service will pay essentially no embedded costs. But the transmission system is not a one-and-done investment. The system evolves and requires maintenance to ensure reliability, resilience, and quality of service, all of which comes at a cost. Over time, the existing load ratio allocation scheme imposes more costs on the large loads. (Which is why the large loads do not like the model and propose alternatives.) Allowing a model where initial investment absolves some loads from financial contributions associated with the ongoing use of the system leaves other customers holding the bag.

Second, such an approach creates challenging dynamics like those we have seen in the generator interconnection space. For example, this approach likely benefits earlier loads that identify favorable interconnection points, only for later customers to trigger significant upgrades, which once completed may lower costs for future load interconnection requests. Furthermore, transmission system upgrade needs can be very sensitive to other large loads modifying their requests or withdrawing, as well as overlapping issues with other aspects of transmission planning. Not only do these dynamics threaten to create inequities, they create incentives for speculative behavior and point of interconnection “shopping,” with associated unpredictable requests and withdrawals. This is precisely the kind of behavior that became so problematic, resource-intensive, and delay-inducing in the generator interconnection queue.

Third, not all large loads are as financially strong as data center owners. Allocating transmission system upgrade costs up-front to those customers runs counter to the policy objective of promoting economic development by imposing too many near-term financial hurdles. While some loads may have substantial access to capital, significant up-front requirements could hinder

PDF page 34

34

economic development, particularly for many commercial and industrial customers that find themselves included in a new paradigm designed to support AI data center interconnections. It also bears emphasis that large loads, co-located or otherwise, will not always trigger significant transmission upgrades. The expectation is that large new loads will make every effort to choose sites where the upgrades will be minor, and the harmful impact of their future exemption from transmission costs on other customers will not be offset at all. In short, it should not be assumed that large loads will trigger system upgrades with costs in excess of what they would otherwise contribute to the system if they paid traditional network rates based on their load-share ratio, and the June 18, 2026 Order erred in adopting a funding model around such a false premise.71

D. The Commission Is Wrong In Suggesting That CD Service Will Promote
Efficiency Or Change Siting.
To be clear, under any circumstance, project development teams for new load, whether that load is co-located or not, already have a strong incentive to site their facilities on the grid at a location that minimizes the need for transmission upgrades. Project developers understand that additional work can add cost, increase complexity, risk project delay, and result in lost opportunity. In addition, and as discussed above, wise siting decisions will minimize the need for system upgrades, which will hasten interconnection. That benefit is real. But it has nothing to do with the proposed CD Service. This is because the impacts to the grid are based on physics and engineering.

71  The Commission also lacked evidence to eliminate rolled-in rate treatment as an option for network upgrades. Here again, the Commission failed to satisfy its burden under the APA.  By replacing rolled‑in rate treatment with direct assignment to the co-located generator, without at least providing customers the option to select rolled-in rate treatment, the June 18, 2026 Order is arbitrary and capricious.  In the June 18, 2026 Order, the Commission failed to (a) address material comments demonstrating system-wide benefits of transmission upgrades required by exiting generation, or (b) consider the alternative of permitting both rolled‑in rate treatment and direct assignment.

PDF page 35

35

Whether the service paid for is based on net load or gross load does not change that planning and siting depend on the physics and engineering of the grid.

The Commission’s decision to require options for CD Service does not change how the study process should work. Regardless of cost-allocation, ensuring there is a reliable grid is essential and understanding what load amount the system needs to support is necessary. If transmission providers are forced to pretend a 500 MW load is only 50 MW, or even that it is zero, and pretend away the physics and engineering impacts, it will threaten reliability and resource adequacy and therefore cannot be said to be just and reasonable.

While protective systems can be beneficial, any suggestion that regional planning needs are automatically reduced by the establishment of CD Service is also not supported by evidence. No loads should be taken out of the broader planning process—to do so would only threaten reliability of the system. Grid operators must plan for such eventualities to ensure system reliability.72

The Commission finds in the December 18, 2025 Order that the BTMG “rules in PJM’s Tariff are no longer just and reasonable because loads with BTMG are not fully accounted for in resource adequacy planning and shift costs onto other transmission customers contrary to the Commission’s cost causation principles.”73 In other words, the netting of BTMG against load for calculating network cost responsibilities effectively shifts transmission costs. This ruling was upheld in the June 18, 2026 Order.74 Therefore, in the context of BTMG, FERC determined that BTMG, above a certain materiality threshold, should be considered to ensure resource adequacy

72  See PJM Tariff §§ 31.1-31.3, 31.6, 32.
73  December 18, 2025 Order, 193 FERC ¶ 61,217 at P 2.
74  June 18, 2026 Order at P 145.

