ER26-3531-000 · 2026-09-23 · American Transmission Company LLC (ATC)
Motion for Leave to Answer and Answer of American Transmission Company LLC to the Comments and Protests filed by Midcontinent Independent System Operator,…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
American Transmission Company LLC
Docket No. ER26-3531-000
MOTION FOR LEAVE TO ANSWER AND ANSWER OF
AMERICAN TRANSMISSION COMPANY LLC
Pursuant to Sections 212 and 213 of the Commission’s Rules of Practice and Procedure,1 American Transmission Company LLC by its corporate manager, ATC Management Inc. (collectively, ATC) hereby files this Motion for Leave to Answer and Answer to the Comments and Protests filed by the Midcontinent Independent System Operator, Inc. (MISO) and Microsoft Corporation (Microsoft).2 On August 17, 2026, ATC filed its proposed revisions to Attachment FF-ATCLLC of MISO’s Open Access Transmission, Energy and Operating Reserve Markets Tariff (Tariff) in response to the Commission’s Show Cause Order.3 In this Answer, ATC (1) proposes modifications to its Attachment FF-ATCLLC in response to MISO’s operational concerns, and (2) responds to other comments on ATC’s planning process, cost allocation and the proposed template large load agreements. ATC’s proposed revisions address the immediate need for large load integration in the ATC service territory and are just and reasonable and should be accepted by the Commission without hearing or settlement proceedings with an effective date of October 17, 2026.
1 18 C.F.R. § 385.212-213 (2026).2 Comments and Protest of the Midcontinent Independent System Operator, Inc. (MISO Protest) and Protest of Microsoft Corporation (Microsoft Protest).3 Midcontinent Indep. System Op., Inc., Order Instituting Proceeding Under Section 206 of the Federal Power Act, 195 FERC ¶ 61,212 (2026) (Show Cause Order).
PDF page 2
2
I. SUMMARY OF ANSWER
For nearly two decades, ATC has operated under its own local planning rules that are incorporated in the MISO Tariff. Among other things, Attachment FF-ATCLLC currently governs load interconnections to the ATC transmission system. ATC studies load interconnection requests, determines what facilities are needed and then feeds the study results and proposed transmission facilities to MISO for evaluation in the regional planning process for inclusion in the MISO Transmission Expansion Plan (MTEP) through the regular annual process or the Expedited Project Review (EPR) process. ATC’s Commission-approved local planning process has worked without issue since it was approved. ATC’s proposed revisions to Attachment FF- ATCLLC are intended to codify and reflect the processes that ATC follows today with respect to managing the challenges of large load interconnections and other revisions that reflect new, proposed practices to comply with the Show Cause Order.
Since the Commission approved ATC’s transmission planning process in Attachment FF- ATCLLC under Order No. 890, ATC has revised that process to comply with Order No. 1000 and other transmission planning-related reforms issued by the Commission – all of which complement MISO’s regional planning process. ATC’s proposed revisions in this docket are no different: they update the local planning process per the Commission’s direction. In ATC’s view, the Show Cause Order builds on the Commission’s previously approved local planning framework by requiring updates to meet the specified requirements.
ATC began receiving requests in 2023 from the Local Distribution Companies (LDCs) connected to its transmission system requesting studies for large load interconnections. ATC responded to concerns about cost allocation and transparency related to large loads by developing the processes reflected in the proposed revisions to Attachment FF-ATCLLC. As the
PDF page 3
3
Commission noted in the Show Cause Order, ATC’s Attachment FF-ATCLLC includes an approved distribution-to-transmission interconnection process and a load interconnection procedure, but it does not have procedures specific to large loads.4 ATC’s proposed revisions in this filing are intended to fill that gap and are tailored to work within the established Attachment FF-ATCLLC procedures. In sum, ATC’s proposal here is intended to formalize what ATC is already doing in its footprint to manage the challenges of large load integration and add new practices that build upon ATC’s long-standing local planning processes. Nevertheless, ATC recognizes MISO’s need for regional visibility into, and operational authority over, loads of 50 MW or more. As discussed below, ATC proposes targeted revisions to Attachment FF-ATCLLC to address MISO’s concerns and eliminate any perceived operational gaps. ATC will modify its Large Load definition threshold to 50 MW as follows:
• ATC’s large load criteria will apply within the ATC footprint. Large loads over 50 MW connecting to ATC’s system will be required to comply with MISO’s IRR requirements when they become effective if ATC does not have applicable criteria on a given topic.
