ER26-3380-000 · 2026-08-20 · Individual No Affiliation
Attachment_B_PJM_ELCC_Sensitivity_Analyses_May2025
PDF page 1
PJM © 2025
www.pjm.com | Public
ELCC Accreditation Methodology:
Update on Sensitivity Analyses
ELCCSTF
May 22, 2025
PDF page 2
PJM © 2025
2
www.pjm.com | Public
ELCC Sensitivity Analyses
• This presentation provides ELCC sensitivity analyses that were requested by stakeholders and/or initiated by PJM to help inform the discussion and development of accreditation proposals at the ELCCSTF
• All values are presented for informational purposes only
PDF page 3
PJM © 2025
3
www.pjm.com | Public
List of Sensitivity Analyses
ELCC Sensitivity Runs
Review Results
Base
Case
2026/27 BRA ELCC run that also includes the DR modeling and accreditation reforms recently accepted by FERC in Docket No. ER25-1525
Today (May 22nd meeting)
1
Remove 1993/94 from historical weather period
Today
2
Extend historical weather period back to 1970s *
Today
3
Remove WSE and 2014 Polar Vortex performance
Today
4
Alternative approach to better align load scenarios and temp. / performance (new) Today
5
Incorporate thermal winter capability above CIRs
Today
6
Combine sensitivities 1 and 3 (No 1993/94 or WSE/PV1)
Today
7
Combine sensitivities 4 and 5 (Improved temp/load alignment and WICAP) Today
8
Combine sensitivities 3 and 5 (WICAP with no WSE/PV1)
Today
9+
Performance Weighting sensitivities with est. 2025 winter performance data May 30th
* Sensitivity based on run done during CIFP stakeholder process
PDF page 4
PJM © 2025
4
www.pjm.com | Public
Base Case
• 26/27 BRA Case run during the first quarter of 2025
• Plus DR changes recently accepted by FERC in Docket No. ER25- 1525
– No limited DR Performance Window
– Changes to DR winter performance shape
PDF page 5
PJM © 2025
5
www.pjm.com | Public
Base Case
PDF page 6
PJM © 2025
6
www.pjm.com | Public
1. Removing DY 1993/94 Load Scenarios (“No93”)
• The load scenarios associated with weather from DY 1993/94 were removed from the model
• Weather data starts on June 1st 1994
• Weather bins were recalculated
PDF page 7
PJM © 2025
7
www.pjm.com | Public
1. Removing DY 1993/94 (“No93”)
-
Decrease in overall system
risk (IRM drops and system
is less tight)
-
Majority of LOLH remains in
the winter season
-
Class ratings increase for all
classes except wind classes
PDF page 8
PJM © 2025
8
www.pjm.com | Public
2. Weather history back to 1970s
• During the CIFP stakeholder process, sensitivity analyses was run using an extended weather history back to 1973 and compared to the base case at that time
• The following shows the relative shift in seasonal risk for different loss-of-load metrics that were provided when this analysis was run:
CIFP Base Case
(Back to 1993)
Weather History
Back to 1973
Diff
LOLE Winter Share (%)
31%
42%
+11% Winter
LOLH Winter Share (%)
49%
57%
+8% Winter
EUE Winter Share (%)
64%
71%
+7% Winter
PDF page 9
PJM © 2025
9
www.pjm.com | Public
3. Removing Forced Outages
from PV1 and WSE (“NoPV1WSE”)
• The forced outage data from Polar Vortex 1 (PV1) and Winter Storm Elliott (WSE) were removed from the model
– PV1 was defined as including 3 days Jan 6 – Jan 8, 2014
– WSE was defined as including 4 days Dec 23 – Dec 26, 2022
• After removing those days from the respective bin, the rest of the bin was left unmodified. This means that the probability of drawing performance from other days in the bin increased, after the removal of the days
PDF page 10
PJM © 2025
10
www.pjm.com | Public
3. Removing Forced Outages
from PV1 and WSE (“NoPV1WSE”)
-
Decrease in overall system
risk (IRM drops and system
is less tight)
-
Majority of LOLH is in the
summer season
-
Class ratings significantly
increase and are consistent
with a system with majority
of risk in summer
PDF page 11
PJM © 2025
11
www.pjm.com | Public
Target
Forecast
Day 26/27
A1993
B1993
C1993
….