PDF page 36

36

and that such BTMG output should not be netted against load. The Commission’s decision against the netting of BTMG above a materiality threshold and the stated reasons for that decision cannot be logically reconciled with the structure it proposed for the new transmission services. The very reasons that the Commission made this BTMG change are the same reasons that the new transmission services are not just and reasonable – that is, loads served by BTMG impose demands on the system (such as the need for reserves and capacity) that must be accounted for, and the new services ignore those demands on the system. On this basis, the requirement for PJM to offer these services cannot be said to be reasoned decision making and the Commission’s decision is arbitrary and capricious.75

E. The Commission’s Disregard of Reliability Considerations Underscores That
The Replacement Rate Is Not Just and Reasonable.
The new transmission service options reflect that the Commission overlooked important reliability concerns. The Commission’s ruling in the June 18, 2026 Order that the issue is premature highlights the fact that the Commission has not yet dealt with this issue.76 Further, the June 18, 2026 Order continues to fail to address the fact that loads impact the system even when there is no net power draw on the system. The Commission acknowledges as much when it finds that the loads use the grid for load following based on gross load, not net load.77 Protective systems, even when fully functioning, are intended to keep net load at zero or below, but as the Commission has held, it is the gross load that is being followed by resources elsewhere on the grid every minute

75  See State Farm, 463 U.S. at 43.
76 June 18, 2026 Order at P 131.
77  See December 18, 2025 Order, 193 FERC ¶ 61,217 at P 209.

PDF page 37

37

of the day, and thus using and impacting the system every minute of the day.78 The suggestion that protective systems that only address net load obviate reliability concerns ignores physical reality. Further, the Commission in the June 18, 2026 Order does not squarely address flaws in that reasoning even though they were directly raised in the record regarding risks associated with protective system failures or removal. Even if protective systems operated perfectly (and they do not necessarily work perfectly) and penalties addressed any residual risk (again, they do not, especially, and indeed, because the penalties are currently unknown), large loads may have an incentive to exceed their contract limitations for transmission service in some circumstances. The Commission has not explained how reliability planning may proceed in the face of that prospect. The Commission’s decision to direct Interim Service be offered to load served by BTMG until all Network Upgrades necessary to provide the requested Network Service are completed overlooks potential resource adequacy risks. This service is, by definition, offered before needed transmission upgrades are completed and it is unclear from the June 18, 2026 Order how it will be determined whether the load may be reliably served. The purpose of this interim service is “more rapid interconnection and operation of Co-Located Loads” and the only reliability check is a determination by PJM that it can provide “some level of interim service reliably.”79 The Commission’s decision is arbitrary and capricious. Among other things, we still do not know how PJM will determine whether it can provide “some level of interim service reliably” which is an issue that has been left for later compliance filings.80 Because “[t]he reasonableness of a rate is assessed in light of the FPA’s goals of promoting reliable service at reasonable rates and

78  See id.
79  Id. P 200.
80     June 18, 2026 Order at P 575.

PDF page 38

38

developing plentiful energy supplies,”81 and given that it is still unknown how one could reasonably determine what level of service can be provided before studies are conducted, it cannot be said that these transmission service options are just and reasonable.82 The Commission has failed to seriously take into account reliability implications in setting a replacement rate, and its decision is therefore not reasoned decision making and is arbitrary and capricious.

IV. FERC Exceeded Its Jurisdiction.
A. FERC’s Replacement Rate Violates the Major Questions Doctrine.
There is no basis to change the PJM Tariff under FPA section 206 when the purpose of the change is to provide preferential treatment or a preferred service to a certain category of customers. Such action would violate the major questions doctrine. If Congress wanted to give the

Commission authority to direct its preferred transmission service to benefit certain categories of customers, it could have done so.83 It did not do so. FERC, like all agencies, “ha[s] only those powers given to [it] by Congress, and ‘enabling legislation’ is generally not an ‘open book to which