• ATC will modify Attachment FF-ATCLLC and any related business practices to ensure that ATC’s large load planning and interconnection criteria will apply to all Large Loads over 50 MW.
• For Large Loads over 50 MW, ATC will distinguish between computational loads and other large loads for power factor and other requirements as deemed necessary by ATC. For cost allocation purposes, ATC will maintain the 100 MW threshold for application of ATC’s proposed Large Load Project Commitment Agreement (LLPCA) and Minimum
4 Show Cause Order at P 21, n. 75.
PDF page 4
4
Transmission Charge Agreement (MTCA). The 100 MW threshold is important for cost allocation purposes to coincide with the Public Service Commission of Wisconsin’s (PSCW) established 100 MW threshold for large load tariffs to avoid stranded costs to ATC’s interconnected LDCs. If ATC is required to lower its threshold to 50 MW for cost allocation purposes, LDCs with large load tariffs in ATC’s footprint will be unable to directly assign the large load upgrade costs to the particular large loads causing those costs to be incurred. As a result, any upgrade costs for large loads between 50 and 100 MW would be spread to the LDC’s other customers.
If these modifications are acceptable, ATC requests that the Commission issue an order accepting the Attachment FF-ATCLLC filing on the condition that ATC submit a compliance filing implementing the proposed changes above within 30 days.
The remainder of ATC’s Attachment FF-ATCLLC revisions should be accepted as just and reasonable. ATC’s template large load agreements (LLPCAs and MTCAs) will be posted on ATC’s website. While ATC is not requesting approval of these template agreements as pro forma agreements, they nevertheless provide consistency and allow flexibility for large load customers. As mentioned previously, Attachment FF-ATCLLC was developed and approved in a series of planning orders, as meeting Order 890’s5 transmission planning process and Order 1000’s requirements.6 ATC’s proposed changes are consistent with Order No. 890 principles. Finally, there are no material issues of fact that warrant hearing and settlement procedures
5 Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890, FERC Stats. & Regs. ¶ 31,241, order on reh’g, Order No. 890-A, FERC Stats. & Regs. ¶ 31,261 (2007), order on reh’g, Order No. 890-B, 123 FERC ¶ 61,299 (2008), order on reh’g, Order No. 890-C, 126 FERC ¶ 61,228 (2009), order on clarification, Order No. 890-D, 129 FERC ¶ 61,126 (2009).
6 Midwest Indep. Transmission Sys. Operator, Inc., 147 FERC ¶ 61,127 at P 76 (2014) (Order 1000 Compliance Rehearing Order); Midwest Indep. Transmission Sys. Operator, Inc., 130 FERC ¶ 61,232, at
PDF page 5
5
II. MOTION FOR LEAVE TO ANSWER
To the extent required, ATC respectfully requests leave to submit this Answer. The Commission’s Rules of Practice and Procedure prohibit answers to protests unless otherwise authorized.7 The Commission regularly allows answers for good cause shown, such as when the answers help ensure a more accurate and complete record, clarify the issues, or provide useful and relevant information that will assist the Commission in its deliberative process.8 ATC’s Answer will clarify the record and ensure a more accurate and complete record. Because this information will assist the Commission in its decision-making, ATC respectfully requests that the Commission accept this Answer for good cause shown.
III. ANSWER
A. ATC’s Proposed Attachment FF-ATCLLC Revisions Address the Immediate
Need for Large Load Integration in ATC’s Footprint.
ATC appreciates the potential complexity caused by the misalignment in the Show Cause Order compliance schedules of ATC and MISO. MISO’s compliance processes are working their way through the stakeholder process. Once filed, MISO’s proposed compliance filing could take many months to finalize with follow-up compliance filings and potential challenges. Given that transmission owners in the MISO Region have their own local planning process (even though they are not included in the MISO Tariff), existing practices may vary greatly across the region.
