ER26-1479-001 · 2026-07-20 · Eolian, L.P.Calibrant EnergyVerrus LLC

Eolian, L.P., et. al. submit Request for Clarification or, in the Alternative, Rehearing of the 06/18/2026 Order

PDF page 1

1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.,

Docket Nos. EL25-49-000
                      EL25-49-002
Large Loads Co-Located at
Generating Facilities
                      AD24-11-001
Constellation Energy Generation
L.L.C.
v. PJM Interconnection, L.L.C.
                      EL25-20-001
                      (consolidated)

PJM Interconnection, L.L.C.
                      ER26-1479-000

REQUEST FOR CLARIFICATION OR, IN THE ALTERNATIVE, REHEARING
OF EOLIAN, L.P., CALIBRANT ENERGY HOLDINGS, LLC, AND VERRUS, LLC
Pursuant to section 313(a) of the Federal Power Act (“FPA”), 16 U.S.C. § 825l (2024), and Rule 713 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission” or “FERC”),1 Eolian, L.P. (“Eolian”), Calibrant Energy Holdings, LLC (“Calibrant”), and Verrus, LLC request clarification, and the in alterative rehearing of the Commission’s June 18 Order in the above-captioned proceeding (Order). In brief, we seek clarification of two aspects of the Order concerning the new Interim Network Integration Transmission Service (“Interim NITS”). First, the Commission should clarify that PJM's tariff must generally describe the reliability principles and circumstances under which these services may be curtailed, and not merely their relative curtailment priority. Second, the Commission

1 18 C.F.R. § 385.713.

PDF page 2

2
should clarify that a transmission customer taking Interim NITS may rely on any resource whose capacity is not committed to be delivered to PJM or another entity during curtailment events. LIST OF ERRORS/STATEMENT OF ISSUES

We seek clarification or rehearing on two issues:
1. The Commission should clarify that, in providing details on the curtailment priority of Interim NITS, non-firm and firm contract demand service vis-à-vis existing transmission services, PJM must specify at least the general reliability circumstances under which curtailment may occur.

a. Failure to provide clarity on these service terms fails to adequately specify tariff terms as required by the Federal Power Act. See 16 U.S.C. § 824d(c); City of Cleveland v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985); Hecate Energy Greene County 3 LLC v. FERC, 72 F.4th 1307, 1314 (D.C. Cir. 2023).

b. Lack of specificity in curtailment terms is unjust and unreasonable because it will make use of these services commercially unworkable and therefore will not adequately enable the avoidance of costly and inefficient transmission system buildout that may not be necessary. See 16 U.S.C. § 824d(a); PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025). c. Lack of specificity in curtailment terms risks undue discrimination as between transmission customers in application. See 16 U.S.C § 824d(a); E.ON Climate & Renewables N. Am., LLC, 137 FERC ¶ 61,076, at P 38 (2011); Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, 104 FERC ¶ 61,103, at P 11 (2003).

PDF page 3

3
2. The Commission should clarify that any resource that has not committed its capacity to PJM or another entity may be relied upon by a transmission customer taking Interim NITS during curtailment events to the extent it is capable of delivering capacity to the customer.

a. Prohibiting such resources from offering their services to Interim NITS customers during curtailment events would not be just and reasonable because it would prevent efficient use of Interim NITS and unreasonably deny resources the opportunity to sell their services. See 16 U.S.C. § 824d(a); PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025);

Electric Storage Participation in Markets Operated by Regional
Transmission Organizations and Independent System Operators, Order
No. 841, 162 FERC ¶ 61,127 (2018).
b. Prohibiting such resources from offering their services to Interim NITS customers during curtailment events would be unduly discriminatory

because all resources whose services are not committed to PJM or another entity are similarly situated to the two specific classes of resources the Commission requires PJM to allow Interim NITS customers to rely upon. See 16 U.S.C. § 824d(b); Associated Gas Distributors v. FERC, 824 F.2d 981, 998 (D.C. Cir. 1987); Consol. Edison Co. of N.Y. v. FERC, 45 F.4th 265, 281 (D.C. Cir. 2022); El Paso Natural Gas Co. Aera Energy, L.L.C., 104 FERC ¶ 61,045, at P 115 (2003); N.Y. Indep. Sys. Operator, Inc., 162 FERC ¶ 61,124, at P 10 (2018).

To the extent that the requested clarifications are denied, we respectfully request rehearing.

II. The Commission Should Clarify that PJM Must Describe the General Reliability Circumstances Pursuant to Which Interim NITS, Non-Firm and Firm Contract Demand Services May Each Be Curtailed.

The June 18 Order “disagree[s] with commenters that PJM must provide specific details in its Tariff, such as the trigger and procedures for curtailment of Interim NITS and FCD or NFCD transmission services, or how PJM will enforce its curtailment procedures.”2 It finds that “requiring PJM to specify the curtailment priority of [the] new transmission services in its Tariff, while leaving specific implementation details in its manuals and individual service agreements, provides transmission customers sufficient certainty as to their priority relative to other

2 Order at P 552.

PDF page 4

4
transmission services and ensures that PJM has sufficient flexibility to preserve system reliability in varying operating conditions.”3

As a general matter, Eolian believes that a unified, specific approach to reliability triggers for non-firm service adopted across grid operators and based on existing reliability frameworks would provide clear and consistent rules of the road to developers of load and generation resources, thereby reducing transaction costs, and facilitating the scale-up of efficient, cost- effective business models for the development of load and supply designed to take advantage of non-firm service. And by basing such triggers on transparent, actionable, and already-established reliability criteria—such as limiting resource adequacy-based curtailment to NERC energy emergency alert thresholds of EOP-011, and limiting transmission security-based curtailment based on market-based dispatch of a dispatchable load bidding at the cap—a clear and consistent trigger across regions would provide grid operators controls within the existing reliability framework and procedures that ensure adequate system reliability.4 And by basing such triggers on the existing reliability framework and procedures, regions can avoid needless disputes about application of business practices. While we urge the Commission to consider providing all regions with direction or other encouragement to adopt such criteria, we recognize that this proceeding may not be the appropriate place for the Commission to establish such a specific, nationwide rule.

3 Id.
4 See Attachment A, Affidavit of Andrew Levitt on Behalf of Eolian, L.P. (July 17, 2026) (“Levitt Affidavit”) (explaining the benefits of a clear standard, and reasons to set the curtailment trigger for resource adequacy events at EEA2 and for transmission security events based on market- based dispatch of a dispatchable load as a suitable trigger for transmission security, with a cap on bid prices (e.g., $3,700/MWh, as for certain demand response in PJM today)).

