ER26-3531-000 · 2026-09-08 · Midcontinent Independent System Operator Inc.

Comments and Protest of Midcontinent Independent System Operator Inc. in response to American Transmission Company LLC’s tariff filing

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

American Transmission Company, LLC
)
)
)

Docket No. ER26-3531-000
COMMENTS AND PROTEST OF THE
MIDCONTINENT INDEPENDENT SYSTEM OPERATOR, INC.

The Midcontinent Independent System Operator, Inc. (“MISO”) submits1 these comments and protest in response to the proposed revisions to Attachment FF-ATCLLC of MISO’s Open Access Transmission, Energy, and Operating Reserve Markets Tariff (“Tariff”) filed by MISO as the Transmission Provider on behalf of American Transmission Company, LLC, by its corporate manager, ATC Management Inc. (collectively, “ATC”).  MISO appreciates the steps taken by ATC to expeditiously address the mandates of the Commission’s Order Instituting Proceeding Under Section 206 of the Federal Power Act (“Show Cause Order”).2  MISO submits these comments and protest because ATC proposes Tariff changes related to the interconnection and operation of large loads in the ATC footprint that conflict with MISO’s pending Interconnection Reliability Requirements for Large Loads proposal (“IRR Proposal”).3  While MISO appreciates that the sequence and timing of MISO and ATC’s filings may be the underlying cause of the differences in ATC’s proposal and MISO’s IRR Proposal, MISO is concerned that ATC’s proposal, if accepted, would establish a separate large load framework rather than complementing

1 This submission is made pursuant to Rules 211 and 212 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”), 18 C.F.R. §§ 385.211 and 385.212 (2026).
2 Midcontinent Indep. System Op., Inc., 195 FERC ¶ 61,212 (2026) (“Show Cause Order”).
3 Ltr. To the Hon. Debbie-Anne Reese regarding the Midcontinent Independent System Operator, Inc.’s Interconnection Reliability Requirements for Large Loads, Docket No. ER26-3600 (Aug. 28, 2026).

PDF page 2

2
a common MISO regional baseline consistent with ATC’s stated intent in its filing.4  Accordingly, MISO respectfully requests that the Commission direct ATC to revise Attachment FF-ATCLLC either to: (1) require ATC to submit revised Tariff sheets that adopt or integrate with MISO’s large load rules and procedures, remove redundant processes, and explicitly provide that any requirements imposed by Attachment FF-ATCLLC or ATC’s business practices on ATC Large Load are additional to those applicable to Large Load under the MISO Tariff and that, in the event of a conflict, the more restrictive rule governs; or (2) reject ATC’s proposal as unjust, unreasonable, and unduly discriminatory for large loads taking Transmission Service under the MISO Tariff.

I. BACKGROUND
MISO submits these comments and protest to resolve the mismatch in large load definitions and rules between MISO’s IRR Proposal and ATC’s proposed Tariff revisions.  This mismatch involves conflicting thresholds between the 100 MW large load threshold in ATC’s proposed Tariff revisions and the 50 MW large load threshold in MISO’s pending IRR Proposal, separate study processes, and related downstream impacts.  This issue appears to be a matter of timing resulting from the time lag between the issuance of the Show Cause Order, MISO’s request to hold those compliance directives in abeyance, ATC’s filing in this docket, and submission of MISO’s IRR Proposal.

The Commission issued the Show Cause Order on June 18, 2026.5  The Show Cause Order directed MISO and the Transmission Owners to either: (1) show cause as to why MISO’s Tariff

4 Ltr. To the Hon. Debbie-Anne Reese regarding the American Transmission Company LLC’s Proposed Revisions to Attachment FF-ATCLLC of the MISO Tariff in Response to Show Cause Order, Docket No. ER26-3531 (Aug. 28, 2026) at p. 2. 5 See Show Cause Order.

PDF page 3

3
remains just and reasonable without provisions addressing certain large load issues; or (2) explain what changes to the Tariff would address the Commission’s concerns, if the Commission were to determine that the Tariff has in fact become unjust and unreasonable.6  The Show Cause Order afforded MISO and the Transmission Owners 60 days to make their respective filing(s).7 On August 3, 2026, MISO moved to hold all proceedings related to the Show Cause Order in abeyance for 90 days.8  The Abeyance Motion explained that MISO and the MISO Transmission Owners required additional time to continue the stakeholder process and submit FPA section 2059 filings that address the concerns raised in the Show Cause Order.10  The Commission granted the 90-day abeyance requested in the Abeyance Motion on August 14, 2026.11  ATC filed its proposed Tariff revisions three days later, on August 17, 2026.  MISO, in turn, filed the IRR Proposal on August 28, 2026.

