EL25-49-000 · 2026-07-28 · Indicated PJM Transmission Owners

Motion for Extension of Compliance Deadline of the Indicated PJM Transmission Owners and Request for Expedited Action and Shortened Comment Period

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-002
)
Docket No. EL25-49-000
)
Large Loads Co-Located at Generating Facilities
)
Docket No. AD24-11-001
)
Constellation Energy Generation, LLC
)
v. )
Docket No. EL25-20-001
PJM Interconnection, L.L.C.
)
(Consolidated)
)
PJM Interconnection, L.L.C.
)
Docket No. ER26-1479-000
MOTION FOR EXTENSION OF COMPLIANCE DEADLINE OF THE
INDICATED PJM TRANSMISSION OWNERS
AND REQUEST FOR EXPEDITED ACTION
AND SHORTENED COMMENT PERIOD
Pursuant to Rule 212 of the Rules of Practice and Procedure of the Federal Energy
Regulatory Commission’s (“Commission” or “FERC”),1 the Indicated PJM Transmission Owners (“PJM Transmission Owners”)2 respectfully request that the Commission grant an extension of time with respect to the compliance obligations imposed on the PJM Transmission Owners in the

1 18 C.F.R. § 385.212 (2025).
2 The Indicated PJM Transmission Owners are:  American Electric Power Service Corporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc., AEP Indiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and AEP West Virginia Transmission Company, Inc.; The Dayton Power and Light Company d/b/a AES Ohio; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc.; Duquesne Light Company; East Kentucky Power Cooperative, Inc.; Exelon Corporation on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, on behalf of its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, The Potomac Edison Company, Monongahela Power Company, Keystone Appalachian Transmission Company, and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); PPL Electric Utilities Corporation; Public Service Electric and Gas Company; Rockland Electric Company; and the Southern Maryland Electric Cooperative.

PDF page 2

2
Commission’s June 18, 2026 Order on Rehearing, Clarification, Compliance Filing, and Paper Hearing in these proceedings.3  The PJM Transmission Owners request that the Commission extend the compliance deadline in this proceeding for 90 days, until November 16, 2026,4 so that it aligns with the deadline by which PJM and the PJM Transmission Owners have requested to submit one or more filings pursuant to section 205 of the Federal Power Act (“FPA”) in response to the Commission’s show cause order in Docket No. EL26-67-000.5

Good cause exists to grant this motion because the issues the Commission has required PJM and the PJM Transmission Owners to address in the compliance filing in the above-captioned proceedings significantly overlap those being addressed by PJM and the PJM Transmission Owners in response to the PJM Show Cause Order.6  Granting this request will ensure the PJM Transmission Owners have adequate time to determine the appropriate additions and revisions to the PJM Open Access Transmission Tariff (“PJM Tariff” or “Tariff”) for transmission services applicable to co-located load customers as well as other large load customers, and will avoid unnecessary duplication, confusion, and potential inconsistencies between provisions being developed to address issues relevant to both proceedings.  The PJM Transmission Owners further request a shortened comment period of five (5) days to facilitate the Commission’s issuance of an order granting the motion to extend the compliance deadline no later than August 10, 2026. 3

PJM Interconnection, L.L.C., et al., 195 FERC ¶ 61,209 (2026) (“June 18 Order”). 4

November 16 is the first business day after the end of the 90-day abeyance period. 5

See PJM Interconnection, L.L.C., et al., 195 FERC ¶ 61,211 (2026) (“PJM Show Cause Order”); see also Motion for Abeyance of the Indicated PJM Transmission Owners and Request for Expedited Action and Shortened Comment Period, Docket No. EL26-67-000 (filed July 28, 2026).

In the event that the Commission grants less than a 90-day abeyance in the PJM Show Cause Order proceeding, the PJM Transmission Owners request the Commission adopt that date as the deadline for submitting the compliance filing required in the instant proceedings.

6
The PJM Transmission Owners understand that PJM will submit certain of the compliance changes directed to it by the June 18 Order by the existing 60-day deadline of August 17, 2026.  The PJM Transmission Owners are currently working with PJM to determine if it would be necessary or efficient to submit certain of their own complementary compliance changes by August 17, 2026 as well.

PDF page 3

3
I. BACKGROUND
A. The PJM Co-Located Load Proceeding
On December 18, 2025, the Commission issued an order in Docket Nos. EL25-49-000, et al., pursuant to section 206 of the FPA, finding the PJM Tariff unjust and unreasonable because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to generators serving Co-Located Load and Eligible Customers taking transmission service on behalf of Co-Located Load.7

The Commission directed PJM, inter alia, to submit revisions to its Tariff to require that the Eligible Customer taking transmission service on behalf of the Co-Located Load takes one of three transmission services:  (1) Network Integration Transmission Service (“NITS”), including a new interim, non-firm transmission service available until all Network Upgrades necessary to provide the requested NITS are complete (“Interim NITS”), (2) a new Firm Contract Demand (“Firm Contract Demand”) transmission service, or (3) a new Non-Firm Contract Demand (“Non- Firm Contract Demand”) transmission service.8  The Commission also established a paper hearing to determine the just and reasonable rates, terms, and conditions for these new transmission services.9  On February 23, 2026, in Docket Nos. EL25-49-000, et al., PJM and the PJM Transmission Owners each submitted an initial brief to address the Commission’s paper hearing questions with respect to the new transmission services.  On March 25, 2026, and on April 24, 2026, various parties submitted response briefs and reply briefs, respectively.

