Eolian, L.P., et. al. submit Request for Clarification or, in the Alternative, Rehearing of the 06/18/2026 Order
Text extracted from the eLibrary original (SHA-256 783b97ea229f28e4…). Download the original from the official source.
Contents · 8 sections
- II. The Commission Should Clarify that PJM Must Describe the General Reliability
- III. The Commission Should Clarify that PJM Must Allow Load Taking Interim NITS to
- Attachment A
- I. QUALIFICATIONS
- II. ASSIGNMENT AND SUMMARY
- A. Mohan, Accelerating the Integration of New Co-located Generation and Loads, prepared for Bloom Energy
- III. BACKGROUND
- IV. CURTAILMENT TRIGGERS
Read topic-matched comments in ER26-1479
Topics in the text: Reliability and curtailment · Filing procedure · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
The Commission should clarify that, in providing details on the curtailment priority of Interim NITS, non-firm and firm contract demand service vis-à-vis existing transmission services, PJM must specify at least the general reliability circumstances under which curtailment may occur. a.Read this passage Filed comments: Reliability and curtailment
II. The Commission Should Clarify that PJM Must Describe the General Reliability
printed heading · Topic match: Reliability and curtailment
While we urge the Commission to consider providing all regions with direction or other encouragement to adopt such criteria, we recognize that this proceeding may not be the appropriate place for the Commission to establish such a specific, nationwide rule. 3 Id. 4 See Attachment A, Affidavit of…Read this passage Filed comments: Reliability and curtailment
III. The Commission Should Clarify that PJM Must Allow Load Taking Interim NITS to
printed heading · Topic match: Reliability and curtailment
The Commission Should Clarify that PJM Must Allow Load Taking Interim NITS to Rely on Any Resource Not Obligated to Deliver to PJM or Another Entity The Commission’s Order addresses the question whether an Interim NITS customer may access a Co-Located Generator during curtailments (i.e., the…Read this passage Filed comments: Reliability and curtailment
CERTIFICATE OF SERVICE
printed heading
Dated: July 20, 2026 /s/ Eric Stoutenburg Eric Stoutenburg Eolian L.P. 988 Howard Ave.Read this passage
Attachment A
printed heading
Attachment A Affidavit of Andrew Levitt Docket No.Read this passage
I. QUALIFICATIONS
printed heading · Topic match: Connecting load and generation
I hold an MMP from the University of Delaware and a BSc 10 in physics from the University of Toronto. 11 I have worked extensively on the benefits of co-located load and generation and how these 12 arrangements can be facilitated to reduce costs, achieve faster connection of new loads and 13…Read this passage Filed comments: Connecting load and generation
II. ASSIGNMENT AND SUMMARY
printed heading · Topic match: Filing procedure
ASSIGNMENT AND SUMMARY 20 I was asked by Eolian, L.P. to assess the recent Commission Order on Rehearing, Clarification, 21 and Compliance Filing (addressing co-located large loads),2 focused on enhancing PJM’s process 22 for interconnecting and serving large loads and paired generation.Read this passage Filed comments: Filing procedure
A. Mohan, Accelerating the Integration of New Co-located Generation and Loads, prepared for Bloom Energy
printed heading · Topic match: Reliability and curtailment
Specifically, this affidavit addresses the implications of omitting from the tariff details 2 of the conditions under which a paired generator and large load would be curtailed. 3 We explain that substantial uncertainties about expected curtailment volumes are associated with 4 the vague and…Read this passage Filed comments: Reliability and curtailment
III. BACKGROUND
printed heading · Topic match: Connecting load and generation
BACKGROUND 18 In February 2025, the Commission initiated a show cause proceeding investigating whether 19 sections of PJM’s tariff related to co-location of generation with loads are just and reasonable. 20 FERC’s subsequent Order on December 18, 2025 found that PJM’s Tariff did not address with 21…Read this passage Filed comments: Connecting load and generation
IV. CURTAILMENT TRIGGERS
printed heading · Topic match: Reliability and curtailment
That can be achieved by establishing 13 principles for curtailment conditions or triggers, and describing the specific reliability conditions 14 that would cause PJM to issue a curtailment directive to non-firm CDS or Interim NITS 15 customers. 16 This underlying curtailment trigger is not a minor…Read this passage Filed comments: Reliability and curtailment