The mismatch in large load definitions and rules is understandable when viewed against this procedural backdrop.  At the time ATC filed its proposed Tariff revisions in this docket, the abeyance period had not expired, and MISO had yet to file its IRR Proposal and related large load threshold.  MISO believes this outcome was unintentional; after all, ATC’s filing states that ATC’s proposal is intended to be “complementary to MISO’s future filings” and to “work together with MISO’s process ….”12  The ATC proposal, however, asks the Commission to act on separate a

6 Id. at P 3.
7 Id.
8 Motion of the Midcontinent Independent System Operator, Inc. and the MISO Transmission Owners to Hold Proceeding in Abeyance and Request for Shortened Comment Period and Expedited Treatment, Docket No. EL26-70-000 (Aug. 3, 2026) (“Abeyance Motion”). 9 16 U.S.C. § 824d.
10  Abeyance Motion at 2. 11  Midcontinent Independent System Operator, Inc., et. al., 196 FERC ¶ 61,133 (August 14, 2026) (“Abeyance Order”). 12  ATC Transmittal Letter at p. 2.

PDF page 4

4
separate large load framework for ATC instead of supplementing a common MISO regional baseline.  This raises practical and other challenges, including potential reliability impacts.  The appropriate solution in this instance is for the Commission to direct ATC to revise Attachment FF- ATCLLC either to: (1) require ATC to submit revised Tariff sheets that adopt or integrate with MISO’s large load rules and procedures, remove redundant processes, and explicitly provide that any requirements imposed by Attachment FF-ATCLLC or ATC’s business practices on ATC Large Load are additional to those applicable to Large Load under the MISO Tariff and that, in the event of a conflict, the more restrictive rule governs; or (2) reject ATC’s proposal as unjust, unreasonable, and unduly discriminatory for large loads taking Transmission Service under the MISO Tariff.

II. COMMENTS AND PROTEST
A. ATC’s Proposal Is Contrary to its Stated Goal of Complementing MISO’s
Large Load Framework.

MISO appreciates that ATC’s goal is to provide a rule set that addresses concerns specific to large loads in the ATC footprint and that ATC intends for their proposal to complement MISO’s Large Load filings.  As ATC stated at the outset of its filing:

ATC’s filing here is intended to establish requirements in its
footprint and be complementary to MISO’s future filings. As
described below, ATC’s proposed revisions to Attachment FF-
ATCLLC describe processes that are designed to work together with
MISO’s process in the same way ATC’s local planning process in
Attachment
FF-ATCLLC
works
with
the
annual
MISO
Transmission Expansion Plan (“MTEP”) process today. ATC also
seeks approval for modifications to the local planning process that
is utilized today in ATC’s footprint.13

13  ATC Transmittal Letter, at p. 2.

PDF page 5

5
MISO supports ATC’s stated goal and has long acknowledged the importance of allowing its Transmission Owners to establish additional or supplemental requirements in its footprint that work together with MISO’s Tariff rules.  Unfortunately, ATC’s proposed Tariff revisions may frustrate this goal and lead to unjust or unexpected outcomes for Large Load connecting to the MISO Transmission System.  This is because ATC’s proposed Tariff revisions create a different process with requirements that supersede MISO’s Large Load and Computational Load definitions and baseline reliability requirements for loads in the ATC footprint.

Proposed Section V.F provides that “ATCLLC Local Planning Criteria and requirements established by ATCLLC’s Business Practices, as described herein, shall govern in ATCLLC’s footprint.”14  Taken together, these provisions create an entirely different rule set for large loads connecting to ATC’s transmission facilities—which are part of the MISO Transmission System and take Transmission Service pursuant to MISO’s Tariff—and purport to make the definitions, requirements, and studies that are or will be required by MISO’s Tariff for large loads inapplicable in the ATC footprint.  If the large load connects to the Transmission System through distribution facilities, including those built to support a large load, then ATC further proposes that its own cost allocation, study processes, readiness requirements, and forms of agreement will govern and that the requests for such interconnections will be processed by ATC rather than by MISO.15  Given

14  Proposed Revisions to Attachment FF-ATCLLC at Section V.F.  These include: (1) Steady State Criteria (including steady state voltage criteria); (2) Dynamic Stability Assessments; (3)  Resource Facility Requirements (including Voltage, Reactive Power, and Power Factor Control); (4) ATC Large Load Interconnection Requirements  (including Active Power Oscillations, Ramp Rate Limits, Voltage Ride Through, Load Power Factor)l and; (5) Large Load data monitoring, data retention, forecasting, and design criteria.  See, Proposed Revisions to Attachment FF-ATCLLC at Section V.E
15  Proposed Revisions to Attachment FF-ATCLLC at Sections VI.A.1-VI.A12. Because ATC proposes to include many details of its rules in its business practice manuals, there is also a risk that new conflicts between ATC’s and MISO’s rules could arise as the rule sets develop.

