Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C. to the Answer of Constellation Energy Generation, LLC filed on 08/03/2026
Text extracted from the eLibrary original (SHA-256 94ec833b8df3a20a…). Download the original from the official source.
Contents · 4 sections
Read topic-matched comments in EL25-49
Topics in the text: Filing procedure · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
EL25-49-000, et al. (Aug. 3, 2026) (“Constellation Answer”); PJM Interconnection, L.L.C., Motion for Extension of Time for Specified Compliance Requirements and Request for Expedited Treatment of PJM Interconnection, L.L.C., Docket Nos.Read this passage Filed comments: Filing procedure
I. BACKGROUND
printed heading · Topic match: Filing procedure
On August 3, 2026, the PJM Industrial Customer Coalition filed an answer in support of PJM’s extension request.7 The PJM Industrial Customer Coalition agreed with 4 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209, at ordering paras. (C)-(H) (2026). 5 PJM Motion for Extension of Time at 7-8. 6 Id. at…Read this passage Filed comments: Filing procedure
II. MOTION FOR LEAVE TO ANSWER
printed heading
Therefore, PJM respectfully requests that the Commission accept this answer. 8 Id. at 2-3. 9 See generally Constellation Answer. 10 Id. at 2. 11 Id. at 1-2. 12 See 18 C.F.R. § 385.213(a)(2); see, e.g., PJM Interconnection, L.L.C., 193 FERC ¶ 61,192, at P 28 (2025) (accepting PJM’s answer to…Read this passage
III. ANSWER
printed heading · Topic match: Reliability and curtailment
First, Constellation asks the Commission to clarify that PJM will consider an earlier effective date for Interim NITS given the urgency surrounding this issue.14 PJM has evaluated opportunities to implement Interim NITS earlier than other new transmission services, consistent with the Commission’s…Read this passage Filed comments: Reliability and curtailment
IV. CONCLUSION
printed heading
CONCLUSION For the foregoing reasons, PJM requests that the Commission: (1) grant this motion for leave to answer; (2) consider this answer; and (3) grant the motion for extension of certain compliance obligations. 17 Id. 18 See PJM Interconnection, L.L.C., Reply Brief of PJM Interconnection,…Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 10th day of August 2026. /s/ Ruth M.Read this passage