EL25-49-000 · 2026-08-04 · Constellation Energy Generation, LLC

Motion for Leave and Answer of Constellation Energy Generation, LLC to Indicated PJM Transmission Owner's Rehearing Request

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.

Large Loads Co-Located at Generating Facilities

Constellation Energy Generation, LLC

     v.

PJM Interconnection, L.L.C.

PJM Interconnection, L.L.C.
)
)
)
)
)

)
)
)

)
)
)
)
)
)
)

)
)
)

Docket Nos. EL25-49-002
EL25-49-000

Docket No. AD24-11-001

Docket No. EL25-20-001
(consolidated)

Docket No. ER26-1479-000
MOTION FOR LEAVE AND ANSWER OF
CONSTELLATION ENERGY GENERATION, LLC
Constellation submits this motion for leave and answer1 to emphasize one point: if the
Commission’s goal is to interconnect loads faster than the current 7-to-10-year timeframe,2 it must

1 Constellation Energy Generation, LLC (“Constellation”) submits there is good cause to accept this answer to the rehearing requests filed by Indicated PJM Transmission Owners and jointly by Exelon Corporation (“Exelon”) and FirstEnergy Service Company (“FirstEnergy”) (collectively, Transmission Owner Rehearing Requests) as our answer is intended to assist the Commission in its decision making. See, e.g., Tex. E. Transmission, LP, 127 FERC ¶ 61,162, at P 6 (2009) (finding good cause to accept an answer to a rehearing request because the answer “provides information that will assist [the Commission] in [its] decision-making process”).
2 See, e.g., Comments of Talen Energy Corp., Docket No. AD24-11-000, Analysis Group Report at 12 n.43 (Oct. 28, 2024) (describing wait times to plan, design, site and construct a new grid connection to be as long as seven years for Dominion and seven to ten years for AEP).

PDF page 2

2
continue to promptly deny the Transmission Owners’ rehearing requests3 – filed in this docket and in response to the Large Load Show Cause Order.4 Despite the Commission’s clear determinations that there are benefits to allowing alternative configurations to traditional front-of-the-meter (“FTM”) connections, the Transmission Owners’ acceptance of alternative configurations has not evolved, and they steadfastly persist in refiling the same challenges that the Commission has already comprehensively rejected. Indeed, much of Exelon and FirstEnergy’s July 20th Rehearing Request repackages verbatim their January 16th Rehearing Request, swapping “co-located load” for “load served by BTMG.”5 Moreover, in so doing, they fail to address the legal and policy grounds on which the Commission previously disposed of these same challenges.

Unfortunately, the Transmission Owners’ rehearing request underscores the fact that the only configuration that they support is a fully FTM one. They continue to point to the Susquehanna ISA Proceeding and Talen’s transition to an FTM arrangement as demonstrating that Network Service is sufficient for co-located load.6 But the question before the Commission is not what is

3 See Request for Rehearing and Clarification of the Indicated PJM Transmission Owners, Docket No. EL25-49-000, et al. (July 20, 2026) (“Indicated TO June 2026 Co-Location Order Rehearing”); Request for Rehearing of Exelon Corporation and FirstEnergy Service Company, Docket No. EL25-49-000, et al. (July 20, 2026) (“Exelon & FirstEnergy July 20th Rehearing Request”).
4 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026) (“Large Load Show Cause Order”). Similar to this proceeding, the Indicated PJM Transmission Owners and Exelon together with FirstEnergy filed requests for rehearing of the Large Load Show Cause Order. See Request for Rehearing of Exelon Corporation and FirstEnergy Service Company, Docket No. EL26-67-000 (July 20, 2026); Request for Clarification, or in the Alternative, Rehearing of the Indicated PJM Transmission Owners, Docket No. EL26-67-000, at 6-8 (July 20, 2026) (“Indicated TO Large Load Show Cause Rehearing”).
5 Compare Exelon & FirstEnergy July 20th Rehearing Request at 3 (“There is No Evidence In the Record That Loads Served by BTMG Are Unable to Obtain Reliable, Timely, and Reasonably Priced Service Using the Existing Network Service Construct. Therefore, the Commission Fails To Satisfy the Requirement Under the Administrative Procedure Act That Its Decision Be Supported With Substantial Evidence.”) with Request for Rehearing of the Indicated PJM Transmission Owners at 5 (Jan. 16, 2026) (with the Indicated PJM Transmission Owners listed as Exelon and FirstEnergy) (“Exelon & FirstEnergy January 16th Rehearing Request”) (“There is No Evidence In the Record That Co-Located Loads Are Unable to Obtain Reliable, Timely, and Reasonably Priced Service Using the Existing Network Service Construct. Therefore, the Commission Fails To Satisfy the Requirement Under the Administrative Procedure Act That Its Decision Be Supported With Substantial Evidence.”).
6 Exelon & FirstEnergy July 20th Rehearing Request at 14-15.