P 36, on reh’g, 132 FERC ¶ 61,119, PP 20-22 (2010); Midwest Indep. Transmission Sys. Operator, Inc., 123 FERC ¶ 61,165 (2008), order on reh’g, 127 FERC ¶ 61,169 (2009).
7 18 C.F.R. § 385.213(a)(2).8 See, e.g., Midcontinent Indep. Sys. Operator, Inc., 191 FERC ¶ 61,131 at P 24 (2025) (accepting answers to answers “because they have provided information that assisted us in our decision-making process”); Texas Eastern Transmission, LP, 122 FERC ¶ 61,205 at P 8 (2008) (accepting answer that completed the record); California Indep. Operator Corp., 105 FERC ¶ 61,284 at P 10 (2003) (accepting ISO’s answer that clarified the issues).
PDF page 6
6
Thus, any consensus proposal that MISO develops may necessarily be at a high level, with room for individual variation. It could be well into 2027 before any MISO-wide large load rules are in effect. ATC’s proposed revisions provide an immediately implementable path forward, consistent with ATC’s current practices, offering certainty for large-load projects already underway in ATC’s footprint and establishing urgently needed protections against cost shifting. ATC has already committed to adjusting its processes, if necessary, through its Business Practices or otherwise, as MISO’s requirements develop through the stakeholder process. MISO suggests that ATC should defer its proposal because it may conflict with MISO’s future compliance filing. ATC is participating in the stakeholder process for developing MISO’s region-wide Show Cause Order compliance filing and intends that ATC’s processes will continue to work with MISO’s planning processes similar to how ATC’s Attachment FF-ATCLLC works with MISO’s Attachment FF today. A direct conflict is even less likely after the changes ATC is proposing in Section C, below. However, if a direct conflict arises, ATC will work with MISO to resolve it. Implementing ATC’s revisions on October 17, 2026 will provide timely clarity and certainty while advancing changes that are independently just and reasonable and responsive to the Show Cause Order.
B. Uniform Rules Across the MISO Region May Be Unjust and Unreasonable if
They Impose Unnecessary Burdens or Conflict with State Requirements.
Consistent with Wisconsin state law, local planning is a core function of ATC’s operations. ATC’s own robust local planning process has worked collaboratively within MISO’s regional planning umbrella for nearly two decades. Nothing in ATC’s proposed changes to Attachment FF-ATCLLC is intended to change that collaborative framework. For nearly three years, ATC’s studies and reliability analyses have determined that the appropriate threshold for categorizing large loads in ATC’s footprint should be 200 MW. That threshold has thus far not
PDF page 7
7
resulted in any reliability or instability issues to date. In light of the current development efforts and the PSCW actions to date, ATC determined that 100 MW would strike the right balance between state cost allocation determinations and maintaining system reliability in ATC’s footprint.
A single set of uniform rules for the entire MISO region9 will necessarily have to reflect a broadly applicable regional baseline, which could impose unduly burdensome requirements in ATC’s footprint. Each new large load presents its own unique characteristics, and ATC’s system is uniquely situated among the Great Lakes and the Mississippi River. Load interconnections are dynamic and reliability issues can be highly technical; a one-size-fits-all approach can result in unnecessarily onerous requirements and costly equipment specifications. ATC has confronted the challenges posed by large loads, studied them, and developed workable, proven requirements. ATC engaged specialized power system consultants to study large loads, including flicker analyses, rotor-swing modes, generator-shaft studies to develop ramp-rate, oscillation, and voltage-ride-through requirements. The Commission should give due weight to ATC’s preparedness and should not disadvantage ATC for advancing proven large load processes developed over the past several years and submitting them within the Show Cause Order’s original timeframe.
ATC disagrees with MISO’s assertion that ATC’s large load processes would produce “unjust and unexpected outcomes” for large loads. Rather, requiring ATC to alter its existing practices – particularly for large load projects already underway in its footprint – would itself produce an unjust result. This does not mean that ATC’s processes will remain static. ATC has continually reassessed them and will continue to do so in light of MISO’s forthcoming
9 MISO Protest at 6.
PDF page 8
8
compliance filing and the new NERC Reliability Standards under development. No reliability gaps will arise because the NERC Reliability Standards will soon apply to all large loads, including those in ATC’s footprint.
