AD26-7-000 · 2026-08-21 · Constellation Energy Generation, LLC

Post-Conference Statement of Constellation Energy Generation, LLC addressing issues raised at the Commissioner-led technical conference held on 07/23/2026…

Text extracted from the eLibrary original (SHA-256 22be024ef2d91a4d…). Download the original from the official source.

Contents · 6 sections
  1. I. INTRODUCTION AND SUMMARY p. 1
  2. II. QUESTION RESPONSES p. 2
  3. A. PJM Board Independence p. 2
  4. B. Stakeholder Process p. 16
  5. C. State Participation p. 16
  6. III. CONCLUSION p. 19

Read topic-matched comments in AD26-7

Topics in the text: Reliability and curtailment · Cost allocation · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) PJM Governance and Stakeholder Reforms ) ) Docket No.
Read this passage

I. INTRODUCTION AND SUMMARY

printed heading · Topic match: Reliability and curtailment

Most of the unrest in PJM over the last decade has involved issues related to resource adequacy, generator retirements and replacements, and capacity market rules changes—matters over which PJM already has section 205 filing rights and is able to take action 1 PJM Governance and Stakeholder…
Read this passage Filed comments: Reliability and curtailment

II. QUESTION RESPONSES

printed heading

II.
Read this passage

A. PJM Board Independence

printed heading · Topic match: Reliability and curtailment

Having a one-member residency requirement is consistent with other Board membership qualification quantities in Section 7.2 of the Operating Agreement that can be satisfied with one qualified member (e.g., “one [member] shall have expertise and experience in the operation or concerns of…
Read this passage Filed comments: Reliability and curtailment

B. Stakeholder Process

printed heading

Should the approval threshold in the Members Committee be lowered from two-thirds sector-weighted voting?
Read this passage

C. State Participation

printed heading · Topic match: Cost allocation

Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes?
Read this passage Filed comments: Cost allocation

III. CONCLUSION

printed heading

CONCLUSION Constellation appreciates the Commission’s leadership in addressing potential governance reforms and looks forward to participating in further discussion during the Dispute Resolution Proceeding this September.
Read this passage

CERTIFICATE OF SERVICE

printed heading

CERTIFICATE OF SERVICE I hereby certify that I have on this 21st day of August 2026 served a copy of the foregoing upon all parties on the service list in this proceeding in accordance with Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010. /s/ Sara Gordon…
Read this passage