PDF page 3

3
sufficient but in fact what is just and reasonable and consistent with the public interest. And the Commission has found that alternative configurations indeed meet this standard. The Transmission Owners fail to acknowledge the Commission’s finding that Talen’s decision to transition to front- of-meter “in fact, might support” a showing “that there is a lack of sufficient clarity related to Co- Location Arrangements writ large,”7 while at the same time seeking to perpetuate continued regulatory uncertainty through multiple rehearing requests recycling the same arguments. The Transmission Owners also renew their challenge to the Commission’s denial of PJM’s unauthorized replacement of “Point of Interconnection” with “Point of Change in Ownership” in the definition of Co-Located Load.8 The Commission should reject this argument, as it did PJM’s, for failure to timely raise it on rehearing of the December 2025 Co-Location Order.9 As the Commission observed recently, “an attack on a judgment in a proceeding other than a direct appeal” is a collateral attack and “is generally prohibited.”10

Looking forward, the Commission should grant Constellation’s Request for Rehearing and implement three reforms to expedite interconnection: (1) establish study deadlines binding both PJM and Transmission Owners, (2) require PJM to spell out its methodology and process for completing Necessary Studies in its Tariff, and (3) require all Transmission Owner standards, requirements, guidance, and practices related to necessary control technologies and/or protection

7 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209, at P 63 (2026) (“June 2026 Co-Location Order”).
8 Indicated TO June 2026 Co-Location Order Rehearing at 3, 6, 16-17; see also Indicated TO Large Load Show Cause Rehearing at 6-8 (requesting that the Commission “clarify that in any Section 205 filing or other response to the PJM Show Cause Order, PJM and/or the PJM Transmission Owners are not limited to defining ‘large load’ or ‘electrically proximate large load’ based on reference to the point of interconnection, and that they will have sufficient flexibility to propose other points of reference, such as the Point of Change of Ownership.”) (emphasis added).
9 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 2025 Co-Location Order”).
10 Voltus, Inc. v. PJM Interconnection, L.L.C., 196 FERC ¶ 61,074, at P 65 (2026).

PDF page 4

4
schemes to be filed with the Commission.11 Filing these standards is especially critical if the Commission clarifies that Transmission Owners may require protection schemes on both sides of the Point of Interconnection.12 In light of this approach, establishing study deadlines and ensuring all requirements are clear and enforceable are critical paths to faster interconnection. CONCLUSION

For the reasons stated above, Constellation respectfully requests that the Commission grant Constellation’s Request for Rehearing of the June 2026 Co-Location Order and reject the

Transmission Owner Rehearing Requests.

11 See generally Request for Rehearing and Clarification of Constellation Energy Generation, LLC (July 20, 2026) (“Constellation’s Request for Rehearing”).
12 Indicated TO June 2026 Co-Location Order Rehearing at 3 (“The Commission should clarify that PJM and the PJM Transmission Owners will be permitted to require protection on both the customer and Transmission Owner sides of the Point of Interconnection, to the extent that a study determines that such protection is necessary and appropriate.”).

PDF page 5

5

    Respectfully submitted,

    /s/ Paul F. Wight

August 4, 2026
Carrie Hill Allen
Sr. Vice President & Deputy General Counsel Seth T. Lucia

Assistant General Counsel
Constellation Energy Generation, LLC 250 Massachusetts Ave. NW, Suite 760 Washington, D.C. 20001

carrie.allen@constellation.com
seth.lucia@constellation.com

Christopher A. Wilson
Vice President, Federal Regulatory Affairs Constellation Energy Generation, LLC 250 Massachusetts Ave. NW, Suite 760 Washington, D.C. 20001

202-347-7500
FERCe-filings1@constellation.com

Paul F. Wight
Carolyn E. Clarkin
DLA Piper LLP (US)
500 Eighth Street NW
Washington, D.C. 20004
703-773-4058
paul.wight@us.dlapiper.com
carolyn.clarkin@us.dlapiper.com

Sophia Browning
DLA Piper LLP (US)
4365 Executive Drive
Suite 1100
San Diego, CA 92121
858-677-1455
sophia.browning@us.dlapiper.com

Counsel for Constellation Energy
Generation, LLC

PDF page 6

CERTIFICATE OF SERVICE
I hereby certify that I have on this 4th day of August 2026, caused to be served a copy of the foregoing upon all parties on the service lists in these proceedings in accordance with the requirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2026).

/s/ Sophia Browning

Sophia Browning
DLA Piper LLP (US)
4365 Executive Drive
Suite 1100
San Diego, CA 92121
858-677-1455
sophia.browning@us.dlapiper.com