Comments of Voltus, Inc. on the PJM Interconnection LLC’s Federal Power Act Section 205 filing requesting the approval of tariff amendments to establish a…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Reliability Backstop Procurement to Address
Resource Adequacy and Large Loads
Docket No. RM26-3380-000
COMMENTS OF VOLTUS
Pursuant to Rule 211 of the Federal Energy Regulatory Commission’s (“FERC’s” or “Commission’s”) Rules of Practice and Procedure, and the August 3 Combined Notice of Filings #1 setting a comment date, Voltus respectfully submits the following comments on PJM Interconnection LLC’s (“PJM’s”) Federal Power Act Section 205 filing requesting the approval of tariff amendments to establish a Reliability Backstop Procurement (“RBP”). I.
INTRODUCTION
Voltus, Inc., (“Voltus”) is a distributed energy resource (“DER”) aggregator operating in all nine North American wholesale electricity markets. Voltus is a registered curtailment service provider (“CSP”) with PJM Interconnection, L.L.C., (“PJM”) aggregating the flexible attributes of retail load across the footprint and offering capacity, energy, and ancillary services products into PJM markets. Relevant to the provision of capacity, Voltus has participated in all Reliability Pricing Model (“RPM”) since BRA 2022/23 (held in early 2021) and has delivered its capacity commitments as Load Management in the associated delivery years. Voltus also has experience transacting PJM-accredited capacity bilaterally. Voltus’s commercial experience developing demand-side capacity resources closely informs these comments.
Page 1 of 15
PDF page 2
Voltus participated actively throughout the Critical Issue Fast Path (“CIFP”) RBP process and had engaged in a limited manner in the preceding CIFP on Large Load Additions1, which introduced the notion of a “reliability backstop mechanism” as among the near-term tools to address the capacity shortage and associated reliability risks driven by rapid data center load growth.2 Voltus’s comments herein reflect a subset of the same issues Voltus raised through commentary3, proposals, and a formal Stage 4 package4 during the CIFP-RBP stakeholder process.
Voltus contends that incentivizing Bring Your Own New Capacity (“BYONC”) and
related frameworks is generally more effective and efficient at developing new capacity than central procurement, while better protecting non-cost-causers. However, recognizing the urgency of the moment and substantial efforts made by PJM, industry, consumer interests, state and federal government actors, and FERC to reach this point, Voltus does not oppose approval of PJM’s filing.
Voltus wishes to recognize that the inclusion of demand-side resources for either RBP or QRBPO was not a foregone conclusion, and Voltus commends PJM for responding to broad stakeholder support for including the demand side. For the benefit not only of the RBP framework but also to continue to incentivize investment in the demand side and for precedential
4 See the Executive Summary and proposals filed by Voltus in Stage 4 - https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-item-02l---voltus---c m-and-rbp---executive-summary.pdf. 3 See the presentation from Voltus as part of the CIFP – Reliability Backstop Procurement – Stages 2 and 3 - https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260504/20260504-item-02p---voltus-pr esentation.pdf.2 See the Joint Parties Proposal https://www.pjm.com/-/media/DotCom/committees-groups/cifp-lla/2025/20251024/20251024-item-04i---joint-stake holder-proposed-package.pdf, at slides 5-6. 1 CIFP process on RBP (https://www.pjm.com/committees-and-groups/cifp-rbp ) and CIFP process on Large Load Additions (https://www.pjm.com/committees-and-groups/cifp-lla). Page 2 of 15
PDF page 3
reasons, demand-side eligibility as currently written in the tariff filing must, at minimum, be retained in the final tariff.
Given that RBP is highly likely to proceed, Voltus’s main concern is that the current framework unduly discriminates against demand-side resources that can provide near-term but durable capacity. First, the criteria for Qualifying RBO Offset (“QRBPO”) will count “reactivated” generation and storage resources against a zone’s RBP procurement target but not reactivated DR/DER sites. Not only is this difference in treatment unexplained, it also ignores existing arrangements with DR sites willing to reactivate on the basis of large load revenues that overcome the economic and operational dynamics that led the sites to drop-out in the first place. Ignoring these arrangements risks overprocurement and concomitant socialization of more-than-the-necessary costs to the PJM system. Second, the Stage 1 “gating criteria” for RBP offers do not recognize the actual commercial development pathways of distributed demand-side resources. If unchanged, they will function as a fence, not a gate, with the result that few if any demand-side resources will actually offer, subverting PJM’s intention to afford demand-side developers an opportunity to secure long-term price certainty to enable broad and deep new investment in behind-the-meter assets.