C. ATC’s Proposed Modifications Will Address MISO’s Operational Concerns. MISO suggests there will be practical implementation problems if it is unclear how ATC's separate application, study, and agreement processes would interface with MISO's own transmission service and Large Load Section 205 filings currently in development. MISO asks the Commission to direct ATC to file revised tariff sheets that “adopt or integrate with” MISO’s large load rules and remove redundant processes.
ATC recognizes MISO’s concerns and agrees to modify its Attachment FF-ATCLLC proposal in certain respects to eliminate any perceived operational gaps that could arise for loads between 50 and 100 MW. ATC will agree to modify its Large Load definition threshold to 50 MW for certain operational processes as follows:
• ATC’s large load criteria will apply within the ATC footprint. Large loads over 50 MW connecting to ATC’s system will be required to comply with MISO’s IRR requirements when they become effective if ATC does not have applicable criteria on a given topic.
• ATC will modify Attachment FF-ATCLLC and any related business practices to ensure that ATC’s large load planning and interconnection criteria will apply to all Large Loads over 50 MW. As described above and in the filing letter, ATC’s planning and interconnection criteria is study-based and tailored to ATC’s footprint.10 MISO’s
10 Transmittal Letter at 4.
PDF page 9
9
proposed 50 MW threshold is based on the threshold suggested in the Show Cause Order and is not based on studies specific to the MISO region.
• For Large Loads over 50 MW, ATC will distinguish between computational loads and other large loads for power factor and other requirements as deemed necessary by ATC.
If the Commission accepts these modifications, ATC requests that the Commission issue an order accepting the Attachment FF-ATCLLC filing on the condition that ATC submit a compliance filing with revised tariff sheets implementing the proposed changes above within 30 days.
ATC’s proposed revisions to Attachment FF-ATCLLC describe processes that are designed to work together with MISO’s process in the same way ATC’s local planning process in Attachment FF-ATCLLC works with the annual MTEP process today. ATC’s application process and studies of all distribution interconnections, including large load interconnections, contemplates close coordination with MISO. ATC works closely with MISO to provide it with all necessary information so that the interconnection can be integrated into the annual MTEP, which may include on an as needed basis, review and approval on an expedited timeline through MISO’s EPR process. Moreover, NERC’s new large load Reliability Standards will soon be applicable to all large loads, including those in ATC’s footprint. Upon Commission acceptance of these changes to Attachment FF-ATCLLC, ATC will continue to coordinate with MISO to ensure all projects interconnecting to ATC’s system are included in MTEP either through the standard planning process or the EPR process.1111 Attachment FF-ATCLLC at VI.C.10 (“Inclusion in the MTEP. ATCLLC shall, consistent with Appendix B of the ISO Agreement and in accordance with the provisions of the Attachment FF of this Tariff, upon completion of the analysis of any proposed Transmission Facilities project, or upon the
PDF page 10
10
D. ATC’s 100 MW Threshold for Cost Allocation is Driven By a State-
Determined Threshold and Should Be Accepted.
ATC proposes to maintain its 100 MW threshold for large loads for cost allocation purposes. ATC’s threshold aligns with the PSCW's determination in separate retail proceedings that 100 MW is the appropriate threshold for large load cost-shifting protections at the retail level.12 The PSCW made a finding of fact that it would be reasonable to make the large load tariffs mandatory for all customers with an aggregate load forecast of 100 MW and therefore ordered the large load tariff mandatory for all customers with an aggregated load forecast of over 100 MW.13 If ATC is required to implement a 50 MW threshold for cost allocation purposes, there will be a cost allocation gap at the state level. LDCs with those large load tariffs in Wisconsin will be unable to directly assign costs to the large loads between 50 and 100 MW that cause the network upgrade costs to be incurred.14 Thus, network upgrade costs regarding loads between 50 and 100 MW will be spread to the LDC’s other customers.
completion of the evaluation of its network adequacy, identify to the Transmission Provider those provisional, proposed or planned projects that ATCLLC, in its judgment, has determined should be constructed to meet the needs of its Interconnection Customers and Transmission Customers in order to fulfill ATCLLC’s obligation to provide interconnection service and open access transmission service for the benefit of all users of its Transmission Facilities.”).
