ER26-1479-001 · 2026-07-20 · Indicated PJM Transmission Owners

The Indicated PJM Transmission Owners submit Request for Rehearing and Clarification of the 06/18/2026 Order

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-002
)
Docket No. EL25-49-000
)
Large Loads Co-Located at Generating Facilities )

Docket No. AD24-11-001
)
Constellation Energy Generation, LLC
)
v. )
Docket No. EL25-20-001
PJM Interconnection, L.L.C.
)
(Consolidated)
)
PJM Interconnection, L.L.C.
)
Docket No. ER26-1479-000
REQUEST FOR REHEARING AND CLARIFICATION OF THE

INDICATED PJM TRANSMISSION OWNERS

PDF page 2

2
Pursuant to Section 313 of the Federal Power Act (“FPA”)1 and Rule 713 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission”),2 the Indicated PJM Transmission Owners (“PJM Transmission Owners”)3 respectfully request

rehearing of the Commission’s June 18, 2026 order in this proceeding (“June 18 Order”).4 As discussed below, the Commission should grant rehearing or provide clarification of the June 18 Order, as follows:


The Commission erred in concluding that co-located load and generation interconnected and synchronized with the transmission system should be exempt from any minimum

charge, such as the Grid Reliance Charge proposed by the PJM Transmission Owners.
The Commission failed to address the substantial evidence provided by the PJM
Transmission Owners regarding the need for such a charge.

The Commission erred by failing to address the substantial evidence provided by the PJM Transmission Owners regarding justness and reasonableness of the Grid Reliance Charge methodology for calculating such charge.


The Commission erred in rejecting the PJM Transmission Owners’ proposal to set the
maximum rate for Non-Firm Contract Demand Transmission Service at the rate for Firm
Contract Demand Service.  The Commission failed to provide an adequate reason for
rejecting PJM Transmission Owners’ proposal, in particular distinguishing the
Commission’s precedent regarding non-firm point-to-point transmission service and
addressing the PJM Transmission Owners’ explanation that further analysis and study
regarding the use of these new services would be necessary before determining the
1 16 U.S.C. § 825l(a).
2 18 C.F.R. § 385.713 (2025).
3 The PJM Transmission Owners are: American Electric Power Service Corporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc., AEP Indiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and AEP West Virginia Transmission Company, Inc.; The Dayton Power and Light Company d/b/a AES Ohio; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc.; Duquesne Light Company; East Kentucky Power Cooperative, Inc.; Exelon Corporation on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, on behalf of its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, The Potomac Edison Company, Monongahela Power Company, Keystone Appalachian Transmission Company, and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); PPL Electric Utilities Corporation; and Rockland Electric Company.
4 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026) (“June 18 Order”).

PDF page 3

3
appropriate level of discount to offer for Non-Firm Contract Demand Transmission Service.  That further study and analysis is to determine, in accordance with the principles of Order No. 888, the economically appropriate and efficient rate at the point of receipt that maximizes the use of the transmission system or signals the need to add capacity. As long as that rate is posted and offered in a non-discriminatory manner, it comports with existing precedent.  Thus, the Commission’s decision is arbitrary and capricious.5 

The Commission erred in rejecting PJM Interconnection L.L.C.’s (“PJM”) proposal to define Co-Located Load based on facilities located on the customer’s side of the Point of Change of Ownership, rather than the Point of Interconnection.  The Commission’s explanation that PJM’s proposal was barred for failure to seek rehearing of the December 18 Order is arbitrary and capricious and fails to account for the substantial evidence provided by PJM and the PJM Transmission Owners regarding the flaws of utilizing the Point of Interconnection to define Co-Located Load.


The Commission erred in rejecting PJM’s proposal to require Co-Located Load to take sufficient transmission service to cover its entire gross load.  PJM’s proposal is a just and reasonable means to ensure that Co-Located Load can be served reliably and does not threaten the integrity of the transmission system.


The Commission should clarify its ruling regarding the ability to require control technologies and/or protection systems on both the customer and Transmission Owner sides of the Point of Interconnection.  The Commission should clarify that PJM and the PJM Transmission Owners will be permitted to require protection on both the customer and Transmission Owner sides of the Point of Interconnection, to the extent that a study determines that such protection is necessary and appropriate.

I. BACKGROUND
On December 18, 2025, the Commission issued an order in the show cause proceeding in Docket Nos. EL25-49-000, et al., pursuant to section 206 of the FPA, finding PJM’s Open Access Transmission Tariff (“Tariff”) unjust and unreasonable because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to generators serving Co-Located Load and Eligible Customers taking transmission service

5 See Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. By Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036 (1996) (cross-referenced at 75 FERC ¶ 61,080), on reh’g, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 (cross-referenced at 78 FERC ¶ 61,220), on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom., Transmission Access Policy Study Grp., v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom., N.Y. v. FERC, 535 U.S. 1 (2002).

