ER26-3380-000 · 2026-08-21 · American Transmission Systems, Inc., Mid-Atlantic Interstate Transmission LLCTrans-Allegheny Interstate Line Company and 5 others

Protest of the Indicated PJM Transmission Owners re PJM Interconnection, L.L.C.’s proposed tariff amendment

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.

)
)
)
)
)
)
)
)
)
)
Docket No. ER26-3380-000
PROTEST OF THE INDICATED PJM TRANSMISSION OWNERS
Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or the “Commission”),1 the Indicated PJM Transmission Owners2 respectfully submit this Protest to PJM Interconnection, L.L.C.’s (“PJM”) proposed tariff amendment (“Proposed Tariff”) concerning its Federal Power Act (“FPA”) section 205 filing seeking to amend its tariff to adopt a Reliability Backstop Procurement (“RBP”). Specifically, this Protest addresses section 18.7 of PJM’s Proposed Tariff (the “Exit Amendment”), which would establish new prerequisites to a Transmission Owner (“TO”) exiting PJM and new exit fees.  This Protest is not brought on by any desire to exit PJM; rather, the Protest aims to confront PJM’s deviation from the Consolidated Transmission Owners

1 18 C.F.R. § 385.211 (2026).
2 The Indicated PJM Transmission Owners are American Transmission Systems, Inc., Mid-Atlantic Interstate Transmission, LLC, Trans-Allegheny Interstate Line Company, Keystone Appalachian Transmission Company, Jersey Central Power & Light Company, Monongahela Power Company, and The Potomac Edison Company (collectively, “The FirstEnergy Transmission Companies”), and Duquesne Light Company.  Each of the Indicated PJM Transmission Owners is also submitting a separate protest in the instant proceeding focusing on other aspects of the Proposed Tariff.  Indicated PJM Transmission Owners join in this narrowly-focused Protest concerning section 18.7 of the Proposed Tariff.

PDF page 2

2
Agreement’s (“CTOA”) processes and the Exit Amendment proposal that conflicts with relevant Commission precedent.

As set forth herein, the Exit Amendment is procedurally and substantively defective and should be rejected by the Commission.

First, PJM did not follow the required procedure under the CTOA to file the amendment.  Contrary to PJM’s position, the Exit Amendment is not a mere change to the “terms and conditions of the PJM Tariff” that PJM may unilaterally file under Section 9.2(a) of the PJM Open Access Transmission Tariff (“OATT”).  Rather, the Exit Amendment effectively amends the CTOA, and therefore could be filed only after a vote of the TOs with sufficient support—a requirement that was indisputably not met here.  Under CTOA section 8.5.1, amending the CTOA requires a two-thirds majority of both representatives holding two- thirds of the Individual Votes cast and representatives holding two-thirds of the Weighted Votes cast.  There is a narrow fallback—a simple majority of both Individual Votes and Weighted Votes suffices only if opposition stays below five percent of Weighted Votes (for the Individual-Vote count) and below three Parties (for the Weighted-Vote count).  PJM’s Exit Amendment met neither of these requirements.

Second, the Exit Amendment is inconsistent with Commission precedent and violates cost-causation principles by assigning generation- and capacity-related costs to TOs rather than to Load Serving Entities (“LSEs”).  The Commission has never allocated generation- and capacity-related costs to TOs and, more specifically, the Exit Amendment conflicts with highly relevant precedent in the Duquesne Light Co. proceeding where the Commission notably did not apply generation-related costs to an exiting TO in its capacity as a TO.3

3 Duquesne Light Co., 122 FERC ¶ 61,039 (2008).

PDF page 3

3
As explained herein and for the reasons set forth below, the Commission should reject the Exit Amendment.

I. BACKGROUND
On December 15, 2005, the TOs and PJM entered into the CTOA, whose purpose is to establish the “rights and commitments” of PJM and the TOs.4

PJM’s RBP proposal had its origins in a January 2026 statement of principles signed by the governors of the states within PJM’s territory.5  PJM advanced the proposal through its Critical Issue Fast Path (“CIFP”) process, presenting an initial proposal at an April 16–17, 2026 set of meetings and revising it at further CIFP meetings on May 4–5, May 27, and June 10–11, 2026.6  In these latter meetings, PJM began to highlight the purported risk posed by a TO exiting PJM during the RBP’s 15-year term.

