AD26-7-000 · 2026-08-21 · Constellation Energy Generation, LLC
Post-Conference Statement of Constellation Energy Generation, LLC addressing issues raised at the Commissioner-led technical conference held on 07/23/2026…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Governance and Stakeholder Reforms
)
)
Docket No. AD26-7-000
POST-CONFERENCE STATEMENT OF
CONSTELLATION ENERGY GENERATION, LLC
Pursuant to the Commission’s July 30, 2026 notice in the above-captioned proceeding,1 Constellation Energy Generation, LLC (Constellation) submits these comments addressing issues raised at the Commissioner-led technical conference held on July 23, 2026, and responding to the Commission’s issues list found in the appendix of the Notice.
I. INTRODUCTION AND SUMMARY
Constellation commends the Commission for proactively addressing issues with the PJM stakeholder process. While we caution against overhauling a governance process that, despite its challenges, has led to the successful implementation of many market enhancements over the years, resulting in a regional market that saves consumers approximately $5 billion annually,2 there are nonetheless a number of reforms that can be made to improve the efficiency of the existing stakeholder process. As explained in responses to the Commission’s questions, Constellation does not support altering section 205 filing right authority or reforms that may result in undue political influence on market rules. Most of the unrest in PJM over the last decade has involved issues related to resource adequacy, generator retirements and replacements, and capacity market rules changes—matters over which PJM already has section 205 filing rights and is able to take action
1 PJM Governance and Stakeholder Reforms, Notice Requesting Post-Conference Comment, Docket No. AD26-7- 000 (July 30, 2026) (Notice).2 The Value of PJM, PJM Interconnection, L.L.C. (Jan. 21, 2026), https://www.pjm.com/-/media/DotCom/about- pjm/the-value-of-pjm.pdf.
PDF page 2
2
under section 205 even when the Membership disagrees. Instead, Constellation urges the Commission to focus on reforms that are tailored to the problems the region is trying to solve, including the suggestions we offer herein (with a more detailed path forward in the appendix).
II. QUESTION RESPONSES
A. PJM Board Independence
1. Should Board members’ terms be extended to five or more years?
Yes. Board terms should be lengthened to five years with two full terms possible, and substantive criteria should be considered for removing Board members. Terms exceeding five years may be too long of a commitment period for Board member candidates and could inadvertently limit Board member candidates. Further discussion on this matter should be pursued.
2. Should there be a maximum number of years that a Board member may serve (e.g., 10 years)?
Yes. See our response to Question 1. Constellation generally agrees that a maximum number of years is reasonable and welcomes discussion on determining the most appropriate number of years any Board member may serve. For example, a limit of two, five-year terms—for a ten-year cap—could make sense.3
3. Should the Board member qualification rules be revised to provide a preference for some Board members that reside in the PJM region?
Yes. The key focus on Board qualifications should remain (as it has in the past) on relevant experience and expertise. If strictly applied, a residency requirement risks diminishing the number of otherwise qualified Board candidates. Nonetheless, the deeper appreciation of a region that could be gained through living there (and being directly impacted by decisions made by the Board) could be beneficial. Constellation recommends a requirement that one PJM Board member reside
3 We would suggest not counting years served replacing a Board member who is leaving the Board prior to the end of her/his term against the ten-year cap.
PDF page 3
3
within the PJM footprint. Having a one-member residency requirement is consistent with other Board membership qualification quantities in Section 7.2 of the Operating Agreement that can be satisfied with one qualified member (e.g., “one [member] shall have expertise and experience in the operation or concerns of transmission dependent utilities, one [member] shall have expertise and experience in the operation or planning of transmission systems, and one [member] shall have expertise and experience in the area of commercial markets and trading and associated risk management”).4
4. Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year?
Yes. The two-year cooling off period may unduly limit the pool of candidates—who are otherwise qualified—from Board participation. A one-year cooling off period may be more appropriate and would be generally consistent with the Commission’s own cooling off period for former Commissioners and senior Commission staff.5
5. Should restrictions on Board communications be relaxed to enable more communication between the Board and stakeholders?
Yes. Additional opportunities for Board and stakeholder communications should be pursued as long as such additional communication opportunities are fair for all stakeholders and Board independence is preserved.
6. In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning?
Yes. While disclosing individual Board member votes would chill robust Board discussion of issues and should remain non-public, the Board should be required to provide a written explanation supporting its decisions and how the decision will achieve a just, reasonable and not unduly
4 Operating Agreement, Section 7.2 (emphasis added).5 See 18 U.S.C. § 207(c); 5 C.F.R. § 2641.204.
PDF page 4
4
discriminatory or preferential outcome. In addition, such explanation should include a discussion of why it rejected other views.