7 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 2 (2025) (“December Order”).
8 December Order at P 2.
9 Id. at PP 2, 194, 219.  The Commission also found the Behind the Meter Generation (“BTMG”) rules in the Tariff to be no longer just and reasonable, and the Commission directed PJM to submit in its compliance filing revisions to its Tariff to revise the retail BTMG netting rules and to implement a transition process for existing BTMG participants.  Id. at PP 2, 179, 186, 221-224.

PDF page 4

4
In the June 18 Order, the Commission addressed the rates, terms, and conditions for the required new transmission services as developed through the paper hearing submissions, including the rate proposals made by the PJM Transmission Owners.  The Commission accepted certain of the proposals and rejected others, and directed PJM and the PJM Transmission Owners to submit compliance filings with 60 days of the date of the June 18 Order (i.e., August 17, 2026) to reflect the rates, terms, and conditions for the new transmission services in the PJM Tariff.10

B. The PJM Large Load Show Cause Proceeding
On June 18, 2026, the Commission also issued a show cause order under section 206 of the FPA to PJM, together with the PJM Transmission Owners, directing PJM to justify or reform the Tariff provisions governing how large loads connect to and receive service from the transmission system.11  The PJM Show Cause Order preliminarily found that PJM’s Tariff appeared to be unjust, unreasonable, or unduly discriminatory or preferential because of a lack of sufficiently clear and consistent provisions to address service for large loads and related configurations.12  The Commission therefore directed PJM and the PJM Transmission Owners, within 60 days, to show cause why the Tariff remains just and reasonable without provisions addressing:  (1) the application process, study procedures, and ongoing operational requirements for Eligible Customers seeking transmission service on behalf of large loads; (2) additional transparency concerning Network Upgrade costs for such service, together with the absence of a pro forma cost recovery agreement and a mechanism to ensure related payments are properly credited to transmission owners’ revenue requirements; (3) transmission service options tailored to flexible large loads willing and able to limit their use of the transmission system under certain conditions;

10 June 18 Order at Ordering Para. (C)-(H).
11 PJM Show Cause Order at PP 3, 35.
12 Id. at PP 3, 35.

PDF page 5

5
and (4) rates, terms, and conditions applicable to interconnection customers serving “electrically proximate large load” or co-located load.13  The Commission directed PJM either to justify the absence of such provisions or to propose Tariff revisions addressing those concerns.14 The PJM Show Cause Order indicated that the Commission would consider requests from PJM and/or transmission owners to hold all or certain aspects of the FPA section 206 proceeding in abeyance, for up to 90 days, including the August 17, 2026, deadline to respond.15  The Commission explained that the purpose of such an abeyance would be to provide PJM and the PJM Transmission Owners time while they work through the stakeholder process to develop FPA section 205 filings to revise the PJM Tariff to address the issues raised in the PJM Show Cause Order.16

II. MOTION FOR EXTENSION
On the same date as the instant motion, the PJM Transmission Owners are submitting a motion, consistent with the PJM Show Cause Order, requesting that the Commission hold the deadline to respond to that order in abeyance for a 90-day period in order to allow the PJM Transmission Owners to address, through one or more FPA section 205 filings, the issues identified in the PJM Show Cause Order.  The PJM Transmission Owners understand that PJM is submitting a substantially similar request.  In their abeyance motion, the PJM Transmission Owners commit to file their FPA section 205 filing(s) responsive to the PJM Show Cause Order

13 Id.
14 Id.
15 Id. at P 39.  Because 60 days from issuance of the PJM Show Cause Order falls on a Saturday, the deadline to respond does not end until the close of business on Monday, August 17.  See 18 C.F.R. § 385.2007(a)(2).
16 PJM Show Cause Order at P 39.

PDF page 6

6
by no later than November 16, 2026, which is the date 90 days after the deadline to respond to the PJM Show Cause Order.17

The issues the PJM Transmission Owners are addressing in response to the PJM Show Cause Order substantially overlap with those that the Commission directed the PJM Transmission Owners to address in the June 18 Order.  Many of the issues addressed in the PJM Show Cause Order incorporate or otherwise build off of the requirements imposed by the Commission in the PJM Co-Located Load proceeding.  For instance, the PJM Show Cause Order preliminarily found that new transmission services should be available to “flexible large loads” willing and able to limit their withdrawals, specifically the three new services it required in the PJM Co-Located Load proceeding:  (1) Interim NITS, (2) Firm Contract Demand, and (3) Non-Firm Contract Demand.18 In effect, the PJM Show Cause Order contemplates expanding the scope of these new transmission services to a broader set of customers.  Therefore, the PJM Transmission Owners anticipate that the underlying rate design approaches that the Commission directed be adopted in compliance with the June 18 Order would serve as the basis for these new services as applied to both Co-Located Load customers and flexible large load customers.  However, the PJM Transmission Owners will still need to carefully consider, in coordination with PJM and other interested stakeholders, what additions and modifications are necessary to adapt those rate proposals to new services available under the PJM Show Cause Order.