PDF page 5

5
Nonetheless, we request clarification, or in the alternative, rehearing, of the Commission’s findings because while “specific details” regarding the curtailment trigger may be appropriately included in the business practices manuals, Commission precedent and case law interpreting the Federal Power Act make clear that the tariff must at least describe generally when curtailment will occur. Moreover, including such general circumstances in the tariff will help avoid commercial uncertainty that risks undermining the Commission’s objectives in requiring PJM to establish these new transmission services in the first place. PJM must at minimum provide tariff language that not only specifies curtailment priority order but also explains the reliability circumstances when curtailment may occur. PJM’s proposal has not cleared that low bar. The Commission should provide further guidance to PJM, which would set the stage for PJM to follow up with manual language establishing workable specific implementation details that enable commercial investments while ensuring reliable system operations.5 Providing the general boundaries for curtailment would be consistent with PJM’s tariff terms for other types of transmission service.6 Far from compromising system operations, providing more guidance on curtailment triggers will ameliorate potential challenges to dispatch coordination.7 PJM’s far more detailed tariff provisions on curtailment for products such as demand response help support investments into such resources, which enhances system reliability.8 More specificity regarding when transmission services may be curtailed would do the same.

5 As Andrew Levitt describes in affidavit attached hereto as Attachment A, a reasonable standard—though not necessarily the only reasonable standard—would establish that non-firm NITS and non-firm contract demand service may be curtailed when specific resource adequacy or transmission security triggers occur. Levitt Affidavit at 7-11.
6 Id. at 5-6.
7 Id.
8 Id.

PDF page 6

6
As described in the attached affidavit of Andrew Levitt, PJM’s proposal does not set any limit on the circumstances in which it may curtail customers taking the new transmission services, because while it provides that such customers will be curtailed before pre-emergency demand response, it provides no condition after which such curtailment will be called.9 As explained in the Joint Co-Location Developers Reply Brief, “[t]his open-ended process . . . theoretically allows PJM to curtail such services at any time.”10 Without any boundary limiting the conditions under which curtailment may occur (e.g. limiting curtailment to certain defined reliability circumstances), the tariff proposal fails to provide adequate notice of its service terms. The Commission’s Order requires PJM to provide greater specificity insofar as PJM must amend its proposal to provide for the relative curtailment priority of these new transmission services and PJM’s existing services. Depending on how PJM responds, however, this may not necessarily guarantee that PJM will book-end its proposal to provide a clear boundary beyond which curtailment will not occur. For example, if PJM provides that curtailment of non-firm contract demand service may occur prior to curtailment of other services, then the outer boundary of when curtailment may occur would remain entirely undefined. In particular, to the extent that PJM indicates that the new services may be curtailed prior to non-firm point-to-point service, or in circumstances that differ from point-to-point service, then such a response to the Commission’s directive would fail to provide market participants with any clear limits on or ability to forecast when curtailment may be called. It is not clear that the Commission

9 Id. at 4. PJM’s proposed tariff provisions specified that PJM “may curtail Interim Network Integration Transmission Service prior to dispatching the Pre-Emergency Load Response Program as further set forth in the PJM Manuals, or in response to a transfer capability shortage as a result of system reliability conditions.” PJM Initial Brief, Illustrative Tariff, Part XI, Subpart B, § 705.2 & Subpart C, § 713.4.
10 Reply Brief of Joint Co-location Developers and Motion to Intervene Out-of-time of Calibrant, Convergent, U.S. Energy Storage Coalition, and Verrus, at 17 (filed Mar. 25, 2026).

PDF page 7

7
contemplated this circumstance and intended such open-ended levels of curtailment. As such, the Commission should clarify its order by directing PJM to include general principles and conditions where curtailment may occur when using Interim NITS. PJM could then provide additional specificity in its manuals.

Under City of Cleveland v. FERC and the Commission’s “rule of reason” precedent, a tariff must include “practices that affect rates and service significantly, that are realistically susceptible of specification, and that are not so generally understood in any contractual arrangement as to render recitation superfluous.”11 While it is true that tariffs “need not include mere implementation details,”12 the general circumstances when curtailment may occur are core to the definition of the new transmission services. As Levitt states, the “curtailment trigger is not a minor feature of the new FERC-required transmission services, but one of the key attributes that determines the value of the service and the associated impacts of the new large load on the balance of transmission customers.”13 Decisions whether to take such services hinge on the ability to estimate the depth and length of potential curtailments, and to plan for such curtailments, such as assessing the extent to which investments in on-site resources or other measures would allow the load to withstand such curtailments.14 As developers of generation,

11 773 F.2d 1368, 1376 (D.C. Cir. 1985) (emphasis in original). 12 Hecate Energy Greene County 3 LLC v. FERC, 72 F.4th 1307, 1312 (D.C. Cir. 2023)
13 Levitt Affidavit at 4.
14 See id. (“The difference between a service curtailed only during defined emergency conditions and one curtailed based on broad operational discretion is not small, and will directly impact the investment feasibility, characteristics, and impact of each of these services.”). For example, in assessing the potential for energy storage resources located at the point of interconnection to support a transmission customer’s ability to take one of the new transmission services, a developer may assess whether a 6-hour storage resource sized to the nameplate load is likely to be sufficient to guard against curtailment risk to the level required by the load customer. Is a battery double or quadruple that size required? The answers to these questions cannot be known or even estimated without at least general guidance on the circumstances under which curtailment will be triggered.

PDF page 8

8
storage, and load resources, our development choices depend heavily on the level of curtailment risk predicted by the transmission services tariff terms. As Levitt explains, “a financial model supporting a co-location investment would need assumptions regarding expected curtailment hours, maximum event duration, seasonal concentration, event time, and whether curtailment is tied to conditions affecting the specific delivery path or to broader PJM system conditions.”15 While developers do not need certainty with respect to each of these variables, they need sufficient, general parameters of a service to make reasonable assumptions and assign informed probabilities. The vague curtailment language set forth by PJM in its proposed Tariff is so open- ended that it does not provide a basis for any particular assumptions, and so is not adequate to support investment in co-located generation, energy storage, demand response, and other resources to support transmission customers. The Commission’s directive to PJM to indicate relative curtailment order is helpful, but it does not ensure that PJM will bound curtailment in a manner necessary to ameliorate the open-ended commercial risk that its original tariff proposal would establish. While PJM asserts in its reply brief dated April 24, 2026, that  “...all generating resource that are available ...will be utilized to serve the Interim NITS customer,” that commitment does not appear in its Tariff language.

