ER26-3531-000 · 2026-08-17 · Midcontinent Independent System Operator, Inc., American Transmission Company LLC
2026-08-17_Revisions to Attachment FF-ATCLLC re: Show Cause Order
PDF page 1
MAILING ADDRESS: P.O. BOX 47 ▪ WAUKESHA, WI 53187-0047 ▪ Phone: 262-506-6830 ▪ Fax: 262-506-6710 STREET ADDRESS: W234 N2000 RIDGEVIEW PARKWAY COURT ▪ WAUKESHA, WI 53188-1022
Legal Department
Direct Line: (262) 506-6170
E-Mail: sneitzel@atcllc.com
August 17, 2026
The Honorable Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, N.E.
Washington, DC 20426
Re:
American Transmission Company LLC, Docket No. ER26-___-000
Proposed Revisions to Attachment FF-ATCLLC of the MISO Tariff in Response to Show Cause Order
Dear Secretary Reese:
Pursuant to Section 205 of the Federal Power Act (“FPA”),1 Part 35 of the Federal Energy Regulatory Commission’s (“Commission”) regulations,2 and the Commission’s directives in the Order Instituting Proceeding Under Section 206 of the Federal Power Act (“Show Cause Order”),3 the Midcontinent Independent System Operator, Inc., (“MISO” as the Transmission Provider),4 on behalf of American Transmission Company LLC, by its corporate manager, ATC Management Inc. (collectively, “ATC”)5, hereby submits proposed revisions to Attachment FF-ATCLLC of MISO’s Open Access Transmission, Energy, and Operating Reserve Markets Tariff (“Tariff”).
Paragraph 36 of the Show Cause Order indicates that Transmission Owners may elect to submit their own FPA Section 205 filings to address matters discussed in the Show Cause Order. Because ATC currently has its own local planning process included in Attachment FF-ATCLLC of the MISO Tariff, ATC is proposing certain revisions to Attachment FF-ATCLLC to fulfill obligations outlined in the Show Cause Order to address large load integration in the ATC service territory. ATC understands that MISO intends to file various amendments to its Tariff in future filings to comply with the Commission’s directives in the Show Cause Order and ATC
1 16 U.S.C. § 824d.2 18 C.F.R. Part 35 (2026).3 Midcontinent Indep. System Op., Inc., Order Instituting Proceeding Under Section 206 of the Federal Power Act, 195 FERC ¶ 61,212 (2026) (“Show Cause Order”).4 MISO joins this filing as the administrator of its Tariff, and reserves the right to comment or protest. 5 Note, in Attachment FF-ATCLLC, ATC is generally referred to as ATCLLC. Therefore, for purposes of this filing, ATC and ATCLLC may be used interchangeably.
PDF page 2
August 17, 2026Page 2
may also join in those filings.6 ATC’s filing here is intended to establish requirements in its footprint and be complementary to MISO’s future filings. As described below, ATC’s proposed revisions to Attachment FF-ATCLLC describe processes that are designed to work together with MISO’s process in the same way ATC’s local planning process in Attachment FF-ATCLLC
works with the annual MISO Transmission Expansion Plan (“MTEP”) process today. ATC also seeks approval for modifications to the local planning process that is utilized today in ATC’s footprint.
I. Background
A. ATC
ATC is a Wisconsin limited liability company created as a single-purpose, for-profit transmission company.7 ATC began operations under the terms of its own open access
transmission tariff on January 1, 2001, and currently owns and operates over 10,000 miles of jurisdictional transmission facilities in the states of Wisconsin, Illinois, Minnesota, and Michigan. Many of ATC's facilities were acquired, with Commission approval, from a number of previously vertically integrated companies, municipalities, and electric cooperatives. On February 1, 2002, ATC transferred operational control of its facilities to MISO.8 Since that time, MISO has provided transmission service over ATC’s transmission facilities pursuant to the terms of the MISO Tariff, with ATC operating its transmission facilities at MISO’s direction. ATC has its own Commission-approved local planning process set forth in the MISO Tariff at Attachment FF-ATCLLC.
B. ATC’s Planning Functions and Attachment FF-ATCLLC
Since beginning operations in 2001, ATC has engaged in local transmission planning as one of its core functions. ATC’s local transmission planning process is open, collaborative, driven by stakeholder needs, and responsive to industry changes and technology developments. Attachment FF-ATCLLC sets forth ATC’s planning functions and the manner in which ATC meets the transmission needs of its customers, which is a key element of ATC’s operations. Pursuant to Wisconsin law,9 ATC is a transmission only company and not permitted to directly
6 See MISO’s Motion to Hold Proceeding in Abeyance, Docket No. EL26-70, filed on Aug. 3, 2026 (MISO Abeyance Motion). As noted in MISO’s Abeyance Motion, ATC is filing a separate Section 205 filing in response to certain of the Commission’s directives in the Show Cause Order. In future MISO filings, ATC will indicate whether it joins MISO and the MISO Transmission Owners in the proposed changes.7 Wis. Stats. § 196.485(3m) established the framework for the formation of ATC as a single-purpose transmission company to own and operate the electric transmission facilities as a single transmission grid in the areas in which facilities are contributed, and authorized ATC to plan, construct, operate, maintain, and expand the transmission facilities to provide adequate and reliable transmission service.8 Transfer of operational control of ATC’s facilities to MISO was authorized in Am. Transmission Co. LLC, 97 FERC ¶ 62,182 (2001).9 Under the Wisconsin law that enabled ATC to be formed, ATC sought and thereafter became “a transmission company” and “public utility” which obligated ATC to engage in as “its sole purpose the planning, constructing, operating, maintain and expanding of transmission facilities, and the providing of transmission service, to
PDF page 3
August 17, 2026Page 3
serve retail customers. Therefore, ATC engages in the necessary planning to provide for changes, modifications, or additions to its transmission facilities to provide adequate, reliable, and sufficient transmission capability so that entities that rely on ATC’s transmission facilities are able to meet the needs of their respective retail customers.
