ER26-3380-000 · 2026-08-21 · NRG Business Marketing LLCAspen Gen Funding, LLCDirect Energy Business, LLC and 15 others

Limited Protest of the NRG Companies re PJM Interconnection, L.L.C.’s 07/31/2026 filing proposing a Reliability Backstop Procurement

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3380-000
LIMITED PROTEST OF THE NRG COMPANIES
Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (the “Commission”)1 and in accordance with the Commission’s notice issued August 3, 2026,2 the NRG Companies3 hereby submit this limited protest to the July 31, 2026, filing by PJM Interconnection, L.L.C. (“PJM”)4 proposing a Reliability Backstop Procurement (the “RBP”), a one-time procurement of new capacity to cover shortfalls in the Base Residual Auctions for the 2027/2028 Delivery Year (the “2027/2028 BRA”) and 2028/2029 Delivery Year (the “2028/2029 BRA”).5  The NRG Companies are supportive of the RBP concept and are filing this limited protest with respect to two discrete and severable elements of the July 31 Filing that are not just and reasonable and should be modified.  For the reasons set forth herein and

1 18 C.F.R. § 385.211 (2025). 2 Combined Notice of Filings #1, Docket Nos. EC26-106-000, et al. (Aug. 3, 2026) (unreported).
3 The NRG Companies include the following subsidiaries of NRG Energy, Inc. (“NRG”): NRG Business Marketing LLC, Aspen Gen Funding, LLC, Direct Energy Business, LLC, Doswell Limited Partnership, Energy Plus Holdings LLC, Enerwise Global Technologies, LLC dba CPower, Green Mountain Energy Company, Helix Ironwood, LLC, Independence Energy Group LLC, LSP University Park, LLC, Midwest Generation LLC, NRG Curtailment Solutions, Inc., Reliant Energy Northeast LLC, Riverside Generating Company, LLC, Stream Energy Pennsylvania, LLC, University Park Energy, LLC and XOOM Energy, LLC.  The NRG Companies have separately moved to intervene in this proceeding. See (doc-less) Motion to Intervene of NRG Business Marketing LLC, et al., Docket No. ER26-3380-000 (filed Aug. 21, 2026).
4 Capitalized terms not defined herein have the meaning set forth in PJM’s Open Access Transmission Tariff (the “PJM Tariff”) or the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region (the “RAA”).
5 Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads, Docket No. ER26-3380-000 (July 31, 2026) (the “July 31 Filing”).

PDF page 2

2
in the affidavit of John R. Morris, Ph.D., provided in Attachment A hereto (the “Morris Affidavit”) and the affidavit of Thomas E. Atkins provided in Attachment B hereto (the “Atkins Affidavit”), the NRG Companies respectfully urge the Commission to accept the July 31 Filing subject to the modifications proposed herein.

I.

BACKGROUND
As indicated in the July 31 Filing, both the 2027/2028 BRA and the 2028/2029 BRA cleared at the market price cap of $325/MW-day and over 6 GW short of the applicable PJM Regional Reliability Requirement.6  In the July 31 Filing, PJM proposes the RBP to procure capacity outside the Reliability Pricing Model (“RPM”) construct to a target based on the shortfall in the 2028/2029 BRA for commitment periods of up to 15 years ending, in all cases, with the 2042/2043 Delivery Year.7  PJM describes the RBP as “a critical safety net designed to address current resource adequacy shortfalls”8 and explains that the 15-year term is informed by the statement of principles agreed between and among governors of PJM states and the National Energy Dominance Council,9 “which seeks ‘[r]evenue [c]ertainty to [n]ew [g]eneration’ through ‘15-year price certainty for new capacity resources.’”10

6 See id., Transmittal Letter at 7-8.
7 See id. at 8.
8 Id. at 26.
9 D. Burgum, et al., Statement of Principles Regarding PJM (Jan. 15, 2026) (“Statement of Principles”), https://www.energy.gov/documents/statement-principles-regarding-pjm. 10 July 31 Filing, Transmittal Letter at 48 (alteration in original) (quoting Statement of Principles at 1).

PDF page 3

3
The RBP will be a pay-as-bid auction conducted for three weeks following Commission acceptance of the July 31 Filing.11  PJM proposes a soft cap, or “maximum willingness to pay,”12 of $555/MW-day applied to all selected offers on a MW-weighted average basis over all Delivery Years of the RBP.13  This figure represents the cap that would have applied under the Variable Resource Requirement (“VRR”) curve for the 2028/2029 BRA but for the separate price collar.14 RBP commitments will be settled as contracts-for-differences with the seller’s offer price as the strike price and the RPM Auction clearing price as the market price.15  Subject to a narrow exception, a supplier with an RBP commitment is required to submit price-taker offers into RPM Auctions for the Delivery Years covered by its RBP commitment.16  PJM states that this requirement is meant to ensure that “load does not double pay for capacity.”17

II.

PROTEST
As noted, the NRG Companies generally support PJM’s RBP proposal as a necessary “stop- gap solution[]”18 to fill the reliability gap.  Nonetheless, there are two elements of that proposal that are not just and reasonable and that must be modified to ensure that the RBP serves its intended purpose and does not create further market distortions that will, in turn, necessitate further one-off solutions.  First, the soft cap is set at a level that does not adequately reflect current costs of adding

11 See id. at 65. 12 Id. at 61.
13 See id.
14 See id. at 62.
15 See id. at 79-80.
16 See id. at 56.
17 Id. at 57. 18 Id. at 5.

PDF page 4

4
new resources to the system and that will, therefore, greatly increase the risk that the RBP fails to fulfill its role as “a critical safety net designed to address current resource adequacy shortfalls.”19 Second, the price-taker requirement for offers into RPM Auctions from resources with RBP commitments should be eliminated, and an offer floor should be imposed if and to the extent that the associated load does not materialize in order to prevent systematic price distortion. Importantly, the proposed modifications do not present concerns under NRG Power Marketing, LLC v. FERC,20 because PJM has “consent[ed] to the Commission’s exercise of authority to modify and/or sever any element of the proposed [PJM] Tariff and RAA language . . . [,] where such modification and/or severance is consistent with PJM’s overarching objectives in this filing.”21  As PJM notes, the July 31 Filing “is not a stakeholder compromise package,”22 so these modifications will not upset the terms of a proposal that was “the subject of extensive negotiation and compromise among PJM’s stakeholders.”23  And the NRG Companies’ proposed modifications, while important, are “minor deviations” from PJM’s proposal,24 that will not have the Commission “transform[ing] [PJM’s] proposal into an entirely new rate of FERC’s own making.”25

19 Id. at 26.
20 862 F.3d 108 (D.C. Cir. 2017) (“NRG-PML”).
21 July 31 Filing, Transmittal Letter at 3. 22 Id. at 132.
23 Hecate Energy LLC v. FERC, 126 F.4th 660, 667 (D.C. Cir. 2025).
24 NRG-PML, 862 F.3d at 115 (quoting Western Res., Inc. v. FERC, 9 F.3d 1568, 1579 (D.C. Cir. 1993)).
25 Id. at 110.  See also City of Winnfield v. FERC, 744 F.2d 871, 875-76 (D.C. Cir. 1984) (suggesting that a utility acquiescing to a Commission proposal that “involved the Commission’s own original notion of a new form of rate” could “remove[] the Commission from an essentially passive and reactive role envisioned by § 205 and place[] it in a more active role of the sort it occupies under § 206”).

PDF page 5

5
PJM requests that if the Commission requires modifications, it “expressly prescribe the revised rate or rule in its order.”26  In keeping with that request, the NRG Companies have proposed specific modifications to the RBP proposal that the Commission could expressly prescribe as conditions to its acceptance of the July 31 Filing.

A. Any Soft Cap Should Be Set at a Level Reflecting Current Costs of Resources Whose Capacity Could Be Procured through the RBP

PJM fails to carry its burden to demonstrate that setting the RBP soft cap at $555/MW-day is just and reasonable.  PJM asserts that its “proposal to limit the maximum willingness to pay is necessary,” because “[t]he RBP is not disciplined by direct buy bids that explicitly express willingness to pay.”27  According to PJM, “it is not reasonable to assume that load should be obligated to pay an unlimited amount for supply.”28  The $555/MW-hour figure was calculated based on outdated estimates of the cost of new entry (“CONE”) and the energy and ancillary services revenues for the reference combustion turbine (“CT”) in PJM’s most recent quadrennial review.  As such, it is not representative of the current CONE for such a unit, much less of the costs of other resources whose capacity could be procured through the RBP, including resources whose technology or circumstances do not match those of the reference CT.

As an initial matter, while the NRG Companies understand the “consumer protection considerations”29 that have prompted PJM’s decision to impose a cap, it bears emphasis that the Commission’s statutory mission under the Federal Power Act is not just to protect consumers from

26 July 31 Filing, Transmittal Letter at 131.
27 Id. at 63.  The suggestion that PJM’s proposed soft cap represents load’s “willingness to pay,” id., is, at best, dubious.  The soft cap was not calculated based on any value of lost load study or other analysis intended to assess load’s actual willingness to pay for capacity being procured through the RBP.  See Morris Affidavit at ¶ 12.  Rather, it would simply be an administratively determined limit on what PJM will pay.
28 July 31 Filing, Attachment C, Affidavit of Danielle Croop on Behalf of PJM Interconnection, L.L.C. at ¶ 26 (the “Croop Affidavit”).
29 Id., Transmittal Letter at 62.

PDF page 6

6
excessive rates but “to encourage the orderly development of plentiful supplies of electricity . . . at reasonable prices.”30  As Dr. Morris observes, running the RBP with any cap necessarily increases the risk that the RBP will clear short, because if the cap binds, PJM will not procure the full RBP target.31  As he puts it, the assumption implicit in the soft cap proposal is that “it is just and reasonable to sacrifice reliability in exchange for lower RBP Prices.”32  With the last two BRAs having failed to procure adequate, much less plentiful, supplies of capacity, the NRG Companies do not believe such a sacrifice is justified, particularly when, as Dr. Morris notes, “[m]arket power is not a concern with the prices in the [RBP].”33  The top priority here should be allowing the RBP to fulfill its purpose of covering the shortfall.

Further, the assumed tradeoff between reliability and cost does not exist.  It is true that the cap, if it binds, will sacrifice reliability for lower RBP prices.  But, as Dr. Morris explains, the interplay between the RBP and the RPM Auctions is such that, over time, consumers will have sacrificed reliability in exchange for higher, not lower, prices overall.34  If the soft cap binds and the RBP clears short, there will be less capacity available for future RPM Auctions (or other capacity constructs to incent current capacity to stay in the market), which will increase the single clearing prices paid to all capacity cleared in those auctions.35  Dr. Morris observes that the increased costs resulting from higher clearing prices in those future RPM Auctions – which will

30 NAACP v. FPC, 425 U.S. 662, 670 (1976).
31 See Morris Affidavit at ¶ 10.
32 Id. at ¶ 13. 33 Id. at ¶ 23.
34 See id. at ¶ 14.
35 See id. at ¶ 16.