PDF page 6

6
the broad sweep of these proposed rules, it is unclear what parts of MISO’s Large Load rules will still apply in ATC’s footprint and how conflicting requirements can be reconciled.

MISO does not object to ATC developing supplemental rules and procedures needed to implement the rules contained in MISO’s Tariff in ATC’s footprint or to supplement MISO’s Tariff rules for Large Loads to the extent that ATC needs to impose additional reliability or operations requirements on ATC Large Load.  MISO welcomes ATC’s feedback on whether adjustments or additional flexibility is needed for individual requirements either included in the IRR Proposal or currently being developed in the Large Load Federal Power Act Section 205 filings described in MISO’s Abeyance Request.  However, MISO is concerned that even with ATC’s good intentions to develop complementary processes, the proposed Tariff language describes an entirely separate rule set and creates a high risk of discordant rates, terms, and conditions for Transmission Service under the MISO Tariff for ATC Large Loads as opposed to those connecting to other parts of the MISO Transmission System.16

B. ATC’s Proposal Is Impractical Because It Would Require ATC to Integrate
ATC-Specific Requirements with MISO’s Broader Process.

i. A uniform Large Load framework for the MISO Transmission
System is necessary to establish a common regional reliability
baseline.

MISO’s Large Load reliability framework submitted in the IRR Proposal includes
definitions, basic facility data, modeling, telemetry, forecasting, Phasor Measurement Unit (PMU),

16  A similar concern applies to ATC proposal to maintain its own study process—the Generating Facilities Modification Notification (“GFMN”) Process separate from MISO’s Interconnection Procedures. See, ATC Transmittal Letter at p. 18.  As defined in ATC’s Tariff sheets, this process covers “modifications, retirements, suspensions, testing results, model updates, or other changes associated with a generating facility.”  See, Proposed Revisions to Attachment FF-ATCLLC at Section IV (Definitions)—Generating Facility Modification Notification.  Unlike the Large Load provisions, ATC’s GFMN revisions do indicate that customers may also be subject to study processes under the Transmission Provider’s Tariff.  However, this still requires customers to undergo two separate study processes and it is not clear how conflicts would be resolved if ATC’s GFMN process reaches different conclusions regarding permissible changes or assigns different costs than those identified through MISO’s generating facility retirement, replacement, or material modification rules.

PDF page 7

7
ramp and ride-through requirements, as well as distinguishes Large Loads and Computational Loads with targeted requirements reflecting their specific reliability risks.  This is intended to provide a common regional reliability baseline and rule set that facilitates comparable treatment for Large Loads seeking to connect to all parts of the MISO Transmission System.  This uniformity both promotes fairness and will better expedite the development of large loads by promoting commercial certainty to Large Loads.

Permitting ATC to implement different large load thresholds and accompanying rules for large loads interconnecting within the ATC footprint versus those interconnecting in the rest of the MISO region will create confusion and divergent reliability requirements within the MISO region. Ultimately, accepting ATC’s proposal as filed would fragment the MISO region and create an unlevel playing field for similarly situated loads seeking to interconnect to the MISO Transmission System as ATC’s proposed revisions to Attachment FF-ATCLLC extend beyond establishing local planning criteria resulting in disparate operational and economic treatment of loads interconnected to the MISO Transmission System.  ATC would impose a lower burden on Computational Loads, which—together with the higher threshold for load classification as a large load, could result in those loads realizing lower compliance costs than Large Loads in the rest of the MISO region by avoiding reliability requirements.

ii. Granting ATC’s requested relief would create reliability
coverage gaps.

Large Loads could face a reliability coverage gap if ATC’s Large Load framework replaces, rather than supplements, MISO’s framework.  As noted, MISO defines Large Loads by applying a 50 MW threshold, whereas ATC Large Load applies a 100 MW threshold.  As such, Loads ranging from 50 MW to 100 MW in ATC’s footprint would be excluded from requirements applicable to comparable loads elsewhere in MISO.  This gap has significant  downstream impacts.

