Protest of the Indicated PJM Transmission Owners re PJM Interconnection, L.L.C.’s proposed tariff amendment
Text extracted from the eLibrary original (SHA-256 fe1f142927f76c28…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in ER26-3380
Topics in the text: Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) ) ) ) ) ) ) ) ) ) Docket No.Read this passage
I. BACKGROUND
printed heading · Topic match: Cost allocation
BACKGROUND On December 15, 2005, the TOs and PJM entered into the CTOA, whose purpose is to establish the “rights and commitments” of PJM and the TOs.4 PJM’s RBP proposal had its origins in a January 2026 statement of principles signed by the governors of the states within PJM’s territory.5 PJM…Read this passage Filed comments: Cost allocation
II. ARGUMENT
printed heading
II.Read this passage
A. PJM Lacked Authority To File The Exit Amendment
printed heading · Topic match: Reliability and curtailment
The Exit Amendment Effectively Amends The CTOA Without A Majority Vote In Support By The Transmission Owners Under CTOA section 8.5.1, any amendment to the CTOA may be filed only after an approval vote of the TOs with either a two-thirds majority voting in favor, or a simple majority voting in…Read this passage Filed comments: Reliability and curtailment
B. The Exit Amendment Improperly Assigns Generation- And Capacity-
printed heading · Topic match: Cost allocation
Pursuant to the Exit Amendment, an exiting TO with “Committed RBP Resources” (i.e., resources that were cleared to provide capacity in the RBP) “located within the physical boundaries of the Transmission Owner’s Zone” must, before exiting, either preserve the RBP commitments with the owners of RBP…Read this passage Filed comments: Cost allocation
III. CONCLUSION
printed heading
CONCLUSION For the foregoing reasons, the Indicated PJM Transmission Owners respectfully request that the Commission reject PJM’s proposed Exit Amendment.Read this passage