And while it is true that “even specifiable practices that significantly affect rates need not be included if they are clearly implied by the tariff’s express terms,”16 in this case neither PJM nor the Commission has pointed to any express tariff terms that imply when and how curtailment may occur. The Commission’s Order appropriately requires PJM to spell out curtailment priority of both new and existing transmission services. But if curtailment priority of the new services is

15 Id. at 4-5. 16 Hecate Energy Greene County 3 LLC v. FERC, 72 F.4th 1307, 1314 (D.C. Cir. 2023).

PDF page 9

9
not equal to existing services or nested within them, the tariff may not even imply the circumstances when curtailment may occur. The Commission’s should therefore clarify that, in addition to providing curtailment order, PJM’s tariff must at minimum set forth general reliability principles and circumstances when curtailment may occur so that it can implement these principles and provide greater detail on the circumstances in its manuals. As Levitt persuasively argues, the most efficient approach would be to provide a clear and precise curtailment directive in the tariff.17 But even general tariff language providing guidance to be implemented more precisely in a manual would be a significant improvement upon the manifestly open-ended approach taken by PJM. Such a directive would be consistent with the level of specificity set forth for non-firm point-to-point transmission service, where the tariff provides the following general direction regarding when curtailments for reliability or economic reasons may occur:

The Transmission Provider reserves the right to Curtail, in whole or in part, Non- Firm Point-To-Point Transmission Service provided under the Tariff for reliability reasons when an emergency or other unforeseen condition threatens to impair or degrade the reliability of the Transmission System or the systems directly and indirectly interconnected with Transmission Provider's Transmission System. . . . The Transmission Provider reserves the right to Interrupt, in whole or in part, Non-Firm Point-To-Point Transmission Service provided under the Tariff for economic reasons in order to accommodate (1) a request for Firm Transmission Service, (2) a request for Non-Firm Point-To-Point Transmission Service of greater duration, (3) a request for Non-Firm Point-To-Point Transmission Service

17 See Levitt Affidavit.

PDF page 10

10
of equal duration with a higher price, or (4) transmission service for Network Customers from non-designated resources.18

Notably, the point-to-point curtailment language in the tariff includes both a relative priority order of curtailment and a description of the general reliability circumstances that trigger when the service may be curtailed, thus providing a bound on how much curtailment could be anticipated based on a range of potential system conditions. To satisfy the rule of reason, the Commission must require PJM to provide at least this same level of specificity regarding the circumstances pursuant to which the new transmission services may be curtailed. PJM could satisfy such a requirement by, for example, describing in its tariff the potential reliability trigger. For instance, the tariff could allow for reliability-based curtailment when (1) an emergency or other unforeseen condition threatens to impair or degrade the reliability of the Transmission System or the systems directly and indirectly interconnected with Transmission Provider’s Transmission System, as evaluated consistent with NERC reliability standards, or (2) when no generating resource is available (i.e., not on outage or otherwise unable to be brought on-line in a timely manner) to serve the customer. Under the rubric of this broad framework, PJM could then set forth the specific curtailment triggers in its manuals. For example, as Levitt explains, PJM should set forth specific resource adequacy and transmission security curtailment triggers (including both pre- and post-contingency actions), so as to support commercial investments and reliable system operations.19

Providing this basic (or even a much more detailed) set of curtailment guidelines in the tariff would not compromise PJM’s ability to preserve system reliability in varying operating

18 PJM, Intra-PJM Tariffs, OATT, § II.14.7 Curtailment or Interruption of Service.
19 Levitt Affidavit at 8-11.

PDF page 11

11
conditions, and is in fact necessary to ensure the service terms are just and reasonable and not unduly discriminatory. Rather, as set forth in Levitt’s affidavit, greater detail from PJM would enhance orderly system operations. Providing at least a general description of curtailment triggers in the tariff will enhance reliability by supporting greater use of non-firm NITS and contract demand transmission services. In fact, based on our commercial experiences as long- standing developers of co-located load, generation, and storage resources, at least this level of certainty is necessary for a material number of projects to use these services. By their nature, these services each give PJM a greater set of curtailment options than were the customers to instead take NITS. In contrast, failure to provide even the general circumstances when curtailment may occur is not just and reasonable because it will not support investments that avoid costly and inefficient transmission system buildout. This was the very basis of the Commission’s co-location order.20 Additionally, leaving curtailment decisions unbounded and at the complete discretion of PJM risks introducing the prospect of discriminatory treatment of similarly situated transmission customers. Without even general curtailment conditions, PJM need not work to call curtailment consistently across customers or time based on verifiable reliability conditions. The prospect of differential treatment will further undermine customer interest in these services and can introduce undue discrimination in the practical application of

20 See PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 at P 160 (Dec. 2025) (“December Co- Location Order”) (highlighting the potential avoidance of transmission system costs as a principal benefit of the new transmission services).

PDF page 12

12
the tariff.21 These risks can be resolved by including “a standard set of procedures as part of the OATT.”22

Clarification about the need for some general guidelines on curtailment trigger, beyond just that which may but need not necessarily be implied by curtailment priority order, is necessary to achieve the Commission’s objectives.

III. The Commission Should Clarify that PJM Must Allow Load Taking Interim NITS to Rely on Any Resource Not Obligated to Deliver to PJM or Another Entity

The Commission’s Order addresses the question whether an Interim NITS customer may access a Co-Located Generator during curtailments (i.e., the transmission customer’s curtailment obligation is reduced according to the output of its Co-Located Generator). It finds that “it is just and reasonable to prohibit the Eligible Customer taking Interim NITS on behalf of Co-Located Load from drawing energy from the Co-Located Generator when the Eligible Customer is curtailed, if the Co-Located Generator is a capacity resource.”23 At the same time, however, the Commission identifies two specific circumstances where “such a restriction would not be applicable”24: (1) “if the associated Co-Located Generator does not yet have any interconnection service or has only provisional interconnection service”; or (2) “if the associated Co-Located Generator is seeking capacity resource status, but [has] not yet obtained such status.”25

21 E.ON Climate & Renewables N. Am., LLC, 137 FERC ¶ 61,076, at P38 (2011) (“The Commission would find any policy that creates opportunities for such discriminatory behavior to be unacceptable”).
22 Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, 104 FERC ¶ 61,103, at P 11 (2003), order on reh'g, Order No. 2003-A, 106 FERC ¶ 61,220, order on reh'g, Order No. 2003-B, 109 FERC ¶ 61,287 (2004), order on reh'g, Order No. 2003-C, 111 FERC ¶ 61,401 (2005), aff'd sub nom. Nat'l Ass'n of Regulatory Util. Comm'rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007) (“A standard set of procedures as part of the OATT . . . will minimize opportunities for undue discrimination”).
23 Order at P 576. 24 Id.
25 Id.