ATC’s planning processes are structured to include all interested parties and treat all similarly situated interconnected customers in a similar, consistent manner. Additionally, while ATC maintains its own planning processes in Attachment FF-ATCLLC, ATC coordinates extensively with MISO. Under the Transmission Owners Agreement,10 ATC conducts “bottom- up” local planning to implement its planning functions and obligations to ensure the adequacy and reliability of the ATC system for the benefit of all customers. As the utility industry changes and new technology develops, especially with the recent advent of large load data centers, ATC has actively engaged with the changing landscape to continue to fulfill its obligations.
C. ATC’s Distribution – Transmission Interconnection Process
Attachment FF-ATCLLC sets forth ATC’s process for Distribution – Transmission Interconnections. The process is initiated by one or more of ATC’s distribution customers through submission of a Load Interconnection Request Form (“LIRF”). Upon receipt of a complete LIRF, ATC will begin its studies and analyses of the interconnection. More specifically, ATC will engage with its Best Value Planning process, as defined in Attachment FF-ATCLLC, and collaborate with the customer to determine the best value solution to interconnect the new load request.
Upon ATC’s development of the project containing the transmission facilities necessary to facilitate the load interconnection in a safe, reliable, and cost-effective manner, ATC coordinates with MISO and engages with MISO’s planning process. ATC will submit the proposed project to MISO either through the annual MTEP process or MISO’s Expedited Project Review (“EPR”) process. Upon MISO’s approval, the project would be included in Appendix A of MTEP.
As an active participant in the MISO stakeholder process, ATC is aware that MISO is developing proposals to comply with the requirements in the Show Cause Order. ATC will continue to engage with the stakeholder process and work with MISO to ensure that ATC’s local planning and interconnection processes in Attachment FF-ATCLLC comply with the Show Cause Order and can be implemented in a manner that complements MISO’s process. ATC intends for the revisions to Attachment FF-ATCLLC to integrate into MISO’s processes in the
provide for an adequate and reliable transmission system that meets the needs of all users that are dependent on the transmission system and that supports effective competition in energy markets without favoring any market participant.” Wis. Stat. § 196.485(ge) (2025) (emphasis added). ATC, therefore, is not permitted to delegate its planning obligations under state law to any other entity.
10 Agreement of Transmission Facilities Owners to Organize the Midcontinent Independent System Operator, Inc., a Delaware Non-Stock Corporation, Appendix B-Planning Framework, available at: https://www.misoenergy.org/legal/rules-manuals-and-agreements/tariff/.
PDF page 4
August 17, 2026Page 4
same way ATC’s existing Distribution – Transmission Interconnection process interplays with MTEP and the EPR process.
D. ATC’s Development of Large Load Studies and Requirements
In 2022, ATC began receiving serious inquiries about potential new large loads, and in particular data centers. While ATC had already developed a robust local planning process, internal planning experts quickly realized that more than traditional steady state analysis would be needed to appropriately study and determine the system impacts of the unique characteristics presented by large load data centers. ATC began intensive internal studies and engaged with vendors to develop concepts for mitigation of key concerns related to large data center loads. Subsequently, in 2024 through 2025, ATC elevated its engagement with external resources, including specialized power system consultants. Specifically, ATC and its consultants engaged with new and unique types of analyses to study large loads, including flicker analysis, rotor swing modes, and generator shaft studies. ATC determined that to safely and reliably interconnect large loads, more robust planning criteria requirements that apply specifically to these new, unique large loads must be developed and implemented. Development of these requirements posed unique challenges as there was no industry documentation of these issues, concerns, impact, mitigation measures, or performance requirements. Authorities such as NERC had not yet engaged with these issues. Recognizing the need for transformation in response to the characteristics of new large loads, ATC stepped into the role of industry leader in developing reliability criteria.
Each new large load presents its own unique characteristics and challenges, however ATC realized early in the development phase that it would not be practical to perform custom studies for each load interconnection request and to derive bespoke project-specific limits to address reliability concerns. Therefore, through intensive studies and analyses, internally and with consultants, ATC developed new local planning criteria, including new criteria developed exclusively to apply to large load interconnections across ATC’s footprint. Uniquely situated among the Great Lakes and Mississippi River, ATC’s geography stands out from other areas in the MISO footprint. Additionally, as a transmission-only company, ATC has developed close relationships with its customers. These factors have contributed to ATC’s ability to develop processes and requirements that are specifically applicable to ATC’s system without compromising reliability.
Through studies and analysis, ATC initially determined that the appropriate threshold for categorizing large loads in the ATC footprint would be 200 MW. As discussed below, ATC continues to analyze, on no less than an annual basis, the appropriate threshold for categorizing large loads and associated reliability and operational criteria. Through the proposed Attachment FF-ATCLLC updates described below, ATC is now updating its large load threshold to 100 MW to align with directives from the Public Service Commission of Wisconsin (“PSCW”) regarding appropriate measures to mitigate cost shifting concerns at the retail level.11 ATC has determined
11 See Public Service Commission of Wisconsin Order Docket 6630-TE-113 Final Decision (PSC REF# 591873) (“PSCW Retail Tariff Order"). The PSCW made a finding of fact that it would be “reasonable to make the VLC
PDF page 5
August 17, 2026Page 5
that 100 MW is an initially appropriate threshold for categorizing large loads for cost allocation and to ensure reliability, but will continue to re-evaluate and apply reliability criteria for large loads that present unique characteristics as necessary. ATC also continues to be an active stakeholder and participant in MISO and NERC efforts to ensure reliable service. ATC will continue to be responsive to industry standards, as needed.
As described in depth below, ATC proposes to revise Attachment FF-ATCLLC to
include requirements, processes, and procedures associated with the interconnection of large loads, including the operational and reliability requirements discussed above.