PDF page 7

7
impact all consumers, not just the large loads for which the RBP is meant to procure capacity – are likely to dwarf the added cost of acquiring more capacity through the RBP.36

Even assuming arguendo that some cap is appropriate, PJM fails to explain why a soft cap based on CONE for the reference CT in the last quadrennial review is a just and reasonable level for this soft cap.  The best it can offer is that the longer commitment term provides benefits to suppliers such that “it is reasonable to conclude that PJM’s willingness to pay for a 15-year commitment should not exceed the amount that load would be willing to pay for a single-year commitment under the RPM framework for the targeted Delivery Year.”37  But the RBP is not a BRA.  A BRA is a single clearing-price auction for a uniform commodity with a downward sloping demand curve designed to send price signals “guiding resource entry and exit.”38  In contrast, the RBP is a one-time, pay-as-bid auction being conducted solely for the purpose of procuring enough new capacity to cover the shortfall from the last two BRAs.39  Indeed, PJM itself highlights the distinct nature of the RBP, including the fact that it is “not . . . procuring a uniform commodity”40 and that it has no “‘marginal unit’ in any meaningful sense of the term . . . .”41 The NRG Companies do not disagree with the implicit assumption that, all other things being equal, a supplier should be willing to accept a lower price for a commitment of up to 15 years than it would be for the one-year commitment obtained through an RPM Auction.  The

36 See id.
37 July 31 Filing, Transmittal Letter at 64.
38 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 at 70 (2025). 39 See July 31 Filing, Transmittal Letter at 25-26 (“The RBP is designed to be a one-time mechanism for procuring new capacity (i.e., UCAP MW only) to address the PJM Region shortfall observed in the BRA for the 2027/2028 and 2028/2029 Delivery Years caused by the rapid load growth in the PJM Region.”).
40 Id. at 65.
41 Id. at 66.

PDF page 8

8
problem is that, as is often the case, all other things are not equal.  There are a number of material risks concerning both the costs associated of new construction as well as the risks and costs of providing service out 15 Delivery Years, including, but not limited to, indeterminate network upgrade costs that may be allocated to a new project, costs and risks associated with uncertainty about potential changes in Effective Load Carrying Capability, fuel delivery costs, and energy and ancillary services prices.  Indeed, Dr. Morris explains that the $450/MW-day energy and ancillary services offset underlying the $555/MW-day soft cap exacerbates the risk surrounding future energy and ancillary services prices, as this level is substantially higher than past offsets and the average of the offsets over the previous nine BRAs, which would be $225.49/MW-day.42 There is no logical reason why the prices paid to individual suppliers in the RBP should be subject to a cap based on CONE for a CT when the capacity shortfall could be covered with any number of resources, including resources using different technologies or having other characteristics that cause their costs to significantly exceed those of the reference CT.  None of that variation is captured in the price of the reference CT, which is only “a representative, theoretical new plant.”43  As the Commission has observed, a “reference unit is hypothetical, and the actual new entrant may be different . . . .”44  That the costs of new entry can vary dramatically based on technology and location is illustrated by the range of default MOPR Offer Floor Prices

42 See Morris Affidavit at ¶ 21.
43 PJM Interconnection, L.L.C., 194 FERC ¶ 61,049 at P 2 (the “Quadrennial Order”), on reh’g, 196 FERC ¶ 61,007 (2026).
44 ISO New England Inc., 175 FERC ¶ 61,172 at P 127 (2021).

PDF page 9

9
for the 2028/2029 BRA, which ranged from $68.69/MW-day (UCAP) for a CT in the APS zone to $3,135.04/MW-day (UCAP) for a solar project in the PECO zone.45

NRG’s real-world experience confirms that actual costs can and do differ significantly from the $555/MW-day calculated based on the reference CT’s CONE.  Mr. Atkins, NRG’s Vice President of Development, explains that NRG has several development projects that are sufficiently advanced to participate in the RBP.  One of these projects, which would be located in a historically import-constrained zone and would provide significant locational benefits, has costs, net of expected energy and ancillary services revenues, that are substantially greater than the current proposed cap.46  Given the costs and size of this project, it would be hard to justify the time and expense of even offering it into the RBP if it is conducted with a soft cap of $555/MW-day.47 Finally, even as a measure of the reference CT’s CONE, the CONE value underlying the $555/MW-day is outdated. As PJM has recognized, “capital costs have escalated sharply” in recent years.48  The $555/MW-day cap is based on a gross CONE estimate of $776/MW-day calculated in a CONE study concluded over a year ago.49  As Dr. Morris and Mr. Atkins observe, capital costs have continued to escalate sharply since that time.50

45 See PJM, Default New Entry MOPR Offer Prices (Mar. 16, 2026), https://www.pjm.com/-/media/ DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-default-new-entry-mopr-offer-prices. xlsx.
46 See Atkins Affidavit at ¶ 16.
47 See id.
48 PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and Stimulating Investment To Support Durable Reliability at 4 (May 6, 2026) (“Powering Reliability”), https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/2026 0506-powering-reliability-through-market-design.pdf.
49 See 2025 Periodic Review of Variable Resource Requirement Curve Shape and Key Parameters at 5-7, Docket No. ER26-455-000 (filed Nov. 7, 2025) (discussing the CONE study process), accepted, Quadrennial Order, 194 FERC ¶ 61,049.
50 See Morris Affidavit at ¶¶ 18-19; Atkins Affidavit at ¶¶ 13-15.

PDF page 10

10
If the Commission is not going to eliminate the soft cap, the NRG Companies would urge the Commission to reset it at a level reflecting a more current estimate of the reference CT’s CONE and an energy and ancillary services offset that better accounts for the risks around future energy and ancillary services prices.  Dr. Morris calculated such a cap price using an updated CONE of $900/MW-day51 and the average of the energy and ancillary services offsets for the nine BRAs prior to the 2028/2029 BRA ($225/MW-day).52  This calculation yields a soft cap of $866/MW- day.53  If the RBP is going to be run with a soft cap, the NRG Companies urge that the soft cap be reset at $866/MW-day, which will reduce the risk that the RBP clears short.

B. The Commission Should Impose a Price Floor on Offers for Resources with RBP
Commitments to the Extent the Load Prompting the RBP Does Not Materialize
As Dr. Morris explains, the proposed requirement that resources with RBP commitments offer as price-takers into RPM Auctions for the associated Delivery Years “is antithetical to creating a normal capacity market.”54  PJM itself has recognized the “credibility trap” where “[t]he signal that is required to attract investment is the same signal that triggers the intervention that undermines it.”55  After interventions that produced “unsustainably low price levels for three delivery years,”56 Dr. Morris states, “the market is waiting for PJM – and implicitly, the Commission – to make credible moves that they will not allow capacity prices to crash to levels that make new investments likely unprofitable over the life of the assets.”57  In this environment,

51 See Morris Affidavit at ¶ 19.
52 See id. at ¶¶ 21-22.
53 See id. at ¶ 22.
54 See id. at ¶ 25.
55 Powering Reliability at 24. 56 Morris Affidavit at ¶ 29.
57 Id. at ¶ 31.

PDF page 11

11
the price-taker offer requirement “send[s] the wrong signals [to] potential investors of PJM generation capacity.”58

To be clear, a requirement that resources with RBP commitments offer as price-takers is not necessary to ensure that load does not pay twice for the same capacity.  Dr. Morris describes an alternative approach that would achieve the same result without such a requirement.59  Under this approach, commitments would be structured so that any RBP capacity that does not clear in an RPM Auction has its strike price reset to zero for that RPM Auction and all future RPM Auctions for the remainder of the commitment period.60  The RBP supplier would have a compelling incentive to ensure that its capacity clears the RPM Auctions, but it would still be a voluntary choice.61

Even if the price-taker offer requirement is retained, the Commission should direct PJM to establish a narrow exception to this requirement that would apply when the forecasted load for which PJM is procuring through the RBP does not materialize.  In the July 31 Filing, PJM proposed measures to protect load in the event new capacity procured through the RBP does not materialize62 and to protect cooperatives and municipal utilities “if a particular large load included in the forecast were to fail to materialize.”63  What is missing is any comparable measure to preserve the integrity of future RPM Auctions if the forecasted large load does not materialize.  The Commission should direct PJM to impose an offer floor on RBP resources if and to the extent the forecasted large loads

58 Id.
59 See id. at ¶ 27.
60 See id.
61 See id.
62 See July 31 Filing, Transmittal Letter at 60-61.
63 Id. at 45.

PDF page 12

12
necessitating the RBP do not actually appear.  The NRG Companies propose that such a floor be set at $175/MW-day (UCAP), which was the floor price applied as part of the price collar in the RPM Auctions for the 2026/2027, 2027/2028, 2028/2029 and 2029/2030 Delivery Years.64 As noted above, PJM has proposed that resources with RBP commitments be required to submit price-taker offers (i.e., offers priced at $0/MW-day) into RPM Auctions for the Delivery Years of their RBP commitments in order to “ensure[] that load does not double pay for capacity.”65 If the forecasted load for which the RBP is procuring capacity materializes as expected, the price- taker offer requirement will approximate the outcome in which both the RBP load and RBP supply are excluded from future RPM Auctions.  If the large loads do not materialize, however, the price- taker offer requirement will depress prices in the RPM Auctions, and this “stop-gap solution[]”66 to the shortfall in two BRAs could be another in a series of interventions that undermine the viability of PJM’s capacity market.  To prevent such an outcome, the NRG Companies propose that an offer floor of $175/MW-day (UCAP) apply to offers from resources with RBP commitments equal to the forecasted load does not materialize, if and to the extent such a situation occurs.  While a floor set at each resource’s actual cost, which would likely be higher than $175/MW-day, would also be justifiable, the NRG Companies propose using the previously accepted $175/MW-day for the sake of simplicity and uniformity.

64 See PJM Interconnection, L.L.C., 191 FERC ¶ 61,066 (“PJM I”) (accepting price collar, including $175/MW-day (ICAP) price floor, for the RPM Auctions for the 2026/2027 and 2027/2028 Delivery Years), on reh’g, 192 FERC ¶ 61,258 (2025) (“PJM II”); PJM Interconnection, L.L.C., 195 FERC ¶ 61,076 (2026) (“PJM III”) (accepting price collar, including $175/MW-day (ICAP) price floor, for the RPM Auctions for the 2028/2029 and 2029/2030 Delivery Years).
65 July 31 Filing, Transmittal Letter at 57. 66 Id. at 5.

PDF page 13

13
In accepting $175/MW-day (UCAP) as part of the price collar, the Commission found that it “reasonably narrows potential auction outcomes to maintain investor confidence.”67  The Commission also agreed with PJM that the price floor “help[ed] to broadly assure investors in capacity supply that in cases where PJM finds it appropriate to intervene in its capacity market in extraordinary circumstances, those interventions will not be one-sided.”68  That is, the price floor makes clear that, “in extraordinary circumstances like these, PJM will not leave investors disproportionately exposed to the downside risk of lower market prices and reduced capacity revenues.”69  By its terms, the RBP is an extraordinary intervention:  it is a “one-time, supplementary mechanism to procure additional supply to meet the resource adequacy needs of the PJM Region”70 outside the RPM construct.  With multiple gigawatts of resources being awarded commitments of up to 15 years and being required to be offered on a price-taker basis for the duration of those commitments, investors will naturally be concerned about the potential impact that this intervention will have on clearing prices in future RPM Auctions if the “unprecedented addition of large loads . . . in the PJM Region”71 does not actually come to pass and need assurance that this “intervention[] will not be one-sided.”72  The proposed offer floor would provide such assurance, will have limited applicability (i.e., only in a volume equal to the foregone load), and will apply to a quantity no greater than that procured in the RBP.

