Limited Protest of the NRG Companies re PJM Interconnection, L.L.C.’s 07/31/2026 filing proposing a Reliability Backstop Procurement
Text extracted from the eLibrary original (SHA-256 9b9cb875485a1836…). Download the original from the official source.
Contents · 29 sections
- I. BACKGROUND
- D. Burgum, et al., Statement of Principles Regarding PJM (Jan. 15, 2026) (“Statement of
- II. PROTEST
- A. Any Soft Cap Should Be Set at a Level Reflecting Current Costs of Resources Whose
- B. The Commission Should Impose a Price Floor on Offers for Resources with RBP
- III. CONCLUSION
- Attachment A
- Attachment A
- Attachment A
- Attachment A
- Attachment A
- Attachment A
- Attachment A
- I. The “Soft” Price Cap of $555/MW-Day Can Only Serve to Raise Costs to
- Attachment A
- Attachment A
- Attachment A
- Attachment A
- Attachment A
- Attachment A
- Attachment A
- Attachment A
- Attachment A
- Attachment A
- Attachment A
- Attachment B
- I. BACKGROUND
- B. The Proposed RBP
- II. The Soft Cap is Based on an Outdated CONE Value for a CT and Fails Adequately
Read topic-matched comments in ER26-3380
Topics in the text: Reliability and curtailment · Cost allocation · Registry access
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword. Pages with no text layer: 50.
Opening text
opening text · Topic match: Reliability and curtailment
EC26-106-000, et al. (Aug. 3, 2026) (unreported). 3 The NRG Companies include the following subsidiaries of NRG Energy, Inc. (“NRG”): NRG Business Marketing LLC, Aspen Gen Funding, LLC, Direct Energy Business, LLC, Doswell Limited Partnership, Energy Plus Holdings LLC, Enerwise Global Technologies,…Read this passage Filed comments: Reliability and curtailment
I. BACKGROUND
printed heading · Topic match: Reliability and curtailment
BACKGROUND As indicated in the July 31 Filing, both the 2027/2028 BRA and the 2028/2029 BRA cleared at the market price cap of $325/MW-day and over 6 GW short of the applicable PJM Regional Reliability Requirement.6 In the July 31 Filing, PJM proposes the RBP to procure capacity outside the…Read this passage Filed comments: Reliability and curtailment
D. Burgum, et al., Statement of Principles Regarding PJM (Jan. 15, 2026) (“Statement of
printed heading
Burgum, et al., Statement of Principles Regarding PJM (Jan. 15, 2026) (“Statement of Principles”), https://www.energy.gov/documents/statement-principles-regarding-pjm. 10 July 31 Filing, Transmittal Letter at 48 (alteration in original) (quoting Statement of Principles at 1). 3 The RBP will be a…Read this passage
II. PROTEST
printed heading · Topic match: Reliability and curtailment
Nonetheless, there are two elements of that proposal that are not just and reasonable and that must be modified to ensure that the RBP serves its intended purpose and does not create further market distortions that will, in turn, necessitate further one-off solutions.Read this passage Filed comments: Reliability and curtailment
A. Any Soft Cap Should Be Set at a Level Reflecting Current Costs of Resources Whose
printed heading
There are a number of material risks concerning both the costs associated of new construction as well as the risks and costs of providing service out 15 Delivery Years, including, but not limited to, indeterminate network upgrade costs that may be allocated to a new project, costs and risks…Read this passage
B. The Commission Should Impose a Price Floor on Offers for Resources with RBP
printed heading · Topic match: Reliability and curtailment
The Commission Should Impose a Price Floor on Offers for Resources with RBP Commitments to the Extent the Load Prompting the RBP Does Not Materialize As Dr.Read this passage Filed comments: Reliability and curtailment
III. CONCLUSION
printed heading · Topic match: Reliability and curtailment
CONCLUSION For the reasons set forth herein, the NRG Companies respectfully request that the Commission condition its acceptance of the July 31 Filing on the modifications proposed herein.Read this passage Filed comments: Reliability and curtailment
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 21st day of August 2026. /s/ David Tewksbury David G.Read this passage
Attachment A
printed heading
Attachment A The Morris AffidavitRead this passage
Attachment A
printed heading
Attachment A UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.Read this passage
Attachment A
printed heading