II. Discussion
ATC’s proposed revisions to Attachment FF-ATCLLC are just and reasonable. The
Commission acknowledged in the Show Cause Order that ATC has its own distribution interconnection request process and load interconnection procedures described in Attachment FF-ATCLLC, but that Attachment FF-ATCLLC did not explicitly address interconnections of large loads.12 Over the last few years, ATC has developed company-specific business practices containing policies, practices, and requirements directed specifically at large loads that also address several concerns identified by the Commission in the Show Cause Order.13 Therefore, in this filing, ATC is seeking to amend Attachment FF-ATCLLC to add these requirements and processes associated with large loads in ATC’s footprint.
As discussed above, many of the revisions to Attachment FF-ATCLLC reflect existing processes, practices, and requirements in ATC’s footprint. Therefore, ATC’s proposed revisions should not disrupt existing commercial arrangements and in-flight projects. By allowing ATC to maintain existing process and requirements, while seamlessly building in additional requirements and provisions necessary to address several of the Commission’s concerns in the Show Cause Order, the proposed revisions are just and reasonable and will provide clarity and transparency for the reliable interconnection of large loads in the ATC footprint.14
tariff mandatory for all customers with an aggregate load forecast of 100 MW” and therefore ordered the “VLC tariff mandatory for all customers with an aggregated load forecast of over 100 MW” Id., Finding of Fact 3, Order Point 5. See also Public Service Commission of Wisconsin Order Docket 6680-TE-115 Final Decision (PSC REF# 594678) (“PSCW Individual Contract Order"), Finding of Fact 3 (finding 100 MW to be the appropriate threshold to apply a new large load retail tariff).
12 Show Cause Order at P 21, FN 75 (“Although Attachment FF-ATCLLC includes ATC’s distribution-to- transmission interconnection request process and load interconnection procedure, Attachment FF-ATCLLC does not include provisions specific to large loads.”); id. at P 21, FN 77 (noting that ATC has developed specific procedures and requirements outside of the Commission-jurisdictional tariff).13 ATC’s current business practices can be found on its website. During the pendency of this filing, ATC will make administrative updates to its website and Business Practices to ensure that all language proposed to be revised in Attachment FF-ATCLLC corresponds to the website and Business Practices.14 See Show Cause Order at P 36 (noting that filers should provide explanation for how FPA section 205 filings will avoid disrupting existing commercial arrangements).
PDF page 6
August 17, 2026Page 6
A. Interconnection Process for Large Loads
1. Application Process
i. FERC Directive
In the Show Cause Order, the Commission made a preliminary finding that the MISO
Tariff appears to be unjust and unreasonable because it lacks an application process for Eligible Customers15 seeking transmission service on behalf of large loads.16 The Commission
emphasized that “clear and consistent provisions” will deter speculative requests and provides certainty and clarity for stakeholders.17 The Commission indicated that applications should be accepted on a rolling basis.18
ii. ATC Compliance
As the Commission acknowledged in the Show Cause Order, ATC has developed local
planning processes and requirements in Attachment FF-ATCLLC, including processes for
Distribution – Transmission Interconnections.19 ATC’s local planning process for Distribution – Transmission Interconnection applies to all ATC customers (i.e., Eligible Customers), including large loads, seeking transmission service on ATC’s system.
ATC proposes to add the following Tariff language to further clarify that the Distribution
– Transmission Interconnection planning functions, processes, and requirements apply to large loads:
• Sections V.C and VI.A.1 state that Distribution – Transmission Interconnection
Planning Function includes Large Load Distribution – Transmission
Interconnection Planning.
15 Defined by MISO as “(i) Any electric utility (including the Transmission Owner(s), ITC Participants(s), and any power marketer), Market Participant, Federal Power Marketing Agency, or any person generating electric Energy for sale or resale is an Eligible Customer…; or (ii) Any retail customer taking unbundled transmission service pursuant to a state requirement that a Transmission Owner or ITC Participant offer the transmission service, or pursuant to a voluntary offer of such service by a Transmission Owner or ITC Participant, that is an Eligible Customer under this Tariff. Unbundled retail customers that seek to take local distribution service cannot be Eligible Customers under this Tariff with respect to that service.” MISO, FERC Elec. Tariff, Module A, §1.E (Definitions E) (93.0.0). In ATC’s footprint, an Eligible Customer includes ATC’s distribution customers with which ATC has a Commission-accepted Distribution – Transmission Interconnection Agreement. Any new distribution customer in ATC’s footprint would be required to enter into a Distribution – Transmission Interconnection Agreement prior to interconnecting to ATC system to ensure compliance with ATC’s requirements and procedures as outlined in Attachment FF-ATCLLC.16 Show Cause Order at PP 3, 57.17 Id. at P 56.18 Id. at P 59.19 Id. at P 21, FN 77. See Attachment FF-ATCLLC §§ V.C (identifying ATC’s Planning Functions); VI.A (describing the Distribution – Transmission Interconnection Planning Function and associated process).
PDF page 7
August 17, 2026Page 7
The Distribution – Transmission Interconnection process in Attachment FF-ATCLLC details clear and specific procedures for submitting a load interconnection request form (“LIRF”), which kicks off applicable study procedures as described below. ATC accepts applications on a first-come, first-served basis, upon completion of applicable readiness requirements, also described below. ATC proposes additional Tariff language to Attachment FF- ATCLLC to establish these procedures, including:
• Section IV defines the LIRF as the form in which a distribution customer initiates a request for a distribution interconnection to ATC’s system that includes a request for service to a large load.
• Section IV also includes in the definition of “Distribution – Transmission Interconnection Requests” that the processes for distribution interconnections in ATC’s footprints apply to large load interconnections, plus any requirements or processes exclusively applicable to large loads.