….
….
M2023
June 1,
2026
140,000
139,500
138,000
….
….
….
145,000
June 2,
2026
137,000
134,000
136,000
….
….
….
140,000
….
….
….
….
….
….
….
….
May 31,
2027
133,000
134,000
132,000
….
….
….
135,000
4. Improve Alignment of Load Scenarios
with Temperature Bins (“Align”)
Currently, to identify the temperature bin from which to sample resource performance, we use the target forecast date (e.g., June 2) combined with the delivery year of the scenario under consideration (e.g., 1993 in the case of A1993, B1993, or C1993). We then find the bin that contains the resulting date. Therefore, June 2, 2026 under A1993 June 2, 1993 Bin containing June 2, 1993 June 2, 2026 under B1993 June 2, 1993 Bin containing June 2, 1993 June 2, 2026 under C1993 June 2, 1993 Bin containing June 2, 1993 June 2, 2026 under M2023 June 2, 2023 Bin containing June 2, 2023
PDF page 12
PJM © 2025
12
www.pjm.com | Public
Target
Forecast
Day 26/27
A1993
B1993
C1993
…. …..
….
M2023
June 1,
2026
June 1,
1993
June 2,
1993
June 3,
1993
….
….
….
May 26,
2023
June 2,
2026
June 2,
1993
June 3,
1993
June 4,
1993
….
….
….
May 27,
2023
….
….
….
….
….
….
….
….
May 31,
2027
May 31,
1994
June 1,
1994
June 2,
1994
….
….
….
May 25,
2024
However, the actual weather that is used to calculate the forecasted loads in the weather scenarios is as shown below. PJM is proposing to better align each forecasted load with the temperature bin that contains the weather that was used to calculate the forecasted load per the following example:
June 2, 2026 under A1993 June 2, 1993 Bin containing June 2, 1993 June 2, 2026 under B1993 June 3, 1993 Bin containing June 2June 3, 1993 June 2, 2026 under C1993 June 4, 1993 Bin containing June 2June 4, 1993 June 2, 2026 under M2023 May 27, 2023 Bin containing June 2 May 27, 2023
4. Improve Alignment of Load Scenarios
with Temperature Bins (“Align”)
PDF page 13
PJM © 2025
13
www.pjm.com | Public
Improve Alignment of Load Scenarios
with Temperature Bins (“Align”)
Target
Forecast
Day 26/27
A1993
B1993
C1993
…. …..
….
M2023
June 1,
2026
June 1,
1993
June 1,
1993
June 1,
1993
….
….
….
June 1,
2023
June 2,
2026
June 2,
1993
June 2,
1993
June 2,
1993
….
….
….
June 2,
2023
….
….
….
….
….
….
….
….
May 31,
2027
May 31,
1994
May 31,
1994
May 31,
1994
….
….
….
May 31,
2024
Target
Forecast
Day 26/27
A1993
B1993
C1993
…. …..
….
M2023
June 1,
2026
June 1,
1993
June 2,
1993
June 3,
1993
….
….
….
May 26,
2023
June 2,
2026
June 2,
1993
June 3,
1993
June 4,
1993
….
….
….
May 27,
2023
….
….
….
….
….
….
….
….
May 31,
2027
May 31,
1994
June 1,
1994
June 2,
1994
….
….
….