PDF page 4

4
on behalf of Co-Located Load.6  The December Order defined the Tariff as PJM’s Open Access Transmission Tariff, the Amended and Restated Operating Agreement of PJM, and the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region.7

The Commission directed PJM to file, within 60 days of the date of issuance of the December Order, a compliance filing to revise its Tariff to set forth specific terms and conditions that an Interconnection Customer in PJM seeking to serve Co-Located Load must follow to effectuate a Co-Location Arrangement.8  In addition, the Commission directed PJM to submit in its compliance filing revisions to its Tariff to require that the Eligible Customer taking transmission service on behalf of the Co-Located Load takes one of three transmission services:  (1) Network Integration Transmission Service (“NITS”), including a new interim, non-firm transmission service available until all Network Upgrades necessary to provide the requested NITS are complete (“Interim NITS”), (2) a new Firm Contract Demand (“Firm Contract Demand”) transmission service, or (3) a new Non-Firm Contract Demand (“Non-Firm Contract Demand”) transmission service.  The Commission also established a paper hearing to determine the just and reasonable rates, terms, and conditions for these new transmission services.9

Various parties filed requests for rehearing and clarification of the December Order.  On February 23, 2026, in Docket No. ER26-1479-000, PJM filed its second compliance filing as directed by the December Order.  On February 23, 2026, in Docket Nos. EL25-49-000, et al., PJM

6 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 2 (2025) (December Order).
7 December Order at P 1.
8 “Co-Location Arrangements” refers to both the Co-Located Load and the associated generator.  See December Order at n.2 (citing PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 3 & n.4 (2025)).
9 December Order at PP 2, 194, 219.  The Commission also found the Behind the Meter Generation (“BTMG”) rules in the Tariff to be no longer just and reasonable, and the Commission directed PJM to submit in its compliance filing revisions to its Tariff to revise the retail BTMG netting rules and to implement a transition process for existing BTMG participants.  Id. at PP 2, 179, 186, 221-224.

PDF page 5

5
and the PJM Transmission Owners each submitted an initial brief to address the Commission’s paper hearing questions with respect to the new transmission services.  On March 25, 2026, and on April 24, 2026, various parties submitted response briefs and reply briefs, respectively. In the June 18 Order, the Commission addressed the requests for rehearing and clarification of the December Order, PJM’s second compliance filing, and the paper hearing on the new transmission services.  The Commission found that PJM’s compliance filing partially complied with the directives of the December Order.  Accordingly, the Commission accepted in part and rejected in part PJM’s proposed Tariff revisions, and directed a further compliance filing.10 Finally, the Commission established as just and reasonable certain rates, terms, and conditions for the new transmission services directed in the December Order in response to the record developed in the paper hearing.  The Commission directed PJM and the PJM Transmission Owners to file, within 60 days of the date of issuance of the June 18 Order, compliance filings to revise the Tariff.

II. REQUESTS FOR REHEARING AND CLARIFICATION
A. Statement of Issues and Specification of Errors
The PJM Transmission Owners submit the following Statement of Issues and Specification of Errors pursuant to Rules 713(c)(1) and 713(c)(2) of the Commission’s Rules of Practice and Procedure.11


The June 18 Order’s conclusion that co-located load and generation interconnected and synchronized with the transmission system should be exempt from any

minimum charge is arbitrary and capricious, does not reflect reasoned decision- making, and is unsupported by substantial evidence in violation of the

Administrative Procedure Act (“APA”).  Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto Ins. Co., 463 U.S. 29, 43 (1983) (an agency “must examine the relevant data and articulate a satisfactory explanation for its action including a ‘rational

10 June 18 Order at P 8.
11 18 C.F.R. § 385.713(c)(1), (c)(2).

PDF page 6

6
connection between the facts found and the choices made’”) (citation omitted) (“State Farm”); Consol. Edison Co. of N.Y. v. FERC, 45 F.4th 265 (D.C. Cir. 2022); Consol. Edison Co. of N.Y. v. FERC, 347 F.3d 964, 972 (D.C. Cir. 2003); PJM Interconnection, L.L.C., 161 FERC ¶ 61,252 (2017); Fla. Gas Transmission Co. v. FERC, 604 F.3d 636, 639 (D.C. Cir. 2010) (quoting Pac. Gas & Elec. Co. v. FERC, 373 F.3d 1315, 1319 (D.C. Cir. 2004)) (“Fla. Gas”); PJM Interconnection, L.L.C., 119 FERC ¶ 61,318 (2007); Midwest Indep. Transmission Sys. Operator, Inc., 117 FERC ¶ 61,113 (2006) (“Midwest ISO”).