PDF page 8

8
MISO’s IRR Proposal explains that the 50 MW threshold defining Large Load is based on industry precedent and the need for a clear and administratively workable means of identifying significant, concentrated loads that warrant additional reliability visibility.17  A load of 50 MW is sufficiently large that its characteristics and behavior can be relevant to transmission planning and system operations.18  Because Large Loads above 50 MW increasingly exhibit dynamic operating characteristics and concentrated demand and utilize sophisticated power-electronic equipment and controls, additional facility information, telemetry, and modeling detail may be necessary to evaluate reliability impacts under both normal and contingency conditions.19  The data and modeling requirements in the IRR Proposal are intended to support reliable operation of the entire MISO Transmission System by improving the accuracy of planning assumptions, strengthening operational awareness, supporting disturbance analysis and model validation, and enabling more consistent evaluation of system performance associated with Large Load integration.20  As such, allowing ATC to apply the definition of ATC Large Load in the ATC footprint will have wide ranging impacts on reliability, system planning and operational awareness.

ATC’s proposed 100 MW Large Load threshold would exempt 50–99 MW facilities— including both traditional industrial loads and Computational Loads—from MISO’s day-ahead and real-time forecasting requirements.  These forecasts are essential inputs to MISO’s Reliability Assessment Commitment (RAC), Security Constrained Economic Dispatch (SCED), Look-Ahead Commitment (LAC), and real-time dispatch processes.

17  IRR Proposal, Testimony of B. Li, p. 12 (Aug. 28, 2026) (“Li Testimony”).
18  Id. at p. 14.
19  Id. at p. 24.
20  Id.

PDF page 9

9
If ATC’s threshold replaces MISO’s 50 MW baseline in ATC’s footprint, a 75 MW load would provide no Large Load forecast submissions.  Because this data is needed for real time processes, MISO needs the ability to require this information directly from the Large Load in real time in order to anticipate demand swings, commit generation reliably, maintain reserve sufficiency, and manage real time system balance.

MISO’s concern does not end at the 100 MW threshold.  Because ATC proposes to
supersede MISO’s requirements, even a 100+ MW Large load connected through ATC
transmission facilities would still be excused from MISO’s requirements, including the requirement to provide data to MISO in real time.21

If the ATC Large Load definition is accepted, neither MISO’s nor ATC’s requirements would apply to a 75 MW Computational Load.  This load source could fall outside MISO’s targeted the Phasor Measurement Unit / high-resolution measurement requirements.  If an oscillation occurs in the area with the 75 MW load, failure to apply large load data monitoring and communication rules would prevent MISO from performing the synchronized measurements needed to determine whether the load is the source, contributing to the oscillation, or responding to it.  This makes source identification and mitigation more difficult, impacting Transmission System reliability.

This problem is compounded for Computational Loads.  MISO applies targeted modeling and PMU requirements to Computational Loads to address their distinct dynamic and oscillatory risks.  ATC does not appear to establish an equivalent separate classification, potentially resulting

21  Many of MISO’s Large Load rules focus on facilitating real-time visibility into how large loads are operating in order to gauge system-wide effects and potential responses. Even if ATC is correct that 100 MW is an appropriate threshold for their facilities, the concern remains that their proposal would leave an ATC-shaped hole in MISO’s real-time view of Large Loads on the MISO Transmission System. ATC may ultimately require reporting from the large load to ATC.  But even good collaboration and data sharing between ATC and MISO cannot fully substitute for instantaneous communications directly between the large load and MISO’s systems.

PDF page 10

10
in different requirements for similar loads based on where they interconnect.  This disconnect imposes challenges because Computational Loads often exhibit highly coordinated, rapid demand swings and power-electronic dynamics that can impact the entire MISO Transmission System.22 If MISO cannot apply its Large Load data and visibility requirements and Computational Load classification to loads connecting through ATC transmission facilities, this would further inhibit MISO’s ability to anticipate demand swings, commit generation reliably, maintain reserve sufficiency, and manage real time system balance to account for loads whose impact shifts definitionally can be sudden and significant given their size.