I was retained by NRG Energy, Inc. (“NRG”) to opine on issues related to the price cap and must offer conditions of the Reliability Backstop Procurement (“RBP”) proposal that PJM filed with the Commission on July 31, 2026 (“RBP Proposal”). 2.Read this passage
Attachment A
printed heading
As a staff economist, I focused much of my time on investigations of the natural gas industry and became familiar with rate-setting principles in that industry at both the federal and state levels. 4.Read this passage
Attachment A
printed heading
I have previously taught economics at the University of Washington, Indiana University, and Stanford University (Washington, DC, campus).Read this passage
Attachment A
printed heading
Attachment A Page 5 of 17 auctions, it would be able to procure capacity directly to ensure system reliability.Read this passage
Attachment A
printed heading
Attachment A Page 6 of 17Read this passage
I. The “Soft” Price Cap of $555/MW-Day Can Only Serve to Raise Costs to
printed heading
The “Soft” Price Cap of $555/MW-Day Can Only Serve to Raise Costs to Residential Customers 10.Read this passage
Attachment A
printed heading · Topic match: Reliability and curtailment
In the instant case, the question is what is the incremental probability of having to shed load when PJM is 6,800 MW short of what is necessary to ensure a load shed even only once every 10 years.Read this passage Filed comments: Reliability and curtailment
Attachment A
printed heading
Attachment A Page 8 of 17 Cap comes into play only if PJM procures less capacity for at least one auction.Read this passage
Attachment A
printed heading
Both Brattle and PJM acknowledge the generation costs are increasing.Read this passage
Attachment A
printed heading
Attachment A Page 10 of 17 1+47% multiplied by 1+13% gives 1+66%; that is, a 13% increase in costs on top of a 47% cost increase results in a 66% cost increase compared to the starting period.Read this passage
Attachment A
printed heading
Another major uncertainty over 15 years is the EAS offset of $450/MW-day underlying the proposed $555/MW-day Soft Cap.Read this passage
Attachment A
printed heading
Attachment A Page 12 of 17 new capacity, and the Commission has previously found that “absent entry barriers, long-term capacity markets are inherently competitive because new market entrants can build alternative generating supply.” (Market-Based Rates for Wholesale Sales of Electric Energy,…Read this passage
Attachment A
printed heading
A Zero Must Offer Price Is Inconsistent with Returning PJM to Market Fundamentals 25.Read this passage
Attachment A
printed heading
NRG proposes placing a price floor of $175/MW-day on the seller’s capacity offers to ensure a just and reasonable outcome in BRA auctions should the load that necessitated the RBP procurement not materialize.Read this passage
Attachment A
printed heading
Short of significant structural change, like adopting the California system for resource adequacy, the market is waiting for PJM—and implicitly, the Commission—to make credible moves that they will not allow capacity prices to crash to levels that make new investments likely unprofitable over the…Read this passage
Attachment A
printed heading
Not enough dispatchable capacity is in the PJM interconnection queue to provide for future reliability.Read this passage
Attachment A
printed heading · Topic match: Cost allocation
EC23-36- 000 (2022, 2023) • Affidavits, Building for the Future Through Electric Regional Transmission Planning and Cost Allocation and Generator Interconnection, Docket No.Read this passage Filed comments: Cost allocation
Attachment B
printed heading
Attachment B The Atkins Affidavit 1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket No.Read this passage
I. BACKGROUND
printed heading
NRG is a Delaware corporation and an integrated wholesale power generation and retail electricity company.Read this passage
B. The Proposed RBP
printed heading
As described in greater detail in PJM’s July 31, 2026, filing in this proceeding, the RBP is a one-time procurement of new capacity to address shortfalls in PJM’s last two Base Residual Auctions (“BRAs”), specifically, the BRAs for the 2027/2028 and the 2028/2029 Delivery Years.Read this passage
II. The Soft Cap is Based on an Outdated CONE Value for a CT and Fails Adequately
printed heading
The Soft Cap is Based on an Outdated CONE Value for a CT and Fails Adequately to Reflect Costs of Building New Generation in the PJM Region 12.Read this passage