Voltus addresses each of these two issues, and provides targeted tariff modifications to address them, in the sections below.
II.
THE ELIGIBILITY OF DEMAND-SIDE RESOURCES FOR QRBPO MUST BE
CLARIFIED TO REFLECT THE CONSENSUS REACHED DURING THE
STAKEHOLDER PROCESS
PJM’s proposed tariff language provides limited specification on the kinds of DR/DER resources that are eligible to be counted as QRBPO, introducing ambiguity as to the Page 3 of 15
PDF page 4
requirements on the underlying sites. To reflect the consensus reached in the stakeholder process, and to ensure that DR/DER resources are eligible to offset RBP procurement on the same terms as generation and storage resources, FERC should direct PJM to amend its tariff language to clearly allow incremental and reactivation capacity for demand-side resources. A. The Proposed Tariff Language Is Ambiguous as to the Eligibility of New Capacity at Existing Locations and the Renewed Capacity of “Deactivated” Locations
PJM defines QRBPO resource eligibility in proposed Tariff, Attachment DD, section 18.2:
(a) Qualifying RBP Offset UCAP MW is capacity that (i) has not
previously supported a capacity commitment or been committed in an FRR Plan as of the commencement of the Reliability Backstop Procurement; and (ii) is supplied by a resource that satisfies each of the criteria set forth in Tariff, Attachment DD, section 18.2(b).
(b) Resources Eligible to Supply Qualifying RBP Offset UCAP MW
A resource eligible to supply Qualifying RBP Offset UCAP MW must have an expected commercial operation date, or is reasonably expected to be an Annual Demand Resource or DER Capacity Aggregation Resource that will be registered with the Office of the Interconnection and under a contract to perform based on PJM dispatch instructions, by no later than June 1, 2032 and be: (i) a new build generation resource including new resources that obtain Capacity Interconnection Rights transferred from deactivated resources or resources that have announced deactivation as of April 10, 2026; (ii) the incremental capacity created by an uprate of existing Generation Capacity Resources, but only to the extent such incremental capacity is created through an increase in such Generation Capacity Resource’s installed capacity and increase in Capacity Interconnection Rights associated with that Generation Capacity Resource; (iii) the incremental capacity created by the utilization of Surplus Interconnection Service; (iv) repowering of a deactivated generation resource that deactivated prior to April 10, 2026; (v) incremental capacity, whether due to greater Unforced Capacity or a higher level of Capacity Interconnection Rights, created by an existing Generation Capacity Resource’s changing fuel type to a more efficient fuel type; or (vi) Planned Demand Resource or Planned DER Capacity Aggregation Resources, as described in the RAA, Schedule 6 and Schedule 6.2.
[. . .]
Page 4 of 15
PDF page 5
Thus, to be a QRBPO UCAP MW, a unit of capacity must not have previously supported a capacity commitment or FRR Plan (18.2(a)(i)), must be expected to be operational in time for Delivery Year 2032/2033 (18.2(b)), and must be backed by a resource falling into any of the categories defined in 18.2(b)(i)-(vi).
The first five of these categories pertain to generation/storage resources, and only the last covers DR/DER. On the generation/storage side, it is explicitly specified that incremental capacity tied to existing resources (18.2(b)(ii)-(iv)), and the “repowering of a deactivated generation resource” (18.2(b)(v)) may provide new capacity eligible as QRBPO if the other requirements of 18.2(a)-(b) are met. By contrast, the single specified category for DR/DER, “Planned Demand Resource or Planned DER Capacity Aggregation Resources” (18.2(b)(vi)) leaves open whether (1) incremental capacity at existing locations and (2) reactivations of locations that once did but are not currently participating in aggregations, could provide QRBPO-qualified capacity.