• Section VI.A.1-2 provides clarifying edits to sections of Attachment FF-ATCLLC addressing Distribution – Transmission Interconnection Requests and Study Sequencing to establish procedures that apply to large load interconnections. Generally, ATC’s established local planning procedures in Attachment FF-ATCLLC apply to large load interconnections, as clarified by the proposed revisions above. Notably, however, certain existing and proposed new requirements will apply exclusively to large loads. These large load-specific requirements are detailed herein. ATC has added the following Tariff language to state that while the general Distribution – Transmission Interconnection Process applies to all loads in ATC’s footprint, including large loads, certain requirements apply exclusively to large loads:
• Section III proposes to add to the “Purpose” section of Attachment FF-ATCLLC Tariff language stating that ATC has developed certain policies that apply exclusively to large loads.
Importantly, as described above, ATC’s application process and studies of all distribution interconnections, including large load interconnections, contemplates close coordination with MISO. While ATC has developed its own process to accept and study distribution interconnections within its footprint, ATC works closely with MISO to provide it with all necessary information so that the interconnection can be integrated into the annual MTEP, which may include on an as needed basis, review and approval on an expedited timeline through MISO’s Expedited Project Review (“EPR”) process. Upon Commission acceptance of these changes to Attachment FF-ATCLLC, ATC will continue to coordinate with MISO to ensure all projects interconnecting to ATC’s system are included in MTEP either through the standard planning process or the EPR process.
2. Readiness Requirements
i. FERC Directive
PDF page 8
August 17, 2026Page 8
The Commission indicated that sufficient readiness requirements may be necessary to address concerns associated with speculative large loads.20 The readiness requirements may include a fee and certain requirements associated at different phases of the study process.21 Further, as a component of the readiness requirements, the Commission indicated that it may be helpful to collect information regarding the characteristics of the large load customer.22
ii. ATC Compliance
Prior to initiation of a System Impact Study (described in detail below), ATC requires all distribution customers to meet certain readiness requirements to deter speculative requests and ensure accurate studies. First, distribution customers must submit a LIRF that is deemed complete, pursuant to criteria outlined by the applicable ATC Business Practice. Additionally, any distribution customer that seeks to add a new large load must submit a Large Load Interconnection Criteria Confirmation Form which details specific operating characteristics of the proposed load increase so that ATC has sufficient information to appropriately analyze the large load impacts. Other documentation may be necessary prior to ATC’s initiation of the System Impact Study to ensure that ATC can accurately study the new interconnection and ensure resources are allocated only to non-speculative requests. ATC proposes to add these requirements to Attachment FF-ATCLLC, including:.
• Section VI.A.4 contains a new section detailing the readiness requirements to initiate a System Impact Study, including requirements specifically applicable to large load interconnections.
Additionally, ATC proposes to implement a new requirement associated with large load interconnections in response to the Commission’s Show Cause Order. Any new distribution interconnection request that exceeds the large load threshold shall be required to pay an initial non-refundable deposit, in an amount of $50,000 which will be established by the applicable ATC Business Practice. Subsequently, the distribution customer shall be invoiced by ATC for time and materials above and beyond the initial deposit necessary to complete the System Impact Study. In ATC’s experience, implementation of this charge will help to defer speculative requests and ensure that distribution customers will provide accurate and up to date information to ATC when submitting a new LIRF and other required documentation.
• Section VI.A.5 adds a section requiring an initial deposit and any time and materials cost in exceedance of the deposit necessary for ATC to complete the System Impact Study.
20 Show Cause Order at P 59.21 Id.22 Id.
PDF page 9
August 17, 2026Page 9
3. Study Procedures
i. FERC Directive
In the Show Cause Order, the Commission expressed concern that the MISO Tariff lacked specific study procedures for Eligible Customers seeking transmission service on behalf of large loads for new and incremental additions.23 Additionally, the Commission indicated that studies to produce a non-binding good-faith estimate of the cost and time to construct facilities necessary to interconnect a large load customer should take no more than 90 days to complete.24 The Commission also indicated that studies should consider operational characteristics and that accurate models using Electromagnetic Transient studies may be helpful in analysis of large loads.25
ii. ATC Compliance
As described above, Attachment FF-ATCLLC has guided ATC’s interconnection process since its adoption in MISO’s Tariff. In response to the Commission's Show Cause Order and changing industry needs, ATC proposes to add additional detail and requirements to its distribution interconnection study process. Upon completion of all applicable readiness requirements as discussed above, ATC will initiate a System Impact Study. System Impact Studies are split into two distinct phases: (1) steady state analysis, and (2) applicable special studies.
All load interconnections require ATC to conduct the steady state analysis. The steady state analysis phase of the System Impact Study shall result in a non-binding good-faith estimate of time, cost, and potential facilities necessary to interconnect a load, responsive to the Commission's directives outlined in the Show Cause Order. Upon completion of the steady state analysis, ATC can move into the special studies phase, as needed. Not all load interconnection requests require special studies, and the extent to which depends upon the complexity of the project. However, potential projects that exceed ATC’s large load threshold or display unique characteristics will require additional studies during the special studies phase. The special studies phase includes analysis of, but is not limited to, transfer analysis, reactive power analysis, angular and voltage stability of nearby generators, load voltage stability, voltage ride through of both generators and loads, power quality analysis, short-circuit analysis, and other transient study analyses. The special studies phase analyses may also involve several positive sequence and Electromagnetic Transient study tools and result in technical reports or recommendations for potential mitigation of any limitations observed.
ATC proposes to include the requirements of System Impact Studies in Attachment FF- ATCLLC and include additional detail, procedures, or other relevant information associated with
23 Show Cause Order at PP 3, 39.24 Id. at PP 39, 63.25 Id. at P 60.
PDF page 10
August 17, 2026Page 10
the System Impact Studies in applicable Business Practices and the ATCLLC Local Planning Criteria.
• Section VI.A.3 proposes to add a section to Attachment FF-ATCLLC detailing the process and requirements of a System Impact Study, as described above.