The June 18 Order’s rejection of the PJM Transmission Owners’ proposed Grid Reliance Charge does not reflect reasoned decision-making, and is unsupported by substantial evidence in violation of the APA.  State Farm, 463 U.S. at 43 (an agency “must examine the relevant data and articulate a satisfactory explanation for its action including a ‘rational connection between the facts found and the choices made’”) (citation omitted); Consol. Edison Co. of N.Y. v. FERC, 45 F.4th 265; Consol. Edison Co. of N.Y. v. FERC, 347 F.3d at 972 ; PJM Interconnection, L.L.C., 161 FERC ¶ 61,252; Fla. Gas, 604 F.3d at 639 (quoting Pac. Gas & Elec. Co. v. FERC, 373 F.3d at 1319); PJM Interconnection, L.L.C., 119 FERC ¶ 61,318; Midwest ISO, 117 FERC ¶ 61,113.


The June 18 Order’s rejection of the PJM Transmission Owner’s proposal to set the maximum rate for Non-Firm Contract Demand transmission service at the rate for Firm Contract Demand transmission service, subject to discount, is arbitrary and capricious, does not reflect reasoned decision-making, and is unsupported by substantial evidence in violation of the APA.  State Farm, 463 U.S. at 43 (an agency “must examine the relevant data and articulate a satisfactory explanation for its action ‘including a rational connection between the facts found and the choices made’”) (citation omitted); Consol. Edison Co. of N.Y. v. FERC, 45 F.4th 265; Consol. Edison Co. of N.Y. v. FERC, 347 F.3d at  972; PJM Interconnection, L.L.C., 161 FERC ¶ 61,252; Fla. Gas, 604 F.3d at 639 (quoting Pac. Gas & Elec. Co. v. FERC, 373 F.3d at 1319); PJM Interconnection, L.L.C., 119 FERC ¶ 61,318 (2007); Midwest ISO, 117 FERC ¶ 61,113; lll. State Chamber of Commerce v. EPA, 775 F.2d 1141 at 1147 (“[The agency] is entitled to change its policy, but it must do so on the basis of a reasoned analysis.”) (7th Cir. 1985).


The June 18 Order’s rejection of PJM’s proposal to define Co-Located Load based on facilities located on the customer’s side of the Point of Change of Ownership, rather than the Point of Interconnection, is arbitrary and capricious, does not reflect reasoned decision-making, and is unsupported by substantial evidence in violation of the APA.  State Farm, 463 U.S. at 43 (an agency “must examine the relevant data and articulate a satisfactory explanation for its action including a ‘rational connection between the facts found and the choices made’”) (citation omitted); Consol. Edison Co. of N.Y. v. FERC, 45 F.4th 265; Consol. Edison Co. of N.Y. v. FERC, 347 F.3d at 972; PJM Interconnection, L.L.C., 161 FERC ¶ 61,252; Fla. Gas, 604 F.3d at 639 (quoting Pac. Gas & Elec. Co. v. FERC, 373 F.3d at 1319);

PDF page 7

7
PJM Interconnection, L.L.C., 119 FERC ¶ 61,318; Midwest ISO, 117 FERC ¶ 61,113.


The June 18 Order’s rejection of PJM’s proposal to require Co-Located Load to take sufficient transmission service to cover its entire gross load is arbitrary and capricious, does not reflect reasoned decision-making, and is unsupported by substantial evidence in violation of the APA.  State Farm, 463 U.S. at 43 (an agency “must examine the relevant data and articulate a satisfactory explanation for its action including a ‘rational connection between the facts found and the choices made’”) (citation omitted); Consol. Edison Co. of N.Y. v. FERC, 45 F.4th 265; Consol. Edison Co. of N.Y. v. FERC, 347 F.3d at 972; PJM Interconnection, L.L.C., 161 FERC ¶ 61,252; Fla. Gas, 604 F.3d at 639 (quoting Pac. Gas & Elec. Co. v. FERC, 373 F.3d at 1319); PJM Interconnection, L.L.C., 119 FERC ¶ 61,318; Midwest ISO, 117 FERC ¶ 61,113.

B. Arguments
1. The Commission Erred in Concluding That Co-Located Load and
Generation Interconnected and Synchronized With the Transmission
System Should be Exempt From any Minimum Charge, and Rejecting
the PJM Transmission Owners’ Proposed Grid Reliance Charge.
In the June 18 Order, the Commission rejected the PJM Transmission Owners’ proposed Grid Reliance Charge, concluding that the record does not adequately substantiate the need for an additional charge for co-located load at this time or how such a charge should be calculated and assessed.12  The Commission indicated that it will consider such a charge after more experience with the actual use of the new transmission services.13  The Commission should reverse this finding on rehearing.

a. A Minimum Charge Such as the Grid Reliance Charge is
Necessary to Ensure That Co-Located Loads pay Their Fair
Share of System Costs.
The Grid Reliance Charge or some other minimum charge is a necessary component of the new transmission services required under the Commission’s December Order.  The PJM

12 June 18 Order at P 455.
13 Id. at P 456.

PDF page 8

8
Transmission Owners developed the Grid Reliance Charge partially in response to Commissioner Chang’s guidance that a just and reasonable replacement rate for the new transmission services should reflect “some form of minimum transmission service charge, which would protect other customers against cost shifts resulting from Co-Located Loads that rely upon the transmission system but do not directly or meaningfully contribute to its costs via transmission service payments.”14  The Grid Reliance Charge achieves this goal by reflecting the costs of using the transmission system to deliver black start and regulation services, as well as the costs of providing the inherent benefits that all customers, including Contract Demand customers, receive as a result of their synchronization to and reliance on the grid.