7. In order to increase transparency, should some Board meetings be open or available to the public?
No. The PJM Board is a decision-making body, unlike the boards of some other RTOs/ISOs that advise on decisions being made by the RTO/ISO leadership. The PJM Board therefore needs an independent opportunity to deliberate, and requiring all deliberation to occur in a public arena would chill effective Board meeting discussions. Non-public Board meetings are necessary for efficient discussion of often very technical matters to support well-informed policy decisions. To the extent additional information on Board decisions is desired, this can be addressed through a Board memo as described in our response to Question 6. Additionally, the Board should consider making all relevant, non-confidential material presented by PJM staff, the market monitor, and other participants at Board meetings public contemporaneously with the meeting. If additional Board interaction with stakeholders is pursued, as suggested in our response to Question 5, it must be fair for all stakeholders, preserve Board independence, and should be in addition to the existing, separate Board meetings.
8. Should PJM’s governing documents be revised to explicitly state that the responsibility of PJM and its Board is to serve the public interest?
No. PJM is already required to provide service consistent with the public interest by Federal Power Act (FPA), 16 U.S.C. § 824d(a), and it would be redundant and encourage disputes to attempt to restate that obligation in PJM’s governing documents using different words.
9. Should state representatives have at least one voting member on the Nominating Committee?
No. States can and should make their views known about selection of potential Board members by taking advantage of existing opportunities to engage. This could include coordinating efforts
PDF page 5
5
by developing a list of suggested nominees, perhaps through OPSI or through the formation of nomination advisory group consisting of state-designated representatives. Some suggest that the Board member selection is “slanted” and “deep[ly] biased” and seek to have specific interests dominate the Nominating Committee.6 Those suggestions are not correct. A number of prior participants in the Nominating Committee, including two current Constellation employees, signed an affidavit being submitted contemporaneously in this proceeding explaining the robust and fair nature of the Nominating Committees’ work.
10. Should PJM adopt public performance metrics and tie management compensation to their achievement?
Yes. To the extent the Board already has or adopts performance metrics for senior PJM management, those metrics should be made public.
11. Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board?
No. The stakeholder process should not be made advisory-only and should remain as is for the reasons discussed below.7
PJM’s Section 205 Filing Rights Should Remain As Is
PJM has authority to file changes to rules related to resource adequacy issues under section 205. Section 205 filings related to energy and ancillary market matters (Operating Agreement, Schedule 1) and to regional transmission planning matters (Operating Agreement, Schedule 6) are conditioned on PJM first obtaining Members Committee approval, and PJM has complained that “PJM may be required to proceed under more restrictive requirements of section 206 [if it does
6 See, e.g., Pre-Technical Conference Statement of Jacob Finkel, Office of Governor Josh Shapiro, Deputy Secretary of Policy, Docket No. AD26-7-000, at 9 (July 16, 2026).7 We interpret the suggestion of an “advisory” stakeholder process to mean that PJM would have filing rights under section 205 even if it would consider stakeholder input.
PDF page 6
6
not obtain Member Committee approval].”8 To avoid the “more restrictive” requirements of section 206, PJM seeks discretion to file under section 205 for energy and ancillary service market and regional transmission planning matters even if the PJM Members disagree.9 As discussed in the following sub-sections, PJM has no need for such authority, which could be more damaging than helpful. Moreover, PJM lacks a legal basis to abrogate the long-standing allocation of section 205 filing rights.10
PJM’s Concern Is a Red-Herring and Is Unsupported
Virtually all discussions of significance related to PJM in recent years focus on resource adequacy issues, where PJM already has section 205 authority. For example, of the six principles involving PJM in the Statement of Principles Regarding PJM signed by the National Energy Dominance Counsel and all thirteen PJM state governors, PJM already has section 205 filing rights over all six principles.11 PJM’s concern (particularly with respect to filing authority over the energy and ancillary service markets) seem particularly out of place against this backdrop. As Constellation’s Mason Emnett explained in a pre-conference statement filed in this proceeding: [M]ost of the unrest in PJM over the last decade has involved issues
related
to
resource
adequacy,
generator
retirements
and
replacements, and capacity market rules changes—matters over
which PJM already has section 205 filing rights and is able to take
action under section 205 even when the Membership disagrees.
When PJM has delayed action, it has been because its leadership has
decided not to proceed, not because of any lack of authority. In the
8 Comments from PJM Interconnection, L.L.C., Docket No. AD26-7-000, at 6 (July 16, 2026) (PJM Pre-Conference Comments).
9 Id. at 6-7; see also FERC Mediation Term Sheet, PJM Interconnection, L.L.C., Term 1 (Aug. 10, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/committees/mc/2026/20260819/20260819-item-08---1- ferc-mediation-term-sheet.pdf.10 As Constellation owns and operates generation assets, its focus in this discussion is on PJM authority over energy and ancillary services markets.11 Statement of Principles Regarding PJM, National Energy Dominance Council (Jan. 16, 2026), https://www.energy.gov/documents/statement-principles-regarding-pjm. The seventh principle, regarding cost allocation, involves only the PJM state governors and not PJM.