67 PJM I, 191 FERC ¶ 61,066 at P 55.  See also PJM III, 195 FERC ¶ 61,076 at P 51 (finding extension of the price collar appropriate “to narrow the range of potential price outcomes”).
68 PJM II, 192 FERC ¶ 61,258 at P 31.
69 Id.
70 July 31 Filing, Transmittal Letter at 7.
71 Id. at 1.
72 PJM II, 192 FERC ¶ 61,258 at P 31.

PDF page 14

14
III.

CONCLUSION
For the reasons set forth herein, the NRG Companies respectfully request that the Commission condition its acceptance of the July 31 Filing on the modifications proposed herein. Respectfully submitted,

NRG BUSINESS MARKETING LLC
ASPEN GEN FUNDING, LLC
DIRECT ENERGY BUSINESS, LLC
DOSWELL, LLC
ENERGY PLUS HOLDINGS LLC
ENERWISE GLOBAL TECHNOLOGIES, LLC DBA CPOWER
GREEN MOUNTAIN ENERGY COMPANY
HELIX IRONWOOD, LLC
INDEPENDENCE ENERGY GROUP LLC
LSP UNIVERSITY PARK, LLC
MIDWEST GENERATION LLC
NRG CURTAILMENT SOLUTIONS, INC.
RELIANT ENERGY NORTHEAST LLC
RIVERSIDE GENERATING COMPANY, LLC
STREAM ENERGY PENNSYLVANIA, LLC
UNIVERSITY PARK ENERGY, LLC
XOOM ENERGY, LLC
By:
  /s/ David G. Tewksbury

David G. Tewksbury
Stephanie S. Lim
MCDERMOTT WILL & SCHULTE LLP
The McDermott Building
500 North Capitol St., NW
Washington, DC  20001
Cortney Madea Slager
Vice President & Assistant General Counsel
Jennifer S. Hsia
Assistant General Counsel
Brianna Anderson
Regulatory Counsel
NRG Energy, Inc.
804 Carnegie Center
Princeton, NJ  08540
Counsel for the NRG Companies
Dated:  August 21, 2026

PDF page 15

CERTIFICATE OF SERVICE
I hereby certify that I have this day caused the foregoing document to be served upon each person designated on the official service list compiled by the Secretary of the Federal Energy Regulatory Commission in this proceeding.

Dated at Washington, D.C., this 21st day of August 2026.
  /s/ David Tewksbury

David G. Tewksbury

PDF page 16

Attachment A
The Morris Affidavit

PDF page 17

Attachment A

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
DOCKET NO. ER26-3380-000

ON BEHALF OF

NRG ENERGY, INC.

August 21, 2026

AFFIDAVIT OF
JOHN R. MORRIS

PDF page 18

Attachment A

Page 2 of 17

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
DOCKET NO. ER26-3380-000

AFFIDAVIT
OF
JOHN R. MORRIS

1. My name is John R. Morris, and my business address is 2121 K Street, Northwest, Washington, DC.  I am currently employed as a Managing Director at Secretariat Advisors LLC.  I was retained by NRG Energy, Inc. (“NRG”) to opine on issues related to the price cap and must offer conditions of the Reliability Backstop Procurement (“RBP”) proposal that PJM filed with the Commission on July 31, 2026 (“RBP Proposal”).

2. I received a bachelor’s degree in economics from Georgetown University and a master’s degree and a Ph.D. in economics from the University of Washington.  My primary field is industrial organization, which is the study of company behavior in competitive, oligopolistic, and monopolistic markets.  This field also covers the business regulation of companies through the antitrust laws and the price and entry regulation of electric and natural gas utilities.

3. I have been studying and consulting in the energy industry since joining the Federal Trade Commission in 1985.  At the Federal Trade Commission, I served as a staff economist, a Commissioner Advisor, and as the Assistant to the Deputy Director for

PDF page 19

Attachment A

Page 3 of 17

Antitrust.  As a staff economist, I focused much of my time on investigations of the natural gas industry and became familiar with rate-setting principles in that industry at both the federal and state levels.

4. Since joining what is now Secretariat in 1992, I have consulted on many matters involving electric and natural gas companies, examined issues relating to utility rates, examined issues concerning undue discrimination by operators of natural gas and electric power transmission facilities, calculated damages, and calculated amounts of alleged unjust enrichment.  I have worked for a wide range of clients including many governmental entities—e.g., the Antitrust Division of the U.S. Department of Justice, the Federal Trade Commission, the City of San Antonio, the City of San Diego, and the New Jersey Board of Public Utilities—and many major corporations—e.g., American Electric Power Corporation, Berkshire Hathaway Energy, Energy Transfer Partners, Exelon Corporation, Public Service Enterprise Group Incorporated, Tampa Electric Company, TC Energy Corporation, and WEC Energy Group. The Federal Energy Regulatory Commission (“the Commission” or “FERC”), state public utility commissions, and federal courts have accepted me as an expert witness on energy matters.

5. I have conducted a wide range of professional activities during my career.  I have spoken before the Commission, the U.S. Department of Justice, and the Federal Trade Commission.  I have published articles in journals such as the Antitrust Bulletin, the Journal of Regulatory Economics, the Electricity Journal, and Public Utilities Fortnightly.  Formerly I was the chairman of the Antitrust Committee of the Energy

PDF page 20

Attachment A

Page 4 of 17

Bar Association.  I have previously taught economics at the University of Washington, Indiana University, and Stanford University (Washington, DC, campus).  A complete listing of my experience, publications, and testimony is contained in my resume, presented in Attachment A2.

6. I have been studying the PJM market for about 30 years.  My research has included studies into the functioning of PJM markets, the resulting rates, and the competitive effects of mergers and acquisitions.  This breadth of research gives me an historical perspective of how the PJM market has evolved over the years.  My opinions below are based upon this historical perspective as well as my examination of the RBP Proposal.

7. Although the RBP Proposal has many elements, the following are the essential elements for my affidavit.  PJM will conduct a RBP to acquire up to 6,831.3 MW Unforced Capacity (“UCAP”).  (RBP Proposal at 31.)  This amount will be decreased to the extent that qualifying bilateral contracts matching new capacity to large loads are identified before the RBP.  The net amount will be the RBP Target.  The RBP will be a pay-as-bid solicitation, so each contract would have a different price.  The RBP Proposal has a “Soft Cap” of $555/MW-day, so that the average procurement price (“RBP Price”) cannot be above this average.  The capacity that is accepted in the procurement will be the “RBP Capacity.”

8. I support the concept of the RBP.  From the original construct of the capacity market, it was envisioned that, when PJM does not procure sufficient capacity via its capacity

PDF page 21

Attachment A

Page 5 of 17

auctions, it would be able to procure capacity directly to ensure system reliability. That was one of the main reasons to have a three-year forward auction: it would give PJM time to solicit contracts for new capacity before the delivery year if the auction did not clear sufficient capacity for reliability.

9. In this affidavit I discuss two aspects of the RBP Proposal.  First, I will discuss the Soft Cap.  We can all hope that PJM will be able to procure the full “Final RBP Target” (up to 6,800 MW) at an average price below the Soft Cap so that it is not binding.  But if the Soft Cap is binding, then PJM will procure less than this amount.  As discussed in more detail below, failing to procure the full Final RBP Target of capacity is likely to raise prices in subsequent Base Residual Auctions (“BRAs”) and hence raise prices to residential customers in PJM.  Therefore, I recommend that the Commission either eliminate the Soft Cap or raise it to a level reflecting more recent costs facing the industry for procurement and construction of new supply resources.  Second, I discuss the requirement that for 15 years all the capacity procured in the RBP be offered into the BRAs at zero prices.  Although this has some appeal, other more market-oriented solutions can achieve just and reasonable prices without a requirement that makes it more difficult to achieve the goal of returning PJM capacity prices to market fundamentals.  Although my preference would be that the Commission not mandate zero-priced offers in the BRAs for the RBP resources and instead give incentives to clear the capacity, I would recommend that, at a minimum, the Commission establish an offer floor for RBP resources that would apply if and to the extent that the large loads prompting the need for the RBP do not materialize.

PDF page 22

Attachment A

Page 6 of 17

I. The “Soft” Price Cap of $555/MW-Day Can Only Serve to Raise Costs to Residential Customers

10. The Soft Cap is pitched in the RBP Proposal as a just and reasonable limit on the willingness to pay for new capacity.  (RBP Proposal, at 62.)  We can all hope that sufficient capacity at low enough prices is available so that the Soft Cap will not become binding.  But if the Soft Cap is binding—that is, PJM does not purchase the full RBP Target because the Soft Cap requires PJM to reject offers from willing sellers—then the main effect of the Soft Cap is to raise capacity prices in general, and indirectly to residential customers.  Accordingly, I recommend that the Commission does not accept the proposed Soft Cap; or, at a minimum, the Commission raises the Soft Cap to reflect increases in costs and uncertainty for new construction since PJM’s last Cost of New Entry (“CONE”) study.

11. The Soft Cap is a mechanism by which PJM will procure capacity only if the quantity- weighted average prices of the accepted pay-as-bid prices are less than $555/MW- day.  (RBP Proposal, at 63.)  This is a “soft” price cap because it does not limit every accepted price to be equal or less than $555/MW-day, but PJM can pay more than $555/MW-day for one or more contracts if the prices for other RBP contracts are sufficiently low so that the overall average of purchases is less than or equal to $555/MW-day.

12. Although the RBP Proposal couches the Soft Cap as a “willingness to pay” (RBP Proposal, at 61–64.), it is not based on any studies of the actual willingness to pay. For energy, the willingness to pay is measured in the Value of Loss Load (VOLL).  I

PDF page 23

Attachment A

Page 7 of 17

have seen estimates of VOLL as high as $17,000/MWh, and those estimates were for 20 years ago.  In the instant case, the question is what is the incremental probability of having to shed load when PJM is 6,800 MW short of what is necessary to ensure a load shed even only once every 10 years.  The RBP Proposal does not calculate, and does not claim, that the load would be willing to pay more than $555/MW-day for 15 years of capacity and additional reliability.  Moreover, as discussed below, load will be willing to pay more than the average of $555/MW-day for incremental capacity for the likelihood of lower capacity prices in future BRAs.

13. In other words, in a mechanism designed to procure capacity to ensure reliability, PJM is claiming that it is just and reasonable to sacrifice reliability in exchange for lower RBP Prices.  BRAs are already intended to provide a mechanism to attract and retain the resources needed to maintain reliability; however, the BRA process has price caps and recognizes that at times it may not procure sufficient capacity and it will be necessary for PJM to run a supplemental procurement process.  Given that PJM is already short and into the backstop process, placing a price cap on the RBP process says that PJM, and implicitly the Commission, are willing to force operators to shed load when capacity would be available but for the caps.  There is no backstop to the backstop.

