ER26-3531: the filed comments

These passages match a topic and a request or argument in the same sentence. A filing can quote another party. Read its page before attributing a position.

Cost allocation

American Transmission Company LLC (ATC)

ER26-3531-000 · 2026-09-23

In light of the current development efforts and the PSCW actions to date, ATC determined that 100 MW would strike the right balance between state cost allocation determinations and maintaining system reliability in ATC’s footprint. PDF p. 7

Filing procedure

Midcontinent Independent System Operator Inc.

ER26-3531-000 · 2026-09-08

This issue appears to be a matter of timing resulting from the time lag between the issuance of the Show Cause Order, MISO’s request to hold those compliance directives in abeyance, ATC’s filing in this docket, and submission of MISO’s IRR Proposal. PDF p. 2