PDF page 13

13
The reasonable implication of these findings is that a co-located resource may be relied upon where it is not a Generation Capacity Resource under the PJM tariff or is not otherwise obligated to deliver its services to PJM or another entity apart from the relevant transmission customer taking Interim NITS. Eolian agrees that it is reasonable to bar resources from delivering solely to the Interim NITS customer when they are obligated to serve Network Load.26 However, clarification is needed to confirm that all resources not obligated to deliver to PJM or another entity are eligible to support Interim NITS customers, because the Commission explicitly requires tariff modification only with regard to the specific circumstances it discusses27—leaving out additional circumstances for which a co-located resource could provide capacity to its co-located load without being a Generation Capacity Resource. To more completely effectuate the principle that the Commission is reasonably aiming at, it should make clear that PJM must allow a transmission customer taking Interim NITS to rely on any resource whenever it is not obligated to deliver to PJM or another entity apart from the relevant load taking Interim NITS.

The key challenge which the Commission’s ordering language does not necessarily overcome is that for Interim NITS to be commercially workable, most loads must be able to rely upon a co-located or electrically proximate resource until the load’s network upgrades are completed. Where the load is developed in conjunction with a new generation resource, the load’s network upgrades may not be completed on the same timeline as network upgrades required to interconnect the storage or generation capacity resource. If the interconnection of non-provisional CIRs proceeds faster than that of firm service to load, the Interim NITS

26 Id. (“capacity resources have an obligation to serve Network Load”). 27 Id.

PDF page 14

14
customer will nonetheless still need to rely on the co-located generator. For many, if not most, large load customers, the prospect of curtailment without access to a co-located generator or storage resource to help avoid outage is not commercially tenable. Such large load customers are unlikely to invest, directly or through offtake agreements, in co-located or electrically proximate generation if they cannot rely on such generation before network upgrades are completed and NITS is provided. As a result, the very services that the Commission has found are necessary are likely to go underutilized, substantially undermining the policy objectives that the Commission is seeking.28 Put simply, if transmission customers are not given tools to control their own curtailment risk when relying on Interim NITS, the service will not facilitate more timely access to the transmission system.

But this challenge is addressable through clarification of the Commission’s language and through PJM’s development of new interconnection service options pursuant to the Commission’s June 18 large load show cause order.29 While the Commission offers only two specific examples of cases where the Interim NITS customer may rely on generation resources, there is a broader range of circumstances where co-located or electrically proximate generation should be able to be relied upon. For example, PJM offers Energy Resource Interconnection Service, pursuant to which resources may obtain interconnection rights that do not grant them Generation Capacity Resource status, or otherwise obligate them to deliver to PJM.30 PJM may

28 See, e.g., December Co-Location Order at P 201 (finding “that this new interim, non-firm transmission service will facilitate the timely provision of transmission service to Eligible Customers taking transmission service on behalf of Co-Located Loads”).
29 See PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, at PP 95-101 (2026) (preliminarily finding that PJM must provide new generator interconnection study procedures and services to prevent “unnecessary interconnection delays” and “unnecessary delays and costs on transmission customers”).
30 See, e.g., PJM Manual 14A, at section 5 (2026) (explaining how PJM offers Energy Resource interconnection service in addition to Capacity Resource interconnection service).

PDF page 15

15
develop future interconnection pathways, such as generator interconnection mechanisms in response to the Commission’s June 18 show cause order,31 which either do not vest a resource with Generation Capacity Resource status or else facilitate the delay in such status pending an interim period where the resource is dedicated to the load with which it is paired. In addition, transmission customers taking Interim NITS may seek to rely on behind-the-meter resources. Where these resources are not used to enable the associated load to offer into the capacity market as demand response, their capacity is not committed to PJM. The Commission’s Order expressly extends eligibility for the new transmission services to “Eligible Customers taking transmission service on behalf of load with BTMG” because such customers “are willing and able to limit their energy withdrawals from the transmission system under certain conditions.”32 This conclusion would make little sense were such customers unable to rely on their behind-the-meter generation to support the load when Interim NITS is curtailed.

In the event that the Commission intended to limit load to relying on co-located generators under only the explicitly named circumstances, it should reverse that position on rehearing. It would be unjust and unreasonable to bar Interim NITS from relying on non-capacity resources. This is true both because workable commercial arrangements necessary to support Interim NITS rely on the ability of transmission customers to rely on non-capacity resources to prevent curtailment, and because Commission precedent dictates that resources should be permitted to offer the services that they are technically capable of providing. Further, it would not be just and reasonable and would be unduly discriminatory to restrict the use of such resources to prevent curtailment when such use would be consistent with

31 See PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, at PP 95-101 (2026).
32 Order at P 91.

PDF page 16

16
their reliability obligations and reliable system operations. While the Commission reasonably rests its prohibition of reliance on capacity resources upon the determination that “capacity resources have an obligation to serve Network Load,”33 this logic does not extend to prohibiting reliance on resources that are not obligated to offer into the capacity market, or that do not clear the market to take on a capacity commitment where such resources have not otherwise committed themselves to deliver to another entity. Commission precedent supports the proposition that it is unjust and unreasonable for RTOs to foreclose the ability of resources to sell services where they are technically capable of providing them.34 Just as barriers to wholesale market participation of energy storage resources reduces market competition and thereby contribute to unjust and unreasonable rates, barriers to the use of resources technically capable of supporting Interim NITS customers will limit the use of that service below efficient levels and thereby render rates unjust and unreasonable. Moreover, barring use of generation, storage, or other resources to meet the demand of Interim NITS customers during a curtailment event when such resources are—like the resources in the specific circumstances identified by the Commission—technically capable of providing service to Interim NITS customers and free from Network Load capacity service obligations, would constitute undue discrimination.35

33 Id. P 576.
34 See, e.g., Order No. 841, 162 FERC ¶ 61,127, at PP 19-20 (2018) (finding that tariffs are unjust and unreasonable where they impose barriers to wholesale market participation by energy storage resources technically capable of providing service).
35 16 U.S.C. § 824d(b); Associated Gas Distributors v. FERC, 824 F.2d 981, 998 (D.C. Cir. 1987) (the Act's "concern about undue discrimination" extends to all similarly situated parties); Consol. Edison Co. of N.Y. v. FERC, 45 F.4th 265, 281 (D.C. Cir. 2022) (The Commission must provide an adequate explanation to justify treating similarly situated parties differently") (cleaned up); El Paso Natural Gas Co. Aera Energy, L.L.C., 104 FERC ¶ 61,045, at P 115 (2003) ("Discrimination is undue when there is a difference in rates or services among similarly situated customers that is not justified by some legitimate factor."); N.Y. Indep. Sys. Operator, Inc., 162 FERC ¶ 61,124, at P 10 (2018) (finding entities are similarly situated where they are “equally capable of providing [a] service, notwithstanding other significant differences.”).

PDF page 17

17
 For the foregoing reasons, the Commission should grant the requested clarifications or, in the alternative, grant rehearing.