14. In this case, however, such a trade-off between prices and reliability is misplaced because total capacity costs to Load Serving Entities (“LSEs”) and consumers would likely be less over time if supply is brought into balance with demand than if the Soft Cap is adopted by the Commission and shortages persist.  The reason is that the Soft

PDF page 24

Attachment A

Page 8 of 17

Cap comes into play only if PJM procures less capacity for at least one auction. Although there would be no effect for delivery years in which the BRA has already occurred—for example, the 2028/2029 delivery year—effects would likely occur in some future delivery years.

15. To provide an example, I use the prices used in the RBP Proposal; specifically, I assume that an offer for $800/MW-day is rejected because the price is too high and the maximum acceptable price is $720/MW-day given all the other offers to sell capacity.  (RBP Proposal at 63.)  For ease of exposition, I assume that PJM would not acquire 1,000 MW of capacity because of the Soft Cap.

16. Not acquiring capacity means that less capacity would be available in some future BRAs.  Given the demand slope parameters for the BRA for the 2028/2029 delivery year, not clearing 1,000 MW of capacity under normal market conditions would raise market prices by $76.43/MW-day.  Based on a reliability requirement of 145,000 MW per day, that amounts to an annual difference in payments of $4 billion per year.  In comparison, the added cost of acquiring capacity at $800/MW-day is only $29 million per year.  To the extent that the additional capacity is truly needed to meet reliability requirements, it is economically rational that paying a little more for capacity the consumers in PJM would likely pay substantially less for capacity until the market settles toward prices consistent with the long-run price of capacity.

17. The value of $555/MW-day, although couched as consistent with the PJM Tariff (RBP Proposal, at 61–62), is an outdated number.  It is based upon a Brattle Report,

PDF page 25

Attachment A

Page 9 of 17

released in April 2025.  (Newell, Thompson, Zhou, et al., Brattle 2025 CONE Report for PJM, Informing Parameters for PJM’s RPM Auctions for Delivery Year 2028/29 through

2031/32,
§
II
(Apr.
9,
2025),
https://www.brattle.com/wp-
content/uploads/2025/04/Brattle-2025-CONE-Report-for-PJM.pdf
(“Brattle
2025
CONE Report”).)  This report led to a Gross CONE value of $776/MW-day for the BRA for the 2028/2029 delivery year, and an Energy and Ancillary Service (“EAS”) offset of $450/MW-day.  (PJM, 2028/2029 RPM Base Residual Auction Planning Parameters,

https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-
info/2028-2029/2028-2029-planning-period-parameters-for-base-residual- auction.xlsx.)  Using these figures, the cap is $555/MW-day (equal to 1.15 x $776/MW-day – 0.75 x $450/MW-day).

18. Both Brattle and PJM acknowledge the generation costs are increasing.  For example, the Brattle 2025 CONE Report states that: “Supply shortages and volatile price premiums may last for several years until supply chains can develop sufficient capacity to support demand.”  (Brattle 2025 CONE Report, at 2.)  PJM has acknowledged, “[c]apital costs have escalated sharply” in recent years.  (PJM, Powering Reliability Through Market Design, May 6, 2026, at 4.)  Accordingly, it is reasonable to increase the $555/MW-day Soft Cap to reflect increases in costs.

19. Updating this figure to 2026 costs would increase the Soft Cap to $697/MW-day.  The Brattle 2025 CONE Report indicates that the CONE for the reference combustion turbine have increased about 47% over three years, or about 13% each year.  Hence, adding another year would increase costs by about another 13%.  As for the math,

PDF page 26

Attachment A

Page 10 of 17

1+47% multiplied by 1+13% gives 1+66%; that is, a 13% increase in costs on top of a 47% cost increase results in a 66% cost increase compared to the starting period.  This increase is consistent with reports that construction costs for gas-fired generation have increased 66% in the past three years.  (Josh Saul, Cost to Build a Natural Gas-Fired Power Plant Surges 66%, BNEF Says, EnergyNow Media, April 23, 2026, https://energynow.com/2026/04/cost-to-build-a-natural-gas-fired-power- plant-surges-66-bnef-says/.)  In addition, the RBP contracts are for at most 15 years, whereas the CONE calculation is based upon 20 years.  The shorter period would increase annualized costs by about another 3%.  Combining these changes would produce a total cost increase of about 16%.    This would increase the Gross CONE to $900/MW-day, and the BRA price cap to $697/MW-day.

20. Another factor is that the PJM CONE estimate assumes only $22 million for interconnection costs.  This is based upon an average of completed interconnections. (Brattle 2025 CONE Study, at  43.)  In my experience reviewing many interconnection studies and agreements, many developers essentially wait until transmission upgrades are made so that they are able to reduce their interconnection costs.  But that will not be the case with the RBP; the capacity will need to come online as soon as possible.  Interconnection costs can easily be double or triple the average figure. This can greatly increase the cost of entry, and it is a risk that many new developments will have.  A higher Soft Cap would help to account for this and other uncertainties that developers will face to satisfy RBP obligations.

PDF page 27

Attachment A

Page 11 of 17

21. Another major uncertainty over 15 years is the EAS offset of $450/MW-day underlying the proposed $555/MW-day Soft Cap.  This is the highest EAS offset in 10 years, and perhaps ever.  The average EAS offset over the prior nine BRAs is only $225.49/MW- day, not significantly different from the average of the three prior BRAs, of $228.79/MW-day.  The lowest EAS offset during this period was only $91.67/MW- day.  Moreover, as more solar facilities and batteries enter the system, the net margin in the reference technology, a natural gas-fired combustion turbine, has a strong chance of falling significantly over 15 years.  This creates substantial risks for generation that is making a fixed capacity price commitment for 15 years.

22. Accounting for the historical EAS value of $225/MW-day would produce a Soft Cap of $866/MW-day.  This is equal to the measure of $697/MW-day discussed above, adding back in 0.75 x $450/MW-day (unique EAS offset for the 2028/2029 delivery year), and subtracting 0.75 x $225/MW-day (historical average EAS offset).  At a minimum I recommend that the Commission raise the Soft Cap to $866/MW-day. Having a cap significantly below $866/MW-day creates the risk that developers will not submit economically efficient offers because they believe that there is no feasible way for their projects to be accepted in the RBP.

23. Market power is not a concern with the prices in the auction.  As Danielle Croop states, with a pay-as-bid auction format the price of a contract does not affect the price of other contracts.  (Croop Aff., at Par. 33.)  In such a situation, each project is independent in pricing and that eliminates the incentive to withhold a project to raise the prices on other projects.  In addition, these contracts involve the construction of

PDF page 28

Attachment A

Page 12 of 17

new capacity, and the Commission has previously found that “absent entry barriers, long-term capacity markets are inherently competitive because new market entrants can build alternative generating supply.”  (Market-Based Rates for Wholesale Sales of Electric Energy, Capacity and Ancillary Services by Public Utilities, 119 FERC ¶ 61,295, Order No. 694, P 122 (2007).)  And here there clearly are no barriers to entry. A survey by Charles River Associates found that 87 organizations with over 136 GW of supplies would be interested in participating in a procurement auction.  (Charles River Associates, PJM Reliability Backstop RFI Summary, May 27, 2026, at 5.)  If the average price of accepted projects were over $555/MW-day, the Commission can be assured that the reason for the higher than hoped for average was due to the actual cost of installing generation in PJM and not companies attempting to exercise market power.

24. In short, letting the market work and revealing the true cost of installing generation in PJM is the policy that is most likely to minimize capacity costs for most consumers in PJM.  This is consistent with NEDC/PJM Governors’ Principles that PJM should return to market fundamentals.  (Statement of Principles Regarding PJM, National Energy

Dominance
Council,
1
(Jan.
16,
2026),
https://www.energy.gov/documents/statement-principles-regarding-pjm
(“NEDC/PJM Governors’ Principles”).)

PDF page 29

Attachment A

Page 13 of 17

II. A Zero Must Offer Price Is Inconsistent with Returning PJM to Market Fundamentals

25. The RBP Proposal also has a requirement that the RBP Capacity must offer that capacity into the BRAs at a price of zero to ensure that it clears the auctions.  In their protest, the NRG Companies propose an offer floor of $175/MW-day (UCAP)—the same price as the floor incorporated into the price collar applied in the capacity auctions for the 2026/2027, 2027/2028, 2028/2029 and 2029/2030 Delivery Years— apply to the extent the forecast load prompting the RBP does not materialize.  For the reasons discussed below, requiring capacity to be offered into the BRAs at zero is antithetical to creating a normal capacity market.  Accordingly, I recommend that the Commission adopt alternative measures to protect the buyers and consumers in PJM.

26. A must offer requirement is reasonable given that the purpose of the RBP is to procure capacity to serve PJM for 15 years.  (RBP Proposal, 56–57.)  It is also reasonable to require that the capacity be offered into PJM and not to be allowed to sell RBP Capacity into markets outside of PJM.  (RBP Proposal, at 57.)  Finally, it is reasonable that load will receive the benefit of the capacity it will pay for under the RBP, if all the capacity procured is truly needed to meet the reliability requirement. (RBP Proposal, at 57.)

27. Markets evolve and 15 years is a long time.  Instead of specifying a zero offer price for the full 15 years, contracts could be structured so that any uncleared capacity has its strike price set to zero for that BRA and all future BRAs until the end of the contract.

PDF page 30

Attachment A

Page 14 of 17

That would provide a strong incentive to clear the capacity and provide equal protection to the buyer.  The buyer would never “double pay” for capacity because the seller would be forced to “pay” for the capacity that the buyer would implicitly acquire from the BRA.  To avoid losing the secure income stream the seller might willingly offer the capacity with a price-taking offer, but that would be a voluntary choice of the seller.

28. NRG proposes placing a price floor of $175/MW-day on the seller’s capacity offers to ensure a just and reasonable outcome in BRA auctions should the load that necessitated the RBP procurement not materialize.  I support the concept of a floor on capacity prices in PJM in general today and on offers if not on auction prices. Such a floor will would lead to lower capacity prices over time, not higher prices, as the floor provides greater certainty on cost recovery and hence less risks for the owners of new generation.

29. Although this is not the forum to reform PJM’s capacity market, some perspective on the necessity of the procurement is reasonable.  The main function of the BRAs is to acquire sufficient generation capacity to provide electricity reliably.  With its performance capacity proposal, PJM proposed and the Commission accepted a system that provided for new capacity that was replacing retiring capacity and matching load growth.  The RTO capacity prices under that system ranged from $76.53/MW-day to $164.77/MWh, with an average of $120.33/MW-day.  Some thought these prices were “too high” and sought rule changes to reduce capacity prices.  They were successful, and capacity prices crashed to the range of

PDF page 31

Attachment A

Page 15 of 17

$28.92/MW-day to $50/MW-day, an average of $37.68/MW-day, for the 2022/2023 through the 2024/2025 delivery years.  These prices were too low to maintain capacity in the market.  Although it is difficult to identify exactly how much capacity retired because of the low prices, I estimate it to be about 10,000 MW.  The effect has been substantially higher RTO prices to the range of $269/MW-day to $333/MW-day in the past four auctions.  And the only reason that BRA prices were not higher in the last three auctions is that the Commission adopted a “collar” that capped the prices to around $330/MW-day in exchange for a floor of $175/MW-day.  In short, attempts to lower prices resulted in prices being substantially above the levels that they would have been but for the actions that resulted in unsustainably low price levels for three delivery years.