PDF page 7
7
same vein, PJM’s lack of section 205 rights over energy market
issues has not deterred PJM’s action under section 206 when its
leadership decided to proceed without Membership endorsement.12
There is no evidence contradicting Mr. Emnett’s statement, and PJM’s concerns are overstated and unsupported. For example, in its pre-conference comments, PJM lists nine instances in recent years of a “failed” stakeholder vote.13 However, PJM’s recitation of recent stakeholder history deserves some scrutiny. Of the nine “failed” stakeholder votes only one of the nine (i.e., 11%) did not involve a resource adequacy-related matter (over which PJM already has section 205 filing authority).14 In other words, the stakeholder vote is already advisory for eight of the items listed, so PJM could file under section 205 regardless of the voting outcome. For the one item not covered under PJM’s section 205 rights, reserve requirement revisions, a majority (although not a required super-majority) of Members did support PJM’s proposal. And a separate proposal on reserve deployment revisions was endorsed by acclamation.
PJM raised a single instance where it believes the lack of unfettered section 205 filing rights has undermined its ability to make needed reform (i.e., certain reserves markets improvements).15 While Constellation fully supports reserve market improvements, we are concerned, based on PJM’s track record with respect to resource adequacy (described below), whether PJM would actually exercise its authority in a manner that alleviates, rather than contributes to, the “credibility gap” discussed in PJM’s recent paper. With respect to the issue of reserve market reforms referenced by PJM, Constellation notes that PJM failed to vigorously pursue it in the designated senior task force, which contributed to its delay progressing through the
12 Pre-Conference Statement of Mason Emnett on Behalf of Constellation Energy Generation, LLC, Docket No. AD26-7-000, at 2 (July 16, 2026).13 PJM Pre-Conference Comments at 3-4.14 Id. at 4.15 Id.
PDF page 8
8
stakeholder process. It is PJM’s failure to timely articulate the needs and goals of the reserve stakeholder process, rather than Member voting, that is responsible for delay of these much-needed reforms. If PJM believes this reserves change is critical, then it should not have allowed the stakeholder process to languish as it did and PJM should not be allowed to point to this process— where it contributed significantly to the delay—as justifying its claim for section 205 filing rights. In addition, rather than pursue complete abrogation of the Members’ long-standing section 205 filing rights, PJM could pursue reform via other means. Specifically, PJM can file a well- supported proposal under section 206 of FPA. Section 206 of the FPA is the long-established means for those lacking section 205 filing rights to seek recourse, and courts unsurprisingly agree that section 206 provides an adequate remedy.16 PJM arguments that section 206 is “more restrictive” compared to section 205 are not relevant under the FPA if there is no underlying right to file under section 205. As the Commission found in a recent decision responding to a similar PJM complaint about section 206 filings, “the fact that PJM may benefit from what it views as a more timely and efficient process under FPA section 205 compared to section 206 does not render the [transmission planning] Protocol’s existing location in the OA to be unjust and unreasonable.”17 PJM has demonstrated skill at filing under section 206, particularly in response to an urgent situation,18 so it is unclear there is a problem at all. Simply put, PJM has not demonstrated that there is any meaningful issue that it cannot already address.
16 See, e.g., Sacramento Mun. Util. Dist. v. FERC, 616 F.3d 520, 542 (D.C. Cir. 2010) (in the event of “an unjust outcome, San Diego may petition the Commission to order appropriate changes . . . under section 206”).17 Duquesne Light Co., 189 FERC ¶ 61,181, at P 106 (2024), order on reh’g, 192 FERC ¶ 61,051 (2025), aff’d sub nom. PJM Transmission Owners v. FERC, Nos. 25-1064, 25-1100, 2026 U.S. App. LEXIS 16255 (D.C. Cir. June 5, 2026).18 See, e.g., PJM Interconnection, L.L.C., 178 FERC ¶ 61,104 (PJM filing to change transmission constraint penalty factor contained within the Operating Agreement so as to avoid unjust and unreasonable energy market rates for consumers on the Northern Neck peninsula in the Dominion Transmission Zone), order on reh’g, 179 FERC ¶ 61,161 (2022), aff’d sub nom. Citadel FNGE Ltd. v. FERC, 77 F.4th 842 (D.C. Cir. 2023).
