Comments of Voltus, Inc. on the PJM Interconnection LLC’s Federal Power Act Section 205 filing requesting the approval of tariff amendments to establish a…
Text extracted from the eLibrary original (SHA-256 c9ee9fb851acbad0…). Download the original from the official source.
Contents · 2 sections
Read topic-matched comments in ER26-3380
Topics in the text: Reliability and curtailment · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Reliability Backstop Procurement to Address Resource Adequacy and Large Loads Docket No.Read this passage Filed comments: Reliability and curtailment
INTRODUCTION
printed heading · Topic match: Reliability and curtailment
Page 2 of 15 reasons, demand-side eligibility as currently written in the tariff filing must, at minimum, be retained in the final tariff.Read this passage Filed comments: Reliability and curtailment
CONCLUSION
printed heading
CONCLUSION Voltus thanks the Commission for this opportunity to comment and is hopeful of an effective procurement that incentivizes critical investment in new capacity, including distributed, demand-side resources.Read this passage