81  Constellation Mystic Power, LLC, 45 F.4th at 1035.
82  Cf. Ameren Servs. Co. v. FERC, 880 F.3d 571, 580–81 (D.C. Cir. 2018) (finding that FERC “ma[de] no real attempt to holistically assess all of the various risks and benefits to the transmission owner caused by the addition of the upgrade facilities,” that “FERC inadequately considered [the] argument that all costs, and risks, are not baked in—that, in fact, shareholders are forced to accept incremental exposure to loss with no corresponding benefit” and therefore, that FERC’s “failure to meaningfully respond to it makes FERC’s decision arbitrary and capricious”) (footnote omitted); Advanced Energy Mgmt. All., 860 F.3d at 664–65 (explaining the Commission’s rationales that “support[ed] the Commission’s finding that the energy market rules were unjust and unreasonable,” which included a rationale that “existing generator outage provisions ‘impede PJM’s ability to ensure reliability’ because they do not give PJM the authority to rescind approval for a planned outage when there is an emergency”) (citation omitted); Cent. Hudson Gas & Elec. Corp. v. FERC, 783 F.3d 92, 111 (2d Cir. 2015) (explaining that FERC, in creating the Lower Hudson Zone, considered long-term benefits that would follow accurate price signals, including that it would “alleviate the risk of reliability problems in the long run”).
83  Cf. Whitman v. Am. Trucking Ass’ns, 531 U.S. 457, 468 (2001) (“Congress, we have held, does not alter the fundamental details of a regulatory scheme in vague terms or ancillary provisions—it does not, one might say, hide elephants in mouseholes.”); see Atl. City Elec. Co., 295 F.3d at 8 (As a federal agency, “FERC is a ‘creature of statute,’ having ‘no constitutional or common law existence or authority, but only those authorities conferred upon it by Congress. Thus, if there is no statute conferring authority, FERC has none.”) (citation omitted).

PDF page 39

39

the agency [may] add pages and change the plot line.”84 The Commission lacks authority under the FPA to order a new type of transmission service with the sole purpose to benefit some categories of load and to treat it differently from other loads that have similar system impacts and usage. Accordingly, the replacement rate directed by FERC—because it favors a narrow category of customers (i.e., load served by BTMG) without reasoned explanation—violates the requirement in the FPA that no rate by a public utility grants an undue preference or advantage or unreasonable difference in rates.85

B.  The Commission’s New Approach Infringes On State Retail Authority.

The states, not the Commission, have jurisdiction to decide when and in what
circumstances retail load will be curtailed, and how utilities should charge and treat retail customers in those circumstances. The Commission has jurisdiction over “the transmission of electric energy in interstate commerce and to the sale of electric energy at wholesale in interstate commerce,” and over “all facilities for such transmission or sale of electric energy.”86 Except as otherwise provided in the FPA, the states retain jurisdiction over “any other sale of electric energy” and “over facilities used for the generation of electric energy or over facilities used in local

84 West Virginia v. EPA, 597 U.S. 697, 723 (2022) (third alteration in original) (citation omitted); see also Midship Pipeline Co. v. FERC, 45 F.4th 867, 877 (5th Cir. 2022) (vacating part of the Commission’s order and remanding the remainder because “[t]he FERC’s interpretation of the NGA to give the agency power to determine ‘the reasonable cost’ of remediation efforts ‘change[d] the plot line’ of its enabling legislation, and was therefore erroneous” and “[t]he FERC lacks such authority under the NGA, and it likewise lacked authority to order an ALJ to make such a determination indirectly”) (second alteration in original) (quoting West Virginia v. EPA, 597 U.S. at 723).
85  16 U.S.C. § 824d(b).
86  16 U.S.C. § 824(b).

PDF page 40

40

distribution or only for the transmission of electric energy in intrastate commerce, or over facilities for the transmission of electric energy consumed wholly by the transmitter.”87 States decide how the retail obligation to serve should be met. For example, states might require the provision of backup service to retail customers who lose supply from their contracted supplier (even if that supplier is BTMG), would regulate the distribution system costs associated with such service that would be charged to the retail customer (even if the customer’s primary service is provided by BTMG), and would regulate the costs and terms of the backup service. Rather than honoring the states’ freedom and flexibility to exercise their jurisdiction over such questions, the Commission’s new rule appears to create a new federal construct that defines the extent and terms of service in such situations. That is, the Commission’s new rules leave it entirely up to the customer to specify a contract demand service level that it will purportedly not exceed, even if state law mandates that the local utility provide the customer with backup service in the event of an outage. The Commission’s conclusion that the customer will not take additional service lies in direct conflict with the states’ backup service mandates. The Commission does not have authority under the FPA to dictate the terms of retail service in that fashion. Unlike wholesale demand response programs, which “allow[] any state regulatory body to prohibit consumers in its retail market from taking part in wholesale demand response programs,” thereby “not requir[ing] any “‘action[ ] that would violate State laws or regulations,’” the Commission’s new forms of transmission services provide no such limitation.88 As the Supreme Court has explained, however, “if indirect or tangential impacts on wholesale electricity rates sufficed, FERC could regulate now in one industry, now in another, changing a vast array of rules

87  Id.
88  FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 275 (2016) (third alteration in original) (citation omitted).