Respectfully submitted,

/s/ Eric Stoutenburg
Eric Stoutenburg
Eolian L.P.
988 Howard Ave. Suite 200,
Burlingame, CA 94010
eric.stoutenburg@eolianenergy.com

/s/ Gabe Tabak
Gabe Tabak
Head of Energy Policy
Verrus, LLC
918 N Rengstorff Ave.
Mountain View, CA 94043
gabe@verrusdata.com

/s/ Judith Judson
Judith Judson
Executive Vice President of Regulatory and Polcy
Calibrant Energy
4830 W. Kennedy Blvd, Suite 600
Tampa, Florida 33609
judith.judson@calibrantenergy.com

PDF page 18

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Commission in this proceeding.

Dated: July 20, 2026
/s/ Eric Stoutenburg
Eric Stoutenburg
Eolian L.P.
988 Howard Ave. Suite 200,
Burlingame, CA 94010
eric.stoutenburg@eolianenergy.com

PDF page 19

Attachment A

PDF page 20

Affidavit of Andrew Levitt
Docket No. EL25-49-000 et al. | Page 1 of 13

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al.,

Docket Nos. EL25-49-000
                      EL25-49-002
Large Loads Co-Located at Generating Facilities

                      AD24-11-001
Constellation Energy Generation L.L.C.
v. PJM Interconnection, L.L.C.
                      EL25-20-001
                      (consolidated)

PJM Interconnection, L.L.C.
                      ER26-1479-000
AFFIDAVIT OF
ANDREW LEVITT
ON BEHALF OF
EOLIAN, L.P.
July 20, 2026

PDF page 21

Affidavit of Andrew Levitt
Docket No. EL25-49-000 et al. | Page 2 of 13
I. QUALIFICATIONS
1
My name is Andrew Levitt. I am a Senior Consultant at The Brattle Group (Brattle). 2

I am an expert on wholesale market design and reliability implications of changes in the power 3

system. I have consulted to Independent System Operators and Regional Transmission 4

Organizations (ISO/RTOs) such as the Midcontinent Independent System Operator (MISO), the 5

New York Independent System Operator (NYISO), the Alberta Electric System Operator 6

(AESO), and the Independent Electricity System Operator (IESO) of Ontario, and helped other 7

clients navigate ISO/RTO changes nationwide. Prior to joining Brattle in 2022, I was on staff at 8

PJM for seven years (most recently as Lead Market Designer), where I developed reforms to 9

reliably integrate new resource types. I hold an MMP from the University of Delaware and a BSc 10

in physics from the University of Toronto.
11
I have worked extensively on the benefits of co-located load and generation and how these 12

arrangements can be facilitated to reduce costs, achieve faster connection of new loads and 13

generation, and ensure reliability. This includes co-authored affidavits and reports in prior filings 14

before the Federal Energy Regulatory Commission (FERC or Commission) on co-location 15

including an affidavit on behalf of Eolian filed in FERC Docket No. RM26-4-000 16

on Interconnection of Large Loads to the Interstate Transmission System and a report on behalf 17

of Bloom Energy filed in Docket EL25-49-000 on Accelerating the Integration of New Co- 18

located Generation and Loads.1
19
II. ASSIGNMENT AND SUMMARY
20
I was asked by Eolian, L.P. to assess the recent Commission Order on Rehearing, Clarification, 21

and Compliance Filing (addressing co-located large loads),2 focused on enhancing PJM’s process 22

for interconnecting and serving large loads and paired generation. We were asked to assess 23

1 Affidavit of Andrew Levitt, Aniruddh Mohan, Ryan Quint, and Sirisha Tanneeru on Behalf of Eolian Energy, Inc., before the Federal Energy Regulatory Commission in the matter of Interconnection of Large Loads to the Interstate Transmission System, Docket No. RM26-4-000, November 21, 2025; A. Levitt, J. Pfeifenberger, and
A. Mohan, Accelerating the Integration of New Co-located Generation and Loads, prepared for Bloom Energy as part of Docket No. EL25-49-000, April 23, 2025.

2 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026) (PJM Co-location Rehearing Order).

PDF page 22

Affidavit of Andrew Levitt
Docket No. EL25-49-000 et al. | Page 3 of 13
certain provisions in the order, the impacts of any challenges, and recommend potential paths 1

forward. Specifically, this affidavit addresses the implications of omitting from the tariff details 2

of the conditions under which a paired generator and large load would be curtailed. 3

We explain that substantial uncertainties about expected curtailment volumes are associated with 4

the vague and operationally unbounded description of curtailment conditions that PJM is 5

expected to file, and that this can substantially impact commercial viability and efficiency. We 6

set forth potential principles that would more precisely define curtailment conditions and allow 7

for less uncertain projections of potential curtailment volumes. We discuss different options for 8

mandatory resource adequacy and transmission security curtailment triggers.
9
We identify a NERC-defined Energy Emergency Action level 2 (EEA 2) as a suitable mandatory 10

trigger for resource adequacy, and market-based dispatch of a dispatchable load as a suitable 11

trigger for transmission security, with a cap on bid prices (e.g., $3,700/MWh, as for certain 12

demand response in PJM today) serving to communicate a desire to continue purchasing energy 13

until conventional economic actions to maintain transmission security have been exhausted. 14

Finally, we point to tariff language related to other curtailable service products in PJM to support 15

the principles associated with triggering these load reductions, and the associated Commission 16

precedent.
17
III. BACKGROUND
18
In February 2025, the Commission initiated a show cause proceeding investigating whether 19

sections of PJM’s tariff related to co-location of generation with loads are just and reasonable. 20

FERC’s subsequent Order on December 18, 2025 found that PJM’s Tariff did not address with 21

sufficient clarity and consistency the rates, terms, and conditions applicable to generators serving 22

co-located load, nor those applicable to eligible customers taking transmission service on behalf 23

of such load. It required PJM to submit a compliance filing, and initiated paper hearing 24

procedures.3 These submissions informed the Commission’s PJM co-location Rehearing Order 25

issued on June 18, 2026, setting aside some portions of the December co-location Order, 26

