Motion for Leave to Answer and Answer of Vistra Corp. to Northern Virginia Electric Cooperative, Inc.'s 07/29/2026 Motion for Clarification of the…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
Docket Nos. EL25-49-002
EL25-49-000
Docket No. AD24-11-001
Docket No. EL25-20-001
(consolidated)
Docket No. ER26-1479-000
MOTION FOR LEAVE TO ANSWER AND ANSWER OF VISTRA CORP. TO
NOVEC’S MOTION FOR CLARIFICATION
Pursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission” or “FERC”),1 Vistra Corp. (“Vistra”) hereby moves to answer and answers the pleading that Northern Virginia Electric Cooperative, Inc. (“NOVEC”) filed on July 29, 2026,2 in the above-captioned proceeding. Although styled as a motion for clarification, NOVEC’s motion is in reality an impermissible, out-of-time request for rehearing because it contests determinations the Commission made in its June 18, 2026 order in the above- captioned dockets (“June 2026 Order”).3 Because NOVEC’s pleading was filed after the statutory deadline for requests for rehearing, it must be denied as untimely.
1 18 C.F.R. §§ 385.212, 385.213. 2 PJM Interconnection, L.L.C., Motion for Clarification of NOVEC, Docket No. EL25-49-000 (filed July 29, 2026) (“NOVEC Filing”).3 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026) (“June 2026 Order”).
PDF page 2
-2-
I. MOTION FOR LEAVE TO ANSWER
Although the Commission’s procedural rules generally do not allow answers to requests
for rehearing, the Commission may permit them for good cause.4 The Commission frequently accepts answers that clarify the issues before the Commission, ensure a complete record, or otherwise assist the Commission in its decision-making.5 Vistra respectfully requests that the Commission accept this answer to clarify that NOVEC’s motion is in fact, a request for rehearing.
II. ANSWER
A. The Commission should reject NOVEC’s motion as an untimely request for
rehearing.
Although NOVEC styles its filing as a motion for clarification, the substance of the filing directly contests the merits of the Commission’s June 2026 Order, which renders the pleading a request for rehearing. The Commission categorizes pleadings based on their “substance,” not “party-bestowed title.”6 As NOVEC acknowledges, the Commission “concluded” in the June
2026 Order that the record “[did] not adequately substantiate the need for an additional [Grid Reliance Charge] at this time” or provide sufficient information on “how such a charge should be
4 18 C.F.R. § 385.213(a)(2) (“An answer may not be made to a protest, an answer, a motion for oral argument, or a request for rehearing, unless otherwise ordered by the decisional authority.”).5 See, e.g., PJM Interconnection, L.L.C., 182 FERC ¶ 61,073, at P 13 (2023) (accepting answers to answers that “provided information that assisted us in our decision-making process.”); New Fortress Energy LLC, 174 FERC ¶ 61,207, at P 7 (2021) (accepting answers because they provided information that assisted the Commission’s decision-making process); Alaska Gasline Dev. Corp., 171 FERC ¶ 61,134, at P 7 (2020) (accepting answers that “clarify the concerns raised and provide information that has assisted in our decision making.”); Saltville Gas Storage Co., L.L.C., 164 FERC ¶ 61,212, at P 2 n.6 (2018) (accepting answers that “assist the Commission in understanding the issues raised, and will ensure a complete record.”).6 San Diego Gas & Elec. Co. v. Sellers of Energy & Ancillary Servs., 133 FERC ¶ 61,014, at P 15 (2010) (“While PG&E has styled this filing as a motion for clarification, we are not obligated to accept a filing solely on the basis of its party-bestowed title. Instead, we examine the substance of the pleading. We find that PG&E’s motion cannot be interpreted to be a motion for clarification because PG&E is not asking that we clarify any previous Commission order. Rather, we find PG&E’s motion to be an untimely attempt by PG&E to seek rehearing of a prior Commission order.”)