PDF page 9
9
The Members’ Retention of Section 205 Filing Rights Was Heavily Negotiated and Cannot Be Set Aside Because PJM Wants Control
Nor can the Members Committee section 205 filing rights be abrogated simply because PJM wants control. The allocation of those rights, as set forth in Sections 8.8 and 10.4 of the Operating Agreement, is entitled to Mobile-Sierra protection,19 meaning that by operation of law the filing rights can only be abrogated upon a finding of “unequivocal public necessity” or “extraordinary circumstances.”20
Section 8.8 grants the Members Committee the authority to “amend any portion of this Agreement, including the Schedules hereto, or create new Schedules, and file any such amendments or new Schedules with FERC.”21 This includes Schedule 1, which governs the energy and ancillary services markets. Section 10.4 sets forth PJM’s duties and responsibilities, including “[filing] on behalf of the Members any amendments to this Agreement or the Schedules hereto, any new Schedules hereto, and mak[ing] any other regulatory filings on behalf of the Members or the LLC necessary to implement this Agreement.”22 Thus, while the Members entered into an agreement that requires PJM to run the energy markets and to submit filings under section 205, PJM can only submit those filings on behalf of the Members, not on its own behalf. The allocation of section 205 filing rights falls squarely within “contract rates” afforded Mobile-Sierra protection.23 As Atlantic City Electric Company states, public utilities may only cede their section 205 filing rights “voluntarily,” that is “by contract” under the Mobile-Sierra
19 United Gas Pipe Line Co. v. Mobile Gas Serv. Corp., 350 U.S. 332 (1956); FPC v. Sierra Pac. Power Co., 350 U.S. 348 (1956).20 Morgan Stanley Cap. Grp. Inc. v. Pub. Util. Dist. No. 1, 554 U.S. 527, 534, 551 (2008) (quoting Permian Basin Area Rate Cases, 390 U.S. 747, 822 (1968)).21 Operating Agreement, Section 8.8(ii).22 Operating Agreement, Section 10.4(xiii).23 NRG Power Mktg., LLC v. Me. PUC, 558 U.S. 165, 176 (2010).
PDF page 10
10
doctrine,24 and the Commission has approved Mobile-Sierra’s application to such allocations of filing rights between transmission owners and independent system operators across markets.25 In addition, Sections 8.8 and 10.4 are the product of arm’s-length negotiations rather than negotiations “aimed at protecting a common interest” among competitors.26 Sophisticated parties freely negotiated these terms nearly thirty years ago in order to put in place an Independent System Operator for the PJM Power Pool. From January through May 1997, transmission owners and a “large group of interested stakeholders”—including “two major independent power producers” and “two major power marketers”—“met continuously” with “the assistance of a professional facilitator” to “resolve or narrow differences” and “forge consensus where possible” on issues of “ISO governance, reliability, transmission service and the structure of the energy market.”27 The powers of the Members Committee were among those provisions where “compromise” was
achieved.28 The Supporting Companies Filing of the PJM Governing Documents stated that the “proposal to utilize sector voting” for the Members Committee “is the product of compromise with other stakeholders, even though it is not [their] preferred approach.”2924 Atl. City Elec. Co. v. FERC, 295 F.3d 1, 11 (D.C. Cir. 2002).25 See Pennsylvania-New Jersey-Maryland Interconnection, 105 FERC ¶ 61,294, at PP 32-33 (2003); PJM Interconnection, L.L.C., 108 FERC ¶ 61,318, at P 66 (2004) (finding that Mobile-Sierra application to the allocation of all filing rights between PJM and PJM Transmission Owners applies to “all transmission owner filings”); ISO New England Inc., 106 FERC ¶ 61,280, at P 127 (2004) (approving application of Mobile-Sierra to allocation of filing rights to transmission owners); Midwest Indep. Transmission Sys. Operator, Inc., 110 FERC ¶ 61,380, at PP 19, 25-26 (2005) (approving application of Mobile-Sierra to allocation of filing rights).26 PJM Interconnection, L.L.C., 142 FERC ¶ 61,214, at P 189 (2013).27 Filing of the PJM Supporting Companies, Docket Nos. ER97-3189-000, et al., Transmittal at 1-2, 6 (June 2, 1997) (Filing of PJM Governing Documents).28 Id., Transmittal at 6.29 Id., Attachment B at 3 n.1 (Compliance with Criteria for an Independent System Operator); see Pennsylvania-New Jersey-Maryland Interconnection, 81 FERC ¶ 61,257, at 62,261-70 (1997) (conditionally accepting the Supporting Companies proposal to restructure PJM as an ISO and form the PJM Operating Agreement, Transmission Owners Agreement, Tariff, and Reliability Assurance Agreement), reh’g denied, 92 FERC ¶ 61,282 (2000), modified sub nom. Atl. City Elec. Co., 295 F.3d 1.