4. Evaluation of Alternative Transmission Technologies
i. FERC Directive
In the Show Cause Order, the Commission expressed concern with the lack of clear and consistent provisions requiring the evaluation of alternative transmission technologies.26 The Commission indicated that transparent and clear requirements for the evaluation of these technologies be included in Tariff language.27 Similarly, the Commission indicated that a study report should indicate why alternative transmission technologies are not feasible in the event no alternative transmission technology facility is used in response to a request to interconnect a large load.28
ii. ATC Compliance
Attachment FF-ATCLLC requires ATC to engage in Best Value Planning, which is defined as:
[T]he consideration of, or evaluation of, one or more alternatives to the proposed construction of new, or the modification of existing, Transmission Facilities which have been identified in a planning process to determine whether an
alternative or alternatives exist that may include the construction of new, or the modification of the existing, Distribution Facilities or Transmission Facilities owned by others that is/are less costly or which may provide greater enhancement to the reliability, capability or integrity of ATCLLC’s Transmission Facilities and such interconnected Transmission or Distribution Facilities when compared to the estimated cost of the construction and capability of the proposed new, or the proposed modification of, ATCLLC’s Transmission Facilities, while taking into account the environmental considerations, regulatory approvals and the ability to construct the proposed Distribution or Transmission Facilities in a timely and appropriate manner.2926 Show Cause Order at P 51. Alternative transmission technologies are also commonly referred to as Grid Enhancing Technologies (“GETs ”). The terms are used interchangeably in ATC’s footprint and may include static synchronous compensators, static VAR compensator, advanced power flow control devices, transmission switching, synchronous condensers, voltage source converter, advanced conductors, tower lifting, and dynamic line ratings, among other technologies named in the applicable ATC Business Practice.27 Id. at 62.28 Id. at P 62.29 Attachment FF-ATCLLC § IV.
PDF page 11
August 17, 2026Page 11
To facilitate Best Value Planning, ATC engages with evaluation of grid enhancing technologies or alternative transmission technologies for all distribution interconnection requests. ATC proposes to make this requirement clear in Attachment FF-ATCLLC through addition of new, specific language:
• Section VI.A.9 adds language detailing that in Best Value Planning ATC shall evaluate the use of grid enhancing technologies or alternative transmission
technologies in each System Impact Study.
Additionally, Section VI.A.9 requires ATC to provide results of studies to the distribution customer, which is commonly referred to as Best Value Planning documentation or reporting in ATC’s footprint. Specific Best Value Planning documentation requirements are detailed in applicable ATC Business Practices. This documentation, which is required by Attachment FF- ATCLLC, inherently includes narrative information regarding the use of and evaluation of alternative transmission technologies. In the Best Value Planning documentation, ATC provides details on the evaluation including, if applicable, details as to why grid enhancing technologies or alternative transmission technologies were not used.
B. Large Load Definition and Operational Requirements
1. Large Load Definition
i. FERC Directive
In the Show Cause Order, the Commission expressed concern due to the lack of a definition of large load in MISO’s Tariff that sufficiently captures loads that present unique challenges described in the Show Cause Order.30
ii. ATC Compliance
As stated above, ATC previously established a threshold of 200 MW to define large loads in its system. To address the Commission’s concerns in the Show Cause Order, ATC is proposing amended language in Attachment FF-ATCLLC, Section IV to change the threshold to 100 MW. The 100 MW threshold shall serve as ATC’s initial threshold to classify loads to which certain requirements, procedures, and processes shall apply to address reliability, operational, and cost shifting concerns. This threshold shall serve as a baseline threshold and may be adjusted in appliable ATC Business Practices and local planning criteria as necessary. As described above, ATC has determined that 100 MW is an appropriate threshold from a planning, reliability, and operational perspective within ATC’s footprint. ATC consistently coordinates with MISO, other regional and national entities, its customers, and other interconnected entities to ensure that any process or requirement in ATC’s footprint shall not compromise reliability within ATC’s territory, MISO’s service area, or broader. Additionally, the PSCW has recently established that 100 MW is an appropriate threshold to address retail cost
30 Show Cause Order at P 57.
PDF page 12
August 17, 2026Page 12
shifting concerns associated with large loads.31 In its final decisions in a recent retail tariff proceeding and recent individual retail contract proceeding, the PSCW determined that it was most reasonable to set the applicability threshold at 100 MW.32 The PSCW found that the rates and rules established by retail tariffs and retail contracts are appropriately applied to large loads greater than 100 MW.33 In an effort to align with the state’s authority over retail rates of ATC’s distribution customers, ATC has applied the 100 MW threshold to address cost shifting concerns at the wholesale level, as discussed in detail below.
• Section IV adds a definition of “ATCLLC Large Load” to establish that in ATC’s footprint, an initial threshold of 100 MW shall apply.
2. Operational Requirements
i. FERC Directive
The Commission expressed concern in the Show Cause Order that the MISO Tariff lacks ongoing operational requirements to address the unique characteristics and challenges of large loads.34 Specifically, the Commission highlighted several areas of concern, including: (1) lack of sufficient visibility and channels for communication of data; (2) lack of required monitoring equipment to monitor impacts such as ramp rate; (3) requirements related to disconnection of large loads when necessary; (4) lack of ramp rate or ride-through requirements; and (5) lack of necessary protection systems or control technology requirements.35
ii. ATC Compliance
As discussed above, ATC has already developed requirements that are applicable to loads in its footprint that address the Commission’s concerns. In response to the Show Cause Order, ATC proposes to add these requirements to Attachment FF-ATCLLC. ATC is constantly re- engaging with the established requirements, updating and adjusting when necessary and as technology changes. Therefore, specific requirements will be outlined in ATC’s Local Planning Criteria which is submitted to MISO and in applicable Business Practice. ATC has developed its criteria and Business Practices in accordance with its robust analysis process coupled with stakeholder feedback. Therefore, ATC proposes to add specificity and clarity on operational and planning requirements that are applicable in ATC’s footprint, including: .
