Motion for Leave to Answer and Answer of American Transmission Company LLC to the Comments and Protests filed by Midcontinent Independent System Operator,…
Text extracted from the eLibrary original (SHA-256 8df4a6d529fbdc08…). Download the original from the official source.
Contents · 11 sections
- I. SUMMARY OF ANSWER
- II. MOTION FOR LEAVE TO ANSWER
- III. ANSWER
- A. ATC’s Proposed Attachment FF-ATCLLC Revisions Address the Immediate
- B. Uniform Rules Across the MISO Region May Be Unjust and Unreasonable if
- C. ATC’s Proposed Modifications Will Address MISO’s Operational Concerns.
- D. ATC’s 100 MW Threshold for Cost Allocation is Driven By a State-
- E. Template LLPCAs and MTCAs Posted on ATC’s Website Provide
- F. ATC’s Proposed Changes are Consistent with Order No. 890 Principles.
- G. There are No Material Issues of Fact that Warrant Hearing and Settlement
- IV. CONCLUSION
Read topic-matched comments in ER26-3531
Topics in the text: Cost allocation · Connecting load and generation · Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Cost allocation
ER26-3531-000 MOTION FOR LEAVE TO ANSWER AND ANSWER OF AMERICAN TRANSMISSION COMPANY LLC Pursuant to Sections 212 and 213 of the Commission’s Rules of Practice and Procedure,1 American Transmission Company LLC by its corporate manager, ATC Management Inc. (collectively, ATC) hereby files this…Read this passage Filed comments: Cost allocation
I. SUMMARY OF ANSWER
printed heading · Topic match: Cost allocation
ATC studies load interconnection requests, determines what facilities are needed and then feeds the study results and proposed transmission facilities to MISO for evaluation in the regional planning process for inclusion in the MISO Transmission Expansion Plan (MTEP) through the regular annual…Read this passage Filed comments: Cost allocation
II. MOTION FOR LEAVE TO ANSWER
printed heading
MOTION FOR LEAVE TO ANSWER To the extent required, ATC respectfully requests leave to submit this Answer.Read this passage
III. ANSWER
printed heading
III.Read this passage
A. ATC’s Proposed Attachment FF-ATCLLC Revisions Address the Immediate
printed heading · Topic match: Cost allocation
ATC’s proposed revisions provide an immediately implementable path forward, consistent with ATC’s current practices, offering certainty for large-load projects already underway in ATC’s footprint and establishing urgently needed protections against cost shifting.Read this passage Filed comments: Cost allocation
B. Uniform Rules Across the MISO Region May Be Unjust and Unreasonable if
printed heading · Topic match: Cost allocation
In light of the current development efforts and the PSCW actions to date, ATC determined that 100 MW would strike the right balance between state cost allocation determinations and maintaining system reliability in ATC’s footprint.Read this passage Filed comments: Cost allocation
C. ATC’s Proposed Modifications Will Address MISO’s Operational Concerns.
printed heading
MISO asks the Commission to direct ATC to file revised tariff sheets that “adopt or integrate with” MISO’s large load rules and remove redundant processes.Read this passage
D. ATC’s 100 MW Threshold for Cost Allocation is Driven By a State-
printed heading · Topic match: Cost allocation
ATC proposes to maintain its 100 MW threshold for large loads for cost allocation purposes.Read this passage Filed comments: Cost allocation
E. Template LLPCAs and MTCAs Posted on ATC’s Website Provide
printed heading · Topic match: Cost allocation
ATC’s proposes to apply the 100 MW threshold for cost allocation purposes by requiring that all large loads interconnected to ATC’s system execute the LLPCA and MTCA agreements.15 These agreements deliver two layers of protection.Read this passage Filed comments: Cost allocation
F. ATC’s Proposed Changes are Consistent with Order No. 890 Principles.
printed heading · Topic match: Cost allocation
Because ATC is prohibited from providing transmission service directly to retail customers, the local planning process necessarily is focused on the needs of entities, such as LDCs, with distribution facilities connected to ATC’s system.18 ATC does not share information regarding interconnection…Read this passage Filed comments: Cost allocation
G. There are No Material Issues of Fact that Warrant Hearing and Settlement
printed heading · Topic match: Cost allocation
System Op., Inc., 153 FERC ¶ 61,248 at P 22 (2015). 16 ATC’s proposed approach for cost allocation with the MTCA follows the Transmission Security Agreement framework the Commission has already accepted in other proceedings without a hearing.30 Hearing and settlement proceedings would serve no…Read this passage Filed comments: Cost allocation
IV. CONCLUSION
printed heading
ATC respectfully requests that the Commission grant leave to answer, accept this Answer, deny the requests for hearing and settlement judge procedures, and accept the Amended LLPCAs and the MTCA as just and reasonable, effective October 17, 2026 (60 days from the date of filing).Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C. this 23rd day of September 2026. /s/ Emily Starobin Emily Starobin Husch Blackwell LLP 1801 Pennsylvania Ave.Read this passage