PDF page 3
-3-
calculated and assessed.”7 The Commission was crystal clear that “experience with the actual use of these new transmission services” is necessary to create the record the Commission would need to support any revised proposal for a Grid Reliance Charge.8 In response, NOVEC “respectfully disagrees that the record does not substantiate the need for an additional charge.”9 That “disagree[ment]” directly contradicts the Commission’s determination on both the now-rejected Grid Reliance Charge and the evidence on which that determination was based. NOVEC asks the Commission to “clarify” that it did not mean what it said in determining that “experience with the actual use” of the new transmission services is a necessary prerequisite for any future proposals similar to the Grid Reliance Charge.10 Disagreement with clear findings is not grounds for clarification.11 Rather, it is grounds for requesting rehearing, which NOVEC chose not to pursue within the timeframe allotted by the Federal Power Act.
Further, NOVEC mischaracterizes clear Commission statements as ambiguous. For
example, NOVEC argues, “it is not clear what additional support the Commission believes it would have needed to support approval of a rate akin to or serving the purpose of the proposed Grid Reliance Charge.”12 On the contrary, the Commission was quite explicit:
7 NOVEC Filing at 4 (quoting June 2026 Order at P 455).8 June 2026 Order at PP 455-456.9 NOVEC Filing at 5 (emphasis removed).10 NOVEC Filing at 6-7 (“The Commission also suggested that ‘experience with the actual use’ of the new transmission services would help support its understanding . . . NOVEC accordingly requests that the Commission clarify that it is not requiring actual experience with the new transmission services before any filing may be submitted and that the Commission will consider proposals if filed prior to Eligible Customers actually beginning to serve Co- Located Loads.”).11 Supra note 6 (explaining that a motion for clarification must be asking the Commission to clarify a previous order); see also Erie Blvd. Hydropower, L.P., 118 FERC ¶ 61,196, at P 11 (2007) (“To the extent that GIPA and Adirondack seek clarification or reconsideration, styling an improper request for rehearing as a motion for clarification or motion for reconsideration cannot cure its deficiencies.”).12 NOVEC Filing at 5.
PDF page 4
-4-
In particular, the record contains insufficient description of the potential nature or magnitude of the cited benefits or the potential costs that transmission providers or owners may incur when providing these benefits to Eligible Customers on behalf of Co- Located Loads. For example, Indicated TOs state that, even where an Eligible Customer has requested FCD or NFCD transmission service for 0 MW, a large Co-Location Arrangement will still depend on the transmission system for a suite of synchronization support services, such as stable frequency, inertia, stability services (damping, angle stability), fault current capability, and ride-through and protection coordination. However, beyond briefly listing such benefits, the record lacks specificity regarding what these services are, what costs they involve, and how they benefit Eligible Customers on behalf of Co-Located Loads.13
NOVEC disregards this direct statement of missing evidence as merely a request for “cost support for the rate itself,” ignoring that the Commission also found a lack of specificity on the nature of the services and their benefits.14
NOVEC’s explains that it “did not seek rehearing on this issue because NOVEC expects that the PJM stakeholder process will result in submission of another proposal for the Commission’s consideration.”15 Setting aside the troubling implication that some PJM stakeholders might intend to ignore the Commission’s determination on this issue, NOVEC’s explanation cannot rehabilitate its flawed pleading. Ongoing PJM stakeholder processes have no bearing on the statutory deadline for seeking rehearing or other Commission rules of procedure. Instead of filing a timely request for rehearing, NOVEC filed a mislabeled motion for clarification 41 days after the June 2026 Order, well outside the statutory requirements for requests for rehearing. Under Section 313 of the Federal Power Act, requests for rehearing must be made
13 June 2026 Order at P 455.14 NOVEC Filing at 6.15 NOVEC Filing at 5.
PDF page 5
-5-
within 30 days,16 and courts interpret this as a bright-line rule that even the Commission lacks discretion to extend.17 The Commission must deny NOVEC’s filing as untimely.18