PDF page 11
11
Moreover, while Sections 8.8 and 10.4 apply to all Members, they preserve the existing rights of public utilities and do not “delimit, qualify, or restrict”30 the ability of any other market participant. The “division of responsibility” between PJM and its Members “affect[s], predominantly[,] the contracting parties alone.”31 New Members have the same rights as the original parties. Non-market generators and transmission owners retain their individual section 205 filing rights, and all parties retain section 205 filing rights via the Members Committee, where “each major segment of the industry is assured a say” and “no one sector can force the Members Committee to act, and no one sector can block the Members Committee from acting.”32 Indeed, the Commission previously found that similar allocation of filing rights “adequately safeguarded the interests of the region as a whole.”33
Relatedly, some argue that governance structures in other RTOs/ISOs that permit the RTO/ISO to file energy and ancillary services market rule changes under section 205 should apply in PJM.34 But even if other RTOs/ISOs may have section 205 authority that PJM does not, that precedent is not binding on PJM. “The Commission has long recognized regional differences in each of the RTOs/ISOs and has specifically allowed for regional differences in RTOs’ governance structure.”35 These differences make sense given “other RTOs/ISOs have different governance structures that
30 PJM Interconnection, L.L.C., 142 FERC ¶ 61,214, at P 186.31 ISO New England Inc., 106 FERC ¶ 61,280, at P 130.32 PJM Governing Documents, Attachment B at 3.33 Midwest Indep. Transmission Sys. Operator, Inc., 110 FERC ¶ 61,380, at P 19.34 See, e.g., PJM Pre-Conference Comments at 8; Commission-Led Technical Conference on PJM Governance and Stakeholder Reforms, Docket No. AD26-7-000, at 2:25:21 - 2:27:36 (July 23, 2026), https://www.ferc.gov/news- events/events/PJM-Governance-Stakeholder-Reforms (Tech. Conf. Video) (PJM President and CEO, David Mills, discussing section 205 rights over the energy and ancillary services markets).35 Duquesne Light Co., 189 FERC ¶ 61,181, at P 108 (citing Order Nos. 1000 and 2000); see, e.g., Midcontinent Indep. Sys. Operator, Inc., 162 FERC ¶ 61,176, at P 57 (2018) (“[T]he Commission has consistently rejected a one- size-fits-all approach in the various RTOs/ISOs due, in large part, to significant differences between each region and that there can be more than one just and reasonable rate.”).
PDF page 12
12
were arrived at through negotiations and tradeoffs that balance the rights and obligations of diverse stakeholders.”36 The division of filing rights in PJM reflect the stakeholder tradeoffs that were negotiated in PJM to balance the rights and obligations among PJM stakeholders and the agreements struck among stakeholders in other regions does not reflect the PJM balance. Investor Concerns Are Likely to Rise if PJM Authority Is Increased
The Commission should refrain from fundamentally overhauling filing rights in PJM,
especially at this critical time when significant investment is needed to meet tightening system conditions; simply put, a governance overhaul that includes additional PJM filing rights could undermine investor confidence in PJM at a time when their investment is most needed. Investor confidence and willingness to invest in assets in PJM is shaped by (among other things) PJM market outcomes and expectations in the rules that shape those market outcomes into the future. Actions by PJM that are counter to competitive market results undermine investor confidence in the markets and the desire by competitors (and their owners) to invest. The bottom line is that PJM has failed to appropriately consider investor impact in exercising the section 205 authority over resource adequacy matters it already has. This is inconsistent with the Commission’s and Administration’s desire to instill investor confidence and incent new infrastructure in PJM.37 And, against this backdrop, it is particularly difficult to justify increasing PJM’s filing authority.
36 Duquesne Light Co., 189 FERC ¶ 61,181, at P 108.37 Chairman Laura Swett, Chairman Laura Swett’s Comments at PJM’s Annual Meeting in Baltimore, MD, FERC (May 12, 2026), https://www.ferc.gov/news-events/news/chairman-laura-swetts-comments-pjms-annual-meeting- baltimore-md-0 (“[W]e cannot disrupt finalized commercial agreements. At FERC, I have no appetite to compromise investor confidence when those investors are driving the buildout of the generation that PJM desperately needs.”); Tech. Conf. Video at 45:30-46:50 (the Honorable James P. Danly discussing the need to right the capacity market with immediate resolution: “We are facing demand signals like we’ve never seen before. . . . Don’t lose sight of the fact that we actually have to fix the problems that are inhibiting the biggest problem we have which is getting as much supply online as quickly as possible and doing so while protecting ratepayers. . . . PJM’s Board and as an institution needs to recommit itself to the market functions it was originally designed to oversee and execute.”), 55:40-55:52 (Peter Lake: “[I]f were gonna have a market we’ve got to let it work.”), 56:55-57:27 (Peter Lake: “[T]his is the only industry in the world that can stare in the face of trillions of dollars of expected investment and argue amongst each other so effectively as to scare off that investment.”).