3 PJM Interconnection, LLC, 193 FERC ¶ 61,217 (2025) (December co-location Order).

PDF page 23

Affidavit of Andrew Levitt
Docket No. EL25-49-000 et al. | Page 4 of 13
accepting portions of PJM’s compliance filing, and requiring PJM to implement further 1

compliance directives.4
2
IV. CURTAILMENT TRIGGERS
3
IV.A. Problem Statement: The Benefits of Non-Firm Service Are
4
Impacted by Unclear Curtailment Risk
5
PJM’s recently approved proposal features unbounded uncertainty in the curtailment risk for 6

large loads paired with generators seeking to use one of the Commission’s new transmission 7

services. PJM’s approved framework establishes that such large load curtailment will be called 8

before pre-emergency demand response, but is silent on the types of conditions after which such 9

large load curtailment will be called.5 The upper limit of potential curtailments is therefore 10

unbounded, creating unnecessary uncertainty. A principled approach can be developed that 11

meets the reliability exigencies and relative priority of the non-firm large load transmission 12

services without entailing such unnecessary curtailment.  That can be achieved by establishing 13

principles for curtailment conditions or triggers, and describing the specific reliability conditions 14

that would cause PJM to issue a curtailment directive to non-firm CDS or Interim NITS 15

customers.
16
This underlying curtailment trigger is not a minor feature of the new FERC-required 17

transmission services, but one of the key attributes that determines the value of the service and 18

the associated impacts of the new large load on the balance of transmission customers. From the 19

viewpoint of prospective large-load customers, understanding curtailment triggers and the range 20

of potential curtailment volumes and patterns is critically important. The difference between a 21

service curtailed only during defined emergency conditions and one curtailed based on broad 22

operational discretion is not small, and will directly impact the investment feasibility, 23

characteristics, and impact of each of these services. As an example, a financial model 24

supporting a co-location investment will need assumptions regarding expected curtailment hours, 25

4 PJM co-location Rehearing Order.
5 PJM co-location Rehearing Order at P 551.

PDF page 24

Affidavit of Andrew Levitt
Docket No. EL25-49-000 et al. | Page 5 of 13
maximum event duration, seasonal concentration, event time, and whether curtailment is tied to 1

conditions affecting the specific delivery path or to broader PJM system conditions. Specified 2

curtailment triggers allow for a more refined assessment of how these assumptions will evolve 3

over time in the presence of growing large loads and emerging system dynamics. 4

IV.B.
The Solution is to Specify Principles for Curtailment
5
Triggers in the Tariff
6
In the PJM co-location Rehearing Order, the Commission specified that PJM must “specify the 7

curtailment priority” of the new transmission services in its Tariff, while leaving specific 8

implementation details for inclusion in the relevant PJM manuals.6 The Commission found that 9

this structure “provides transmission customers sufficient certainty as to their priority relative to 10

other transmission services and ensures that PJM has sufficient flexibility to preserve system 11

reliability in varying operating conditions.”7 However, this structure entails substantial 12

drawbacks for commercial viability and efficiency as noted above. The solution is to require that 13

PJM file in its Tariff specific curtailment principles that would enable market participants to 14

develop a more precise assessment of curtailment risk.
15
Further, such Tariff-specified curtailment principles are consistent with prior Commission 16

decisions regarding other types of curtailable load products in PJM, including firm and non-firm 17

Point-to-Point (PTP) transmission service, and the suite of pre-emergency and emergency 18

Demand Response (DR) programs offered in PJM’s markets. In these cases, the Commission 19

required or accepted Tariff language describing the circumstances in which load reduction or 20

curtailments would be required. The Commission has previously held that descriptions of 21

curtailment triggers for various transmission and market services materially affected rates, 22

charges, terms of service and were appropriately included in the PJM Tariff. Given this 23

precedent, we suggest that similar Tariff-level principles could apply to non-firm CDS and 24

Interim NITS, with the benefit of improving efficiency of investment and commercial viability 25

6 PJM co-location Rehearing Order at P 552.
7 PJM co-location Rehearing Order at P 552.

PDF page 25

Affidavit of Andrew Levitt
Docket No. EL25-49-000 et al. | Page 6 of 13
for co-located arrangements. The implementation details of these principles would still be left for 1

specification in PJM’s business practice manuals.
2
PJM’s Tariff provisions on PTP transmission service were required by the Commission to 3

include a description of curtailment triggers and associated system conditions. These descriptions 4

extend beyond a sequence of relative curtailment priorities, as the Commission has required in 5

the PJM co-location Rehearing Order. PJM’s current Tariff provisions on PTP service trace back 6

to the service provisions required by the Commission in Order 888.8 Subsequently, in Order 890, 7

the Commission reaffirmed pro-forma tariff language detailing the circumstances under which 8

firm and non-firm P2P transmission could be curtailed, explaining that these pro-forma Tariff 9

provisions “establish the terms and conditions under which a transmission provider may curtail 10

service to maintain reliable operation of the system.”9 The Tariff provisions themselves do not 11

provide a detailed operational framework (as would exist in the PJM manuals), but do provide a 12

general description of the conditions in which curtailments would occur.10
13
Similarly, in the context of PJM’s DR programs, the PJM Tariff more directly specifies the 14

operational expectations of both the pre-emergency and emergency DR categories, as found in 15

Attachment K Appendix § 8.5 (pre-emergency) and 8.6 (emergency). The Tariff explains that a 16

“pre-emergency event is implemented when economic resources are not adequate to serve load 17

and maintain reserves or maintain system reliability, and prior to proceeding into emergency 18

procedures.”11 Similarly, the Tariff explains that emergency DR is triggered “coincident with the 19

declaration of a Maximum Generation emergency,” “whenever economic generating capacity is 20

not adequate to serve load and maintain reserves or maintain system reliability.”12 The Tariff 21

8
Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities, Order No. 888, 75 FERC ¶ 61,080 at 337-339 (1996).

9 Preventing Undue Discrimination and Preference in Transmission Service , Order No. 890, 72 FR 12,266 at P 1620 (2007) (describing the Commission maintaining existing pro-forma language regarding transmission curtailments).
10  See, e.g., PJM OATT at § 14.7 (“The Transmission Provider reserves the right to Curtail, in whole or in part, Non-Firm Point-To-Point Transmission Service provided under the Tariff for reliability reasons when an emergency or other unforeseen condition threatens to impair or degrade the reliability of the Transmission System or the systems directly and indirectly interconnected with Transmission Provider's Transmission System.”)
11  PJM OATT Attachment K Appendix § 8.5.
12  PJM OATT Attachment K Appendix § 8.6.

