Exelon Corporation and FirstEnergy Service Company submit Request for Rehearing of the 06/18/2026 Order
Text extracted from the eLibrary original (SHA-256 d5fec07de81e3c82…). Download the original from the official source.
Contents · 15 sections
- I. Statement of Issues/Specification of Error.
- II. The Burden Under FPA Section 206 Has Not Been Met: The Existing Rate
- A. There is No Evidence In The Record That Loads Served by BTMG Are
- B. The Commission Did Not Engage in Reasoned Decision Making Because It
- C. The Loads Rely Upon The Entire Embedded Transmission System To Serve
- III. The Burden Has Not Been Met Under FPA Section 206: FERC’S Replacement
- A. Allowing Special Treatment For Load Served by BTMG Violates The FPA’s
- B. The Commission’s Emphasis On Protective Systems Is In Tension With The
- C. The June 18, 2026 Order is Arbitrary And Capricious To the Extent it Adopts
- D. The Commission Is Wrong In Suggesting That CD Service Will Promote
- E. The Commission’s Disregard of Reliability Considerations Underscores That
- IV. FERC Exceeded Its Jurisdiction.
- A. FERC’s Replacement Rate Violates the Major Questions Doctrine.
- B. The Commission’s New Approach Infringes On State Retail Authority.
- V. Conclusion
Read topic-matched comments in ER26-1479
Topics in the text: Filing procedure · Connecting load and generation · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
ER26-1479-000 REQUEST FOR REHEARING OF EXELON CORPORATION AND FIRSTENERGY SERVICE COMPANY Pursuant to Federal Power Act (“FPA”) section 3131 and Rule 7132 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”), Exelon Corporation3 and FirstEnergy…Read this passage Filed comments: Filing procedure
I. Statement of Issues/Specification of Error.
printed heading · Topic match: Connecting load and generation
Cir. 2010) (“[T]he Commission ‘must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record.’”) (citation omitted); Consol.Read this passage Filed comments: Connecting load and generation
II. The Burden Under FPA Section 206 Has Not Been Met: The Existing Rate
printed heading
The FPA requires that the rates and charges of a public utility “in connection with the transmission or sale of electric energy subject to the jurisdiction of the Commission, and all rules and regulations affecting or pertaining to such rates or charges shall be just and reasonable.”8 “[A]ny such…Read this passage
A. There is No Evidence In The Record That Loads Served by BTMG Are
printed heading · Topic match: Connecting load and generation
The Commission states that, it continues to be just and reasonable for an Eligible Customer taking transmission service on behalf of Co-Located Load to elect, as one of the required transmission services from which the Eligible Customer must choose, to take NITS. . . .Read this passage Filed comments: Connecting load and generation
B. The Commission Did Not Engage in Reasoned Decision Making Because It
printed heading · Topic match: Filing procedure
As an initial matter, picking and choosing customers to receive preferential rate treatment runs contrary to the FPA’s requirement that “[n]o public utility shall, with respect to any 26 See Fla.Read this passage Filed comments: Filing procedure
C. The Loads Rely Upon The Entire Embedded Transmission System To Serve
printed heading
The Loads Rely Upon The Entire Embedded Transmission System To Serve Their Full Gross Load.Read this passage
III. The Burden Has Not Been Met Under FPA Section 206: FERC’S Replacement
printed heading
All., 860 F.3d at 663 (“If the Commission finds that a rate is ‘unjust, unreasonable, unduly discriminatory or preferential, the Commission shall determine the just and reasonable rate … and shall fix the same by order,’” and “[i]t is the Commission’s job—not the petitioner’s—to find a just…Read this passage
A. Allowing Special Treatment For Load Served by BTMG Violates The FPA’s
printed heading
Interconnecting to the grid burdens the system by adding new loads and operating contingencies that must be addressed by system operators.Read this passage
B. The Commission’s Emphasis On Protective Systems Is In Tension With The
printed heading
Cir. 2014) (per curiam)) (“The cost-causation principle requires that ‘[t]he cost of transmission facilities . . . be allocated to those within the transmission planning region that benefit from those facilities in a manner that is at least roughly commensurate with estimated benefits.’”). 56 See…Read this passage
C. The June 18, 2026 Order is Arbitrary And Capricious To the Extent it Adopts
printed heading · Topic match: Connecting load and generation
The only exception is when the transmission system requires upgrades to accommodate requests by generators (not load) to interconnect.Read this passage Filed comments: Connecting load and generation
D. The Commission Is Wrong In Suggesting That CD Service Will Promote
printed heading · Topic match: Reliability and curtailment
Grid operators must plan for such eventualities to ensure system reliability.72 The Commission finds in the December 18, 2025 Order that the BTMG “rules in PJM’s Tariff are no longer just and reasonable because loads with BTMG are not fully accounted for in resource adequacy planning and shift…Read this passage Filed comments: Reliability and curtailment
E. The Commission’s Disregard of Reliability Considerations Underscores That
printed heading · Topic match: Reliability and curtailment
The Commission’s decision to direct Interim Service be offered to load served by BTMG until all Network Upgrades necessary to provide the requested Network Service are completed overlooks potential resource adequacy risks.Read this passage Filed comments: Reliability and curtailment
IV. FERC Exceeded Its Jurisdiction.
printed heading
IV.Read this passage
A. FERC’s Replacement Rate Violates the Major Questions Doctrine.
printed heading
FERC’s Replacement Rate Violates the Major Questions Doctrine.Read this passage
B. The Commission’s New Approach Infringes On State Retail Authority.
printed heading · Topic match: Retail and wholesale authority
The Commission does not have authority under the FPA to dictate the terms of retail service in that fashion.Read this passage Filed comments: Retail and wholesale authority
V. Conclusion
printed heading · Topic match: Filing procedure
Conclusion Because neither the Commission nor any other complainant have satisfied their burden under FPA section 206 and the Commission has not engaged in reasoned decision making in the June 18, 2026 Order, the Commission should grant rehearing, revoke its directives June 18, 2026 Order to…Read this passage Filed comments: Filing procedure
CERTIFICATE OF SERVICE
printed heading
Dated at Chicago, IL this 20th day of July, 2026. /s/ Geneva Kennedy Geneva Kennedy Exelon CorporationRead this passage