The Indicated PJM Transmission Owners submit Request for Rehearing and Clarification of the 06/18/2026 Order
Text extracted from the eLibrary original (SHA-256 21ef018113f70910…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in ER26-1479
Topics in the text: Connecting load and generation · Filing procedure · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
The Commission’s explanation that PJM’s proposal was barred for failure to seek rehearing of the December 18 Order is arbitrary and capricious and fails to account for the substantial evidence provided by PJM and the PJM Transmission Owners regarding the flaws of utilizing the Point of…Read this passage Filed comments: Connecting load and generation
I. BACKGROUND
printed heading · Topic match: Connecting load and generation
FERC, 535 U.S. 1 (2002). 4 on behalf of Co-Located Load.6 The December Order defined the Tariff as PJM’s Open Access Transmission Tariff, the Amended and Restated Operating Agreement of PJM, and the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region.7 The Commission…Read this passage Filed comments: Connecting load and generation
II. REQUESTS FOR REHEARING AND CLARIFICATION
printed heading · Topic match: Filing procedure
REQUESTS FOR REHEARING AND CLARIFICATIONRead this passage Filed comments: Filing procedure
A. Statement of Issues and Specification of Errors
printed heading · Topic match: Connecting load and generation
EPA, 775 F.2d 1141 at 1147 (“[The agency] is entitled to change its policy, but it must do so on the basis of a reasoned analysis.”) (7th Cir. 1985). The June 18 Order’s rejection of PJM’s proposal to define Co-Located Load based on facilities located on the customer’s side of the Point of Change…Read this passage Filed comments: Connecting load and generation
B. Arguments
printed heading · Topic match: Connecting load and generation
Requiring that an Eligible Customer on behalf of a Co-Located Load must take sufficient transmission service to account for the entire gross demand of the Co-Located Load is just and reasonable to ensure reliable operation of the transmission system. 39 June 18 Order at P 342. 40 Id. 19 To ensure…Read this passage Filed comments: Connecting load and generation
III. CONCLUSION
printed heading · Topic match: Filing procedure
CONCLUSION For the foregoing reasons, the PJM Transmission Owners respectfully request that the Commission grant rehearing of the June 18 Order.Read this passage Filed comments: Filing procedure
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 20th day of July 2026. /s/ Daniel Klein Daniel Klein Davis Wright Tremaine LLP 1301 K Street NW Suite 500 East Washington, DC 20005Read this passage