• Section IV.V.D adds the term “ATCLLC Local Planning Criteria” to define
ATC’s local planning criteria and establish that within the ATCLLC Local
Planning Criteria, ATC has developed certain requirements that apply exclusively
31 PSCW Retail Tariff Order at Order Point 5. PSCW Retail Contract Order at Order Point 2.32 PSCW Retail Tariff Order at 17. PSCW Retail Contract Order at Finding of Fact 3.33 PSCW Retail Tariff Order at Order Point 5. PSCW Retail Contract Order at Order Point 2.34 Show Cause Order at P 41.35 Id. at P 64.
PDF page 13
August 17, 2026Page 13
to large loads.
• Section IV.V.D also includes specific references to ATC’s “Business Practices” which shall provide additional details and procedures to implement the requirements of Attachment FF-ATCLLC, which includes requirements
applicable exclusively to large loads.
• Section IV.V.E. adds a new section to Attachment FF-ATCLLC which includes the performance criteria that ATC must include in the ATCLLC Local Planning Criteria, including but not limited to steady state criteria, dynamic stability assessments, resource facility requirements, large load interconnection requirements including active power oscillations and ramp rate limits, voltage ride through, load power factor, and power quality impacts. Additionally, that section states that ATC shall maintain certain data monitoring, data retention, forecasting, and additional design criteria in applicable business practices.
• Section IV.V.E. also includes language specifically to require all ATC’s customers, including customers service large loads, to comply with ATC’s requirements pursuant to the established Distribution – Transmission Agreements (discussed below). In the event a distribution customer fails to comply with ATC criteria and requirements, ATC shall take appropriate action necessary to maintain reliability in accordance with its operating procedures and as necessary, as directed by MISO pursuant to the ATC operating procedures.
• Section IV.V.F adds language to establish that ATC’s criteria, requirements, processes, and procedures apply in its footprint, may be updated at ATC’s discretion from time to time based on new conditions, safety concerns, operational issues, customer requests, regulatory developments, among other reasons.
Additional details on the requirements and criteria will be included in the applicable ATC Business Practices and in the ATCLLC Local Planning Criteria. In certain circumstances, ATC may elect to defer certain requirements to MISO in areas such as data reporting and providing forecasting information directly to MISO. As MISO continues to develop its own requirements in response to the Show Cause Order via the stakeholder process, ATC will make adjustments to its own Business Practices to outline any areas that ATC may defer to MISO requirements.
C. Service Agreement
1. Transmission Service Agreement
i. FERC Directive
The Commission expressed concern in the Show Cause Order regarding the lack of a pro forma transmission service agreement between MISO and the eligible customer taking
PDF page 14
August 17, 2026Page 14
transmission service on behalf of a large load to memorialize all terms and ensure that MISO may be able to enforce large load requirements.36
ii. ATC Compliance
ATC has executed and filed with the Commission numerous Distribution – Transmission Interconnection Agreements (“D-TIAs”). Prior to interconnecting a new distribution customer to ATC’s system, ATC requires execution and filing of a D-TIA. Each D-TIA is on file with the Commission. Because each D-TIA governs all interconnections among ATC and its distribution customer, all load interconnections, including large load interconnections, are governed by the D-TIAs. The D-TIA requires that all distribution customers comply with ATC’s processes, procedures, and requirements to interconnect with ATC’s system. Further, ATC may take appropriate action as necessary pursuant to its Operating Guides as needed in the event a distribution customer fails to abide by any of ATC’s requirements. ATC respectfully submits that for use in ATC’s footprint, a pro forma transmission service agreement in the MISO Tariff is not necessary as ATC already employs its D-TIAs which serve the same function, as is currently reflected in Section IV:
• Section IV states that any new distribution customer shall be required to enter into a D-TIA prior to interconnecting to ATC’s system and that ATC shall post a
template D-TIA to its public website to ensure transparency.
D. Cost Shifting
1. Agreement to Address Cost Shifting Concerns
i. FERC Directive
In the Show Cause Order, the Commission expressed concern regarding cost shifting that may occur among transmission customers as a result of the interconnection of large loads.37 The Commission made a preliminary finding that a pro forma cost recovery agreement between MISO, the Transmission Owner, and the Eligible Customer taking transmission service on behalf of the large load would mitigate the risk of cost shifting among transmission customers.38 Specifically, the Commission directed MISO and/or the Transmission Owners to address situations in which the proposed load fails to materialize or fails to materialize to the extent initially anticipated.39
The Commission references previously filed agreements designed to address such concerns, including Transmission Security Agreements as possible ways to alleviate cost shifting
36 Show Cause Order at P 65.37 Show Cause Order at PP 3, 69.38 Id. at PP 3, 67.39 Id. at P 80.
PDF page 15
August 17, 2026Page 15
concerns.40 However, the Commission leaves a significant amount of discretion to MISO and/or the Transmission Owners to develop methods, processes, and cost recovery agreements by which it will provide protections against cost shifting.41 The Commission also made a preliminary finding that any such cost recovery agreement should require credit support and/or security sufficient to secure obligations of customer taking transmission service to paid the amounts owned pursuant to the agreement.42
ii. ATC Compliance
For the past two years, ATC has engaged with its customers and other stakeholders to address the concerns described by the Commission. Ultimately, this led ATC to develop a new Business Practice on Large Load Cost Allocation and develop two new agreements to ensure cost shifting concerns are addressed in ATC’s footprint at the wholesale level, and in a manner that allows ATC’s customers who provide retail service, are able to comply with directives from state authorities on cost shifting prevention at the retail level. Specifically, ATC has developed a Large Load Project Commitment Agreement (“LLPCA”) and a Minimum Transmission Charge Agreement (“MTCA”) that it will enter into with its distribution customer. Pursuant to ATC’s Large Load Cost Allocation Business Practice, ATC requires these agreements if the project exceeds the definition of large load (i.e., 100 MW), or exceeds $100M in costs. The PSCW has determined that 100 MW would be an appropriate threshold in the State of Wisconsin to adequately protect against cost shifting concerns.43 Further, ATC recognized the need to address the potential impact from new loads that may be smaller than 100 MW, but because they are in areas of the system that have less transmission buildout than others, drive a disproportionate amount of network upgrades. Therefore, ATC intends to ensure that no cost shifting occurs for distribution interconnection projects that drive projects that exceed $100M in cost. ATC recently filed several LLPCAs and an MTCA associated with a large load in its footprint44 and intends to develop additional LLPCAs and MTCAs with in-flight projects in its footprint. The protections provided by the LLPCA and MTCA work in tandem, each described in detail below.
