ER26-3380-000 · 2026-08-21 · Ohio Federal Energy Advocate

Comments of the Public Utilities Commission of Ohio's Office of the Federal Energy Advocate re PJM Interconnection, L.L.C.'s 07/31/2026 revisions to the…

PDF page 1

1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.                                    )                          Docket No. ER26-3380-000

COMMENTS OF THE PUBLIC UTILITIES COMMISSION OF OHIO’S
OFFICE OF THE FEDERAL ENERGY ADVOCATE

On July 31, 2026, PJM Interconnection, L.L.C. (PJM) submitted, pursuant to section 205 of the Federal Power Act, revisions to the PJM Open Access Transmission Tariff and the Reliability Assurance Agreement to establish a Reliability Backstop Procurement (RBP). In the filing, PJM describes the RBP as a one-time procurement of new capacity that is part of a multi- pronged, ongoing effort to address resource adequacy challenges in the PJM region driven primarily by the unprecedented addition of large loads, most notably data centers.1 Over two consecutive Base Residual Auctions (BRA) for the 2027/2028 and 2028/2029 Delivery Years, an insufficient commitment of capacity was secured to meet the PJM Region Reliability Requirement. As a result, PJM proposes an RBP, to be initiated on September 30, 2026, that aims to procure the most recently identified shortfall of approximately 6,831 megawatts (MW) of capacity less any quantities of qualifying credits (e.g., bilateral contracts) or other adjustments as specified in the filing.2

The Office of the Federal Energy Advocate (Ohio FEA) of the Public Utilities Commission of Ohio (PUCO), fulfilling its statutory duty to advocate on behalf of Ohio’s retail electricity consumers,3 offers the following comments for consideration by the Federal Energy Regulatory Commission (Commission).

1 PJM Transmittal Letter at 1-2.
2 Id. at 8-9.
3 Ohio Revised Code 4928.24.

PDF page 2

2
I. Background
PJM’s capacity market, called the Reliability Pricing Model (RPM), is designed to ensure long-term grid reliability by procuring the appropriate amount of supply needed to meet predicted peak load, plus an adequate reserve margin, three years in the future. A primary objective of the capacity market is to match (or balance) power supply with future demand, thereby creating long-term price signals to attract needed investments to ensure resource adequacy. Under the RPM, capacity resources are procured through an annual, competitive BRA. Starting in 2023, PJM warned of a growing imbalance between supply and demand in the region, driven primarily by large load growth and resource retirements outpacing the buildout of new generation.4 Actions such as delaying auctions or implementing price collars further distorted the intended design of the RPM. Over the next three years, the seriousness of the changing landscape became more widely understood and is now a central, dominant focus for PJM, state regulators, and many other stakeholders. In December 2025, the BRA conducted for Delivery Year 2027/2028 represented the first time in recent history that large load additions significantly increased PJM’s load forecast, which, in turn, significantly increased the PJM Region Reliability Requirement, in megawatts, PJM sought to procure in the auction. The auction resulted in a capacity procurement that was 6,517 MW short of the PJM Region Reliability Requirement and 5.6 percent below the target 20% Installed Reserve Margin (IRM).5

4 Energy Transition in PJM: Resource Retirements, Replacements, and Risks, February 24, 2023, available at https://www.pjm.com/-/media/library/reports-notices/special-reports/2023/energy-transition-in-pjm-resource- retirements-replacements-and-risks.ashx.
5 PJM 2027/2028 Base Residual Auction Reserve Target Shortfall Report, February 9, 2026, available at https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2027-2028/2027-2028-bra-reserve- target-shortfall-report.pdf at 1.

PDF page 3

3
Similarly, in July 2026, the BRA conducted for Delivery Year 2028/2029 cleared 6,831 MW below the PJM Region Reliability Requirement and 5.6 percent below the 20% IRM.6

Over this time, PJM undertook various efforts to address the increasingly urgent resource adequacy needs of the region, including establishing a Reliability Resource Initiative and then an Expedited Interconnection Track to expedite the interconnection of new capacity resources, and initiating multiple Critical Issue Fast Path (CIFP) stakeholder processes to address the challenge of maintaining reliability while efficiently integrating new large loads. In August 2025, PJM initiated a broad CIFP on Large Load Additions, which, among other endeavors, led to an April 2026 CIFP on the RBP. The initial scope of the RBP CIFP was later expanded to include consideration of an “Interim Resource Adequacy Service” framework, which heretofore was ongoing in a PJM Connect and Manage Senior Task Force.

After lengthy discussion over two months and consideration of more than a dozen RBP solution packages, the PJM stakeholders failed to endorse any package to the PJM Board to conclude the CIFP effort. As a result, on July 27, 2026, the PJM Board issued a decisional letter setting forth the RBP mechanism contained in the instant docket.7 The Ohio FEA supports the filing.

II. Comments
A. Data Centers Are the Large Loads Driving Historic Demand.
As an initial matter, the Ohio FEA maintains that data centers are the large loads driving historic demand in the PJM footprint and, therefore, the RBP should be specific to data center

6 PJM 2028/2029 Base Residual Auction Report, July 14, 2026, available at https://www.pjm.com/- /media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra-results-report.pdf at 3.
7 PJM Board Decisional Letter on Critical Issue Fast Path – Reliability Backstop Procurement and Connect and Manage, July 27, 2026, available at https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public- disclosures/2026/20260727-board-decisional-letter-on-cifp-reliability-backstop-procurement-and-connect-and- manage.pdf.

