EL25-49-000 · 2026-07-28 · Indicated PJM Transmission Owners

Motion for Extension of Compliance Deadline of the Indicated PJM Transmission Owners and Request for Expedited Action and Shortened Comment Period

Text extracted from the eLibrary original (SHA-256 5a4bfed8572ff89d…). Download the original from the official source.

Contents · 6 sections
  1. I. BACKGROUND p. 3
  2. A. The PJM Co-Located Load Proceeding p. 3
  3. B. The PJM Large Load Show Cause Proceeding p. 4
  4. II. MOTION FOR EXTENSION p. 5
  5. III. REQUEST FOR EXPEDITED CONSIDERATION AND SHORTENED p. 8
  6. IV. CONCLUSION p. 9

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Filing procedure · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

The PJM Transmission Owners further request a shortened comment period of five (5) days to facilitate the Commission’s issuance of an order granting the motion to extend the compliance deadline no later than August 10, 2026. 3 PJM Interconnection, L.L.C., et al., 195 FERC ¶ 61,209 (2026) (“June 18…
Read this passage Filed comments: Filing procedure

I. BACKGROUND

printed heading

I.
Read this passage

A. The PJM Co-Located Load Proceeding

printed heading · Topic match: Connecting load and generation

The PJM Co-Located Load Proceeding On December 18, 2025, the Commission issued an order in Docket Nos.
Read this passage Filed comments: Connecting load and generation

B. The PJM Large Load Show Cause Proceeding

printed heading · Topic match: Filing procedure

The PJM Large Load Show Cause Proceeding On June 18, 2026, the Commission also issued a show cause order under section 206 of the FPA to PJM, together with the PJM Transmission Owners, directing PJM to justify or reform the Tariff provisions governing how large loads connect to and receive service…
Read this passage Filed comments: Filing procedure

II. MOTION FOR EXTENSION

printed heading · Topic match: Connecting load and generation

Given the substantial overlap between the requirements in the two orders, the best approach is for PJM and the PJM Transmission Owners to develop the Co-Located Load compliance filing 17 See id. (“The Commission will consider requests from PJM and/or the Transmission Owners to hold, for up to 90…
Read this passage Filed comments: Connecting load and generation

III. REQUEST FOR EXPEDITED CONSIDERATION AND SHORTENED

printed heading · Topic match: Connecting load and generation

Expedited consideration will also allow the PJM Transmission Owners to focus their efforts on developing these filings in a holistic consistent fashion, rather than spending critical time preparing a separate Co-Located Load compliance filing that likely would require substantial subsequent…
Read this passage Filed comments: Connecting load and generation

IV. CONCLUSION

printed heading

CONCLUSION For the reasons set forth above, the PJM Transmission Owners’ request that the Commission establish a five (5) day comment period for answers to this motion, and issue an order on or before August 10, 2026, granting the PJM Transmission Owners’ request to extend the compliance deadline…
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C., this 28th day of July 2026. /s/ Daniel Klein Daniel Klein Davis Wright Tremaine LLP 1301 K Street NW Suite 500 East Washington, DC 20005