ER26-3380-000 · 2026-08-21 · Ohio Federal Energy Advocate

Comments of the Public Utilities Commission of Ohio's Office of the Federal Energy Advocate re PJM Interconnection, L.L.C.'s 07/31/2026 revisions to the…

Text extracted from the eLibrary original (SHA-256 69c95c1cdc326647…). Download the original from the official source.

Contents · 5 sections
  1. I. Background p. 2
  2. II. Comments p. 3
  3. A. Data Centers Are the Large Loads Driving Historic Demand. p. 3
  4. III. Conclusion p. 6
  5. D. Andrew Wilson p. 6

Read topic-matched comments in ER26-3380

Topics in the text: Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

As a result, PJM proposes an RBP, to be initiated on September 30, 2026, that aims to procure the most recently identified shortfall of approximately 6,831 megawatts (MW) of capacity less any quantities of qualifying credits (e.g., bilateral contracts) or other adjustments as specified in the…
Read this passage Filed comments: Reliability and curtailment

I. Background

printed heading · Topic match: Reliability and curtailment

A primary objective of the capacity market is to match (or balance) power supply with future demand, thereby creating long-term price signals to attract needed investments to ensure resource adequacy.
Read this passage Filed comments: Reliability and curtailment

II. Comments

printed heading

II.
Read this passage

A. Data Centers Are the Large Loads Driving Historic Demand.

printed heading · Topic match: Cost allocation

“PJM’s proposed methodology for allocating RBP 9 Id. at 99-100. 6 Charges sets the table for states . . . by empowering them to make decisions about how to best further allocate RBP Charges to data centers and other retail customers.”10 The Ohio FEA acknowledges that successful implementation of…
Read this passage Filed comments: Cost allocation

III. Conclusion

printed heading · Topic match: Cost allocation

We urge the Commission to approve the filing to secure long- term capacity commitments from new resources to meet escalating demand and to mitigate any compounding effect on PJM’s energy and capacity markets or other ratepayers.
Read this passage Filed comments: Cost allocation

D. Andrew Wilson

printed heading

Lindgren Assistant Attorney General Public Utilities Section 30 East Broad Street, 16th Floor Columbus, Ohio 43215-3414 614.644.8768 (telephone) 866.818.6152 (facsimile) Thomas.Lindgren@OhioAGO.gov On Behalf of the Public Utilities Commission of Ohio’s Office of the Federal Energy Advocate August…
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated this the 21st day of August 2026, at Columbus, Ohio. /s/ Thomas G.