The LLPCA is designed to protect the Parties and other wholesale customers from costs associated with construction of facilities tied to a new large load and in the event of project cancellation, termination, or substantial modification prior to the project being placed in service. Likewise, ATC can invoke the terms of the LLPCA in the event of cancellation, termination, or substantial modification to recoup costs incurred during project development and construction.
40 Id. at P 83.41 Id. at PP 80-84.42 Id. at P 84.43 See PSCW Retail Tariff Order.44 Docket No. ER26-3265.
PDF page 16
August 17, 2026Page 16
In turn, the LLPCA provides ATC’s distribution customer with a transparent accounting mechanism that will allow it to protect its retail ratepayers either through a specific retail agreement or tariff. In sum, the Amended LLPCAs are designed to provide protections against cost shifting during project development and construction.
After ATC’s transmission facilities go into service, the MTCA provides additional protections to prevent cost shifting associated with transmission buildout in the event the large load that formed the basis for the buildout fails to materialize. As an initial step pursuant to ATC’s Large Load Cost Allocation Business Practice, ATC coordinates with the distribution customer pursuant to Attachment FF-ATCLLC through the Best Value Planning process, as described above, to develop a proposed project including facilities necessary to adequately serve the distribution customer, and by extension, its end-use customer. The distribution customer will continue to benefit from ATC’s entire transmission system and therefore will continue to pay for Network service pursuant to the MISO Tariff. Additionally, under the terms of the MTCA, the distribution customer will pay for Network Service for all capacity it has requested, regardless of actual use, so that other customers do not bear those costs. However, the charges incurred under the MTCA will be limited to the incremental revenue requirement for the transmission facilities, such that the distribution customer, and by extension, its customer, will not subsidize transmission service for other customers.
The protections provided by the LLPCA and MTCA are directly responsive to the
Commission’s Show Cause Order related to large load interconnections.45 In the Show Cause Order, the Commission preliminarily found “that MISO’s Tariff appears to be unjust and unreasonable because it lacks adequate mechanisms to mitigate the risk of cost shifting among transmission customers, which may result in unjust and unreasonable rates for transmission service.”46 The LLPCA and MTCA provide a mechanism by which ATC’s other wholesale customers are protected during the period of construction and also in the event the large load end-use customer fails to materialize or fails to take service to the full extent of its request to ATC’s distribution customer. The protection mechanisms provided by the LLPCA and MTCA directly respond to the Commission’s concerns on the risk of unjust cost shifts.47 The Amended LLPCAs and MTCA offer the protections that the Commission is seeking in a fair, just, and reasonable manner and similar to other accepted cost recovery agreements, such as Transmission Security Agreements, which the Commission recognizes in its Show Cause Order.48 Further, as stated above, the Commission preliminarily found in the Show Cause Order that just and reasonable cost recovery agreements would require credit support or other financial security “sufficient to secure the obligations of the Eligible Customer taking transmission service
45 See Show Cause Order at PP 78 – 85.46 Id. at P 78.47 Id. at P 80 (expressing the Commission’s concern that speculative transmission service requests associated with large loads may lead to unjust and unreasonable rate increases in jurisdictional transmission rates).48 Id. at P 83 (highlighting other filed cost recovery agreements such as the Transmission Security Agreements, which is analogous to the MTCA filed herein).
PDF page 17
August 17, 2026Page 17
on behalf of a large load to pay the amounts owed pursuant to the cost recovery agreement.”49 The MTCA requires a distribution customer to provide security within seven days of the effective date of the MTCA for the full amount that it may be required to pay under the terms of the MTCA, subject to the liability cap established by the terms of the agreement. Therefore, in response to the Show Cause Order. ATC proposes to reference the LLPCA and MTCA, in Section VI.12.B of Attachment FF-ATCLLC as follows:
• Including a provision stating that the Large Load Cost Allocation Business Practice applies exclusively to large loads.
• Stating that ATC and distribution customer must enter into a Large Load Project Commitment Agreement and a Minimum Transmission Charge Agreement to
provide adequate cost shifting protection in ATC’s footprint.
• Requiring that the LLPCA and MTCA templates shall be posted on ATC’s public website and, when executed, filed for acceptance with the Commission.
2. Appropriate Crediting
i. FERC Directive
In the Show Cause Order, the Commission indicated that any cost shifting protections should include a mechanism to ensure such payments are appropriately credited toward transmission owners’ transmission revenue requirements.50
ii. ATC Compliance
As indicated in the pending filing in Docket No. ER26-3265, ATC will include revenues collected under the MTCA in the Account 456.1 revenue credits line in Attachment O, providing supporting detail for the amounts charged via the Attachment O workpapers so that it is clear in ATC’s annual informational filing how payments made under the terms of the LLPCA and MTCA are reflected in ATC’s formula rate.