30. PJM recognizes that it now has a “credibility trap.”  Because of intervention at reasonable capacity price levels that crashed those prices to unsustainably low levels, “[i]nvestors, anticipating further intervention, discount the durability of the [current high] price signal. Capital stays on the sidelines; the shortage persists.” (Powering Reliability, at 5-6.)

31. Short of significant structural change, like adopting the California system for resource adequacy, the market is waiting for PJM—and implicitly, the Commission—to make credible moves that they will not allow capacity prices to crash to levels that make new investments likely unprofitable over the life of the assets.  Steps to force even more generation capacity to offer into auctions zero prices are sending the wrong signals potential investors of PJM generation capacity.

PDF page 32

Attachment A

Page 16 of 17

32. We know that PJM virtually always needs capacity prices at sufficiently high levels to finance new generation capacity.  Even with a 60-year life of capacity, a market with about 180,000 MW of installed capacity (“ICAP”) needs to replace 3,000 MW of capacity each year just to maintain the current fleet size.  And 3% demand growth each year would produce a need for an additional 5,400 MW of capacity.

33. The net CONE value in the last auction was $316/MW-day.  Given this value and the dire need for new capacity in PJM, a price floor of $175/MW-day, or about 55% of the Net CONE value, appears the minimum just and reasonable value to give investors more confidence in capacity prices in PJM.

34. Placing a capacity price floor and allowing generation owners greater flexibility in submitting offers would be consistent with the desires of the National Energy Dominance Counsel and the PJM Governors to return to a normal functioning market as soon as possible.  Not enough dispatchable capacity is in the PJM interconnection queue to provide for future reliability.  Commitments to price floors are necessary to provide investors with the incentives to invest in PJM.

35. The NRG proposed offer floor of $175/MW-day, to be implemented only if the expected demand levels do not materialize, is a more modest proposal.  It helps to protect the market only under the circumstance that this RBP is not necessary for reliability.  The protection is limited because it would not prevent capacity prices from falling below $175/MW-day if PJM has vastly overestimated demand.  At most it would establish a flat section in the capacity offer curve at $175/MW-day.  Moreover,

PDF page 33

Attachment A

Page 17 of 17

although it is desirable for load not to “double pay” for capacity, it is not just and reasonable for PJM to acquire capacity that the market does not need and force generation owners to receive unsustainably low capacity prices.  Removing the excess capacity from the BRAs by an offer price floor of $175/MW-day is a more modest step to achieve just and reasonable prices in the subsequent BRAs.

36. This concludes my affidavit.

VERIFICATION

Pursuant to 28 U.S.C. §1746, I state under penalty of perjury that the foregoing is true and correct to the best of my information, knowledge, and belief.

Executed this 21st day of August, 2026

___________________________________________
Dr. John R. Morris

PDF page 34

Qualifications of Dr. Morris

Attachment A2

Page 1 of 10

EXPERIENCE AND QUALIFICATIONS OF
Dr. John R. Morris

OVERVIEW
Dr. Morris, a recognized expert in studying competition and price formation in energy industries, currently is a Managing Director at Secretariat Advisors LLC (formerly Economists Incorporated).  He began his research of competition in energy industries in 1985 while working for the Federal Trade Commission.  Since joining Economists Incorporated in 1992, he has consulted on many mergers and acquisitions involving energy companies, examined competitive issues relating to rates, and studied issues in state restructuring proceedings. He has published articles on competition and energy matters, and he has spoken on numerous occasions concerning competition in natural gas, electric power and other industries.  He has been accepted as an expert witness on energy matters before the Federal Energy Regulatory Commission, state regulatory commissions, and in federal and state courts.

EDUCATION
Ph.D., University of Washington, August 1985 Dissertation: Intellectual Property: Creating, Pricing, Copying • M.A., University of Washington, December 1983 • A.B., Georgetown University, May 1981

PRESENT POSITION
Dr. Morris is a Managing Director at Secretariat Advisors LLC, an economic consulting firm located at 2121 K Street, NW, Suite 1100, Washington, DC  20037.  (202-223-4700) Secretariat Advisors studies competition and regulation in many industries in the United States and in other countries.  It is a leading firm in studying the competitive effects of mergers and acquisitions, damages, construction costs, and construction delay.

PREVIOUS EXPERIENCE
Principal, Economists Incorporated, December 2002 – July 2021 •  Senior Vice President, Economists Incorporated, December 2001 – December 2002 • Vice President, Economists Incorporated, December 1995 – December 2001 • Senior Economist, Economists Incorporated, June 1992 – December 1995 • Economic Tutorial Leader, Stanford University (Stanford in Washington), April 1993 – June 1995 • Visiting Assistant Professor, Department of Business Economics and Public Policy, School of Business, Indiana University, September 1991 – May 1992 • Assistant to the Director for Antitrust, Bureau of Economics, Federal Trade Commission, November 1989 – August 1991 • Economic Advisor, Office of Commissioner Machol, Federal Trade Commission, December 1988 – October 1989 • Economist, Division of Antitrust, Bureau of Economics, Federal Trade Commission, October 1985 – December 1988

PDF page 35

Qualifications of Dr. Morris

Page 2 of 10

MEMBERSHIPS
Member, International Association of Energy Economics • Associate, Energy Bar Association • Member, American Economic Association • Member, Western Economic Association International • Associate, American Bar Association

AWARDS & HONORS
Award for Excellence in Law Enforcement, Federal Trade Commission, 1988 • Graduate School Scholarship, University of Washington, 1984 • Graduated Cum Laude Georgetown University, 1981 • Senior Comprehensive Passed with Distinction, Georgetown University, 1981

TESTIMONY BEFORE THE FEDERAL ENERGY REGULATORY
COMMISSION
Affidavit, Maryland Energy Administration et al. v. Baltimore Gas and Electric Company et al., Docket No. EL26-87-000 (2026) • Report & Affidavit, NRG East Generation Holdings et al., Docket No. EC25-102-000 (2025) • Report & Affidavit, Vandolah Power Company L.L.C. and Florida Power & Light Company, Docket No. EC25-101-000 (2025) • Prepared Answering Testimony, Deposition, and Hearing, Public Utilities Commission of the State of California v. Sellers of Long-Term Contracts to the California Department of Water Resources, Docket Nos EL02-60-017 and EL02-60-18 (2025) • Milford Gen Lead, LLC, FERC Docket No. ER24-3102-000 (2024) • Prepared Direct Testimony, Algonquin Gas Transmission, LLC, Docket No. RP24-781 (2024) • Prepared Testimony, Louisiana Public Service Commission et al., v. System Energy Resources, Inc., et al., Docket No. EL21-56 (2024) •  Affidavit, Elliott Associates, L.P., et al., Docket No. EC23-112 (2023) • Affidavit, Tampa Electric Company, ER10-1437 (2023) • Affidavits (2), NextEra Energy Resources, LLC, et al., Docket No.  EC23-36- 000 (2022, 2023) • Affidavits, Building for the Future Through Electric Regional Transmission Planning and Cost Allocation and Generator Interconnection, Docket No. RM21-17-000 (2022) • Affidavit, NRG Energy, Inc., Docket No. EC20-96-000 (2020) • Affidavit, Energy Texas, Inc., EC20-85-000 (2020) • Affidavit, Tampa Electric Company, ER10-1437-011 (2020) •  Affidavits, American Transmission System, Inc., Docket No. ER20-1740-000 (2020) • Affidavits, NRG Wholesale Generation LP and Entergy Mississippi, LLC Docket No. EC19-63-000 (2019) • Affidavits, Louisville Gas and Electric Co. and Kentucky Utilities Co., Docket Nos. EC98-2-001, ER18-2162-000 (2018) • Affidavit, Upper Peninsula Power Company, Docket No. ER10-1901-011 (2018)

• Affidavit, NRG Cottonwood Tenant LLC, ER18-1160-001 (2018) • Affidavit, PSEG Energy Resources & Trade LLC, ER10-1789-005 (2018) • Affidavit, Southern Indiana Gas and Electric Co. d/b/a Vectren Energy Delivery of Indiana, Inc., ER10-1338-002 (2017) • Affidavit, PSEG Keys Energy Center LLC, ER17-2426-000 (2017) • Affidavit, Tampa Electric Company, ER10-1437-006 (2017) • Prepared Answering Testimony, Deposition, and Hearing, People of the State of California, ex rel; Bill Lockyer, Attorney General of the State of California v. British Columbia Power Exchange, et al., EL02-71-

PDF page 36

Qualifications of Dr. Morris

Page 3 of 10

000 (2017) • Affidavit, Public Service Electric and Gas Company et al., ER10-1789-004 (2016) • Affidavit, Alabama Power Company, et al., ER17-514-00 (2016) • Affidavits (3), Alabama Power Company, et al., EL15-39-000 (2016) • Affidavit, Combined Locks Energy Center, LLC, et al. , ER10-3042-004 (2015) • Affidavit, Alabama Power Company, et al., EL15-39-000 (2015) • Affidavit, PJM Interconnection, L.L.C., ER15- 623-000 (2015) • Affidavit, Southern Indiana Gas and Electric Co. d/b/a Vectren Energy Delivery of Indiana, Inc., ER10-1338-000 (2014) • Affidavit, Quantum Choctaw Power, LLC et al., ER12-458-007 (2014) • Affidavit, NRG Power Marketing LLC, et al., ER10- 2265-004 et al. (2014) • Affidavit, TransCanada Entities, ER10-2870-004 et al. (2014) • Affidavit, Tampa Electric Company, ER10-1437-002 (2014) • Affidavit, Kendall Green Energy LLC, ER14-1363-003 (2014) • Affidavit, Quantum Lake Power, LP, ER13-1489- 000 (2014) • Affidavit, NRG Power Marketing LLC, et al. ER10-2265-002 (2014) • Affidavit, NRG Yield, Inc., et al., EC14-101-000 (2014) • Affidavit, Community Wind Farm 1 et al., ER14-1668-000 (2014) • Seaway Crude Pipeline Company LLC, OR15-6- 000 (2014) • Affidavit, Public Service Electric and Gas Company et al., ER10-1789-003 (2013) • Affidavits, NRG Energy Holdings, Inc., Edison Mission Energy, EC14-14-000 (2013) • Affidavit, Silver Merger Sub, Inc., et al., EC13-128-000 (2013) • Prepared Answering Testimony, Deposition, and Hearing, Puget Sound Energy, Inc., et al., EL01- 10-085 (2012) • Affidavit, Wisconsin Public Service Corporation, et al., ER10-1894-004 (2012) • Affidavit, PSEG New Haven LLC, ER12-1250-000 (2012) • Affidavit, Enterprise Product Partners L.P. and Enbridge, Inc., OR12-4-000 (2012) • Affidavit, Southern Indiana Gas and Electric Co., ER10-1338-001 (2011) • Affidavit, TransCanada Power Marketing Ltd. et al., ER10-2780-001 (2011) • Affidavit, Tampa Electric Company, ER10-1476-001 (2011) • Affidavit, Cedar Creek Wind Energy, LLC, ER11- 2577-000 (2010) • Affidavit, Public Service Electric and Gas Company et al., ER97-837- 014 (2010) • Affidavit, Morris Energy Group, LLC v. PSEG Energy Resources & Trade LLC; PSEG Fossil LLC; and PSEG Power LLC, EL10-79-000 (2010) • Affidavit, UGI Storage Company and UGI Central Penn Gas, Inc., CP10-23-000 (2010) • Prepared Answering Testimony, People of the State of California, ex rel; Bill Lockyer, Attorney General of the State of California v. Powerex Corp., et al., EL02-71-000 (2009) • Affidavit, Integrys Energy Services, Inc. v. New Brunswick Power Generation Corporation, EL09-32-002 (2009) • Affidavit, People of the State of California, ex rel; Edmund G. Brown Jr. Attorney General of the State of California v. Powerex Corp., et al., EL09-56-000 (2009) • Affidavit, San Diego Gas & Electric Company v. Sellers of Energy and Ancillary Services, EL00-95-000 (2009) • Affidavit, Troy Energy, LLC, et al., ER02-25-010 (2009) • Affidavit, Combined Locks Energy Center, LLC, et al., ER01- 2659-015 (2009) • Prepared Direct Testimony and Deposition, Energy Transfer Partners, et al., IN06-3-003 (2009) • Prepared Direct Testimony and Hearing, Mobil Pipe Line Company, OR07-21-000 (2009) • Idaho Power Company, ER06-787-002 (2009) • Affidavit, Southern Indiana Gas and Electric Co. d/b/a Vectren Energy Delivery of Indiana, Inc. ER96-2734-007 (2008) • Affidavit, Choctaw Gas Generation, LLC, et al. ER08-1332-002 • Affidavit, TransCanada Energy Sales Ltd., ER09-328-001 (2008) •