As the PJM Transmission Owners explained in their evidentiary submissions, even if a Co- Located Load customer is not procuring transmission service for its entire on-site load, being connected to the grid provides benefits in terms of the ability to access resources that are not co- located with load if necessary, backing up co-located generation, and providing critical ancillary services to Co-Located Load, such as regulation and black start.  These grid benefits also include delivering ancillary services and essential reliability services, such as frequency support, inertia, voltage stability, fault current capability, ride-through and protection coordination, and providing sufficient short-circuit capability.15  No party provided any evidence rebutting the nature of these benefits.

The purpose of a Grid Reliance Charge is not merely to recover the costs associated with the delivery of ancillary services.  Rather, its purpose is to ensure that Co-Located Load customers

14 December Order, Chang Concurrence at P 9.
15 See PJM Transmission Owners Initial Brief, Docket Nos. EL25-49-000, et al., Exhibit No. PTO-0001, Direct Joint Testimony of Peter Blazunas, Lance Schafer, and Hanhan Hammer at 18 (Feb. 23, 2026) (“Blazunas, Schafer, and Hammer Direct Testimony”); see also PJM Transmission Owners Reply Brief, Joint Rebuttal Testimony of Peter Blazunas, Lance Schafer, and Hanhan Hammer, Docket Nos. EL25-49-000, et al., Exhibit No. PTO-0005 at 16 (Apr. 24, 2026) (“Blazunas, Schafer, and Hammer Rebuttal Testimony”).

PDF page 9

9
pay their fair share of the transmission system and the associated benefits that it provides to all interconnected customers, including essential reliability services, such as frequency support, inertia, voltage stability, fault current capability, ride-through and protection coordination, and sufficient short-circuit capability.16  Even if a Co-Located Load customer never “pulls energy from the grid,” and only relies on black start and regulation service, it receives the inherent benefits that come with grid interconnection, which requires transmission infrastructure, investment and expense.  A Grid Reliance Charge appropriately captures, with reasonable precision, the costs associated with these inherent benefits by calculating the portions of annual depreciation and operation and maintenance expenses that constitute a reasonable proxy for the costs of providing those benefits.

The June 18 Order fails to meaningfully consider and address these points.  The only rationale provided was that the record contains “insufficient description of the potential nature or magnitude of the cited benefits or the potential costs that transmission providers or owners may incur when providing these benefits to . . . Co-Located Loads.”17  The PJM Transmission Owners disagree that the record is insufficient in this regard.  At a minimum, Co-Located Load will utilize the transmission system to receive black-start and regulation ancillary services, which the Commission has already concluded are used by the entire on-site load of a Co-Located Load facility.18  The Commission’s finding that Co-Located Load will receive the benefits of black-start and regulation ancillary services cannot be squared with the rejection of a minimum charge such as the Grid Reliance Charge.  These findings amount to the unduly discriminatory, arbitrary, and

16 PJM Transmission Owners Reply Brief, Blazunas, Schafer, and Hammer Rebuttal Testimony at 31.
17 June 18 Order at P 455.
18 December Order at P 209 (stating that all Co-Located Load rely on regulation and black start services to be served regardless of whether they are drawing energy from the transmission system).

PDF page 10

10
capricious conclusion that Co-Located Load can receive these services, as provided by the transmission system, at no charge, while all other customers must bear those costs.  Therefore, at a minimum, some additional charge is warranted to account for Co-Located Loads’ use of the transmission system to receive these services.