3. Additional Cost Shifting Protections Provided by ATC’s Business
Practices
In addition to developing methods responsive to the Commission’s directive to provide cost shifting protections described above, over the course of its operations, ATC has developed additional cost shifting protection measures in its footprint, as described in appliable business practices. While these measures do not apply exclusively to large loads, ATC has developed certain policies aligned with Attachment FF-ATCLLC to ensure project specific costs are not inappropriately shifted to other wholesale customers. For example, ATC has developed a Project Acceleration Business Practice and an Elective Facilities Business Practice. In the event a distribution customer requests ATC to “speed up” its design, engineering, scoping, pre- certification, and other timelines, an end-use customer must directly pay for those additional
49 Id. at P 84.50 Show Cause Order at PP 3, 85.
PDF page 18
August 17, 2026Page 18
expenses. Further, if a distribution customer, on behalf of its end-use customer, requests certain facilities that are above and beyond or outside of ATC’s Best Value Plan, the end-use customer will be directly assigned those costs. These protections ensure that any end-use customer that directly causes an additional cost not inherently incorporated into the Network Rate (i.e., acceleration and additional or specialty facilities), will be responsible for that cost.
E. Miscellaneous Updates
1. Generator Interconnection Process
Prior to joining MISO, ATC had developed its own generator interconnection process. The ATC-specific process was maintained after initial development of Attachment FF-ATCLLC, however ATC has since adopted MISO’s processes identified in Attachment X of MISO’s Tariff. As ATC no longer engages with its own specific process for generator interconnections, ATC is proposing to remove outdated references and clarify existing procedures that still exist in ATC’s footprint in conjunction with the MISO Attachment X process.
• Removal of references to Attachment R throughout Attachment FF-ATCLLC.
• Adding the definition of “Generating Facilities Modification Notification
(GFMN) Process” and associated procedures to clearly describe ATC’s process of evaluating modifications or other changes to generating facilities. ATC’s process studies all changes associated with generating facilities, and as appropriate, ATC directs the generating interconnection customer to work with MISO in any
appropriate Attachment X process.51
• Removal of definitions and references to obsolete definitions, practices and procedures.52
2. Miscellaneous Clean-Up Edits
ATC proposes several miscellaneous clean-up edits to Attachment FF-ATCLLC
throughout. Any edits not specifically mentioned in this letter are not substantive, eliminate outdated or confusing language, and/or correct grammatical or formatting errors. For example, ATC updates reference to its public website, certain outdated citations and definitions, adds certain definitions to increase clarity, updates references to other entities, organizations, and terminology, among other miscellaneous corrections. Each edit is shown in redline in the enclosed Redline Tariff Sheets.
51 Redline Tariff Sheets, Attachment FF-ATCLLC § IV (adding the definition of Generating Facilities Modification Notification Process).52 Id. (removing outdated definitions associated with the generator interconnection process).
PDF page 19
August 17, 2026Page 19
III. Information Required Under 18 C.F.R. § 35.13
A. Proposed Effective Date and Waiver
ATC respectfully requests that the Commission accept the proposed revisions to Attachment FF-ATCLLC as of October 17, 2026, 60 days from the date of filing. During this time, ATC shall prepare and update necessary components of its Business Practices, ATCLLC Local Planning Criteria, public website, and other external information to align with the updated Attachment FF-ATCLLC language described herein. ATC shall include in its Load Interconnection Business Practice a detailed table mapping a large load interconnection requirements described in Attachment FF-ATCLLC and where an interested stakeholder can find all applicable requirements, processes, and procedures.
To the extent necessary, ATC respectfully requests waiver of any applicable requirement of Part 35 not addressed herein.
B. Correspondence and Service
Correspondence and service regarding this filing should be sent to the following individuals, who should be placed on the official service list in this proceeding53: Christopher D. Supino*
Managing Senior Corporate Counsel
Michael Kessler*
Managing Assistant General Counsel
Midcontinent Independent System
Operator, Inc.
720 City Center Drive
Carmel, Indiana 46032
Telephone: (317) 249-5400
csupino@misoenergy.org
mkessler@misoenergy.org
James C. Holsclaw*
Calfee, Halter & Griswold LLP
3900 Salesforce Tower
111 Monument Circle
Indianapolis, Indiana 46204
Telephone: (317) 308-4266
jholsclaw@calfee.com
Stephanie Neitzel*
Senior Counsel
American Transmission Company
W234 N2000 Ridgeview Pkwy. Ct.
Waukesha, WI 53188-1022
(262) 506-6170
sneitzel@atcllc.com
Linda Walsh*
Husch Blackwell LLP
1801 Pennsylvania Ave NW Suite 1000
Washington, DC 20006
(202) 378-2308
Linda.Walsh@huschblackwell.com
*Persons authorized to receive service.
53 To the extent necessary, ATC respectfully request a waiver of Rule 203(b)(3) of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.203(b), to permit all of the persons listed to be placed on the official service list for this proceeding.
PDF page 20
August 17, 2026Page 20
C. Service
MISO notes that it has served a copy of this filing electronically, including attachments, upon all Tariff Customers under the Tariff, MISO Members, Member representatives of Transmission Owners and Non-Transmission Owners, as well as all state commissions within the Region. The filing has been posted electronically on MISO’s website at
https://www.misoenergy.org/legal/ferc-filings/ for other interested parties in this matter. In addition, MISO has served a copy of this filing electronically on all parties to this agreement.
D. Documents Submitted with This Filing
In accordance with the Commission’s regulations, MISO submits this transmittal letter and:
Tab A – Redline Attachment FF-ATCLLC Tariff Sheets; and,
Tab B – Clean Attachment FF-ATCLLC Tariff Sheets.
IV. Conclusion
WHEREFORE, MISO on behalf of ATC, respectfully requests that the Commission accept the proposed modifications to Attachment FF-ATCLLC attached hereto for filing with the effective date of October 17, 2026.
Respectfully submitted,
/s/ Stephanie Neitzel
Stephanie Neitzel
Senior Counsel
ATC Management Inc. corporate manager of
American Transmission Company LLC