12 See infra, n. 14, 15.13 See Public Service Commission of Wisconsin Order Docket 6630-TE-113 Final Decision (PSC REF# 591873) (“PSCW Retail Tariff Order on Very Large Customer and Bespoke Resource Tariff"). Id., Finding of Fact 3, Order Point 5; see also Public Service Commission of Wisconsin Order Docket 6680- TE-115 Final Decision (PSC REF# 594678) (“PSCW Individual Contract Order"), Finding of Fact 3 (finding 100 MW to be the appropriate threshold to apply a new large load retail tariff).14 See Wisconsin Power and Light, Application for Approval of Large Load Power Service Tariff, Docket No. 6680-TE-119; Application of Madison Gas and Electric Company, Docket 3270-TE-124 (PSC REF#: 597709); see also Application of Northern State Power Company, Docket 4220-TE-119 (PSC REF#: 594842).
PDF page 11
11
E. Template LLPCAs and MTCAs Posted on ATC’s Website Provide
Consistency and Allow Flexibility.
ATC’s proposes to apply the 100 MW threshold for cost allocation purposes by requiring that all large loads interconnected to ATC’s system execute the LLPCA and MTCA agreements.15 These agreements deliver two layers of protection.
First, during construction, the Amended LLPCAs require LDCs to (1) backstop the cost of the required network upgrades in case the large load project is cancelled before it goes into service and (2) pay the carrying costs for Construction Work in Progress (CWIP) that ATC would otherwise recover from all of its transmission customers through its Attachment O formula rate. These mechanisms protect against other ATC customers paying for stranded costs if the large load projects are canceled before entering service.
Once the facilities are placed into service, the MTCA requires LDCs to pay a minimum contribution to ATC’s transmission revenue requirement based on the amount of transmission capacity that the LDC requested to serve the large load. ATC proposes to roll-in the capital costs of the network upgrades for large loads rather than directly assign them to LDCs. The MTCA with its minimum transmission contribution will ensure the large load project costs are not unreasonably shifted to other transmission customers in the event the large load does not materialize to the extent requested. Moreover, the total charges incurred under the MTCA will be limited to the incremental revenue requirement of the required network upgrades so that the LDC does not overpay under the agreement. ATC’s proposed approach generally follows the
15 ATC recently filed executed LLPCAs and an MTCA with Wisconsin Electric Power Company in Docket No. ER26-3265, which is pending a Commission order.
PDF page 12
12
Transmission Security Agreement framework the Commission has already accepted in other proceedings without a hearing.16
ATC has a series of template agreements that will assist with large load interconnections. First, ATC already employs standardized Distribution-Transmission Interconnection agreements (D-TIAs) that are posted publicly and filed with the Commission when executed, serving the same transparency function. In addition, proposed section VI.12.B of Attachment FF-ATCLLC requires that LLPCA and MTCA templates17 be posted on ATC's public website and filed with FERC for acceptance upon execution. These template agreements achieve comparable transparency and consistency to a pro forma agreement without foreclosing project-specific adjustments that may be needed given the individualized nature of large load projects. Any unreasonable variations in these agreements can be brought to the Commission’s attention via the filing of an unexecuted agreement.
F. ATC’s Proposed Changes are Consistent with Order No. 890 Principles.
ATC is the only transmission owner in MISO that codifies its local planning process in the MISO Tariff and has received specific findings that those local processes are compliant with Orders Nos. 890 and 2000. ATC’s planning processes are structured to include all interested parties and treat all similarly situated interconnected customers the same. ATC's planning process is open, collaborative, and stakeholder driven.
16 See e.g., PECO Energy Co., 195 FERC ¶ 61,074 (2026); Commonwealth Edison Co., 194 FERC ¶ 61,183 (2026); see also Show Cause Order at P 83.17 The LLPCA protects transmission customers from the financing costs of construction and other costs arising if a large load project is canceled before completion. The MTCA, with its Minimum Transmission Charge, protects other transmission customers after the project is placed into service in the event the full amount of the requested load does not materialize. Combined, the agreements protect other transmission customers from unjust and unreasonable cost shifts that could occur if the large load fails to materialize.