PDF page 26

Affidavit of Andrew Levitt
Docket No. EL25-49-000 et al. | Page 7 of 13
language describing these pre-emergency and emergency conditions does not unreasonably
1
restrain PJM, instead providing PJM dispatchers express flexibility while simultaneously 2

providing market participants with a sense of the likely system conditions during which 3

curtailment responsibilities will be triggered.13
4
Notably, the genesis of PJM’s pre-emergency DR product stemmed from a challenge
5
experienced by PJM dispatchers related to the curtailment trigger for the previous generation of 6

PJM DR products.14 Previously, triggering DR would initiate emergency conditions. To resolve 7

these challenges, PJM filed a series of Tariff revisions defining its pre-emergency and 8

emergency DR frameworks, including the dispatch triggers and the implications for emergency 9

procedures.15 In light of the significant magnitude of forecasted large load additions, we observe 10

the potential for the lack of Tariff detail to create further challenges to dispatch coordination. At 11

the least, the degree of curtailment is likely to directly impact the efficiency, commercial 12

viability, and speed to power ultimately enabled by these innovative transmission services 13

conceived by the Commission.
14

13  PJM OATT Attachment K Appendix § 8.5 (pre-emergency)(“Understanding the primary responsibility of the Office of the Interconnection to maintain system security, the Office of the Interconnection will strive to exhaust, but it is not obligated to exhaust, all economic resources prior to initiating a pre-emergency event”); PJM OATT Attachment K Appendix § 8.6 (emergency)(“PJM will dispatch the resources of all Emergency Load Response Program participants (not already dispatched under the Economic Load Response Program) based on the availability, location, minimum notification time, dispatch price and/or quantity of load reduction needed, subject to transmission constraints in the PJM Region.  To give PJM dispatchers the flexibility to address reliability concerns in the most effective and timely manner and invoke the resources that offer the most assurance of effective relief of emergency conditions, the dispatch of Demand Resource Registrations may not be based solely on the least-cost resources since such dispatch shall be based not only on price, but also on availability, location, minimum notification time and/or quantity of megawatts of load or load reduction needed”).
14  PJM Interconnection L.L.C., 147 FERC ¶ 61,103 (2014) At PP 6-7 (“PJM notes, for example, that on two occasions (on July 18, 2013 and September 11, 2013) its dispatchers called on demand response when system conditions gave rise to the expectation that PJM was facing emergency conditions. PJM states that on both occasions these emergency conditions failed to materialize… PJM concludes that its existing rules have created operational inefficiencies, due to PJM’s current inability to call on demand response without first initiating emergency procedures, and PJM’s current inability to call on these demand response resources in a more precise, targeted manner”).
15  PJM Interconnection L.L.C., 147 FERC ¶ 61,103 (2014) At P 6.

PDF page 27

Affidavit of Andrew Levitt
Docket No. EL25-49-000 et al. | Page 8 of 13
IV.C.
Principles for Curtailment Triggers: Preserving Reliability
1
While Avoiding Excess Mandatory Curtailment
2
We outline potential principles for curtailment triggers to maintain reliability and meet the 3

Commission’s other objectives, including maximizing the benefits of non-firm transmission 4

services. Triggers apply to two categories of reliability: (1) resource adequacy (ensuring 5

sufficient supply) and (2) transmission security (keeping power flows within line limits). The 6

impact these triggers are likely to have on the durability and adoption of the transmission service, 7

described below, strongly indicates that these provisions materially affect rates, charges, and 8

terms of these transmission services.
9
In the first instance, triggers need to be able to maintain reliability so that the co-location 10

arrangement has a net zero impact on resource adequacy and on transmission security. Second, 11

they should feature comparable treatment to similarly situated participants. Third, they should be 12

reasonably well specified so that participants can assess curtailment risk without unnecessary 13

uncertainty. Fourth, they should not require more curtailment than necessary for meeting the 14

other principles.
15
In general, these principles can be adhered to by mandating net withdrawal reductions only after 16

ordinary economic actions have been exhausted, with such mandates grouped together with other 17

comparable curtailments. Indeed, PJM themselves have stated this principle, stating that: “…all 18

generating resources that are available (i.e., not on outage or otherwise unable to be brought on- 19

line in a timely manner) will be utilized to serve the Interim NITS customer. The Interim NITS 20

customer would only be curtailed after these actions are taken and if the system is in an 21

unreliable state due to transmission system violations or capacity/reserve shortages.”16 To avoid 22

unnecessary uncertainty in curtailment volumes that significantly impacts commercial viability 23

of the non-firm large load transmission services, PJM need only file this principle in its Tariff. 24

16  PJM Interconnection L.L.C., Reply Brief, filed in Docket No. EL25-49-000 April 24, 2026, page 20.

PDF page 28

Affidavit of Andrew Levitt
Docket No. EL25-49-000 et al. | Page 9 of 13
IV.C.1.a. Resource Adequacy Triggers
1
An RTO or other grid operator is “resource adequate” when it has sufficient generation to serve 2

load except under the most severe operating conditions. If a system does not satisfy resource 3

adequacy criteria, operators may need to rely on excessive curtailments of firm load (rotating 4

brownouts) to keep supply and demand in balance. For a paired generator and load arrangement, 5

the fundamental resource adequacy curtailment trigger is a systemwide shortage in maintaining 6

the supply-demand balance.
7
Such shortages are commonly identified through a NERC-defined energy emergency alert 8

(EEA).17 EEA Level 1 indicates that all available generation is in use; EEA Level 2 indicates that 9

load management procedures are in effect; and EEA Level 3 indicates that firm load interruption, 10

i.e., a rolling brownout, is imminent or already underway. Comparable emergency actions could 11

occur after the issuance of EEA Level 1 (prior to pre-emergency DR, with among the largest 12

curtailment exposure), during the dispatch of pre-emergency DR (prior to EEA Level 2), or 13

during PJM Emergency Procedures Step 2 (which includes issuance of EEA Level 2 and 14

simultaneous dispatch of emergency DR, the least frequent trigger that would meet definitional 15

reliability need and maximize commercial viability).18
16
This choice of trigger would have significant impacts on curtailment volumes: over the last 24 17

months, PJM has had zero EEA 3 events, two emergency demand response deployment events 18

(amounting to EEA 2 events) of 4 and 7.5 hours, and twenty-two pre-emergency demand 19

response deployment events lasting between 4.5 and 10 hours, with a median of 7.5 hours 20

duration.19 This directional trend in curtailment frequency and duration of the EEA levels is a 21

feature of their design, but the absolute value may change as supply conditions continue to 22

tighten, while weather may revert to the mean relative to the unusually high maximum 23

temperatures in PJM during the 2025 and 2026 summers.
24
Accordingly, to remain consistent with NERC definitions surrounding emergency procedures, 25

the resource adequacy triggers for serving non-firm load (or net grid withdrawals) would occur at 26

17  NERC, EOP-011-4 Emergency Operations.
18  See PJM Manual 13 at § 2.3.2.
19  PJM, Emergency Procedures – Postings, accessed July 12, 2026.