B. A Logical Reading of the Proposed Tariff Language Allows Incremental
Capacity at Existing Locations and “Reactivated” Locations for QRBPO
Purposes
Pulling out the pertinent 18.2(a)-(b) language, PJM has defined DR/DER-backed QRBPO UCAP MW as
(a) . . . capacity that (i) has not previously supported a capacity commitment or been committed in an FRR Plan as of the commencement of the Reliability
Backstop Procurement . . . (ii) supplied by a resource that . . . (b) . . . is reasonably expected to be an Annual Demand Resource or DER Capacity Aggregation
Resource that will be registered with the Office of the Interconnection and under a contract to perform based on PJM dispatch instructions, by no later than June 1, 2032 and [is] Planned Demand Resource or Planned DER Capacity Aggregation Resources, as described in the RAA, Schedule 6 and Schedule 6.2.
The requirement of 18.2(a)(i), that the capacity must not have previously supported a capacity or FRR Plan commitment, cannot imply that incremental capacity at existing locations and the capacity contributions of reactivated locations are precluded. If it did, then incremental Page 5 of 15
PDF page 6
capacity from generation storage resources and the repowering of deactivated generators would also be disqualified, nullifying the specified categories in 18.2(b)(ii)-(v).
Nor does “Planned Demand Resource or Planned DER Capacity Aggregation Resource”
in 18.2(b)(vi) independently limit eligibility to locations that have never before participated. In RAA Schedules 6 and 6.2, Planned Demand Resources and Planned DER Capacity Aggregation Resources sit in opposition to Existing Demand Resources5 and Existing Planned DER Capacity Aggregation Resources6. The categories are relevant for the reporting of existing and planned MW in the aggregator’s pre-auction Sell-Offer Plan that determines the maximum MW that an aggregator can bid into an RPM auction. An Existing Demand Resource comprises “end-use customer sites that are registered for the current Delivery Year with PJM” as of the time of Sell-Offer Plan submission. Any other site goes in as Planned Demand Resource. Similar logic holds for DER Capacity Aggregation Resource. Thus “planned” resources may include
incremental capacity at existing locations and reactivated locations.
C. Consistent with the Purpose of the QRBPO Construct, PJM Should Include
Incremental Capacity at Existing Locations and the Capacity of Reactivated
Locations as Eligible to Supply QRBPO UCAP MW
Enabling incremental capacity at existing locations and the capacity of reactivated locations supports PJM’s goals, furthers the principle that large loads should cover their own costs, and reflects the consensus reached during the CIFP process.
6 "Existing DER Capacity Aggregation Resource" shall mean a DER Capacity Aggregation Resource for which the DER Aggregator has identified existing Component DER that are registered in a DER Capacity Aggregation Resource for the current Delivery Year with PJM (even if not registered by such DER Aggregator) and that the DER Aggregator reasonably expects to have under a contract to generate or reduce load based on PJM dispatch instructions by the start of the Delivery Year for which such DER Capacity Aggregation Resource is offered. RAA Definitions.
5 "Existing Demand Resource" shall mean a Demand Resource for which the Demand Resource Provider has identified existing end-use customer sites that are registered for the current Delivery Year with PJM (even if not registered by such Demand Resource Provider) and that the Demand Resource Provider reasonably expects to have under a contract to reduce load based on PJM dispatch instructions by the start of the Delivery Year for which such resource is offered. RAA Definitions. Page 6 of 15
PDF page 7
First, a core function of QRBPO is to reduce the volumes that must be centrally procured whose costs are socialized across the system. (PJM does not propose, and may be jurisdictionally unable, to charge large loads directly for the costs of the RBP, and other ratepayer classes may end up exposed depending on retail rates, large load default risk, etc.) As such, PJM has “defin[ed] [the QRBPO eligibility] criterion broadly to capture all meaningful sources of new UCAP serving new load that contribute to resource adequacy and prevent double procuring for new load that is bringing new capacity to the system” (emphasis added).7 This reflects a dual purpose to encourage and/or enable robust bilateral contracting while ensuring such contracting is recognized against the RBP procurement target and associated cost allocation. Such recognition benefits all ratepayers by reducing the total RBP costs to which ratepayers may be potentially exposed. The recognition also benefits large load buyers in the private market because capacity they procure bilaterally, if eligible for QRBPO, reduces their exposure to the unknown costs of the RBP over a lengthy, fifteen-year term. Ensuring inclusive and comparable recognition of various sources of net-new capacity avoids tipping the scales in favor of particular resource classes—in this case generation/storage over DR/DER. Because uprates and reactivations have been included on the generation/storage side, they should equally be included for DR/DER-backed QRBPO.