PJM addressed this “Transmission Owner Separation Risk” at its May 27, 2026 CIFP meeting and again in its June 11, 2026 proposal paper.7  As of the June 11 paper, PJM had still not settled on the fees a departing TO would owe, presenting instead alternative “Options”, including one that would add a twenty-percent “deficiency penalty” on top of an accelerated payment of the remaining notional contract value.8

4  CTOA at p. 1, available at https://www.pjm.com/pjmfiles/directory/merged-tariffs/toa42.pdf.
5 See Nat’l Energy Dominance Council, Statement of Principles Regarding PJM (Jan. 16, 2026), https://www.energy.gov/documents/statement-principles-regarding-pjm. 6 PJM, CIFP Reliability Backstop Procurement — PJM Proposal, at 1 (June 11, 2026) (“June 11 CIFP Paper”) (initial proposal presented at the April 16–17, 2026 CIFP meetings; further CIFP meetings held May 4–5, May 27, and June 10–11, 2026), available at https://www.pjm.com/- /media/DotCom/committees-groups/cifp-rbp/2026/20260610/20260610-item-04a---pjm-reliability- backstop-procurement-paper.pdf.
7 June 11 CIFP Paper at 18 & n.12.
8 Id. at 18.

PDF page 4

4
On July 31, 2026, PJM filed its RBP proposal with the Commission with a proposed effective date of September 29, 2026.9  The RBP would commit PJM’s members to significant expenditures via the procurement of new capacity resources for a fixed fifteen-year term, from the 2028/2029 through 2042/2043 Delivery Years.10  Unlike the current Base Residual Auction that procures capacity to supply one year’s worth of electricity at a time (in recent years, at a cost of approximately $16 billion per year11), the RBP is a one-time procurement of capacity over fifteen years, which could cost more than $20 billion.12

The Exit Amendment component of the filed proposal would impose penalties on TOs that withdraw from PJM and that take with them either “Committed RBP Resources” or “Load Allocated RBP Charges” within their Zones, as discussed further infra at 8.13

II. ARGUMENT
A. PJM Lacked Authority To File The Exit Amendment
PJM exceeded the bounds of its filing authority in proposing the Exit Amendment. First, because the Exit Amendment effectively amends the CTOA, PJM needed to—but did not—obtain a supporting vote of the TOs in the PJM Transmission Owners Agreement- Administrative Committee (“TOAAC”) before filing the RBP Proposal.  Second, even if the Exit Amendment does not amend the CTOA, PJM can only justify its proposal under cost-

9 PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy and Large Loads, Docket No. ER26-3380-000 (filed July 31, 2026) (“RBP Proposal”).

10 RBP Proposal, Attachment DD § 18.4 (“fixed period of fifteen (15) Delivery Years, starting with the 2028/2029 Delivery Year . . . through the end of the 2042/2043 Delivery Year”). 11 Ethan Howland, PJM Capacity Prices Hit Record High as Grid Operator Falls Short of Reliability Target, Utility Dive (Dec. 18, 2025), https://www.utilitydive.com/news/pjm-interconnection-capacity- auction-data-center/808264/.
12 PJM’s initial procurement target of 6,831.3 MW—at PJM’s proposed price cap of $555-per- megawatt-day—would cost $20.8 billion over the next 15 years. 13 Proposed Tariff § 18.7.

PDF page 5

5
causation principles by casting it as a “provision[] governing the recovery of transmission- related costs incurred by the Transmission Owners”—but such a filing is within the TOs’, not PJM’s, exclusive filing authority.  Third, even if the Exit Amendment is not such a filing and instead merely “relates to or affects” provisions governing the recovery of transmission-related costs, PJM still was required to, but did not, provide detailed advance notice to the TOs before making the filing.

1. The Exit Amendment Effectively Amends The CTOA Without A
Majority Vote In Support By The Transmission Owners

Under CTOA section 8.5.1, any amendment to the CTOA may be filed only after an approval vote of the TOs with either a two-thirds majority voting in favor, or a simple majority voting in favor but with votes in opposition remaining below a certain threshold.14  PJM’s Exit Amendment effectively proposes such an amendment, and yet was filed without the required approval by the TOs in the TOAAC.

Under the current CTOA, an exiting TO’s obligations are governed by sections 3.2 and 3.4.  Pursuant to section 3.2, “[a]ny Party may withdraw from” the CTOA if it meets three preconditions: (1) securing alternative arrangements for comparable transmission service; (2) obtaining FERC approval to withdraw; and (3) “if its Transmission Facilities do not comprise an entire Control Area,” satisfying all applicable NERC and Applicable Regional Reliability Council standards for operating a Control Area or being included within an existing one.15 Pursuant to section 3.4, a withdrawing TO remains liable for obligations it incurred, that were incurred on its behalf, or that arose under the CTOA before the withdrawal’s effective date.16

14 CTOA § 8.5.1.
15 Id. § 3.2 (“Withdrawal From This Agreement”).
16 Id. § 3.4 (“Obligations After Withdrawal, Transfer, or Assignment”).