PDF page 41

41

and practices to implement its vision of reasonableness and justice,” a result that the Court could not “imagine . . . was what Congress had in mind.”89 That is the problem here with FERC’s replacement rate.

As the Supreme Court explained, the FPA
“limit[s] FERC’s sale jurisdiction to that at wholesale,” reserving
regulatory authority over retail sales (as well as intrastate wholesale
sales) to the States. FERC cannot take an action transgressing that
limit no matter how direct, or dramatic, its impact on wholesale
rates. Suppose, to take a far-fetched example, that the Commission
issued a regulation compelling every consumer to buy a certain
amount of electricity on the retail market. Such a rule would
necessarily determine the load purchased on the wholesale market
too, and thus would alter wholesale prices. But even given that
ineluctable consequence, the regulation would exceed FERC’s
authority, as defined in § 824(b), because it specifies terms of sale
at retail—which is a job for the States alone.90
FERC’s CD Services similarly interfere with States’ regulation of the terms of sale at retail, dictating the terms and circumstances of service to end use customers who lose their contracted retail power supplier—an area that is directly within the States’ domain. The Commission is unable to do indirectly what it cannot do directly, which is what it does when it intrudes on state regulatory authority over retail service in this fashion.91

89  Id. at 278.
90  Id. at 279–80 (alteration in original) (citations omitted).
91  Cf. Nat’l Fuel Gas Supply Corp. v. FERC, 909 F.2d 1519, 1522 (D.C. Cir. 1990) (“once want of power to do this directly were established, the existence of power to achieve the same end indirectly through the conditioning power might well be doubted”) (quoting Sunray Mid-Continent Oil Co. v. FPC, 364 U.S. 137, 152 (1960) and citing Richmond Power & Light v. FERC, 574 F.2d 610, 620 (D.C. Cir. 1978) (the Commission may not achieve indirectly through conditioning power of Federal Power Act what it is otherwise prohibited from achieving directly)); Am. Gas Ass’n, 912 F.2d at 1510 (“[T]he Commission may not use its § 7 conditioning power to do indirectly . . . things that it cannot do at all.”); see also FERC v. Elec. Power Supply Ass’n, 577 U.S. at 288 (“The FPA ‘leaves no room either for direct state regulation of the prices of interstate wholesales’ or for regulation that ‘would indirectly achieve the same result.’”) (citation omitted).

PDF page 42

42

The Commission should leave retail service questions to the retail regulator. The imposition of CD Service rates to usurp these questions exceeds the Commission’s lawful authority.

V. Conclusion
Because neither the Commission nor any other complainant have satisfied their burden under FPA section 206 and the Commission has not engaged in reasoned decision making in the June 18, 2026 Order, the Commission should grant rehearing, revoke its directives June 18, 2026 Order to establish new transmission service offerings for load served by BTMG, and instead, take no action pursuant to section 206 and find that the existing PJM Tariff is just and reasonable.

Respectfully submitted,

/s/ William Sauer
William Sauer
Vice President, Federal Regulatory
Affairs
Exelon Corporation
701 Ninth St. N.W.
Washington, DC 20001
Telephone: 202-868-7499
Email: william.sauer@exeloncorp.com
/s/ Bradley R. Perkins
Bradley R. Perkins
Vice President and Deputy General Counsel
Exelon Corporation
Chase Building
10 S. Dearborn, 52nd Floor
Chicago, IL 60603
(312)394-2632
Telephone: 312-394-2632
Email: bradley.perkins@exeloncorp.com

On behalf of Exelon Corporation

/s/ Amanda P. Parker
Amanda P. Parker
Corporate Counsel
FirstEnergy Service Company
341 White Pond Drive
Akron, OH 44320
Telephone: (330) 384-4592
Email: aparker@firstenergycorp.com

On behalf of The FirstEnergy
Transmission Companies

PDF page 43

43

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list in the above captioned dockets.

Dated at Chicago, IL this 20th day of July, 2026.

/s/ Geneva Kennedy

Geneva Kennedy
Exelon Corporation