In addition to providing black-start and regulation services, the PJM Transmission Owners described the other specific benefits that Co-Located Load receives from being interconnected and synchronized to the transmission system.19  If the Commission believes that additional precision is necessary to determine the costs associated with these benefits, and what portion of those costs should be allocated to Co-Located Load, then the appropriate solution would be to direct further briefing or other procedures to obtain such evidence.  It is, however, arbitrary and capricious to simply reject the adoption of any minimum charge under these circumstances.  Doing so will shift costs from Co-Located Load customers to other transmission ratepayers, costs which will

ultimately be borne by retail ratepayers.  Such a subsidy is unjust and unreasonable and
inconsistent with fundamental principles of cost allocation.20
19 PJM Transmission Owners Initial Brief at 14-15.
20 See Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. By Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036 (1996) (cross-referenced at 75 FERC ¶ 61,080), on reh’g, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 (cross-referenced at 78 FERC ¶ 61,220), on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom., Transmission Access Policy Study Grp., v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom., N.Y. v. FERC, 535 U.S. 1 (2002); Preventing Undue Discrimination & Preference in Transmission Serv., Order No. 890, 118 FERC ¶ 61,119, order on reh’g, Order No. 890-A, 121 FERC ¶ 61,297 (2007), order on reh’g, Order No. 890-B, 123 FERC ¶ 61,299 (2008), order on reh’g, Order No. 890-C, 126 FERC ¶ 61,228, order on clarification, Order No. 890-D, 129 FERC ¶ 61,126 (2009); Transmission Plan. & Cost Allocation by Transmission Owning & Operating Pub. Utils., Order No. 1000, 136 FERC ¶ 61,051 (2011), order on reh’g, Order No. 1000-A, 139 FERC ¶ 61,132, order on reh’g & clarification, Order No. 1000-B, 141 FERC ¶ 61,044 (2012), aff’d sub. nom. S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41 (D.C. Cir. 2014); Bldg. for the Future Through Elec. Reg’l Transmission Planning & Cost Allocation, Order No. 1920, 89 FR 49280 (June 11, 2024), 187 FERC ¶ 61,068, order on reh’g, Order No. 1920-A, 89 FR 97174 (Dec. 6, 2024), 189 FERC ¶ 61,126 (2024), order on reh’g, Order No. 1920-B, 191 FERC ¶ 61,026 (2025); see also 16 U.S.C. § 824o(b).

PDF page 11

11
The Commission’s commitment to consider a Grid Reliance Charge after more experience with the actual use of the new transmission services21 is not sufficient.  As discussed above, the case for the Grid Reliance Charge is sound and the need for some minimum charge is imminent. With the Commission’s goal of “speed to market” for Co-Located Loads, it is reasonable to expect that customers will begin using the new transmission services that the Commission has required as soon as feasible.  Without a Grid Reliance Charge or other minimum charge to accompany the implementation of these new services, Co-Located Load customers will enjoy the inherent benefits of the PJM transmission system without providing any contribution to the costs of those benefits, which is unduly preferential to Co-Located Load customers and unfair to the rest of customers who will be responsible for bearing those costs.

b. The Proposed Grid Reliance Charge Methodology is Just and
Reasonable.
In addition to granting rehearing on the need for a minimum charge in the first instance, the Commission should also grant rehearing and find that the Grid Reliance Charge proposed by the PJM Transmission Owners represents a just and reasonable methodology for implementing such a charge.  The Grid Reliance Charge is grounded in sound ratemaking and cost causation principles.  It represents an appropriate balance between fairly estimating the grid reliance benefits to Co-Located Load and the need to ensure the rate can be practically implemented.  Practicality concerns are particularly pertinent here given the Commission’s desire to expedite the interconnection of data center loads.  This approach is also fully consistent with longstanding Commission precedent holding that cost allocation rules do not require exacting precision as long as they represent a comparison of the costs assessed to a party against the burdens imposed or

21 June 18 Order at P 456.

PDF page 12

12
benefits drawn.22  The PJM Transmission Owner’s Grid Reliance Charge proposal meets this standard.

The PJM Transmission Owners provided substantial evidence supporting the calculation of the Grid Reliance Charge, as set forth in expert witness testimony provided by Concentric Energy Advisors.23  By including certain publicly-available costs and excluding others, the Grid Reliance Charge methodology achieves the goal of developing a cost-based, transparent, and practically implementable calculation.24  First, by intentionally limiting the Grid Reliance Charge to specific depreciation and operations and maintenance accounts and excluding return on rate base and associated income taxes, the Grid Reliance Charge methodology produces a conservative result focused on allocating a reasonable share of those costs most directly related  to the ongoing operation and use of the grid, rather than investment return.25  Second, a Grid Reliance Charge avoids the need to relitigate each utility’s rate base, return, or tax components and eliminates the need for company-specific (or project-specific) engineering judgment and allocations.26  Third, by establishing the Grid Reliance Charge as a percentage of the total transmission revenue requirement, the Grid Reliance Charge scales proportionally with each utility’s size and cost structure.27  Lastly, averaging the calculated Grid Reliance Charge percentages across all PJM

22 See, e.g., Ill. Commerce Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009); Transmission Plan. & Cost Allocation by Transmission Owning & Operating Pub. Utils., Order No. 1000, 136 FERC ¶ 61,051, at P 504 and nn.393, 435, 453 (2011) (citing to Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361 at 1369, 1371 (D.C. Cir. 2004) (explaining that cost causation “does not require exacting precision in a ratemaking agency’s allocation decisions.”)).
23 PJM Transmission Owners Reply Brief at 21-30.
24 Blazunas, Schafer, and Hammer Rebuttal Testimony 27.
25 Blazunas, Schafer, and Hammer Direct Testimony at 24-25.
26 Id. at 25.
27 Id.