PDF page 6

6
The Exit Amendment changes both sections.  It modifies section 3.2 by adding new RBP-related preconditions to withdrawal—making it no longer true that a TO “may withdraw from” the CTOA if it meets section 3.2’s preconditions alone.  The Exit Amendment likewise amends section 3.4 by making a withdrawing TO liable for new RBP-related obligations found nowhere in the current CTOA.  Because the Exit Amendment amends these terms of the CTOA, under section 8.5.1, the Exit Amendment could be properly filed only after a vote of TOs in the TOAAC in support, with either a two-thirds majority voting in favor, or a simple majority voting in favor but with votes in opposition remaining below a certain threshold— which PJM did not obtain.

PJM cannot escape section 8.5.1’s limitations by characterizing the Exit Amendment as a change to the “terms and conditions of the PJM Tariff” under CTOA section 7.5.1(i).  If PJM could alter the CTOA’s substance simply by casting the change as an OATT amendment, CTOA section 8.5.1 would be a nullity, as it would effectively provide PJM unilateral discretion to amend the CTOA in clear contravention of that section. The only way to give effect to both provisions is to treat CTOA section 8.5.1 as controlling wherever an amendment would change the CTOA’s substantive terms, as this one does.17

2. If The Exit Amendment Concerns Transmission-Related Rather
Than Generation- and Capacity-Related Costs, It Is Within The
Transmission Owners’, Not PJM’s, Exclusive Authority To File
As discussed infra, the Exit Amendment violates cost-causation principles because it imposes generation- and capacity-related costs on TOs.  But if the proposal could somehow be

17  See, e.g., Transmission Agency of N. Cal. v. FERC, 628 F.3d 538, 547 (D.C. Cir. 2010) (“[i]n construing tariffs, courts and agencies must look to the four corners of the tariff and consider the entire instrument as a whole”) (quoting Consol. Gas Transmission Co. v. FERC, 771 F.2d 1536, 1545 (D.C. Cir. 1985) (brackets in original)).

PDF page 7

7
viewed as imposing transmission-related costs, it would run headlong into CTOA section 7.5.1(iv).  Under CTOA section 7.5.1(iv), the TOs hold “unilateral and exclusive” rights to make an FPA section 205 filing concerning “any provisions governing the recovery of transmission-related costs incurred by the Transmission Owners.”18  If the Exit Amendment is not deemed to impose generation- and capacity-related costs (which it does) and instead deemed to impose transmission-related costs, it would certainly “govern[] the recovery of transmission-related costs incurred by the Transmission Owners” and so lies outside PJM’s unilateral filing authority and within the exclusive filing authority of the TOs.

3. At A Minimum, The Exit Amendment “Relates To Or Affects” The
Recovery Of Transmission-Related Costs, And PJM Failed To
Provide The Transmission Owners The Requisite Advance Notice
Before Proceeding With The Filing
If the Exit Amendment does not concern capacity costs, and if contrary to the argument in Point I.B the Exit Amendment does not concern “the recovery of transmission-related costs incurred by the Transmission Owners,” it at least “relates to or affects . . . [the] provisions governing the recovery of transmission-related costs.”19  A filing in this “relates to or affects” category may proceed only after PJM (a) gives the TOs at least 45 days’ notice of the intended filing, “in sufficient detail to provide them a reasonable opportunity to include appropriate provisions in the PJM Tariff governing these subjects,”20 and (b) “consult[s] with the Transmission Owners and the PJM Members Committee beginning not less than seven (7) days in advance of any such Section 205 filing[.]”21

18 CTOA § 7.5.1(iv).
19 CTOA § 7.5.1(iv). 20 Id. 21 Id. § 7.5.1(ii).

PDF page 8

8
PJM gave no such notice or consultation.  Its high-level policy descriptions were far too general to convey the content of its eventual filing, and the few details it shared changed repeatedly.  As of June 11, 2026 (50 days before PJM submitted its filing), PJM’s proposal still contemplated multiple “options” for the exit fee,22 leaving the TOs unable to discern the contours of PJM’s proposed filing.  The June 2026 iteration of PJM’s proposal offered two options for the exit fee demanded of TOs that “leave with generation that was part of RBP” and cannot be pseudo-tied to PJM:  (1) that the TO “must pay PJM the notional value of remainder of contract value (mws x rate x remaining years) on an accelerated basis[;]” and (2) “Same as Option 1 but prior to exiting, TO must also pay PJM an extra 20% deficiency penalty.”23  PJM’s as-filed proposal discarded both options and would implement a different and more uncertain fee for such TOs, obligating them to pay “costs associated with the remaining term of the RBP Resource, the amount which shall be determined through a filing submitted under the Federal Power Act.”24

By providing only a moving target, PJM denied the TOs any meaningful notice or opportunity for consultation—precisely what the 45-day detailed-notice requirement and 7- day consultation requirement guarantee.