PDF page 37

Qualifications of Dr. Morris

Page 4 of 10

Prepared Direct Testimony and Deposition, Oasis Pipeline L.P., et al., IN06-3-004 (2008)
• Affidavit, Tampa Electric Company, ER99-2342-012 (2008) • Affidavit, ANP Bellingham Energy Company, LLC, et al., ER00-2117-005 (2008) • Affidavit, SUEZ Energy Marketing, NA, et al., ER06-169-003 (2008) • Affidavit, TransCanada Energy Marketing ULC, et al., ER07-1274-001 (2008) • Affidavit, Georgia-Pacific Brewton LLC, et al., ER08-1126-000 (2008) • Affidavit, Montgomery L’Energia Power Partners LP, ER08-864-000 (2008) • Affidavit (with Joseph P. Kalt), Energy Transfer Partners, et al., IN06-3-002 (2008) • Affidavit, Energy Transfer Partners, et al., IN06-3-002 (2008) • Affidavit, TransCanada Maine Wind Development Inc., ER08-685-000 (2008) • Affidavit, O’Connor & Hewitt, LTD, RP08-30-000 (2007) • Affidavit (with Joseph P. Kalt), Energy Transfer Partners, et al., IN06-3-000 (2007) • Affidavit, Energy Transfer Partners, et al., IN06-3-000 (2007) • Affidavit, The People of the State of Illinois, ex rel. Illinois Attorney General Lisa Madigan v. Exelon Generation Co., LLC, et al., EL07-47- 000 (2007) • Affidavit, Baltimore Gas and Electric Company, ER07-576-000 (2007) • Affidavit, Trans-Allegheny Interstate Line Company, ER07-562-000 (2007) • Affidavit, TransCanada Energy Marketing Ltd., et al., ER07-331-000 (2006) • Affidavit, Tampa Electric Company, ER99-2342-000, ER07-173-000 (2006) • Affidavit, Koch Supply & Trading, LP, ER07-100-000 (2006) • WPS Resources Corporation and Peoples Energy Corporation, EC06-152-000 (2006) • Affidavit, Sabine Cogen, LP, ER06-744-000 (2006)

• Affidavit, Air Liquide Large Industries U.S. LP, ER06-743-000 (2006) • Affidavit, ANP Bellingham Energy Company, LLC., et al., ER00-2117-000 (2005) • Affidavit, Duke Energy Corporation and Cinergy Corp., EC05-103-000  (2005) • Affidavit, El Paso Marketing, L.P., et al., ER95-428-000  (2005) • Affidavit, TransCanada Energy Ltd., et al., ER95-692-000  (2005) • Affidavit, Granite Ridge Energy, LLC, ER00-1147-000, ER05-287-001  (2005) • Affidavit, TransCanada Power (Castleton) LLC, ER05-743-000 (2005) • Affidavit, Tampa Electric Company, et al., ER99-2342-003 (2005) • Affidavit, Wisconsin Public Service Corporation, WPS Energy Services, Inc., and WPS Power Development, Inc., ER96-1088-035 and Wisconsin Public Service Corporation, ER95- 1528-010 (2005) • Affidavit, Wisconsin River Power Company, ER05-453-000 (2005) • Affidavit, Upper Peninsula Power Company, ER05-89-001 (2005) • Affidavit, Southern Indiana Gas and Electric Company, ER96-2734-003 (2004) • Affidavit, Tampa Electric Company, et al., ER99-2342-003 (2004) • Affidavits, TransCanada Hydro Northeast, Inc., et al., EC05-12-000, ER05-111-000 (2004) • Affidavits, Dominion Energy New England, Inc., et al., EC05-4-000, ER05-34-000 (2004) • Affidavit, Wisconsin Public Service Corporation, WPS Energy Services, Inc., and WPS Power Development, Inc., ER96-1088-033 and Wisconsin Public Service Corporation, ER95-1528-008 (2004) • Affidavit, NorthPoint Energy Solutions Inc. ER04-1244-000 (2004) • Affidavit, Union Power Partners, L.P., ER01-930-004 (2004) • Affidavit, Panda Gila River, L.P., ER01- 931-004 (2004) • Affidavit, Dominion Energy Kewaunee, Inc., ER04-318-000 (2003) • Affidavit, TPS GP, Inc., TPG LP, Inc., Panda GS V, LLC & Panda GS VI, LLC, EC03- 90-000 (2003) • Affidavit, Berkshire Power Company, L.L.C. et al., ER99-3502-001 (2002) • Affidavit, El Paso Merchant Energy, L.P., ER95-428-024 (2002) • Affidavit,

PDF page 38

Qualifications of Dr. Morris

Page 5 of 10

Tampa Electric Company, ER99-2342-001 (2002) • Affidavit, Hardee Power Partners Limited, ER99-2341-001 (2002) • Affidavit, TECO-PANDA Generating Company, L.P., ER02-1000-000 (2002) • Affidavit, Commonwealth Chesapeake Company, LLC, ER99- 415-004 (2002) • Affidavit, Wisconsin Public Service Corporation, WPS Energy Services, Inc., and WPS Power Development, Inc., ER96-1088-031 and Wisconsin Public Service Corporation, ER95-1528-006 (2001) • Affidavit, TPS McAdams, LLC and TPS Dell, LLC, ER02-507-000 and ER02-510-000 (2001) • Affidavits, Prepared Direct Testimony, and Hearing, CPUC v. El Paso Natural Gas Company, et al., RP00-241-000 (2000-2001), Affidavit, El Paso Energy Corporation and The Coastal Corporation, EC00- 73-000, (2000) • Affidavit, El Paso Energy Corporation and Sonat Inc., EC99-73-000 (1999) • Prepared Testimony, San Diego Gas & Electric Company and Enova Energy, Inc., EC97-12-000 (1997) • Prepared Testimony and Hearing, Wisconsin Electric Power Co., Northern States Power Co. (Minnesota), Northern States Power Co. (Wisconsin), and Cenerprise, Inc., EC95-16-000 (1996)

TESTIMONY BEFORE STATE REGULATORY COMMISSIONS
Prepared Direct Testimony, Hearing, and Affidavit, Monroe Energy et al. v. Laurel Pipe Line Company, L.P., Pennsylvania Public Utilities Commission Docket No. C-2025- 3053018 (2025) • Affidavit, Joint Petition of NRG East Generation Holdings LLC and Lightning Power, LLC, for a Declaratory Ruling Eschewing Further Review of Proposed Transaction, or, in the Alternative, an Order Authorizing the Transaction Pursuant to Sections 70 and 83 of the New York Public Service Law, New York Public Service Commission Case 25-M-0358 (2025) • Affidavit, Investigation of Resource Adequacy Alternatives, New Jersey Board of Public Utilities Docket No. EO20030203 (2020) • Prepared Answering Testimony, Supplemental Testimony, and Cross-Examination, In the Matter of Eligibility Criteria for Energy Service Companies, Case 15-M-0127, New York Public Service Commission (2017) • Prepared Direct Testimony, In re: Petition for Determination of Cost Effective Generation Alternative to Meet Need Prior to 2018, by Duke Energy Florida, Inc., FPSC Docket No. 140111-EI (2014) • Affidavit and Prepared Testimony, In The Matter of the Petition of Public Service Electric and Gas Company for Approval of an Increase in Electric and Gas Rates and for Changes in the Tariffs for Electric and Gas Service, B.P.U.N.J. No. 14 Electric and B.P.U.N.J. No. 14 Gas Pursuant to N.J.S.A. 48:2-21 and N.J.S.A. 48:2-21.1 and for Approval of a Gas Weather Normalization Clause; A Pension Expense Tracker; and for Other Appropriate Relief, BPU Docket No. GR09050422, New Jersey Board of Public Utilities (2010) • Prepared Direct Testimony, Application of Wisconsin Power and Light Company for Issuance of a Certificate of Public Convenience and Necessity for Construction and Placement in Operation of an Approximately 300 MW Coal-Fired Baseload Facility and an Application for Approval of Fixed Financial Parameters and Capital Cost Rate-Making Principles for the Baseload Facility, Docket No. 6680-CE-170, Public Service Commission of Wisconsin (2008) • Prepared Rebuttal Testimony and Hearing, In the Matter of the Joint Petition of Public Service Electric and Gas Company and Exelon