May 25,
2024
Current Approach
to identify temperature
Bin
Proposed Approach
to identify temperature
Bin (aligned with
development of PJM Load
Forecast)
PDF page 14
PJM © 2025
14
www.pjm.com | Public
4. Improve Alignment of Load Scenarios with Temperature Bins (“Align”)
• The graph shows the current forced outage distribution for one of the coldest days in the model (Jan 19, 1994) vs how the distribution would look like under the PJM proposal
• Each distribution was plotted using the 1,300 sampled forced outage values associated with Jan 19, 1994
–
13 weather scenarios (A through M) x 100 performance draws = 1,300
• For Jan 19, 1994, the current
implementation samples higher forced outage levels less frequently than under the proposed implementation
PDF page 15
PJM © 2025
15
www.pjm.com | Public
4. Improve Alignment of Load Scenarios
with Temperature Bins (“Align”)
-
Significant increase in
overall system risk (IRM
increases and system is
tight)
-
Almost all of LOLH is in the
winter season
-
Class ratings decrease for
majority of classes
PDF page 16
PJM © 2025
16
www.pjm.com | Public
5. Additional Winter Capability Overview
To recognize additional output above a
summer based ICAP, PJM estimated a
“Winter ICAP” for Unlimited Resources
equal to:
– Max Winter Net Capability Test
submitted since 22/23 DY, capped at
MFO
– Winter ICAP was assumed to be fully
deliverable
ELCC
Class
Summer
ICAP
Winter
ICAP
Delta
Nuclear
32,144
33,592
1,448
Coal
35,779
36,441
662
Gas CC
(Single and Dual Fuel)
57,664
60,766
3,102
Gas CT
11,030
11,955
925
Gas CT Dual Fuel
13,158
15,099
1,941
Diesel
329
332
3
Steam
10,004
10,189
185
Other Thermal
3,041
3,336
295
163,149
171,710
8,561
PDF page 17
PJM © 2025
17
www.pjm.com | Public
5. Reflect higher Winter output
for Unlimited Resources (“WICAP”)
Winter Months include November through April
PDF page 18
PJM © 2025
18
www.pjm.com | Public
5. Reflect higher Winter output
for Unlimited Resources (“WICAP”)
-
Decrease in overall system
risk (IRM drops and system
is less tight)
-
LOLH is almost evenly split
between winter and summer
-
Class ratings increase for all
classes except wind classes
PDF page 19
PJM © 2025
19
www.pjm.com | Public
6. Removing Forced Outages from PV1 and WSE and removing DY 1993/94 (“NoPV1WSE & No93”) -
Decrease in overall system
risk (IRM drops and system
is less tight)
-
Large majority of LOLH is in
the summer season
-
Class ratings significantly
increase and are consistent
with a system with majority
of risk in summer
PDF page 20
PJM © 2025
20
www.pjm.com | Public
7. “WICAP & Align”
-
Increase in overall system
risk (IRM increases and
system is tighter)
-
Majority of LOLH remains in
the winter season
-
Class ratings increase
significantly for storage and
Gas CT Dual
-
Impact of “Align” is stronger
than impact of “WICAP”
PDF page 21
PJM © 2025
21
www.pjm.com | Public
8. “WICAP & NoPV1WSE”
-
Decrease in overall system
risk (IRM drops and system
is less tight)
-
Almost of LOLH is in the
summer season
-
Significant class ratings
increases (except for wind)
PDF page 22
PJM © 2025
22
www.pjm.com | Public
Comparison of All Sensitivity Results
•
Removing PV1 and WSE
forced outages eliminates
the majority of winter risk
(even when paired with the
“Align” sensitivity)
•
The “Align” sensitivity
increases winter risk and
overall risk. However, this
increase is mitigated when
coupled with the “WICAP”
sensitivity
•
Removing 1993/94 reduces
risk and winter risk but less
so than previously
estimated
PDF page 23
PJM © 2025
www.pjm.com | Public
Appendix
PDF page 24
PJM © 2025
24
www.pjm.com | Public
ELCC Class Ratings - Sensitivities
PDF page 25
PJM © 2025
25
www.pjm.com | Public
ELCC Class Ratings - Sensitivities
PDF page 26
PJM © 2025
26
www.pjm.com | Public
ELCC Class Ratings - Sensitivities
PDF page 27
PJM © 2025
27
www.pjm.com | Public
ELCC Class Ratings - Sensitivities
PDF page 28
PJM © 2025
28
www.pjm.com | Public
ELCC Class Ratings - Sensitivities
PDF page 29
PJM © 2025
29
www.pjm.com | Public
ELCC Class Ratings - Sensitivities
PDF page 30
PJM © 2025
30
www.pjm.com | Public
ELCC Class Ratings - Sensitivities