PDF page 13

13
transmission owners smooths out variations and reduces volatility.28  The Commission failed to consider and address the merits of the Grid Reliance Charge methodology at all, and this failure was arbitrary and capricious and resulted in a decision not supported by substantial evidence.

2. The Commission Erred in Rejecting the PJM Transmission Owners’
Proposal to set the Maximum Rate for Non-Firm Contract Demand
Transmission Service at the Rate for Firm Contract Demand
Transmission Service, Subject to Discount.
In the June 18 Order, the Commission found that the PJM Transmission Owners’ proposal to set the maximum rate for Non-Firm Contract Demand transmission service equal to the rate for Firm Contract Demand transmission service was not just and reasonable.29  In the Commission’s view, Non-Firm Contract Demand transmission service is an inferior service to Firm Contract Demand transmission service and NITS, making it unjust and unreasonable to charge Non-Firm Contract Demand customers the same maximum rate as Firm Contract Demand and NITS customers.30  The Commission should reverse this finding on rehearing.

Contrary to the Commission’s conclusion, the PJM Transmission Owners’ proposal is fully consistent with Order No. 888, as embodied in the provisions of the Tariff addressing the availability of firm and non-firm Point-to-Point Transmission Service.  Rather, it is the June 18 Order that departs from Order No. 888 and related precedent.  In Order No. 888, the Commission rejected arguments that there is no cost-of-service principle justifying charging non-firm rates at the same rate as firm service, making clear that it is important to allow pricing flexibility, and that non-firm service can be priced at the same level of firm service under appropriate circumstances.31

28 Id.
29 June 18 Order at P 402.
30 Id.
31 Order No. 888 at 31,780.

PDF page 14

14
In Order No. 888-A, the Commission emphasized that non-firm transmission prices should “promote efficient use of the transmission system, subject to [the firm service] price cap.”32  In order to allow for the ability to set rates based on efficient system use, including accounting for the amount of available capacity, the Commission permitted transmission providers to offer discounts to the maximum rate, so long as such discounts are offered equally to affiliates and non- affiliates, and are made transparent by posting on OASIS.33

This is precisely the approach the PJM Transmission Owners have proposed here.  In directing the implementation of Non-Firm Contract Demand transmission service, the Commission has required an entirely new transmission service for a customer class of unknown scope and magnitude, with corresponding unknown demand and availability.  The PJM Transmission Owners will only charge the maximum firm rate for Non-Firm Contract Demand transmission service to the extent it is consistent with the efficient use of the transmission system, i.e., when there is scarce or no excess capacity available for use by Co-Located Load customers. Charging the maximum rate under these circumstances is just and reasonable and entirely consistent with Commission precedent insofar as the appropriate price signal should convey such scarcity, thereby indicating that customers may need to procure a firmer level of service.  However, if there is additional capacity available to accommodate requests for Non-Firm Contract Demand transmission service, then the PJM Transmission Owners, in coordination with PJM, will offer an appropriately discounted rate based on extant conditions, such as the demand for non-firm service and availability of capacity.

32 Order No. 888-A at 30,272.
33 Order No. 888 at 31,780.

PDF page 15

15
This is the process contemplated and explicitly permitted in Order No. 888 and its progeny. The Commission’s objection that the PJM Transmission Owners’ commitment to offer appropriate discounts “at some undefined time in the future” is “counterintuitive” cannot be squared with this precedent. It is obvious that a discount based on future system conditions cannot be determined and stated now, but offering a commitment to provide future discounts complies with Order No. 888, which emphasized the need for pricing flexibility based on the efficient use of the system. The illogical nature of the objection here is reinforced by the fact that the June 18 Order provides no directives or guidance as to what a just and reasonable initial discount should be, simply instructing the PJM Transmission Owners to propose some discount.  Moreover, there is nothing “counterintuitive” about assessing the efficiency of system use, including the demand for non-firm service and the availability of excess capacity, upon implementation of an entirely new service. Again, this is entirely consistent with the discounting approach that the Commission adopted in Order No. 888.  If, for instance, there is unused capacity after the implementation of the new Contract Demand services that might otherwise be efficiently utilized by Co-Located Load customers, then an appropriate discount will be offered and implemented.34  If the Commission wishes to deviate from its precedent with respect to the pricing of Non-Firm Contract Demand transmission service, then it must provide a rational explanation for doing so.  The June 18 Order fails to even acknowledge this departure, much less provide such an explanation, and it is therefore arbitrary and capricious.