B. The Commission’s clear conclusion on the Grid Reliance Charge is correct.
Looking past NOVEC’s procedural error, NOVEC is also wrong on the merits. The
Commission’s rejection of the Grid Reliance Charge was the right decision. The proposed Grid Reliance Charge would have applied equally to customers who use the grid in completely different ways, from customers that never reserve service to customers that frequently reserve significant amounts of service. Non-Firm Contract Demand Transmission Service customers who never
reserve transmission service to pull energy from the grid and rely on it only for black start and regulation services would have been forced to pay for something other than those services. That is not consistent with cost causation principles, and it would have been a departure from the Commission’s long-standing policy requiring transmission providers to offer and price ancillary services separately.19
In any event, the Commission’s decision to wait until the new transmission services are
implemented before considering proposals similar to the Grid Reliance Charge makes sense. By waiting for evidence of how parties use the new transmission services, the Commission can best evaluate whether gaps remain in the new transmission service rate structure. Vistra’s position is
16 16 U.S.C. § 825l(a) (“[A] party may apply for a rehearing within thirty days after the issuance of such order.”).17 San Diego Gas & Elec. Co. v. Sellers of Energy & Ancillary Servs., 133 FERC ¶ 61,014 at P 20 (“[C]ourts have repeatedly recognized that the Commission has no discretion to extend the deadline.” (citing Boston Gas Co. v. FERC, 575 F.2d 975 (1st Cir. 1978), Dayton Power & Light Co. v. FPC, 251 F.2d 875, 877 (D.C. Cir. 1957))).18 San Diego Gas & Elec. Co. v. Sellers of Energy & Ancillary Servs., 133 FERC ¶ 61,014 at P 20 (“Accordingly, the Commission itself has long held that we lack the authority to consider requests for rehearing filed more than 30 days after the issuance of a Commission order.” (citing Southern California Edison Co., 116 FERC ¶ 61,287, at P 17 (2006))).19 PJM Interconnection, L.L.C., Response Brief of Vistra Corp., Docket No. EL25-49-000, at 18-23 (filed March 25, 2026) (“Vistra March 2026 Response Brief”).
PDF page 6
-6-
that a customer using the grid solely for regulation and black start service is relying very little on the grid.20 If substantial evidence gathered through actual use of the new transmission services eventually shows otherwise, and PJM is able to demonstrate that the new transmission service rates allow certain customers to receive grid services that they do not pay for, the Commission can revisit the issue based on that evidence, consistent with the June 2026 Order. Unless and until real-world experience with the new transmission services produces such evidence, there is no evidence demonstrating that the alleged problem the Grid Reliance Charge was intended to solve is even a problem at all—much less that it warrants creation of a new charge for an ill-defined service with no identified benefits. Accordingly, the Commission should reject NOVEC’s attempt to resurrect this issue in this proceeding and should review skeptically any attempt, by NOVEC or others, to relitigate this issue through PJM’s eventual compliance filing in response to the June 2026 Order.
III. Conclusion
NOVEC’s motion is in reality an untimely rehearing request that must be rejected as a matter of law. Rejecting NOVEC’s pleading is also consistent with the June 2026 Order. Co- location arrangements are poised to relieve the growing stress of large load growth on the PJM grid, and this docket aims to create clear and readily implementable rules to facilitate those arrangements. Vistra urges the Commission to resist NOVEC’s attempt to inject ambiguity into unambiguous Commission holdings.
[Signatures on Next Page]
20 Vistra March 2026 Response Brief at 21.
PDF page 7
-7-
Respectfully submitted,
/s/ J. Arnold Quinn
J. Arnold Quinn
SVP of Regulatory Policy
Andrew Weinstein
Vice President, FERC Market Policy
Vistra Corp.
325 7th Street NW
Suite 520
Washington, DC 20004
arnie.quinn@vistracorp.com
andrew.weinstein@vistracorp.com
________________
Nicholas M. Gladd
Sarah Greenberg
Katie Mansur
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006
(617) 598-7871
ngladd@wsgr.com
sgreenberg@wsgr.com
cmansur@wsgr.com
Counsel for Vistra Corp.
Dated: August 18, 2026
PDF page 8
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary of the Commission in these proceedings.
Dated: August 18, 2026
Washington, D.C.
/s/ Katie Mansur
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006