PDF page 13
13
However, under Wisconsin law ATC's direct contractual and Tariff relationship is with LDCs, not end-use retail customers. Because ATC is prohibited from providing transmission service directly to retail customers, the local planning process necessarily is focused on the needs of entities, such as LDCs, with distribution facilities connected to ATC’s system.18 ATC does not share information regarding interconnection requests from LDCs with third parties for confidentiality reasons, much like in the generator interconnection context. It is up to the LDC making an interconnection request to determine what information to share with its retail customer. ATC agrees with Microsoft’s contention that stakeholders should have the option to participate in the local planning process, such as to test and validate local transmission needs, explore solutions to challenges and support consideration of GETs.19 Given the confidentiality concerns mentioned above, such stakeholder participation does not occur in connection with a particular interconnection request, but otherwise stakeholders have an ability to participate. ATC’s network adequacy planning process is open to stakeholder engagement. As provided in Attachment FF-ATC, ATC conducts an annual Ten-Year Assessment (TYA) “of the need to modify, extend or construct new Transmission Facilities to provide, safe, reliable, Interconnection Service and transmission Service and to ensure that its Transmission Facilities are capable of providing and have the Physical Capacity and operating Capability to reliably provide adequate transmission Service to meet the needs of all uses of its Transmission Facilities
18 Attachment FF-ATCLLC at VI.A.1: “Any entity that owns or operates Distribution Facilities shall be entitled to make a request to modify any existing Distribution Interconnection or to propose a new Distribution Interconnection, including a Distribution Interconnection to support an ATCLLC Large Load.” Except for the underlined portion of that sentence, which is proposed in this filing, the concept of ATC planning for Distribution Facilities is already included in Attachment FF-ATCLLC. See also existing Section VI.A.2. “ATCLLC maintains a queue of Distribution Interconnection requests made by those entities owning Distribution Facilities that are interconnected to ATCLLC’s Transmission Facilities.” 19 Microsoft Protest at 4-5.
PDF page 14
14
and to fulfill all Public Policy Requirements.”20 For purposes of the TYA, each year ATC solicits information (by letter and by posting on its website) “from all Interconnection Customers, Transmission Customers and the owners of all Distribution Facilities that are interconnected to ATCLLC’s Transmission System, and other stakeholders, specifically including information related to Public Policy Requirements.”21 Following the information gathering and verification, ATC holds meetings with customers and stakeholders to discuss the assumptions and the models that will be used to perform the TYA.22
ATC agrees with Microsoft that large retail customers are important stakeholders in ATC’s transmission planning work.23 That is why as noted above, ATC’s planning process includes entities like Microsoft and has been approved by the Commission as compliant with Order No. 890.24 Microsoft even acknowledges that it “has been working collaboratively with ATC to interconnect and serve Microsoft’s large data center campus in Racine County, Wisconsin.”25
ATC disagrees with Microsoft’s assertion that the reforms give ATC unreasonable
discretion in the planning process.26 More than half of Microsoft’s cited examples that
20 Attachment FF-ATCLLC at VI.C.1.21 Id. at VI.C.2.22 Id. at VI.C.4 (“Any interconnection customer, Transmission Customer, owner of Distribution Facilities or Transmission Facilities, as well as any other stakeholder, including state regulators, local, state and federal governmental officials, and members of interested community organizations shall be entitled to participate in such meeting or meetings held to discuss assumptions and models, specifically including a discussion of ATCLLC’s decision to include in, or exclude from, its proposed models any transmission needs driven by Public Policy Requirements.”) (emphasis added).23 Microsoft Protest at 4. 24 Midwest Indep. Transmission Sys. Operator, Inc., 123 FERC ¶ 61,165 at P 15 (2008) (Order on ATC’s Order No. 890 compliance filing, stating that [w]e find that American Transmission Company’s Attachment FF-ATCLLC provides an opportunity for all affected parties to participate in the transmission planning process.”), order on reh’g, 127 FERC ¶ 61,169 (2009).25 Microsoft Protest at 4.26 Id. at 7.