The  Commission’s concern that the PJM Transmission Owners are under no obligation to lower rates in the future and provide no transparency as to how such a decision would be made is

34 The Commission’s reasoning here is also inconsistent with the explanation offered for denying the implementation of a minimum charge to Co-Located Customers, namely, that additional data is necessary before determining the nature and magnitude of such a charge.

PDF page 16

16
also unconvincing and at odds with Order No. 888 precedent.35  In accordance with the requirements of Order No. 888 and the Tariff, any offer of discount made by the Transmission Provider will be announced to all Eligible Customers by posting on OASIS, and any customer- initiated requests for discounts will also be posted on OASIS.  Once a discount is determined, the details will immediately be posted on the OASIS.  Moreover, any discount agreed upon for service on a path or at a point(s) of receipt will be offered by the Transmission Provider for the same time period to all Eligible Customers on all unconstrained transmission paths that go to the same point(s) of receipt on the Transmission System.  If the Commission believes that this process, which has been in place for over thirty years now, is somehow unjust and unreasonable as applied to Non-Firm Contract Demand transmission service, then the Commission must acknowledge the relevant precedent and provide a rational reason for its decision to depart from that precedent. Having failed to do so renders the June 18 Order arbitrary and capricious.

3. The Commission Erred in Rejecting PJM’s Proposal to Define Co-
Located Load Based on Point of Change of Ownership Rather Than
Point of Interconnection.
In the June 18 Order, the Commission rejected PJM’s proposed definition of Co-Located Load based on the Point of Change of Ownership, and instead required the use of Point of Interconnection.36  The Commission failed to consider the merits of PJM’s proposal, as well as the evidence offered by the PJM Transmission Owners in support thereof, rejecting the proposal based solely on the rationale that no party sought rehearing of the definition of Co-Located Load contained in the December Order.37  The Commission should reverse this holding on rehearing.

35 June 18 Order at P 407.
36 Id. at P 307.
37 Id.

PDF page 17

17
Nowhere in the December Order did the Commission indicate that PJM was prohibited from proposing modifications to the definition of Co-Located Load if such a change was consistent with or superior to the definition set forth in that order.  This narrow and cramped reading of the December Order is particularly problematic here, given the novel and unique nature of the services that the Commission has directed in this proceeding.  Under these circumstances, it is understandable that upon considering the details of implementing these new services, PJM determined that a modification to the definition of Co-Located Load was necessary and appropriate.  Contrary to the Commission’s findings, both PJM and the PJM Transmission Owners provided abundant explanation as to how this modification complied with the December Order, and indeed, that absent this change, the definition of Co-Located Load would fail to satisfy the goals and purpose of the December Order.38  To wit, defining Co-Located Load based on the Point of Change of Ownership, instead of the Point of Interconnection, is consistent with or superior to the December Order’s directive because it provides additional clarity to interconnection parties, is easier to administer, and eliminates the potential for gaming.  If the definition of Co-Located Load were to rely on Point of Interconnection for purposes of eligibility for the new transmission services, that could open the door to potential gamesmanship by customers taking advantage of Co-Located Load arrangements based on the inclusion or use of Transmission-Owner-owned facilities.  The Commission’s decision to ignore this evidence is arbitrary and capricious and should be reversed.

38 See, e.g., PJM Transmission Owners Request for Rehearing or Clarification, Docket No. ER26-1088-000 (filed May 18, 2026).

PDF page 18

18
4. The Commission Erred in Rejecting PJM’s Proposal to Require Co-
Located Load to Take Sufficient Transmission Service to Cover its
Entire Gross Load.
In the June 18 Order, the Commission rejected PJM’s proposal to require that the Eligible Customer taking transmission service on behalf of a Co-Located Load must take sufficient transmission service to account for the entire gross demand of the Co-Located Load.39  The Commission determined that PJM’s proposal did not comply with the December Order and would fundamentally alter the nature of Firm Contract Demand and Non-Firm Contract Demand transmission services.40  On rehearing, the Commission should reverse this finding. PJM proposes to require that the Eligible Customer taking transmission service on behalf of a Co-Located Load must take sufficient transmission service to account for the entire gross demand of the Co-Located Load.  An Eligible Customer taking service on behalf of a Co-Located Load must request Non-Firm Contract Demand transmission service equal to the MW level of the Co-Located Generator dedicated to serving the Co-Located Load.  Any portion of the gross demand of the Co-Located Load not served by the Co-Located Generator must be covered by Firm Contract Demand transmission service.  This arrangement would tie the amount of Firm Contract Demand and Non-Firm Contract Demand transmission services that an Eligible Customer can request to the size of the Co-Located Generator, rather than allowing the Eligible Customer to select any amount, including 0 MW for Non-Firm Contract Demand transmission service. Requiring that an Eligible Customer on behalf of a Co-Located Load must take sufficient transmission service to account for the entire gross demand of the Co-Located Load is just and reasonable to ensure reliable operation of the transmission system.