PDF page 13
13
For example, in February 2025, PJM filed—without Member Committee authorization—a collar mechanism to apply in the capacity market during delivery years 2026/27 and 2027/28. PJM made this filing pursuant to existing authority to file under section 205 with respect to resource adequacy matters.38 A little over a year later, PJM filed to extend the collar to also cover the 2028/29 and 2029/30 delivery years, again filing under section 205, based on its existing authority and without Member Committee authorization.39 The signal to investors from these repeated exercises of PJM’s section 205 filing rights is that market supply/demand fundamentals cannot be counted on in PJM to support new investment; in other words, investors have learned to expect PJM to curb actual market results whenever supply becomes tight compared to demand in PJM,40 and they must factor that PJM intervention expectation when deciding whether to invest through market mechanisms. As a result, in part, of PJM’s repeated artificial reductions in capacity market prices, investors will hesitate to bring new investment through the capacity market. Indeed only 524.7 MWs of new resources entered in PJM’s most recent capacity market auction, although some of the reticence was undoubtedly caused by the knowledge that the Reliability Backstop Procurement (RBP) was around the corner.41 Instead, investors will require something more (e.g., a long-term, out-of-market contract such as those available under the RBP) before they will invest in the region, and this out-of-market contracting will be more costly in the long run compared to
38 Proposal for Revised Price Cap and Price Floor for the 2026/2027 and 2027/2028 Delivery Years of PJM Interconnection, L.L.C., Docket No. ER25-1357, at 6 (Feb. 20, 2025) (Initial Collar Filing).39 Proposal to Extend the Price Cap and Price Floor for the 2028/2029 and 2029/2030 Delivery Years of PJM Interconnection, L.L.C., Docket No. ER26-1556, at 6 (Feb. 27, 2026) (Collar Extension).40 Recent price trends in the oil industry provide a simple example of how supply/demand fundamentals would typically affect price-outcome expectations. World oil market prices have increased, as restrictions on oil shipments (i.e., supply) through the Strait of Hormuz and uncertainty related to such shipments has increased. Conversely, oil prices have decreased as shipment certainty has increased.41 2028/2029 Base Residual Auction Report, PJM Interconnection, L.L.C., 3, 7-8 (July 14, 2026), https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra-results- report.pdf.
PDF page 14
14
the market-driven approach. Given PJM’s repeated interventions in market outcomes, in order for PJM to restore market integrity and investor confidence, it will have to intentionally and consistently embrace competitive markets that reflect market fundamentals. With the current RBP proposal, Constellation is concerned that more of the inefficient out-of-market intervention likely will be required.
PJM has filed numerous other changes recently to resource adequacy market rules under its existing section 205 authority that similarly undermine market outcomes and investor confidence including: the DPL-South market rerun;42 the treatment of Brandon Shores and Wagner as price takers in capacity auctions despite not providing a Capacity Performance product;43 and PJM’s proposal to treat RBP resources as price takers.44
During the technical conference, PJM’s Senior Director of Stakeholder Affairs, David Anders, explained that when PJM was initially formed, the asset owners did not have confidence in PJM, so they intentionally kept the transmission planning and energy and ancillary services markets matters in the Operating Agreement so Members could retain oversight.45 Given PJM’s extensive market-undermining use of the section 205 authority it already has, Constellation, a significant asset owner in PJM, has little confidence in how PJM has used its existing section 205 authority
42 See PJM Power Providers Grp. v. FERC, 96 F.4th 390 (3d Cir. 2024).43 See H.A. Wagner LLC, 187 FERC ¶ 61,176 (2024), order on contested settlement, 191 FERC ¶ 61,098, order on reh’g, 192 FERC ¶ 61,189 (2025), appeal pending, Petition for Review, Maryland Office of People’s Counsel v. FERC, No. 26-1050 (D.C. Cir. Mar. 2, 2026).44 See Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads of PJM Interconnection, L.L.C., Docket No. ER26-3380-000, at 56-60, 129-30 (July 31, 2026); Limited Protest of Constellation Energy Generation, LLC, Docket No. ER26-3880-000 (Aug. 21, 2026).45 Tech. Conf. Video at 6:00:10 – 6:01:20 (David Anders PJM history discussion noting that “there was a certain level of confidence that [asset owners] didn’t have at the time” in “turning over their assets to this new fledgling organization” which led them retaining certain PJM responsibilities under the Operating Agreement so they could maintain some control over decisions affecting their assets).
PDF page 15
15
and does not support an expansion of PJM’s filing authority. The Commission should be similarly concerned.
12. Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?
No. See our response to Question 11.
13. Should PJM have section 205 filing rights over Regional Transmission Expansion Planning (RTEP) unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?
No. See our response to Question 11. However, Constellation acknowledges that extending section 205 filing rights to PJM for non-market matters raises issues that are different than filing rights over market matters.
14. Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal?
No. States and organizations representing state interests seeking changes to PJM’s Tariff, market rules, or other governing documents have long-established rights to pursue such changes under the FPA,46 and state entities have proven well-capable of exercising these rights.47 However, it would be inconsistent with the FPA for the states to have such rights, jump ball or otherwise.48 In addition, as elaborated above in response to Question 11, even if some RTO/ISO allows a jump ball right for certain membership organizations, those RTO/ISO rules are not dispositive for PJM.