Given the substantial overlap between the requirements in the two orders, the best approach is for PJM and the PJM Transmission Owners to develop the Co-Located Load compliance filing

17 See id. (“The Commission will consider requests from PJM and/or the Transmission Owners to hold, for up to 90 days, all or certain aspects of this FPA section 206 proceeding in abeyance, including the deadline to respond to this order.”) (emphasis added).
18 Id. at 86.

PDF page 7

7
and the FPA section 205 filing(s) holistically, rather than separately, and to file them on the same date.  This approach has several benefits.  First, it will be more efficient for PJM, the PJM Transmission Owners, and PJM stakeholders to prepare and consider the necessary tariff changes together.  Absent this coordination, PJM and the PJM Transmission Owners will inevitably end up significantly duplicating their design and stakeholder outreach efforts.  A holistic process will also avoid potential confusion on the part of PJM stakeholders regarding the scope and impact of proposed procedures and other rates, terms, and conditions that will likely end up affecting both Co-Located Loads and other large load customers.  An approach whereby PJM and the PJM Stakeholders are required to submit a compliance filing in the Co-Located Load proceeding at an earlier time most likely would result in the need to amend Tariff revisions submitted in the Co- Located Load compliance filing in response to the PJM Show Cause Order, thus creating the risk of inconsistencies between overlapping and superseding tariff versions.  Finally, having a single filing date for both proceedings will allow interested parties to address any issues or concerns with the proposed tariff provisions filed by PJM and the PJM Transmission Owners, and will allow the Commission to review those revisions, in a coherent and administratively efficient fashion. A modest 90-day extension of the compliance directives in the June 18 Order will not unfairly prejudice PJM stakeholders or other interested parties.  As discussed above, addressing the Co-Located Load revisions in conjunction with the issues identified in the PJM Show Cause Order will provide several advantages to interested parties.  Moreover, this extension will not impact the ultimate effective date of any of the proposed revisions relating to the June 18 Order or the PJM Show Cause Order.  For these reasons, the PJM Transmission Owners respectfully request that the Commission grant a 90-day extension so that the deadline for submitting the compliance

PDF page 8

8
filing in response to the June 18 Order will be the same as the deadline for FPA section 205 filing(s) made in response to the PJM Show Cause Order:  November 16, 2026.

III. REQUEST FOR EXPEDITED CONSIDERATION AND SHORTENED
COMMENT PERIOD
The PJM Transmission Owners request expedited consideration of this motion for extension and request that the Commission issue an order granting the motion no later than August 10, 2026.  Expedited consideration and the issuance of an order by that date will provide the PJM Transmission Owners sufficient assurance that they will have adequate time to develop and submit both the June 18 Order compliance filing, as well as one or more FPA section 205 filings necessary to implement the PJM Show Cause Order.  Expedited consideration will also allow the PJM Transmission Owners to focus their efforts on developing these filings in a holistic consistent fashion, rather than spending critical time preparing a separate Co-Located Load compliance filing that likely would require substantial subsequent amendments.  Consistent with this request, the PJM Transmission Owners also seek a shortened comment period on this motion for an extension of time.  Specifically, the PJM Transmission Owners request that the Commission establish a comment period of five (5) days.  Good cause exists to grant a shortened comment period for the reasons set forth above.  Moreover, no party will be prejudiced as a result of granting a five (5) day comment period, as the additional time and certainty afforded by an expedited order will accrue to the benefit of stakeholders by providing the PJM Transmission Owners sufficient time to solicit and consider stakeholder feedback on their proposals.

PDF page 9

9
IV. CONCLUSION
For the reasons set forth above, the PJM Transmission Owners’ request that the Commission establish a five (5) day comment period for answers to this motion, and issue an order on or before August 10, 2026, granting the PJM Transmission Owners’ request to extend the compliance deadline in the above-captioned proceedings until November 16, 2026, or whatever alternative date the Commission adopts as the deadline to submit one or more FPA section 205 filings in response to the PJM Show Cause Order.

Respectfully submitted,
/s/ Michael Kunselman
Michael Kunselman
Richard P. Sparling

Nicholas J. Cicale
Jonathan A. Namazi
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, DC 20005
Counsel for the FirstEnergy
  Companies
On behalf of the Indicated PJM
  Transmission Owners
Dated:  July 28, 2026

PDF page 10

CERTIFICATE OF SERVICE
Under Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2025), I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary in these proceedings. Dated at Washington, D.C., this 28th day of July 2026.

/s/ Daniel Klein
Daniel Klein
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, DC 20005