Second, PJM’s intention is that “[t]he RBP Resource eligibility criteria are comparatively more restrictive than the criteria for Qualifying RBP Offset UCAP MW.”8 PJM has explicitly proposed to allow asset-backed “uprates” as eligible to support RBP resources: per proposed Tariff, Attachment DD, section 18.5(c), an RBP Demand Resource may “[n]ot be reliant on or composed of registered location(s) that previously supported a Demand Resource that provided
8 Affidavit of Danielle Croop, Page 4, para 15.7 Affidavit of Danielle Croop, Page 4, para 13. Page 7 of 15
PDF page 8
capacity in a prior Delivery Year unless such location represents an incremental increase in capacity resulting from an investment in new generation or new storage resources at that location” (emphasis added). The italicized language makes RBP-eligible the “incremental increase in capacity resulting from an investment in new generation or new storage” at an existing location. Thus QRBPO, a more inclusive construct, must include, at minimum DR uprates.
Third, during the CIFP process, PJM’s QRBPO DR/DER resource eligibility (defined at that time by reference to BYONC resource eligibility, as the term “Qualified RBP Offset” did not yet exist) developed over time to include both incremental capacity and reactivations. These inclusions responded to stakeholder advocacy and were not heavily opposed during the CIFP meetings. PJM’s final proposal on BYONC eligibility included “the incremental amount from any location registered in 26/27 or 27/28” (uprates) as well as locations that had been registered prior to Delivery Year 2026/2027.9
D. Voltus Recommends a Simple Tariff Addition to Clarify that Incremental Capacity at Existing Locations and the Capacity of Reactivated Locations is Eligible to Supply QRBPO UCAP MW
With the RBP proposed to open in just a few weeks, PJM has asked the Commission to provide specificity on any recommended changes and has indicated it would accept discrete changes where the “modification . . . is consistent with PJM’s overarching objectives in this filing.”
Voltus recommends a narrow modification to provide clarity on demand-side QRBPO eligibility thus delivering PJM’s objective to efficiently achieve resource adequacy while 9 See PJM’s Stage 3 Connect-and-Manage presentation,
https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260611/20260611-item-02---pjm-conne ct-and-manage-package-updates.pdf, at slide 6.
Page 8 of 15
PDF page 9
reducing new capacity cost-exposure for non-cost-causers. Voltus recommends the following redline to 18.2(b)(vi), allowing QRBPO UCAP MW to be supported by. . .
. . . (vi) Planned Demand Resource or Planned DER Capacity Aggregation
Resources, as described in the RAA, Schedule 6 and Schedule 6.2, where such resources are not reliant on or composed of registered location(s) supporting a Demand Resource providing capacity in the 2026/2027 Delivery Year unless such location represents capacity resulting from an investment in new generation or new storage resources at that location.
This definition achieves the clear inclusion of new incremental capacity and “reactivations” for sites supporting DR/DER resources while (1) avoiding gaming incentives (locations cannot “sit out” the 2026/2027 Delivery Year as it has already begun and registrations for the year are fixed) and (2) achieving parity in the treatment of distributed and/or behind-the-meter capacity compared to utility-scale generation and storage. For simplicity and consistency, this language hews closely to language PJM has used later in the proposed tariff while defining RBP resource eligibility.
Further, Voltus recommends, and will recommend in the IRAS docket, that the same criteria be used to define resource eligibility for Bring Your Own New Capacity. Such an alignment supports clarity and simplicity and ensures straightforward incentives for large load buyers. A MW used as QRBPO UCAP MW should also qualify as BYONC to reduce a large load’s IRAS exposure, and Voltus understands that it is PJM’s intention to achieve this alignment.
Page 9 of 15
PDF page 10
III.
