Comments and Protest of Midcontinent Independent System Operator Inc. in response to American Transmission Company LLC’s tariff filing
Text extracted from the eLibrary original (SHA-256 3a3f1a71e476fb80…). Download the original from the official source.
Contents · 8 sections
- I. BACKGROUND
- II. COMMENTS AND PROTEST
- A. ATC’s Proposal Is Contrary to its Stated Goal of Complementing MISO’s
- B. ATC’s Proposal Is Impractical Because It Would Require ATC to Integrate
- C. Granting This Protest Is Consistent with ATC’s Stated Intent.
- III. COMMUNICATIONS
- IV. NOTICE AND SERVICE
- V. CONCLUSION
Read topic-matched comments in ER26-3531
Topics in the text: Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
MISO appreciates the steps taken by ATC to expeditiously address the mandates of the Commission’s Order Instituting Proceeding Under Section 206 of the Federal Power Act (“Show Cause Order”).2 MISO submits these comments and protest because ATC proposes Tariff changes related to the interconnection…Read this passage
I. BACKGROUND
printed heading · Topic match: Filing procedure
MISO believes this outcome was unintentional; after all, ATC’s filing states that ATC’s proposal is intended to be “complementary to MISO’s future filings” and to “work together with MISO’s process ….”12 The ATC proposal, however, asks the Commission to act on separate a 6 Id. at P 3. 7 Id. 8…Read this passage Filed comments: Filing procedure
II. COMMENTS AND PROTEST
printed heading
II.Read this passage
A. ATC’s Proposal Is Contrary to its Stated Goal of Complementing MISO’s
printed heading · Topic match: Filing procedure
If the large load connects to the Transmission System through distribution facilities, including those built to support a large load, then ATC further proposes that its own cost allocation, study processes, readiness requirements, and forms of agreement will govern and that the requests for such…Read this passage Filed comments: Filing procedure
B. ATC’s Proposal Is Impractical Because It Would Require ATC to Integrate
printed heading
Because ATC proposes to supersede MISO’s requirements, even a 100+ MW Large load connected through ATC transmission facilities would still be excused from MISO’s requirements, including the requirement to provide data to MISO in real time.21 If the ATC Large Load definition is accepted, neither…Read this passage
C. Granting This Protest Is Consistent with ATC’s Stated Intent.
printed heading
ATC states that ATC’s proposal is intended to be “complementary to MISO’s future filings” and “designed to work together with MISO’s process in the same way ATC’s local planning process in Attachment FF-ATCLLC works with the annual MISO Transmission Expansion Plan (“MTEP”) process today.”27 ATC’s…Read this passage
III. COMMUNICATIONS
printed heading
COMMUNICATIONS MISO requests waiver of Rule 203(b)(3)29 of the Commission’s Rules of Practice and Procedure to the extent necessary to permit the designation of more than two persons for service on behalf of MISO in this proceeding and requests all communications related to this filing be directed…Read this passage
IV. NOTICE AND SERVICE
printed heading
NOTICE AND SERVICE MISO has served a copy of this filing electronically, including attachments, upon each person designated on the official service list compiled by the Secretary as well as on all Tariff customers, MISO Members, Member representatives of transmission owners and non- transmission…Read this passage
V. CONCLUSION
printed heading
CONCLUSION WHEREFORE, MISO respectfully requests that the Commission direct ATC to revise Attachment FF-ATCLLC either to: (1) require ATC to submit revised Tariff sheets that adopt or integrate with MISO’s large load rules and procedures, remove redundant processes, and explicitly provide that any…Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated this 8th day of September 2026, in Carmel, Indiana. /s/ Julie Bunn Julie Bunn Midcontinent Independent System Operator, Inc. 720 City Center Drive Carmel, IN 46032 317-249-5400Read this passage