46 16 U.S.C. § 824e.47 See, e.g., PJM Interconnection, L.L.C., 191 FERC ¶ 61,066 (2025) (Governor Josh Shapiro and the Commonwealth of Pennsylvania price cap complaint that led PJM to submit its section 205 price collar filing); Indep. Mkt. Monitor for PJM v. PJM Interconnection, L.L.C., 174 FERC ¶ 61,212 (2021), order on reh’g, 178 FERC ¶ 61,121 (2022) (granting consolidated complaints filed by several PJM state consumer organizations and denying rehearing thereof), aff’d sub nom. Vistra Corp. v. FERC, 80 F.4th 302 (D.C. Cir. 2023).48 See Joseph Kelliher, States Cannot Be Granted Filing Rights Under Section 205 of the Federal Power Act, Utility Dive (July 27, 2026), https://www.utilitydive.com/news/states-ferc-filing-rights-section-205-pjm/826170/; 16 U.S.C. § 824d.
PDF page 16
16
15. Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal?
No. Constellation supports retention of existing rights rather than the addition of “jump ball” rights. In addition, as elaborated above in response to Question 11, even if some RTO/ISO allows a jump ball right for certain membership organizations those RTO/ISO rules are not dispositive for PJM.
B. Stakeholder Process
16. Should the approval threshold in the Members Committee be lowered from two-thirds sector-weighted voting?
Yes. If the PJM Members Committee agrees to such a change, reducing the voting threshold to a majority vote could support the Commission’s goal of facilitating section 205 filings without upending PJM’s existing governance structure as some have suggested.
17. Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees?
No. Affiliate voting is an important component for balancing interests within the PJM voting structure. Discussion at the lower level committees—where affiliate voting is relied on—are usually more technical and detailed in nature and having the diversity of interests makes for a more robust vetting of issues. At the senior level committees (Markets and Reliability and Members Committees) each Member has only one vote, consolidating the interests to the primary voting member on matters that have already been largely shaped at the lower committee.
C. State Participation
18. In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state legislators’ representatives?
Yes. However, Constellation sees two potential approaches for enhancing governor representation: (1) the “right-sizing” of OPSI, including increased staffing levels so it can cover
PDF page 17
17
its existing constituents as well as an OPSI-enhanced role in representing governors’ and legislators’ interests; or (2) creating and funding a separate entity representing PJM governors and legislators.
In addition to providing these additional resources, protocols should be established for PJM to meet regularly with state commissioners and/or commission staff to seek input on important market and transmission issues, rule changes, and other concerns, including both staff-to-staff and leadership-to-leadership meetings. Also, clear processes for state commissions to request and receive technical information and support on matters related to wholesale markets and/or infrastructure planning and their interactions with state regulation and retail rates should be established.
19. Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes?
No. Consumer interests are already represented through the state-designated consumer advocates. The relationship between state commissions and PJM was developed in a 2005 Memorandum of Understanding between PJM and OPSI which stated that while commissioners and their staff participate, deliberate, give input, and engage at all levels of the PJM stakeholder process they do not vote on any issue.49 Since then, state commissions and representatives have participated in the stakeholder process and have done so very effectively. For example, the current Variable Resource Requirement curve that was endorsed by Members and approved by the Commission was based on a joint proposal between PJM and the office of the Vice Chair of the
49 Memorandum of Understanding Between PJM Interconnection, L.L.C. and the Organization of PJM States, Inc., PJM Interconnection, L.L.C. (June 1, 2005), https://www.pjm.com/-/media/DotCom/documents/agreements/opsi- pjm-memorandum.ashx.
PDF page 18
18
Pennsylvania Public Utilities Commission,50 and at OPSI’s request, PJM facilitated the Clean Attribute Procurement Senior Task Force in 2022 and 2023.51
States are sovereign regulators and policy makers with the ability to make policy decisions that are outside of PJM jurisdiction. That said, states can and have played an important, non-voting, role in the PJM stakeholder process; including, for example, the initiation of the Sub-Annual Capacity Market Senior Task Force, spearheaded by the office of Pennsylvania Governor Josh Shapiro.52 In addition, state commissions and representatives have a variety of opportunities to interact with PJM staff and the PJM Board that are not available to voting Members, some of which are discussed in the 2005 Memorandum of Understanding. To the extent that those opportunities need to be enhanced or expanded, such as assigning a PJM Board member to act as a liaison with each state, Constellation welcomes further discussion on this matter. However, providing the states with an additional voting role at PJM would elevate their status compared to existing PJM voting Members, including the state consumer advocates who have a critical role in representing retail ratepayers. Amending the Operating Agreement to include state commissions or representatives undermines that current, balanced governing structure at PJM that ensures that no Member has undue influence while recognizing and supporting the state’s important, non-voting role in the PJM stakeholder process and community.
