ER26-3531-000 · 2026-08-17 · Midcontinent Independent System Operator, Inc., American Transmission Company LLC

2026-08-17_Revisions to Attachment FF-ATCLLC re: Show Cause Order

Text extracted from the eLibrary original (SHA-256 ec2836d68aebaf23…). Download the original from the official source.

Contents · 16 sections
  1. I. Background p. 2
  2. B. ATC’s Planning Functions and Attachment FF-ATCLLC p. 2
  3. C. ATC’s Distribution – Transmission Interconnection Process p. 3
  4. D. ATC’s Development of Large Load Studies and Requirements p. 4
  5. II. Discussion p. 5
  6. A. Interconnection Process for Large Loads p. 6
  7. B. Large Load Definition and Operational Requirements p. 11
  8. C. Service Agreement p. 13
  9. D. Cost Shifting p. 14
  10. E. Miscellaneous Updates p. 18
  11. III. Information Required Under 18 C.F.R. § 35.13 p. 19
  12. A. Proposed Effective Date and Waiver p. 19
  13. B. Correspondence and Service p. 19
  14. C. Service p. 20
  15. D. Documents Submitted with This Filing p. 20
  16. IV. Conclusion p. 20

Read topic-matched comments in ER26-3531

Topics in the text: Cost allocation · Filing procedure · Retail and wholesale authority

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

BOX 47 ▪ WAUKESHA, WI 53187-0047 ▪ Phone: 262-506-6830 ▪ Fax: 262-506-6710 STREET ADDRESS: W234 N2000 RIDGEVIEW PARKWAY COURT ▪ WAUKESHA, WI 53188-1022 Legal Department Direct Line: (262) 506-6170 E-Mail: sneitzel@atcllc.com August 17, 2026 The Honorable Debbie-Anne A.
Read this passage

I. Background

printed heading

ATC ATC is a Wisconsin limited liability company created as a single-purpose, for-profit transmission company.7 ATC began operations under the terms of its own open access transmission tariff on January 1, 2001, and currently owns and operates over 10,000 miles of jurisdictional transmission…
Read this passage

B. ATC’s Planning Functions and Attachment FF-ATCLLC

printed heading · Topic match: Filing procedure

Pursuant to Wisconsin law,9 ATC is a transmission only company and not permitted to directly 6 See MISO’s Motion to Hold Proceeding in Abeyance, Docket No.
Read this passage Filed comments: Filing procedure

C. ATC’s Distribution – Transmission Interconnection Process

printed heading

ATC’s Distribution – Transmission Interconnection Process Attachment FF-ATCLLC sets forth ATC’s process for Distribution – Transmission Interconnections.
Read this passage

D. ATC’s Development of Large Load Studies and Requirements

printed heading · Topic match: Cost allocation

ATC determined that to safely and reliably interconnect large loads, more robust planning criteria requirements that apply specifically to these new, unique large loads must be developed and implemented.
Read this passage Filed comments: Cost allocation

II. Discussion

printed heading

Discussion ATC’s proposed revisions to Attachment FF-ATCLLC are just and reasonable.
Read this passage

A. Interconnection Process for Large Loads

printed heading

FERC Directive In the Show Cause Order, the Commission made a preliminary finding that the MISO Tariff appears to be unjust and unreasonable because it lacks an application process for Eligible Customers15 seeking transmission service on behalf of large loads.16 The Commission emphasized that…
Read this passage

B. Large Load Definition and Operational Requirements

printed heading · Topic match: Cost allocation

The 100 MW threshold shall serve as ATC’s initial threshold to classify loads to which certain requirements, procedures, and processes shall apply to address reliability, operational, and cost shifting concerns.
Read this passage Filed comments: Cost allocation

C. Service Agreement

printed heading

ATC respectfully submits that for use in ATC’s footprint, a pro forma transmission service agreement in the MISO Tariff is not necessary as ATC already employs its D-TIAs which serve the same function, as is currently reflected in Section IV: • Section IV states that any new distribution customer…
Read this passage

D. Cost Shifting

printed heading · Topic match: Cost allocation

ATC proposes to reference the LLPCA and MTCA, in Section VI.12.B of Attachment FF-ATCLLC as follows: • Including a provision stating that the Large Load Cost Allocation Business Practice applies exclusively to large loads. • Stating that ATC and distribution customer must enter into a Large Load…
Read this passage Filed comments: Cost allocation

E. Miscellaneous Updates

printed heading

Miscellaneous Clean-Up Edits ATC proposes several miscellaneous clean-up edits to Attachment FF-ATCLLC throughout.
Read this passage

III. Information Required Under 18 C.F.R. § 35.13

printed heading

III.
Read this passage

A. Proposed Effective Date and Waiver

printed heading

Proposed Effective Date and Waiver ATC respectfully requests that the Commission accept the proposed revisions to Attachment FF-ATCLLC as of October 17, 2026, 60 days from the date of filing.
Read this passage

B. Correspondence and Service

printed heading

Correspondence and Service Correspondence and service regarding this filing should be sent to the following individuals, who should be placed on the official service list in this proceeding53: Christopher D.
Read this passage

C. Service

printed heading

Service MISO notes that it has served a copy of this filing electronically, including attachments, upon all Tariff Customers under the Tariff, MISO Members, Member representatives of Transmission Owners and Non-Transmission Owners, as well as all state commissions within the Region.
Read this passage

D. Documents Submitted with This Filing

printed heading

Documents Submitted with This Filing In accordance with the Commission’s regulations, MISO submits this transmittal letter and: Tab A – Redline Attachment FF-ATCLLC Tariff Sheets; and, Tab B – Clean Attachment FF-ATCLLC Tariff Sheets.
Read this passage

IV. Conclusion

printed heading

Conclusion WHEREFORE, MISO on behalf of ATC, respectfully requests that the Commission accept the proposed modifications to Attachment FF-ATCLLC attached hereto for filing with the effective date of October 17, 2026.