PDF page 29

Affidavit of Andrew Levitt
Docket No. EL25-49-000 et al. | Page 10 of 13
EEA 2, alongside other emergency load management curtailments and prior to initiating load 1

shed. Strictly speaking, using EEA 3 as the dispatch trigger for reducing net transmission 2

withdrawals would preserve resource adequacy (reducing the incidence of actual firm load shed) 3

while producing the least frequent curtailment. However, it does not score well for the 4

“comparable treatment” principle we outline above, since curtailment of net withdrawals from 5

co-location arrangements is effectively a form of load management, and EEA 2 corresponds to 6

“load management procedures in effect.” A trigger that is coincident with deployment of pre- 7

emergency demand response in PJM would also score well for comparable treatment, although it 8

would exhibit substantially more curtailment volume. Given PJM’s unique sequencing of load 9

management dispatch prior to the defined NERC emergency action level commensurate with 10

load management procedures, and desire to maintain conservative operations, resource adequacy 11

triggers consistent with those of pre-emergency demand response might also be appropriate. 12

PJM’s current proposal to trigger curtailments before even pre-emergency DR is called upon 13

does not score well for comparable treatment, and results in more curtailment volume than 14

necessary and reasonable.
15
IV.C.1.b. Transmission Security Triggers
16
Transmission security is required to keep power flows within the operating limits of transmission 17

facilities and maintain other reliability parameters, such as voltage and stability, within 18

acceptable bounds. Because grid conditions can change instantly, transmission facilities must 19

remain within their limits even after a single contingency, such as the loss of a generating unit or 20

transmission line. For transmission security, we outline two possible categories of triggers: 1) 21

pre-contingency actions, such as operator-directed dispatch and curtailment, and 2) post- 22

contingency actions, made available by automated remedial action schemes (RAS). To preserve 23

transmission security, a load with co-located generation (or paired generation in an electrically- 24

equivalent location) must reduce net grid withdrawals to zero when the grid operator (or an 25

automated RAS) determines that doing so is necessary.20
26

20  Under certain unlikely extreme conditions, especially when there are no protection schemes protecting against internal contingencies associated with loss of co-located generation units, gross load may need to be curtailed to zero. However, adequate design of facilities can relegate these conditions to extremely low probability, comparable to the probability of curtailing ordinary firm load due to transmission security conditions.

PDF page 30

Affidavit of Andrew Levitt
Docket No. EL25-49-000 et al. | Page 11 of 13
For transmission security events, PJM can determine the need for curtailment through Security 1

Constrained Economic Dispatch (SCED), Security Constrained Unit Commitment (SCUC), or 2

other operational planning tools. Because reducing net withdrawals generally requires curtailing 3

high-value load, the efficient approach is to treat that curtailment as a high-cost reliability action 4

and use it only after ordinary economic alternatives, including generator redispatch, have been 5

exhausted. This can be achieved by configuring the load as a dispatchable asset with a high 6

willingness to pay reflected in a bid price at some cap (such as $2,000/MWh, the offer cap for 7

setting price as a generator, or $3,700/MWh, the bid cap for price-sensitive demand in the PJM 8

day-ahead market).21
9
A SCED-based approach would likely set nodal market clearing prices for energy at the bid price 10

during curtailment. A SCUC-based approach may be less direct, especially because it can 11

include other values such as shut-down cost and no-load cost that would not be reflected in 12

prices even after being dispatched to reduce net withdrawals. Either way, the dispatch signal 13

coming from the PJM market engine can serve as the mandatory directive to reduce non-firm 14

load or net withdrawals at a co-location arrangement. The ability to bid at the price cap serves to 15

meet the principle of exhausting economic actions prior to relying on the withdrawal reduction to 16

maintain transmission security, thereby avoiding inefficient curtailment when not strictly needed. 17

This approach has the virtue of using the same mechanism by which co-location arrangements 18

can voluntarily reduce net withdrawals economically in response to market prices. This would be 19

expected when the marginal cost of the co-located generation is lower than market prices, or 20

when the site has been enabled with low-cost load flexibility.
21
For cases where SCED dispatch does not meet the instantaneous reliability needs, RASs are 22

useful to enable the automated reduction of net load (from the paired load and associated 23

generation) immediately upon appearance of certain reliability threshold conditions. These 24

conditions typically involve a contingency, such as the sudden loss of an internal generating unit 25

or a nearby transmission line. RAS is a well-established technology and can be relied upon for 26

ensuring transmission security if it conforms with reliability guidelines, such as those published 27

21  See PJM Manual 11 at § 2.3.2.1 (Fixed and Price Sensitive Demand Bid Business Rules), 2.3.3.2 (Generator Schedules), 2.17 (Applying Transmission Constraint Penalty Factors in the Market Clearing Engine).

PDF page 31

Affidavit of Andrew Levitt
Docket No. EL25-49-000 et al. | Page 12 of 13
by reliability operators who are already utilizing RAS for similar applications (WECC, CAISO, 1

and the AEMO in Australia).22
2
In practice, a RAS initiates reductions in grid withdrawals from a co-location arrangement only 3

after a contingency has actually occurred, which may be a low-probability event. Operator- 4

initiated dispatch, by contrast, tends to reduce net withdrawals from a co-location arrangement 5

for the full period during which such a reduction may be needed to prevent a hypothetical 6

contingency from causing an overload. For example, a conventional operator-initiated approach 7

may require curtailing a large load for the duration of a multi-week planned transmission outage 8

(so a second transmission outage would not cause a reliability violation), while a RAS approach 9

would require no curtailments during that entire period (unless there were an unexpected second 10

transmission contingency were to actually occur, which is very unlikely). The duration and 11

frequency of withdrawal reductions therefore are much greater for operator-initiated dispatch 12

than for RAS-based curtailments. RAS use thus supports commercial feasibility, where 13

appropriate to grid conditions and the capabilities of a co-location arrangement. RAS also allows 14

for the full utilization of transmission capability by offering automated curtailments in response 15

to a transmission contingency, whereas operator-initiated dispatch requires holding back 16

transmission headroom in case that contingency were to occur.23
17

22  WECC, Remedial Action Scheme Design Guide (July, 2022); California ISO Planning Standards (February 2, 2023), at § III; AESO, Remedial Action Scheme Guidelines (September 27, 2022).
23  See Levitt, Thomas, Pfeifenberger, Felmus, Remedial Action Schemes (RAS) to Quickly and Affordably Connect New Generation and Large Loads, presented to FERC staff (June 22, 2026). Available at https://www.brattle.com/wp-content/uploads/2026/06/Remedial-Action-Schemes-RAS-to-Quickly-and- Affordably-Connect-New-Generation-and-Large-Loads.pdf

PDF page 32

Affidavit of Andrew Levitt
Docket No. EL25-49-000 et al. | Page 13 of 13
Affidavit of Andrew Levitt

I, Andrew Levitt, do hereby swear that I have authored the Affidavit of Andrew Levitt and the statements contained therein are true and accurate to the best of my knowledge and belief.

Andrew Levitt

Date: July 20, 2026