39 June 18 Order at P 342.
40 Id.

PDF page 19

19
To ensure reliability, PJM’s studies examine the transmission service requests for the Co- Located Load and the Co-Located Load’s impact on the transmission system.  These studies must capture the effects of any unscheduled energy withdrawals by the Co-Located Load, even if inadvertent or limited in duration, and confirm that any such withdrawals will not jeopardize system reliability.  Thus, there cannot be any unstudied portion of the Co-Located Load that is not subject to either:  (i) Firm Contract Demand transmission service; or (ii) dedicated generation, which must be backed up by Non-Firm Contract Demand transmission service.  Without this sort of arrangement, PJM will not have visibility into situations that may jeopardize grid reliability, including load taking service beyond levels for which PJM has properly studied and planned.  A lack of visibility will expose the system to risk of equipment damage, unintended relay operations, and cascading outages.  The Commission’s disregard of those concerns was arbitrary and capricious.

Moreover, because a Co-Located generating facility will not always be available, any portion of the load not covered by Firm Contract Demand transmission service must be covered by Non-Firm Contract Demand transmission service.  The Non-Firm Contract Demand transmission service will act as a backup to allow the Co-Located Load to meet its full demand, if the Co-Located generating facility is on outage and unable to provide energy.  A Co-Located Load that typically supplies a portion of its load from the co-located generator without using the transmission system may rely on Non-Firm Contract Demand transmission service when the co- located generator is unavailable or operating at a reduced capacity, to enable the Co-Located Load to substitute energy from the system for the energy provided by the Co-Located Generating Facility.  This provides the Co-Located Load with greater flexibility to mix and match between Firm Contract Demand, on-site generation and Non-Firm Contract Demand, provided the

PDF page 20

20
combination of the two transmission services covers the entire gross demand of the Co-Located Load.

5. The Commission Should Clarify its Ruling Regarding Requirements
for Control Technologies and Protection Systems.
In the June 18 Order, the Commission rejected the PJM Transmission Owners’ proposal that the Tariff should specify that control technologies and/or protection systems may be required on both the customer and PJM Transmission Owner sides of the Point of Interconnection.41  The Commission held that the location and number of devices required should be based on engineering judgment of PJM and the PJM Transmission Owners.42  Consistent with this ruling, the Commission should clarify that PJM and the PJM Transmission Owners will be permitted to require protection on both the customer and Transmission Owner sides of the Point of Interconnection, to the extent that a study determines that such protection is necessary and appropriate.

As a general matter, requiring control technologies and/or protection systems on both the Co-Located Load customer’s and the PJM Transmission Owner’s side of the point of interconnection provides much needed redundancy.  On every other element of the bulk electric system in PJM, there is an expectation for redundancy for protection systems that are primarily responsible for fault clearing.  In the case of Co-Located Load, the failure to adequately curtail load or generation can adversely impact the transmission system just as significantly as a fault, especially if there are no limitations on the size of the load and generation connected in one facility. Without protection system redundancy, the transmission system and the millions of customers that

41 June 18 Order at P 488.
42 Id.

PDF page 21

21
rely on it will face significant risks that cannot be addressed effectively through operating procedures, relaying, and remote tripping capability.

 Moreover, cost is not a meaningful barrier to implementing this level of redundancy.  The overall cost of implementing protection systems at a given facility is driven primarily by personnel time for engineering, construction, and subsequent maintenance, rather than by significant material costs.  In any event, the benefits of requiring control technologies and/or protection systems on both the Co-Located Load customer’s and the PJM Transmission Owner’s side of the point of interconnection far outweigh the minimal cost of the protection system equipment, particularly when compared to other costs associated with the development and interconnection of Co-Located Load.  Further, it is best to address system reliability concerns upfront before the Co-Located Load first comes online because it is less expensive to install protection systems as part of initial construction rather than retrofit the site after initial construction.

For these reasons, if the Commission declines to clarify its ruling as stated above, it should grant rehearing so as to allow PJM and the PJM Transmission Owners to require protection on both the customer and PJM Transmission Owner sides of the Point of Interconnection when the relevant study determines that such protection is necessary to provide adequate redundancy.

PDF page 22

22
III. CONCLUSION
For the foregoing reasons, the PJM Transmission Owners respectfully request that the Commission grant rehearing of the June 18 Order.

Respectfully submitted,
/s/ Michael Kunselman
Michael Kunselman
Richard P. Sparling
Nicholas J. Cicale
Jonathan Namazi
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, DC 20005
Counsel for the FirstEnergy
  Companies
On behalf of the Indicated PJM
  Transmission Owners
Dated: July 20, 2026

PDF page 23

CERTIFICATE OF SERVICE
Under Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2025), I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary in these proceedings. Dated at Washington, D.C., this 20th day of July 2026.

/s/ Daniel Klein
Daniel Klein
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, DC 20005