PDF page 15
15
purportedly give ATC broad discretion are provisions that were previously approved and are not proposed to be changed.27 The changes proposed in Section V.F. are designed to allow criteria to be updated at ATC's discretion in response to new conditions, safety concerns, operational issues, customer requests, and regulatory developments — same as it works today. The discretion built into these processes reflects existing, longstanding business practices rather than new or expanded authority. The planning processes have been developed collaboratively with stakeholder input over time and are intended to preserve existing commercial arrangements and in-flight projects rather than introduce new inconsistency.
G. There are No Material Issues of Fact that Warrant Hearing and Settlement
Procedures.
The Commission has discretion to direct an evidentiary hearing where there are genuine issues of material fact that cannot be resolved on the written record.28 Although protests routinely identify disagreements in Section 205 proceedings, it is well established that “mere conjecture does not create a genuine issue of material fact warranting a hearing.” 29 Any factual dispute presented here—although none appears to exist—can be resolved on the written record.
ATC has already agreed to modify the large load threshold regarding the operational issues that MISO identified. ATC has also agreed to continue working with MISO to ensure that its planning process works seamlessly with MISO’s processes as it does today. In addition,
27 Id. at 7-9.28 Southwest Power Pool, Inc. 195 FERC ¶ 61,134 at P 53 (2026), citing Cajun Elec. Power Co-op., Inc.
v. FERC, 28 F.3d 173, 177 (D.C. Cir. 1994) (“Mere allegations of disputed fact are insufficient to mandate a hearing—a petitioner must make an adequate evidentiary proffer to support the existence of such disputes.”).
29 Interstate Power & Light Co., 127 FERC 61,043 at P 44, n. 49 (2009) (finding that a protestor has a burden to do more than make mere unsubstantiated allegations to warrant a hearing); Tenneco Oil Co. 25 FERC ¶ 61,234 (1983); Tilden Mining Co. L.C., v. Midcontinent Indep. System Op., Inc., 153 FERC ¶ 61,248 at P 22 (2015).
PDF page 16
16
ATC’s proposed approach for cost allocation with the MTCA follows the Transmission Security Agreement framework the Commission has already accepted in other proceedings without a hearing.30 Hearing and settlement proceedings would serve no apparent purpose other than potentially preventing proper cost allocation that protects other ratepayers from paying for upgrades to ATC’s system caused by new large loads.
IV. CONCLUSION
For the foregoing reasons, ATC’s proposed revisions to Attachment FF-ATCLLC are just and reasonable and will provide greater clarity and transparency for the immediate and reliable interconnection of large loads in ATC’s footprint. ATC respectfully requests that the Commission grant leave to answer, accept this Answer, deny the requests for hearing and settlement judge procedures, and accept the Amended LLPCAs and the MTCA as just and reasonable, effective October 17, 2026 (60 days from the date of filing). Respectfully submitted,
/s/ Linda Walsh
Ellen Nowak, Vice President, State
Linda Walsh
and Federal Affairs
Husch Blackwell LLP
Stephanie Nietzel, Senior Counsel
1801 Pennsylvania Ave., NW
ATC Management Inc., corporate manager of
Suite 1000
American Transmission Company LLC
Washington, DC 20006
P.O. Box 47
Tel: (202) 378-2308
Waukesha WI 53187-0047
linda.walsh@huschblackwell.com
Tel: (262) 506-6170
sneitzel@atcllc.com
Dated: September 23, 2026
30 See e.g., PECO Energy Co., 195 FERC 61,074 (2026); Commonwealth Edison Co., 194 FERC 1,183 (2026); see also Show Cause Order at P 83.
PDF page 17
17
CERTIFICATE OF SERVICE
Pursuant to Rule 2010 of the Federal Energy Regulatory Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010, I certify that I served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, D.C. this 23rd day of September 2026.
/s/ Emily Starobin
Emily Starobin
Husch Blackwell LLP
1801 Pennsylvania Ave. NW, Suite 1000
Washington, D.C. 20006
Tel: (202) 378-5784
emily.starobin@huschblackwell.com