THE STAGE ONE GATING CRITERIA FOR RBP OFFERS SHOULD
ACCOMMODATE
THE
ACTUAL
COMMERCIAL
DEVELOPMENT
PATHWAYS OF DISTRIBUTED DEMAND-SIDE RESOURCES
A. The Gating Criteria Are Far More Stringent for DR/DER Than
Generation/Storage, Ignore How DR/DER Resources Are Commercially
Developed, and Are Practically Infeasible
PJM proposes that the evaluation of RBP offers proceed in two stages, with the first stage designed to confirm that “the proposed resource will be successfully completed and able to provide capacity.”10 Sellers must present evidence “demonstrat[ing] that the resource is likely to be fully developed and the seller has taken all necessary steps (at this stage) to succeed” (emphasis added).11
For generation and storage resources, the required evidence comprises “[a] critical path construction schedule”; “[e]vidence of 100% Site Control . . . for a term of at least three years” (emphasis added); financing and permitting plans; “[s]igned memoranda or other documentary evidence that the developer has or will procure the major equipment necessary; evidence of experience constructing similar projects or of past or present contracts with a partner with such experience; “evidence of delivery infrastructure arrangements in the form of a notice of intent or attestation” (emphasis added) for natural gas, where applicable; and, for resources outside of PJM, evidence of firm transmission arrangements up to the border of the PJM region, where such evidence may be “a confirmed transmission service request with completed system impact study” (emphasis added).12 These criteria match PJM’s intention to ensure that the seller has taken all necessary steps for this stage of development by recognizing that a developer several years ahead of expected commercial operation date (“COD”) may not have obtained all necessary permits and financing, may not have already purchased all major equipment, and may
12 Proposed Tariff, Attachment DD, sections 18.5(f)(i)(1) to (8).11 Transmittal letter, p. 71-2.10 Transmittal letter, p. 71. Page 10 of 15
PDF page 11
not have confirmed all transmission and infrastructure arrangements. The finalization of the above, and the investments necessary to take a detailed and rigorous development plan to commercial operation, will often depend on the acquisition of price certainty through offtake agreements and other arrangements.
The RBP is precisely an instrument designed to provide long-term price certainty to spur the realization of the potential capacity locked in projects currently in the planning phase, whose final development is uncertain. It is by design that the RBP gating criteria for storage/generation seek rigorous evidence of an advanced stage of project planning, but do not require evidence of the final investments and commitments that are prudently made only once clarity on the revenue stream is in place.
By contrast, DR/DER RBP offers must “[i]dentify, as part of its RBP Sell Offer, for the full length of the fixed term, the location(s) and associated participation contract(s)”13 and will only be considered if they include “[e]xecuted customer agreements or binding commitments covering the proposed RBP UCAP MW commitment, with identified locations, customer names, and expected curtailment/injection capability per site” (emphasis added).14
As Voltus wrote in the Executive Summary to its Stage 4 CIFP Proposal, “This [gating criterion] inverts the development sequence. Customer contracts are entered into against a known price and volume, the output of the auction. Requiring them before the auction removes the commercial basis on which they would be executed.” Voltus generally executes contracts with new suppliers—the retail energy customers providing the curtailment and/or injection capabilities that comprise the capacity resource—on the basis of BRA clearing prices. DR and
14 Proposed Tariff, Attachment DD, sections 18.5(f)(i)(10).13 Proposed Tariff, Attachment DD, sections 18.5(c)(ii), 18.5(d)(i). Page 11 of 15
PDF page 12
DER resources are aggregations, and there are practical constraints on the ability to execute potentially hundreds of underlying contracts by October 21.
While Voltus does contract with the locations it aggregates for multi-year terms, those term lengths are far less than fifteen years and, with new locations, would generally be executed closer to the first year in which the location would participate and receive revenue rather than years ahead. It is (1) infeasible to ask retail energy customers to enter fifteen-year contracts without known pricing up to several years before participation is set to begin, (2) commercially impractical for an aggregator to commit to fixed pricing with up to thousands of suppliers prior to knowing even whether it has cleared the RBP, and (3) generally difficult to achieve this term length with a supplier whose primary use case for the energy it might curtail or the DER whose capabilities it might provide is something other than earning wholesale market revenues. Changing rules and evolving market conditions introduce uncertainty as to the “terms” of participation (e.g., dispatch frequency). Fifteen years is a long time for a retail energy user, who may be industrial, commercial, small commercial, or even residential, to commit to changing its home or business operations when called upon by the system operator.
This does not mean that aggregators like Voltus cannot commit to fifteen-year terms. Rather, the function of an aggregator is to accumulate and blend the capabilities of a large number of individual energy users to produce a reliable resource, sometimes known as a Virtual or Distributed Power Plant (“VPP” or “DPP”). Underperformance of a segment of the portfolio may be probabilistically balanced by overperformance of another segment, and “churn” is preemptively accounted for.