PDF page 4

4
load, not all new loads of a designated size. We support the flexibility that the RBP proposal affords states to rely on their own definitions of data centers or large loads and to determine which retail customers should be allocated RBP Charges.8 The “Statement of Principles Regarding PJM,” as signed by the National Energy Dominance Council and the 13 PJM governors, specified that costs associated with a one-time procurement should be borne by data centers. As this nation, under the current administration’s leadership, works to onshore and expand domestic manufacturing, it is counterproductive to place additional constraints on our traditional manufacturers and on other non-data center large loads. Further, it has become obvious to most that data centers are unique large loads that warrant distinction from other commercial or industrial customers. Ohio was one of the first states to establish data center tariffs with a defined data center customer class. The PUCO has approved, or is currently in the process of reviewing, this tariff for each of its electric distribution utilities.

B. A Parallel Path Is Necessary to Ensure Reliability.
The rate of change in demand/supply conditions in the PJM region warrants a central procurement to comprehensively address the more than six gigawatts of capacity shortfall seen in the last two BRAs. First, it is important to note that the Ohio FEA strongly supports bilateral contracting between data center loads and new capacity resources, as well as PJM’s ongoing bilateral matchmaking effort, to address resource inadequacy in the region caused by data center loads. Bilateral contracting directly assigns the cost of new capacity to new load, removing any risk of cost shifting to other customers. However, bilateral contracting takes time, which will not mitigate escalating reliability concerns in the near term.

8 PJM Transmittal Letter at 98.

PDF page 5

5
To incent new resources to address the capacity shortfall, PJM proposes to procure long- term capacity for a fixed term of up to 15 years, running from Delivery Year 2028/2029 to Delivery Year 2042/2043. Critically, only new megawatts (e.g., new resources, uprates to existing resources, capacity transfers from deactivating resources) will be eligible to participate in the RBP, ensuring that the effort results in new capacity and does not simply shift existing resources from one capacity product to another. Under the RBP, new resources must be online no later than June 1, 2032, assume the obligations of any PJM capacity resource, and assume a must-offer obligation in the RPM at $0 (price taker), along with other supply obligations identified in the filing. PJM proposes a pay-as-bid structure for committed resources in the RBP and establishes a maximum willingness to pay structure set at $555/MW-day on a MW-weighted average basis, which is Point 1 on the Variable Resource Requirement demand curve (unconstrained) for Delivery Year 2028/2029.

A vital and non-divisive component of the RBP is who should pay the costs. While the allocation of any wholesale costs to retail customers is within the purview of each state, the Ohio FEA asserts it is widely agreed that the costs of the RBP should be paid by the data centers seeking new capacity during this time of regional demand/supply constraint. To accomplish this, PJM highlights in the filing that PJM and states must work cooperatively.9 First, PJM will allocate the RBP costs to each zone/area based on the megawatts of load additions each zone/area is forecasted to serve (i.e., pro rata share of the procurement target). The zone/area will then allocate costs pro rata to Load Serving Entities, which, in turn, will allocate them to retail customers consistent with state directives. “PJM’s proposed methodology for allocating RBP

9 Id. at 99-100.

PDF page 6

6
Charges sets the table for states . . . by empowering them to make decisions about how to best further allocate RBP Charges to data centers and other retail customers.”10

The Ohio FEA acknowledges that successful implementation of the RBP means that, upon Commission approval, states and utilities must work expeditiously to align state regulations and cost-allocation frameworks (i.e., tariffs) with the RBP structure, as needed, to ensure that the cost of procuring long-term capacity under the RBP is appropriately assigned to the cost causers.

III. Conclusion
PJM’s RBP is a timely effort to address reliability concerns caused by significant data center load growth in the region. We urge the Commission to approve the filing to secure long- term capacity commitments from new resources to meet escalating demand and to mitigate any compounding effect on PJM’s energy and capacity markets or other ratepayers.

Respectfully submitted,
D. Andrew Wilson
Ohio Attorney General

John H. Jones
Section Chief

/s/ Thomas G. Lindgren

Thomas G. Lindgren
Assistant Attorney General
Public Utilities Section
30 East Broad Street, 16th Floor
Columbus, Ohio 43215-3414
614.644.8768 (telephone)
866.818.6152 (facsimile)
Thomas.Lindgren@OhioAGO.gov

On Behalf of the Public Utilities
Commission of Ohio’s Office of the
Federal Energy Advocate

August 21, 2026

10 Id.

PDF page 7

7
CERTIFICATE OF SERVICE

I hereby certify that I have on this date caused a copy of the foregoing document to be served on each person included on the official service list maintained for this proceeding by the Commission’s Secretary, by electronic mail or such other means as a party may have requested, in accordance with Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010. Dated this the 21st day of August 2026, at Columbus, Ohio.

/s/ Thomas G. Lindgren

Thomas G. Lindgren
Assistant Attorney General