ER26-1479-001 · 2026-07-20 · Eolian, L.P.Calibrant EnergyVerrus LLC

Eolian, L.P., et. al. submit Request for Clarification or, in the Alternative, Rehearing of the 06/18/2026 Order

Text extracted from the eLibrary original (SHA-256 783b97ea229f28e4…). Download the original from the official source.

Contents · 8 sections
  1. II. The Commission Should Clarify that PJM Must Describe the General Reliability p. 3
  2. III. The Commission Should Clarify that PJM Must Allow Load Taking Interim NITS to p. 12
  3. Attachment A p. 19
  4. I. QUALIFICATIONS p. 21
  5. II. ASSIGNMENT AND SUMMARY p. 21
  6. A. Mohan, Accelerating the Integration of New Co-located Generation and Loads, prepared for Bloom Energy p. 21
  7. III. BACKGROUND p. 22
  8. IV. CURTAILMENT TRIGGERS p. 23

Read topic-matched comments in ER26-1479

Topics in the text: Reliability and curtailment · Filing procedure · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

The Commission should clarify that, in providing details on the curtailment priority of Interim NITS, non-firm and firm contract demand service vis-à-vis existing transmission services, PJM must specify at least the general reliability circumstances under which curtailment may occur. a.
Read this passage Filed comments: Reliability and curtailment

II. The Commission Should Clarify that PJM Must Describe the General Reliability

printed heading · Topic match: Reliability and curtailment

While we urge the Commission to consider providing all regions with direction or other encouragement to adopt such criteria, we recognize that this proceeding may not be the appropriate place for the Commission to establish such a specific, nationwide rule. 3 Id. 4 See Attachment A, Affidavit of…
Read this passage Filed comments: Reliability and curtailment

III. The Commission Should Clarify that PJM Must Allow Load Taking Interim NITS to

printed heading · Topic match: Reliability and curtailment

The Commission Should Clarify that PJM Must Allow Load Taking Interim NITS to Rely on Any Resource Not Obligated to Deliver to PJM or Another Entity The Commission’s Order addresses the question whether an Interim NITS customer may access a Co-Located Generator during curtailments (i.e., the…
Read this passage Filed comments: Reliability and curtailment

CERTIFICATE OF SERVICE

printed heading

Dated: July 20, 2026 /s/ Eric Stoutenburg Eric Stoutenburg Eolian L.P. 988 Howard Ave.
Read this passage

Attachment A

printed heading

Attachment A Affidavit of Andrew Levitt Docket No.
Read this passage

I. QUALIFICATIONS

printed heading · Topic match: Connecting load and generation

I hold an MMP from the University of Delaware and a BSc 10 in physics from the University of Toronto. 11 I have worked extensively on the benefits of co-located load and generation and how these 12 arrangements can be facilitated to reduce costs, achieve faster connection of new loads and 13…
Read this passage Filed comments: Connecting load and generation

II. ASSIGNMENT AND SUMMARY

printed heading · Topic match: Filing procedure

ASSIGNMENT AND SUMMARY 20 I was asked by Eolian, L.P. to assess the recent Commission Order on Rehearing, Clarification, 21 and Compliance Filing (addressing co-located large loads),2 focused on enhancing PJM’s process 22 for interconnecting and serving large loads and paired generation.
Read this passage Filed comments: Filing procedure

A. Mohan, Accelerating the Integration of New Co-located Generation and Loads, prepared for Bloom Energy

printed heading · Topic match: Reliability and curtailment

Specifically, this affidavit addresses the implications of omitting from the tariff details 2 of the conditions under which a paired generator and large load would be curtailed. 3 We explain that substantial uncertainties about expected curtailment volumes are associated with 4 the vague and…
Read this passage Filed comments: Reliability and curtailment

III. BACKGROUND

printed heading · Topic match: Connecting load and generation

BACKGROUND 18 In February 2025, the Commission initiated a show cause proceeding investigating whether 19 sections of PJM’s tariff related to co-location of generation with loads are just and reasonable. 20 FERC’s subsequent Order on December 18, 2025 found that PJM’s Tariff did not address with 21…
Read this passage Filed comments: Connecting load and generation

IV. CURTAILMENT TRIGGERS

printed heading · Topic match: Reliability and curtailment

That can be achieved by establishing 13 principles for curtailment conditions or triggers, and describing the specific reliability conditions 14 that would cause PJM to issue a curtailment directive to non-firm CDS or Interim NITS 15 customers. 16 This underlying curtailment trigger is not a minor…
Read this passage Filed comments: Reliability and curtailment