PDF page 39

Qualifications of Dr. Morris

Page 6 of 10

Corporation for Approval of a Change in Control of Public Service Electric and Gas Company, and Related Authorizations, BPU Docket No. EM05020106, OAL Docket No. PUC-01874-05, New Jersey Board of Public Utilities (2005, 2006) • Affidavit, Application of Duke Energy Corporation for Authorization to Enter Into a Business Combination Transaction with Cinergy Corp., Docket No. 2005-210-E, Public Service Commission Of South Carolina (2005) • Prepared Rebuttal Testimony and Hearing, Joint Application of PECO Energy Company and Public Service Electric and Gas Company for Approval of the Merger of Public Service Enterprise Group Incorporated with and into Exelon Corporation, Docket No. A-110550F0160, Pennsylvania Public Utility Commission (2005) • Prepared Direct Testimony and Hearing, Application of Washington Gas Light Company for amendments to Rate Schedule No. 9, Firm Delivery Gas Supplier Agreement of its Gas Tariff, Docket No. PUE-2004-00085 (2005) • Prepared Direct Testimony, Application of Wisconsin Public Service Corporation for a Certificate of Public Convenience and Necessity for Construction of A Large Electric Generating Plant with Associated Facilities, known as Weston 4, at Its Existing Weston Generating Station Located in Marathon County, Docket No. 6690-CE-187, Public Service Commission of Wisconsin (2004) • Prepared Direct Testimony, Metromedia Energy, Inc. - Regarding Washington Gas Light Company's Plan to Return Customers to Sales Service Effective December 1, 2003, Docket No. PUE-2003-00536 (2004) • Report (with Mark Frankena) and Testimony, Analysis of Competitive Implications: An investigations into whether electric industry restructuring and competition in the provision of retail electric service is in the public interest, Louisiana Public Service Commission Docket No. U-21453, U-20925 (SC), U-22092 (SC) (Subdocket A) (2000) • Report and Hearing, Atlantic City Electric Company: Audit of Restructuring, New Jersey Board of Public Utilities, Docket No. EA97060395 (1998) • Prepared Testimony and Hearing, Proceeding on Motion of the Commission to Redesign Niagara Mohawk Power Corporation’s Current SC-7 Service Classification and Implement a New SC-7-A Service Classification, Case 94-E-0172, New York Public Service Commission (1995)

TESTIMONY BEFORE FEDERAL COURTS
Report, Deposition and Bench Trial, Entergy Arkansas, LLC, vs. Ted J. Thomas, in his official capacity as Chairman of the Arkansas Public Service Commission et al., Civil Action No. 4:20-cv-01088-KGB, U.S. Dist. Court, Dist. of Eastern Arkansas (2022, 2023) • Reports and Deposition, Duke Energy Carolinas, LLC, vs. NTE Carolinas II, LLC, NTE Carolinas II Holdings, LLC, NTE Energy LLC, NTE Southeast Electric Company, LLC, NTE Energy Services Co., LLC, and Castillo Investment Holdings II, LLC, vs. Duke Energy Progress, LLC and Duke Energy Corporation, Civil Action No. 3:19-cv-515, U.S. Dist. Court,  (2022) • Report, Deposition, and Bench Trial, FTC v. Arch Coal, Inc., et al., Civil Action 04-0534 (JDB), U.S. Dist. Court, Dist. of Western North Carolina (2004) • Report, Deposition and Jury Trial, Trigen v. OG&E, CIV-96- 1595L, U.S. Dist. Court, Western Dist. of Oklahoma (1998)

PDF page 40

Qualifications of Dr. Morris

Page 7 of 10

TESTIMONY BEFORE STATE COURTS
Report, Deposition, and Trial, CPS Energy v. Houston Pipe Line Company, LP and Oasis Pipeline, LP, Cause No. 2021-CI-05138, District Court of Bexar County, Texas, 407th and 166th Judicial Districts (2023-6) • Affidavit, Retail Energy Supply Association, et al.

v. Public Service Commission of the State of New York, et al., Index No. 870-16, State of New York, Supreme Court, County of Albany (2016) • Affidavit, City Public Service Board of San Antonio vs. Public Utility Commission of Texas, et al., No. 97-02917, District Court of Travis County, Texas, 200th Judicial District (1997)

OTHER TESTIMONY
Report, Metromedia Energy, Inc. v. Mirant Americas Energy Marketing, RE: 18 198 Y 18484 03 (2005) • Report and Deposition, King Provision Corporation v. Burger King Corporation and Grand Metropolitan PLC, 90-05718-CA, 4th Cir., Duval Co., Florida (1992) •  Deposition, West Texas Transmission L.P. v. Enron Corp. et al., SA 88 CA 0638, W.D. Texas, San Antonio Division (1988)

PUBLICATIONS
“Alternative Measures of ‘Representative Market Prices’ for FERC Delivered Price Tests,” Energy Law Journal 42 (2021): 191-235 • “Should market power still be a concern in the U.S. electric power industry?” with Jéssica Dutra and Tristan SnowCobb, Electricity Journal 33 (May 2020): 106725-28 • “Geographic Market Delineation in LMP Electric Power Markets,” with Megan Accordino, Electricity Journal 23(3) (April 2010): 49-60 • “The Likely Effect of the Proposed Exelon-PSEG Merger on Wholesale Electricity Prices,” with Dan Oska, Electricity Journal 21(1) (Jan./Feb. 2008): 45-54 • “FERC MBR Screens: The Good, the Bad, and the Ugly,” Public Utilities Fortnightly 143(7) (July 2005): 37-42 • “Finding Market Power in Power Markets,” International Journal of the Economics of Business, 7(2) (July 2000): 167-178 • “Why Applicants Should Use Computer Simulation Models to Comply with the FERC’s New Merger Policy,” with Mark Frankena, Public Utilities Fortnightly, 135(3) (February 1, 1997): 22- 26 • Electric Utility Mergers, with Mark Frankena and Bruce Owen, Chapters 1, 4, & 5, 1994 • “International Trade and Antitrust: Comments,” University of Cincinnati Law Review, 61(3) (1993): 945-953 • “Upstream Vertical Integration with Automatic Price Adjustments,” Journal of Regulatory Economics 4 (1992): 279-287 • “Should the U.S. Department of Justice deviate from the 5% price test for market definition on a case-by- case basis?”  with Gale Mosteller, International Merger Law, April 1992 • “Defining Markets for Merger Analysis,” with Gale Mosteller, Antitrust Bulletin 36 (Fall 1991): 599-640 • “Analyzing Agreements Among Competitors:  What Does the Future Hold?” with Jim Langenfeld, Antitrust Bulletin 36 (Fall 1991):  651-679 • “In Defense of Antitrust,” with Jim Langenfeld, Regulation 14(2) (Spring 1991):  (Letters) 2-4 • “Enforcement of Property Rights and the Provision of Public Good Attributes,” Information Economics and Policy 3 (1988):  91-108

PDF page 41

Qualifications of Dr. Morris

Page 8 of 10

WORKING PAPERS
“Advertising Restrictions as Rent Increasing Costs,” FTC Bureau of Economics Working Paper No. 196, May 1992 • “Rent Increasing Costs:  The Antitrust Implications from a Paradox in Value Theory,” FTC Bureau of Economics Working Paper No. 182, November 1990 • “The Relationship Between Industrial Sales Prices and Concentration of Natural Gas Pipelines,” FTC Bureau of Economics Working Paper No. 168, November 1988 • “Deregulation by Vertical Integration?”  FTC Bureau of Economics Working Paper No. 166, November 1988

PRESENTATIONS & PROFESSIONAL ACTIVITIES
“Finding ‘representative market prices’ for calculating concentration in electric power markets,” presentation to staff of the Federal Energy Regulatory Commission, March 4, 2020 • Comments to the Antitrust Division of the U.S. Department of Justice and the Federal Trade Commission Concerning U.S. Department of Justice and the Federal Trade Commission Draft Vertical Merger Guidelines Released for Public Comment on January 10, 2020, Feb. 25, 2020 (with Lona Fowdur) • Comments (with 7 others), Notice of Inquiry: Modifications to Commission Requirements for Review of Transactions under Section 203 of the Federal Power Act and Market-Based Rate Applications under Section 205 of the Federal Power Act, Docket No. RM16-21-000, Federal Energy Regulatory Commission, November 28, 2016 • Report, PJM Interconnection, L.L.C., Docket No. ER15-623-000, Federal Energy Regulatory Commission, January 20, 2015 • Comments, Notice of Inquiry: Analysis of Horizontal Market Power under the Federal Power Act, Docket No. RM11-14-000, Federal Energy Regulatory Commission, May 23, 2011 • Comments, Position Limits for Derivatives, RIN 3038–AD15 and 3038–AD16, Commodity Futures Trading Commission, March 28, 2011 • Comments, Guidance on Simultaneous Transmission Import Limit Studies, AD10-2-000, Federal Energy Regulatory Commission, February 12, 2010 • “Geographic Market Delineation in LMP Electric Power Markets,” presentation before representatives of the Federal Energy Regulatory Commission, U.S. Department of Justice, and U.S. Federal Trade Commission, January 27, 2010 • Comments, Notices of Intent to determine that 15 natural gas financial basis contracts traded on the Intercontinental Exchange, Inc. are Significant Price Discovery Contracts, Commodity Futures Trading Commission, October 26, 2009 • “Efficacy of Vertical Integration in Energy Industries with Applications to Proposed Standards of Conduct for Transmission Providers,” submitted to FERC by Santee Cooper in Docket No. RM07-1-000 (2007) • Chair, Antitrust Committee, Energy Bar Association, 2004–2005 • “Competition in the Natural Gas Industry: An Antitrust Perspective, presentation to staff of the Federal Energy Regulatory Commission,” March 28, 2005 • Vice Chair, Antitrust Committee, Energy Bar Association, 2003–2004 • “Weston 4 Effect on Wholesale Competition in WUMS,” submitted to the Public Service Commission of Wisconsin by Wisconsin Public Service Corporation in Docket No. 6690-CE-187, September 26, 2003 • “Computer Models In The Electric Power Industry,” presented to staff of the Federal Trade Commission,

PDF page 42

Qualifications of Dr. Morris

Page 9 of 10

Washington, DC, June 11, 2002 • “TECO EnergySource Market Share Analysis,” submitted to FERC by TECO EnergySource, Inc. in Docket No. ER96-1563-017, September 10, 2001 • “Finding Market Power in Power Markets,” presented to staff of the Federal Trade Commission, Washington, DC, June 20, 2001 • “A Study of Marketing Affiliate and Other Affiliate Holdings of Firm Capacity on Interstate Natural Gas Pipelines and the Effects on Natural Gas Markets,” April 30, 2001, submitted to FERC by the Interstate Natural Gas Association of America in Docket No. PL00-1-003 • “Why We Should Use Computer Models to Unveil Market Power,” presented at the Sixth DOE–NARUC National Electricity Forum, Brown Convention Center, Houston, TX, September 16, 1998 • Comments, Agency Information Collection and Dissemination Activities: Comment Request, U.S. Department of Energy, Energy Information Administration, August 28, 1998 • Comments, Revised filing Requirements Under Part 33 of the Commission’s Regulations, Federal Energy Regulatory Commission Docket No. RM98-4-000, August 21, 1998 • “Use of Computer Simulation Models to Unveil Market Power,” presented to staff of the Federal Trade Commission, Federal Energy Regulatory Commission and U.S. Department of Justice, Federal Trade Commission, Washington, DC, April 10, 1998 • “Use of Computer Simulation Models to Unveil Market Power: The Primergy Case,” presented to the Bureau of Economics, Federal Trade Commission, Washington, DC , December 8, 1997 • “Use of Computer Simulation Models to Unveil Market Power,” presented at the 29th Annual Conference of the Institute of Public Utilities, Williamsburg, Virginia, December 3, 1997 • “Mergers and Market Power,” presented at the National Association of State Utility Consumer Advocates Mid-Year Meeting, Charleston, South Carolina, June 9, 1997 • “Market Power Analysis: An Economic Perspective,” (with Mark Frankena), presented at the Strategic Research Institute Conference on The Legal Challenges of Restructuring, Arlington, Virginia, April 16, 1997 • “Mergers and Market Power,” presented at the Edison Electric Institute Workshop on FERC Merger Policy Guidelines, Arlington, Virginia, April 1, 1997 • “New Approaches to Controlling Distribution Company Market Power,” presented at the New York Energy Efficiency Council Conference on Innovative Solutions to a Changing Energy Market, New York Athletic Club, February 7, 1997 • Description of the Western Power Model, with Mark Frankena, Exhibit 8 to Prepared Testimony Before the Nevada Public Service Commission, January 31, 1997 • Reviewer, American Bar Association, Section of Antitrust Law, Manual on the Economics of Antitrust Law, 14th Supplement, 1995 • Referee, Quarterly Journal of Business and Economics, 1994—1995 • Reviewer, American Bar Association, Section of Antitrust Law, Manual on the Economics of Antitrust Law, 10th Supplement, 1993 • Expert Witness, Federal American Inn of Court, Washington, DC, Winter 1993 • “Advertising Restrictions as Rent Increasing Costs,” presented at a Contemporary Policy Issues Session of the Western Economics Association’s 67th Annual Conference, July 1992 • “Let’s Make Merger Policy ‘Fully Consonant With Economic Theory,’” presented at a Contemporary Policy Issues Session of the Western Economics Association’s 67th Annual Conference, July 1992 • “Advertising Restrictions as Rent Increasing Costs,” Seminar, Department of Business

