EL25-49-000 · 2026-08-18 · Vistra Corp.

Motion for Leave to Answer and Answer of Vistra Corp. to Northern Virginia Electric Cooperative, Inc.'s 07/29/2026 Motion for Clarification of the…

Text extracted from the eLibrary original (SHA-256 61b0834eda5f4ca9…). Download the original from the official source.

Contents · 5 sections
  1. I. MOTION FOR LEAVE TO ANSWER p. 2
  2. II. ANSWER p. 2
  3. A. The Commission should reject NOVEC’s motion as an untimely request for p. 2
  4. B. The Commission’s clear conclusion on the Grid Reliance Charge is correct. p. 5
  5. III. Conclusion p. 6

Read topic-matched comments in EL25-49

Topics in the text: Filing procedure · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

Although styled as a motion for clarification, NOVEC’s motion is in reality an impermissible, out-of-time request for rehearing because it contests determinations the Commission made in its June 18, 2026 order in the above- captioned dockets (“June 2026 Order”).3 Because NOVEC’s pleading was filed…
Read this passage Filed comments: Filing procedure

I. MOTION FOR LEAVE TO ANSWER

printed heading · Topic match: Filing procedure

MOTION FOR LEAVE TO ANSWER Although the Commission’s procedural rules generally do not allow answers to requests for rehearing, the Commission may permit them for good cause.4 The Commission frequently accepts answers that clarify the issues before the Commission, ensure a complete record, or…
Read this passage Filed comments: Filing procedure

II. ANSWER

printed heading

II.
Read this passage

A. The Commission should reject NOVEC’s motion as an untimely request for

printed heading · Topic match: Filing procedure

Instead of filing a timely request for rehearing, NOVEC filed a mislabeled motion for clarification 41 days after the June 2026 Order, well outside the statutory requirements for requests for rehearing.
Read this passage Filed comments: Filing procedure

B. The Commission’s clear conclusion on the Grid Reliance Charge is correct.

printed heading · Topic match: Filing procedure

Sellers of Energy & Ancillary Servs., 133 FERC ¶ 61,014 at P 20 (“Accordingly, the Commission itself has long held that we lack the authority to consider requests for rehearing filed more than 30 days after the issuance of a Commission order.” (citing Southern California Edison Co., 116 FERC ¶…
Read this passage Filed comments: Filing procedure

III. Conclusion

printed heading · Topic match: Filing procedure

Conclusion NOVEC’s motion is in reality an untimely rehearing request that must be rejected as a matter of law.
Read this passage Filed comments: Filing procedure

CERTIFICATE OF SERVICE

printed heading

Dated: August 18, 2026 Washington, D.C. /s/ Katie Mansur Wilson Sonsini Goodrich & Rosati 1700 K Street NW Fifth Floor Washington, DC 20006