Applying this logic to a fifteen-year RBP commitment, the aggregator would be operationally capable of “refilling” the committed UCAP with other eligible sites when a subset Page 12 of 15
PDF page 13
of underlying sites choose not to renew their contracts. This is in contrast to a generation or storage resource; if such a resource becomes unavailable or shuts down prior to the end of the fifteen-year commitment, the resource owner does not have the ability to straightforwardly replace the UCAP with other new development. Note also that RPM deficiency charges discipline the aggregator from bidding unrealistic volumes since RBP commitments expose the aggregator to significant underdelivery penalties through the RPM mechanism. B. Voltus Recommends Reasonable Gating Criteria Appropriate to the
Pre-Auction Stage of Development
Voltus’s recommendation on the DR/DER gating criteria address the twin concerns developed in the previous sub-section: (1) requiring executed contracts at the bid stage inverts commercial development logic, and (2) requiring fifteen-year contracts with all suppliers sets up an undue barrier that ignores the aggregator business model. As to the first, Voltus proposes that the gating criteria for DR and DER be restructured to distinguish between pre-auction criteria, which should reflect the investment commitment made to reach auction readiness, and post-auction criteria, which should reflect the execution steps that follow a successful auction outcome. As to the second, Voltus proposes that contracts may run for a shorter term with the expectation of renewal and/or replacement with other eligible net-new capabilities. Voltus recommends the following redlines to proposed Tariff, Attachment DD, 18.5(c)-(d), defining DR/DER resource eligibility:
(c) RBP Demand Resources
To qualify as a Demand Resource that supplies RBP UCAP MW eligible to be
offered into the Reliability Backstop Procurement, a Demand Resource must meet the requirements of Tariff, Attachment DD, sections 18.5(a), and:
(i) Not be reliant on or composed of registered location(s) that previously
supported a Demand Resource that provided capacity in a prior Delivery Year
unless such location represents an incremental increase in capacity resulting from an investment in new generation or new storage resources at that location; and Page 13 of 15
PDF page 14
(ii) Identify, as part of its RBP Sell Offer, for the full length of the fixed term, the location(s) and associated participation contract(s).
(d) RBP DER Aggregation Resources
To qualify as a DER Capacity Aggregation Resource that supplies RBP UCAP MW eligible to be offered into the Reliability Backstop Procurement, a Planned DER Capacity Aggregation Resource must meet the requirements of Tariff, Attachment DD, sections 18.5(b) and:
(i) Identify, as part of its RBP Sell Offer, for the length of the fixed term, the location(s) and associated participation contract(s).
Voltus further recommends this redline to the DR/DER gating criteria in proposed Tariff, Attachment DD, 18.5(f)(i):
RBP Sell Offers for Demand Resources or DER Capacity Aggregation Resources must be accompanied by:
(9)
Locations within the PJM Region by Zone/Sub-zonal LDA and
aggregate capacity for RBP Sell Offers;
(10)
Executed customer agreements or binding commitments covering
the proposed RBP UCAP MW commitment, with identified locations,
customer names, and expected curtailment/injection capability per siteDetailed description of the expected composition of the offered MW and, where the composition will rely on DER asset partners, evidence of the associated arrangements; and
(11)
Equipment procurement plan or evidence of deployed enabling
infrastructure such as metering, telemetry, load control, SCADA/dispatch systems, or DER major equipment as applicable.
PJM’s proposed gating criteria discriminate unnecessarily between storage/generation and DR/DER resources, and will very likely have the practical result that no DR/DER resources actually offer into the procurement. This would contravene the consensus reached among stakeholders as reflected in PJM’s proposals that DR/DER resources should be included, as well as the preferences publicly expressed by political actors. Voltus’s proposed amendments practically enable DR/DER resources to participate while respecting the purpose of the gating Page 14 of 15
PDF page 15
criteria “to provide assurance that the supply will be available for the 15-year term and manage the risk of the supply being available for the full term that PJM is procuring on behalf of load in the RBP.”15
IV.
CONCLUSION
Voltus thanks the Commission for this opportunity to comment and is hopeful of an effective procurement that incentivizes critical investment in new capacity, including distributed, demand-side resources.
Respectfully submitted,
/s/ Kimaya Abreu
Kimaya Abreu
Sr. Manager, Regulatory Affairs
Voltus, Inc.
2443 Fillmore St.
San Francisco, CA 94115
609.994.7686
kabreu@voltus.co
Dated: August 21, 2026
15 Affidavit of Danielle Croop, Page 6, para 20. Page 15 of 15