ATC’s proposal raises broader reliability concerns that extend throughout the MISO region.  Load loss, ride-through/recovery, and oscillatory behavior do not remain confined within ATC’s footprint; they can affect frequency, voltage, nearby generation, and system stability across MISO.  ATC’s transmission facilities are part of the larger MISO Transmission System, and the electrical impacts of discordant rules cannot be limited to just ATC’s facilities.

iii. Implementing ATC’s Proposal would Create Gaps and
Misalignments with Downstream MISO Processes.

In addition to different definitions, thresholds, and recipients of large load data, ATC proposes to formalize certain business practices “containing policies, practices, and requirements directed specifically at large loads” that are identified on its website without a discussion of how

22  MISO’s IRR Proposal includes a definition of Computational Load to distinguish a subset of Large Loads that may exhibit operational characteristics different from more traditional loads, including rapid changes in demand, highly coordinated control behavior, and power-electronic responses during system disturbances.  This distinction allows MISO to apply certain incremental requirements—such as ramp, PMU, and ride-through requirements— only where those characteristics warrant additional reliability consideration to preserve reliable operations beyond the ATC footprint. Events involving ramp and ride-through requirements can impact the entire MISO Transmission System. Defining Computational Load therefore supports a more targeted and risk-informed approach, rather than applying the same requirements to all Large Loads regardless of facility type or operating behavior.  Li Testimony at p. 13.

PDF page 11

11
they will complement MISO’s business practices manuals.23  These include a form of application specific to large loads connecting to the MISO Transmission System through ATC transmission facilities, their own study procedures, and their own transmission service agreement. 24  Allowing these separate processes creates disconnects with other downstream processes that MISO is charged with implementing.

For example, MISO is charged with providing Transmission Service under a single Tariff.25 As the Commission acknowledged in the Show Cause Order, many of the rules and procedures needed to accommodate large loads will be made applicable through transmission service processes imposing obligations on an Eligible Customer taking service to provide energy to the large load.26  MISO currently is developing revisions to Tariff rules governing transmission service processes and products responsive to the Show Cause Order through its Large Load 205 filings. Leaving aside any fairness implications of granting the same transmission services to Eligible Customers with divergent study and operational requirements, it is unclear from a practical and procedural prospective, how these rules would be implemented if MISO is not the entity that receives the application or operational assumptions that underlie transmission service options may not apply to the large load.  MISO does not object to ATC’s implementation of large load requirements in addition to the baseline established in MISO’s IRR Proposal e.g., if ATC were to

23  ATC Transmittal Letter, at p. 5. 24  ATC Transmittal Letter, at p. 14.  Transmission Owners Agreement, Appendix I, Section 7.1.
25  See Agreement of Transmission Facilities Owners to Organize the Midcontinent Independent System Operator, Inc.. (“Transmission Owners Agreement”) Appendix I, Section 7.1 (Service under the Tariff. Customers will receive transmission service under a single Tariff which will apply to transmission service over the entire MISO Region (including the ITC), subject to changes to the Tariff accepted by FERC that the ITC may propose pursuant to this Appendix I. Customers will apply for service on the MISO OASIS. MISO will execute the agreements with the customers for service and studies. The ITC shall make all decisions on rate discounts for ITC-only transactions.).
26  Show Cause Order at PP 1(noting the distinction between large loads and Eligible Customers) and 13 (discussing the “…need for clear and consistent tariff provisions regarding the provision of transmission service to Eligible Customers on behalf of large loads”).

PDF page 12

12
propose to use the 100 MW load threshold as a trigger for additional requirements in its footprint, but that is not the proposed Tariff languages does.  Rather the point is that a uniform baseline process is needed both to create space for complementary ATC-specific planning criteria and ensure that any required processes appropriately connect with downstream MISO processes.

C. Granting This Protest Is Consistent with ATC’s Stated Intent.

Granting this limited protest would align with ATC’s statements in its filing.  ATC states that ATC’s proposal is intended to be “complementary to MISO’s future filings” and “designed to work together with MISO’s process in the same way ATC’s local planning process in Attachment FF-ATCLLC works with the annual MISO Transmission Expansion Plan (“MTEP”) process today.”27  ATC’s proposed Tariff redlines, however, state that ATC requirements “shall govern” in its footprint and indicates ATC may selectively defer requirements to MISO.28  This provides too much uncertainty to Large Loads and results in inconsistent Large Load requirements. MISO is willing to work with ATC to establish incremental criteria in the ATC region that will complement MISO’s baseline reliability framework.  MISO also understands that ATC made its filing in response to the Show Cause Order, in advance of the submission of MISO’s IRR Proposal, and without time to fully coordinate its proposed framework with MISO.  Now that both parties have filed their respective proposals, there is time for the parties to work together to address the needs of the region while acknowledging that ATC may need to impose requirements on large loads that are in addition to the baseline reliability requirements established in the IRR Proposal. MISO is sensitive to the challenges that ATC faces in filing supplemental requirements that are responsive to needs in the ATC footprint while aligning with MISO processes that are still

27  ATC Transmittal Letter at p. 2.
28  ATC Tariff Redlines at p. 21 (“The ATCLLC Local Planning Criteria and requirements established by ATCLLC’s Business Practices, as described herein, shall govern in ATCLLC’s footprint.”).