50 See 2025 Periodic Review of Variable Resource Requirement Curve Shape and Key Parameters of PJM Interconnection, L.L.C., Docket No. ER26-455-000, at 7-8 (Nov. 7, 2025) (describing the Joint PJM/PA Public Utility Commission, Vice Chair Barrow proposal that received super-majority support from stakeholders and was adopted by the PJM Board without modification), accepted by PJM Interconnection, L.L.C., 194 FERC ¶ 61,049, on reh’g, 196 FERC ¶ 61,007 (2026). 51 Clean Attribute Procurement Senior Task Force, PJM Interconnection, L.L.C., https://www.pjm.com/committees- and-groups/closed-groups/capstf.52 Sub-Annual Capacity Market Senior Task Force, PJM Interconnection, L.L.C., https://www.pjm.com/committees- and-groups/task-forces/sacmstf (originating from Issue Charge, PJM Interconnection, L.L.C. (July 16, 2025), https://www.pjm.com/-/media/DotCom/committees-groups/committees/mrc/2025/20250723/20250723-item-05---3- revised-sub-annual-auction-issue-charge---clean.pdf).
PDF page 19
19
20. Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation?
No. Such a consultation could give OPSI undue influence over PJM and thereby undermine PJM independence.53
III. CONCLUSION
Constellation appreciates the Commission’s leadership in addressing potential governance reforms and looks forward to participating in further discussion during the Dispute Resolution Proceeding this September. As discussed above, investor confidence in PJM has never been more critical. As the Commission considers potential reforms, it is imperative that such reforms improve, not weaken, confidence in PJM’s markets when significant investment is needed to meet tightening system conditions.
Respectfully submitted,
/s/ Christopher A. Wilson
Carrie Hill Allen
Sr. Vice President & Deputy General
Counsel
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
carrie.allen@constellation.com
Sara Gordon
Manager, Federal Regulatory Affairs
Constellation Energy Generation, LLC
1310 Point Street
Baltimore, MD 21231
sara.gordon@constellation.com
Christopher A. Wilson
Vice President, Federal Regulatory Affairs
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
FERCe-filings1@constellation.com
Michael P. McLaughlin
Director, Federal Regulatory Affairs
Constellation Energy Generation, LLC
1310 Point Street
Baltimore, MD 21231
FERCe-filings1@constellation.com
Dated: August 21, 2026
53 See PJM Transmission Owners, 2026 U.S. App. LEXIS 16255, at *13-14 (proposed transmission owner right to arbitrate PJM’s proposed section 205 filings “was not just and reasonable because it diminished PJM’s independence” and “gives the Transmission Owners undue influence over Tariff modifications”).
PDF page 20
APPENDIX
PJM GOVERNANCE SETTLEMENT FRAMEWORK
1. PJM Board
a. Board Seat Duration
i. Extend Board member term to five years, with two full terms (plus any time served replacing an early-exiting Board member) possible; and
ii. Offer current Board the opportunity to extend their term to a five-year term, still ensuring terms are staggered.
b. Board Member Qualifications—(Operating Agreement, Section 7.2)1—New requirements that:
i. One member to reside within PJM – conforming changes within Operating Agreement Section 7.2 may be required to implement this change, including potentially shortening the two-year “stay-out” so as to increase the Board member applicant pool; and
ii. One member has energy regulatory experience.
c. Increased Transparency in Board Determinations – Board to provide a written explanation supporting its decisions and how the decision will achieve a just, reasonable and not unduly discriminatory or preferential outcome along with an explanation for why it rejected other views.
d. Nominating Committee Role (Operating Agreement, Section 7.1) – states to make their views known about potential Board members by developing a list of suggested nominees, perhaps through OPSI or through the formation of nomination advisory group consisting of state-designated representatives.
2. State Focused Reforms
a. OPSI “Right-Sizing”
i. OPSI funding/staffing levels to be increased so OPSI can effectively represent states at PJM and in stakeholder processes.
ii. Governors’ interests to also be represented under the OPSI “umbrella” or alternatively to establish a stand-alone organization to facilitate participation by state elected officials.
b. PJM/OPSI Engagement Protocols
i. Establish protocols for meeting regularly with state commissioners and/or commission staff to seek input on important market and transmission issues, rule changes, and other concerns, including both staff-to-staff and leadership-to-leadership meetings.
1 See PJM Board Member Qualifications Matrix, https://www.pjm.com/-/media/DotCom/committees- groups/committees/nc/postings/nc-board-member-qualifications-oa-section-7-2.pdf.
PDF page 21
2
ii. Establish a clear process for state commissions to request and receive technical information and support on matters related to wholesale markets and/or infrastructure planning and their interactions with state regulation and retail rates.
c. State/Board Member Communications – Each state commission to have a Board member assigned for periodic conversations on state priorities and other pressing PJM matters.
PDF page 22
CERTIFICATE OF SERVICE
I hereby certify that I have on this 21st day of August 2026 served a copy of the foregoing upon all parties on the service list in this proceeding in accordance with Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010.
/s/ Sara Gordon
Constellation Energy Generation, LLC