PDF page 43

Qualifications of Dr. Morris

Page 10 of 10

Economics, Indiana University, October 1991 • “International Trade and Antitrust: Comments,” presented at a Contemporary Policy Issues Session of the Western Economics Association’s 66th Annual Conference, July 1991 • Discussant, Western Economics Association’s 66th Annual Conference, July 1991 • Horizontal Restraints Cases at the Federal Trade Commission: From American Medical Association through the Present,” with Jim Langenfeld, presented at the 60th Annual Conference of the Southern Economics Association, November 1990 • “Defining Markets for Merger Analysis,” with Gale Mosteller, presented at a Contemporary Policy Issues Session of the Western Economics Association’s 65th Annual Conference, cosponsored by the Antitrust Bulletin and the Antitrust and Trade Regulation Section of the Federal Bar Association, July 1990 • “Analyzing Agreements Among Competitors:  What Does the Future Hold?” with Jim Langenfeld, presented at a Contemporary Policy Issues Session of the Western Economics Association’s 65th Annual Conference, cosponsored by the Antitrust Bulletin and the Antitrust and Trade Regulation Section of the Federal Bar Association, July 1990

• “The Relationship Between Industrial Sales Prices and Concentration of Natural Gas Pipelines,” Seminar, Office of Economic Policy, Federal Energy Regulatory Commission, Summer 1989 • “The Relationship Between Industrial Sales Prices and Concentration of Natural Gas Pipelines,” Seminar, Economic Analysis Group, Antitrust Division, U.S. Department of Justice, February 1989 • “Deregulation by Vertical Integration?”  Seminar, Department of Business Economics, Indiana University, January 1989 • Discussant, Industrial Organization Society Session, Annual Meeting of the American Economics Association, December 1988 • “Concentration and Price in the Natural Gas Industry,” Seminar, Federal Trade Commission, July 1988 • “Relevant Measures of Concentration for Antitrust Policy,” presented at an Industrial Organization Society Session of the 57th Annual Conference of the Southern Economics Association, November 1987

PDF page 44

Attachment B
The Atkins Affidavit

PDF page 45

1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3380-000
AFFIDAVIT OF THOMAS E. ATKINS
1. My name is Thomas E. Atkins.  My business address is 804 Carnegie Center, Princeton, New Jersey, 08540.

2. I am the Vice President of Development with NRG Energy, Inc. (“NRG”).  In this capacity, I am responsible for NRG’s utility scale dispatchable generation development projects, including a number of development projects in the PJM Interconnection, L.L.C. (“PJM”) region.  In this role, I lead a team of developers responsible for identifying economic projects supporting future grid needs.  Once identified, my team leads the development effort including siting, concept design, licensing, permitting and ultimately financing.

3. I received my Bachelor of Science degree from Cornell University and hold a  Professional Engineer’s license from the State of New York.  Prior to joining NRG in 2014, I developed numerous dispatchable electric generating facilities including projects within multiple Regional Transmission Organizations, as well as several replacement projects as Chief Engineer for the Virgin Islands Water and Power Authority.  I have over 40 years of experience in the electric power industry.

4. I am submitting this affidavit in support of certain of NRG subsidiaries’ limited protest to a filing in which PJM is proposing rules for its Reliability Backstop Procurement (“RBP”). Specifically, my affidavit addresses the proposed soft cap of $555/MW-day and explains why that cap does not reflect the current costs of resources.

PDF page 46

2
I. BACKGROUND
A. NRG
5. NRG is a Delaware corporation and an integrated wholesale power generation and retail electricity company.  NRG’s common stock is publicly traded on the New York Stock Exchange under the symbol “NRG.”

6. Through various subsidiaries, NRG owns or controls over 9 GW of generation in the PJM footprint and also owns generation in adjacent markets that can be imported into the PJM market.  NRG actively participates in the organized markets administered by PJM, including the PJM capacity market.  Through various other subsidiaries, NRG is also an active retail power marketer in the PJM region and engages in wholesale transactions to support its retail power marketing activities.  NRG’s subsidiaries conduct their retail marketing activities in this region under the brand names NRG Home, Direct Energy, Green Mountain Energy, Gateway Energy Services, Stream Energy and XOOM Energy and pursuant to retail marketing licenses issued by applicable state commissions.

7. NRG is actively developing a number of dispatchable generation projects in the PJM region, including both upgrading existing equipment and building new facilities at our current brownfield sites.  Several of these projects are in a sufficiently advanced stage of development to qualify for participation in the RBP.

B. The Proposed RBP
8. As described in greater detail in PJM’s July 31, 2026, filing in this proceeding, the RBP is a one-time procurement of new capacity to address shortfalls in PJM’s last two Base Residual Auctions (“BRAs”), specifically, the BRAs for the 2027/2028 and the 2028/2029 Delivery Years.  As proposed, the RBP would procure capacity commitments from new

PDF page 47

3
supply resources for up to 15 Delivery Years ending with the 2042/2043 Delivery Year. The aim will be to procure an amount equal to the 6,831.3 MW shortfall in the 2028/2029 BRA, less qualifying new capacity serving new load and load associated with certain cooperatives and municipals that opt out of the RBP.

9. Among other things, PJM has proposed a soft cap, characterized as a “maximum willingness to pay,” for the RBP of $555/MW-day (UCAP).  This represents the effective cap that would have applied in the 2028/2029 BRA but for the separate price collar.  This $555/MW-day cap is soft in the sense that a supplier’s offer can exceed $555/MW-day provided the levelized procurement cost of all selected RBP offers, on a MW-weighted average basis, does not exceed $555/MW-day.

10. According to PJM, $555/MW-day is the price at “Point 1” on the Variable Resource Requirement (“VRR”) curve approved for the 2028/2029 BRA as part of the most recent quadrennial review of Reliability Pricing Model auction parameters.1  In the quadrennial review proceeding, PJM described its calculation of the Point 1 price as follows:2

11. The gross CONE value of $613/MW-day (ICAP) (or $776/MW-day (UCAP)) is intended to represent the cost of new entry for a combustion turbine (“CT”), as estimated through a

1 2025 Periodic Review of Variable Resource Requirement Curve Shape and Key Parameters, Docket No. ER26-455-000 (filed Nov. 7, 2025).
2 Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C. at 14, Docket No. ER26- 455-000 (filed Jan. 2, 2026).

PDF page 48

4
study conducted by the Brattle Group and Sargent & Lundy and submitted as part of PJM’s quadrennial review filing in November 2025.3  The study itself was issued in April 2025.

II. The Soft Cap is Based on an Outdated CONE Value for a CT and Fails Adequately to Reflect Costs of Building New Generation in the PJM Region

12. As PJM noted in a May 2026 report, “capital costs have escalated sharply in recent years.”4 In fact, as PJM explained:

Installed costs for new natural gas combined cycle plants now regularly exceed $2,200 per kilowatt for projects with commercial dates in the late 2020s and early 2030s, and costs for more distant commercial dates are

higher still. This represents a substantial increase over the administrative cost of new entry (CONE) estimates that PJM uses to calibrate its capacity market demand curve . . . .5

13. In a separate affidavit also being submitted in support of NRG’s limited protest, Dr. John R. Morris states that even since the CONE study for the most recent quadrennial update filing was prepared, costs have continued to escalate the CONE value  and the proposed soft cap of $555/MW-day does not reflect the dramatic cost increases in power generation equipment.

14. NRG has witnessed these increased costs in its development efforts. A 2025 paper issued by GridLab, Energy Futures Group and Halcyon reflects the “significant and persistent increase in the capital costs of new gas combustion turbine and combined cycle gas turbine power plants in the United States” and that the “trend marks a stark departure from

3
PJM Interconnection, L.L.C., 2025 Periodic Review of Variable Resource Requirement Curve Shape  and Key Parameters, Docket No. ER26-455-000 (Nov. 7, 2025).

4 PJM, Powering Reliability Through Market Design at 4 (May 6, 2026), https://www.pjm.com/-/ media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through- market-design.pdf.
5 Id.

PDF page 49

5
historical cost assumptions and public cost projections.”6  In 2026, Bloomberg issued a report showing that the “costs to build natural gas-fired power plants in the US increased 66% between 2023 and 2025.”7

15. $555/MW-day is low relative to the costs NRG is seeing as a generation developer.  At the outset, I would note that even if it were not out of date, the $555/MW-day figure would only be tied to the costs of a new CT and would not be representative of the costs of projects using other technologies or having other characteristics different from those of the reference unit.  For example, NRG currently has several projects under development in the PJM footprint using technologies other than simple cycle CT’s that are far enough along in the development process to offer into the RBP.

16. However, all of NRG’s development projects that qualify for the RBP are significantly challenged by the $555/MW-day soft cap.  One of these projects has a capacity in excess of 800 MW and a CONE, less expected energy and ancillary services revenues, substantially greater than the $555/MW-day soft cap. This is a well-formed project that would, among other things, be located in what has historically been an import-constrained zone.  But it is hard to justify the time and expense associated with offering it into the RBP, notwithstanding the fact that the soft cap allows offers above $555/MW-day. * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

17. This concludes my affidavit.

6 The New Reality of Power Generation: An Analysis of Increasing Gas Turbine Costs in the U.S., GridLab, Energy Futures Group & Halcyon, at 4 (Sept. 2025), https://gridlab.org/portfolio-item/gas-tubine-cost- report/ 7 Cost to Build a Natural Gas-Fired Power Plant Surges 66%, BNEF Says, (Apr. 2026), https://energynow.com/2026/04/cost-to-build-a-natural-gas-fired-power-plant-surges-66-bnef-says/