PDF page 13

13
in development.  This is a difficult task and both MISO and ATC are working to develop new rules on accelerated schedules.  To address this issue and better facilitate coordination, MISO suggests that the Commission require ATC to make a future compliance filing no earlier than the date by which MISO will make its Large Load 205 filings---i.e., November 16, 2026, or the date on which the Commission acts on MISO’s IRR filing, whichever is later.  Such a compliance period would align MISO and ATC’s development schedules and allow ATC to see (and participate in developing) the base rule set before it files supplemental requirements.  Such alignment will have long term benefits for ATC and MISO’s large load customers by avoiding rule conflicts, process redundancies, or unduly disparate treatment of large loads.

III. COMMUNICATIONS
MISO requests waiver of Rule 203(b)(3)29 of the Commission’s Rules of Practice and Procedure to the extent necessary to permit the designation of more than two persons for service on behalf of MISO in this proceeding and requests all communications related to this filing be directed to:

Christopher D. Supino
Managing Senior Corporate Counsel
Michael Kessler
Managing Assistant General Counsel
Midcontinent Independent System
Operator, Inc.
720 City Center Drive
Carmel, Indiana 46032
Telephone: (317) 249-5400
csupino@misoenergy.org
mkessler@misoenergy.org

James C. Holsclaw
Calfee, Halter & Griswold LLP
3900 Salesforce Tower
111 Monument Circle
Indianapolis, Indiana 46204
Telephone: (317) 308-4266
jholsclaw@calfee.com

29  18 C.F.R. § 385.203(b)(3) (2026).

PDF page 14

14
IV. NOTICE AND SERVICE
MISO has served a copy of this filing electronically, including attachments, upon each person designated on the official service list compiled by the Secretary as well as on all Tariff customers, MISO Members, Member representatives of transmission owners and non- transmission owners, as well as all state commissions within the MISO Region and the Organization of MISO States.  The filing has been posted electronically on MISO’s website at https://www.misoenergy.org/legal/ferc-filings/ for other interested parties in this matter.

V. CONCLUSION
WHEREFORE, MISO respectfully requests that the Commission direct ATC to revise Attachment FF-ATCLLC either to: (1) require ATC to submit revised Tariff sheets that adopt or integrate with MISO’s large load rules and procedures, remove redundant processes, and explicitly provide that any requirements imposed by Attachment FF-ATCLLC or ATC’s business practices on ATC Large Load are additional to those applicable to Large Load under the MISO Tariff and that, in the event of a conflict, the more restrictive rule governs; or (2) reject ATC’s proposal as unjust, unreasonable, and unduly discriminatory for large loads taking Transmission Service under the MISO Tariff.

Respectfully submitted,
/s/ Christopher D. Supino

Christopher D. Supino
Managing Senior Corporate Counsel
Michael Kessler
Managing Assistant General Counsel
Midcontinent Independent System
Operator, Inc.
720 City Center Drive
Carmel, Indiana 46032
Telephone: (317) 249-5400
mkessler@misoenergy.org
csupino@misoenergy.org

PDF page 15

15

James C. Holsclaw
Calfee, Halter & Griswold LLP
3900 Salesforce Tower
111 Monument Circle
Indianapolis, Indiana 46204
Telephone: (317) 308-4266
jholsclaw@calfee.com

Attorneys for the Midcontinent Independent System Operator, Inc.

DATED: September 8, 2026

PDF page 16

16
CERTIFICATE OF SERVICE
I hereby certify that I have this day e-served a copy of this document upon all parties listed on the official service list compiled by the Secretary in the above-captioned proceeding, in accordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and Procedure (18 C.F.R. § 385.2010).

Dated this 8th day of September 2026, in Carmel, Indiana.
/s/ Julie Bunn
Julie Bunn
Midcontinent Independent
System Operator, Inc.
720 City Center Drive
Carmel, IN 46032
317-249-5400