B. The Exit Amendment Improperly Assigns Generation- And Capacity-
Related Costs To Transmission Owners
The Exit Amendment is not only defective because it violates the terms of the CTOA, but impermissible also because it violates well-established cost-causation principles by

22 PJM Interconnection, L.L.C., Reliability Backstop Procurement Design (June 11, 2026) at 37, https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260611/20260611- item-04a---pjm-reliability-backstop-procurement-design-presentation.pdf.
23 Id.
24 Proposed Tariff § 18.7(a).

PDF page 9

9
allocating generation- and capacity-related costs to TOs, which neither caused nor will benefit from these costs.

Pursuant to the Exit Amendment, an exiting TO with “Committed RBP Resources” (i.e., resources that were cleared to provide capacity in the RBP) “located within the physical boundaries of the Transmission Owner’s Zone” must, before exiting, either preserve the RBP commitments with the owners of RBP Resources within its Zone, pay all costs for those Resources to pseudo-tie into PJM, or “pay costs associated with the remaining term of the RBP Resource” in an amount to “be determined through a filing submitted under the Federal Power Act.”25  For a TO “seeking to exit PJM[] with net load that has been allocated RBP Charges for RBP Resources not located within the physical boundaries of the [TO’s] Zone,” the Exit Amendment requires that TO either to enter into agreements that preserve those RBP commitments or “pay all forward obligations on an accelerated basis” before exiting.26 These charges make an exiting TO responsible for the RBP commitments of generation resources and/or load within its zone.  Those cannot be fairly allocated to a TO as transmission- related costs.  Commission precedent is directly on point: “cost-causation and benefits/burdens principles” require that costs be allocated to those who cause and/or benefit from them.27  In other words, “costs are allocated to the parties who cause the incurrence of such costs.”28  In particular, where “real-time load is the primary beneficiary, and the primary cost-driver” of a program, and where that program “address[es] generation-related reliability concerns, not transmission-related concerns,” the “costs of the Program should be allocated to Real-Time

25 Id.
26 Id. § 18.7(b).
27 ISO New England Inc., 144 FERC ¶ 61,204, at P 70 (2013).
28 ISO New England, Inc., 115 FERC ¶ 61,145, at P 13 (2006).

PDF page 10

10
Load Obligation,” not TOs.29  Notably, Duquesne Light Co., the leading Commission precedent, involved Duquesne Light Company’s (“Duquesne”) planned exit from PJM in both its capacity as a TO and an LSE.  It was only in the context of its role as an LSE, pursuant to the PJM Reliability Assurance Agreement, that the Commission ruled that Duquesne was properly held responsible “for paying for all the capacity PJM acquired on its behalf up through and including the upcoming January auction.”30

Cost-causation principles condemn PJM’s Exit Amendment.  TOs neither cause the costs of procuring generation capacity over the RBP’s 15-year term (nor the costs of procuring generation capacity under PJM’s one-year-at-a-time Base Residual Auction), nor do they directly benefit from those costs.  LSEs and their customers do.  Allocating the costs to TOs, therefore, violates cost-causation principles.

III. CONCLUSION
For the foregoing reasons, the Indicated PJM Transmission Owners respectfully request that the Commission reject PJM’s proposed Exit Amendment.

Dated:  August 21, 2026
Respectfully submitted,
/s/ Evan K. Dean

Evan K. Dean
Managing Counsel, Transmission Rates &
Services
FirstEnergy Service Company
341 White Pond Drive
Akron, Ohio 44320
Telephone: 330-620-9585
edean@firstenergycorp.com
/s/ Sanford I. Weisburst

Sanford I. Weisburst
Matthew Meyer
Madeleine Fleming
QUINN EMANUEL URQUHART
& SULLIVAN, LLP
295 Fifth Avenue, Ninth Floor
New York, New York 10016
Telephone: 212-849-7000
Facsimile: 212-849-7100
sandyweisburst@quinnemanuel.com
matthewmeyer@quinnemanuel.com

29 144 FERC ¶ 61,204, at P 70.
30 Duquesne Light Co., 122 FERC ¶ 61,039, at P 83 (2008).

PDF page 11

11
madeleinefleming@quinnemanuel.com

/s/ Anthony Alden

Anthony Alden
QUINN EMANUEL URQUHART
 & SULLIVAN, LLP
865 S Figueroa St, 10th Floor
Los Angeles, CA 90017
Telephone: 213-443-3000
anthonyalden@quinnemanuel.com
Counsel for the FirstEnergy Transmission Companies

/s/ Michael Brechlin

Michael Brechlin
Manager Asst GC - Regulatory Law State
Regulatory
Duquesne Light Company
Nova Place
100 South Commons, Suite 118
Mail Drop OGC-L1
Pittsburgh, PA 15212
Telephone: 412-393-6431
mbrechlin@duqlight.com

Counsel for Duquesne Light Company