EL25-49-000 · 2026-08-28 · Northern Virginia Electric Cooperative, Inc.

Motion for Leave to Answer and Answer of Northern Virginia Electric Cooperative, Inc. to the 08/18/2026 Answer et al. of Vistra Corp

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company

Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC

Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative

PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company

Trans-Allegheny Interstate Line Company Transource West Virginia, LLC

UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc. The Dayton Power and Light Company

AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc. AEP Ohio Transmission Company, Inc.

AEP West Virginia Transmission Company, Inc. Appalachian Power Company

Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
Duquesne Light Company
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)

Docket Nos. EL25-49-002
                      EL25-49-000

PDF page 2

2

Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public Utilities,
Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company

Large Loads Co-Located at Generating Facilities

Constellation Energy Generation, LLC

v.

PJM Interconnection, L.L.C.

)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)

AD24-11-000

EL25-20-000
                    (Consolidated)

MOTION FOR LEAVE TO ANSWER AND ANSWER OF
NORTHERN VIRGINIA ELECTRIC COOPERATIVE, INC.
TO THE AUGUST 18, 2026, MOTION FOR LEAVE TO ANSWER AND ANSWER OF
VISTRA CORP.

Pursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or the “Commission”),1 Northern Virginia Electric Cooperative, Inc. (“NOVEC”) respectfully submits this Motion for Leave to Answer and Answer to the August 18, 2026, Motion for Leave to Answer and Answer of Vistra Corp. (“Vistra”)2 filed in response to NOVEC’s Motion for Clarification3 of the Commission’s June 18, 2026, Order in these consolidated dockets.4

1 18 C.F.R. § 385.212-213.
2 Vistra Corp., Motion for Leave to Answer and Answer, Docket Nos. EL25-49-000, et al. (Aug. 18, 2026) (Accession No. 20260818-5146) (“August 18 Answer”).
3 NOVEC, Motion for Clarification, Docket Nos. EL25-49-000, et al. (Jul. 29, 2026) (Accession No. 20260729- 5083) (“July 29 Motion for Clarification”).
4 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026) (“Order”).

PDF page 3

3

I. MOTION FOR LEAVE TO ANSWER
NOVEC respectfully requests leave to submit this Answer. The Commission regularly
allows answers for good cause shown, such as when the answers help ensure a more accurate and complete record, clarify the issues, or provide useful and relevant information that will assist the Commission in its deliberative process.5 This Answer will correct Vistra’s mischaracterizations of NOVEC’s pleading and provide other useful and relevant information that will assist the Commission in its deliberative process. As such, the Commission has good cause to accept NOVEC’s Answer.

II. ANSWER

Vistra wrongly asserts that NOVEC’s July 29 Motion for Clarification is an untimely request for rehearing because “the substance of the filing directly contests the merits” of the Order.6 Vistra may disagree with NOVEC as to the clarity of the Order and may disagree with NOVEC’s opinion on aspects of the Order, but it should not inaccurately characterize the nature of NOVEC’s pleading. NOVEC’s Motion for Clarification did not ask the Commission to set aside, in whole or in part, its Order. NOVEC asked the Commission to provide additional detail on cost support information and to clarify whether the Order permits an earlier section 205 proposal on a Grid Reliance Charge than when Co-Located Load begins operating, which the Commission may or may not answer.

NOVEC is quite aware of the difference between a request for rehearing and a motion for clarification. It is precisely because NOVEC is seeking clarification and not rehearing that

5 See, e.g., City Utils. of Springfield, Mo. v. Sw. Power Pool, Inc., 168 FERC ¶ 61,085, P 51 (2019) (“We accept [the] answers…because they have provided information that assisted us in our decision-making process.”), order on reh’g & clarification, 170 FERC ¶ 61,024 (2020); Morgan Stanley Capital Grp., Inc. v. N.Y. Indep. Sys. Operator, Inc., 93 FERC ¶ 61,017, at 61,036 (2000) (accepting an answer as “helpful in the development of the record”). See also, Hawtree Creek Farm Solar, LLC, 179 FERC ¶ 61,048, P 21 (2022); California Ridge Wind Energy, LLC, 175 FERC ¶ 61,110, P 25 (2021); Pleinmont Solar 1, LLC, 173 FERC ¶ 61,126, P 18 (2020).
6 August 18 Answer at 2.

PDF page 4

4

NOVEC did not conform its pleading to any of the requirements set forth by Rule 713. NOVEC also understands that, unlike a request for rehearing, its motion for clarification does not satisfy the statutory precondition for seeking judicial review of the Order. NOVEC’s Motion for Clarification simply is not a request for rehearing. Because the foundational premise of Vistra’s Answer is simply wrong and belied by NOVEC’s pleading, the Commission should reject Vistra’s Answer. Whether or not the Commission elects to provide any clarification of the Order, there is nothing procedurally improper about NOVEC’s request.

III. CONCLUSION
WHEREFORE, for the foregoing reasons, NOVEC respectfully requests that the
Commission reject Vistra’s August 18 Answer and issue an order clarifying the June 18, 2026, Order as requested in NOVEC’s July 29 Motion for Clarification.

Respectfully submitted,

  //s// Alan I. Robbins

Alan I. Robbins
Debra D. Roby
Thomas B. Steiger III
Peter E. Colvin
Washington Energy Law LLP
900 17th Street, N.W., Suite 500-A
Washington, D.C. 20006
Tel: (202) 326-9313
Email: arobbins@washingtonenergylaw.com
droby@washingtonenergylaw.com
tsteiger@washingtonenergylaw.com
pcolvin@washingtonenergylaw.com

Counsel to Northern Virginia Electric Cooperative, Inc.

Dated: August 28, 2026.

PDF page 5

CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Federal Energy Regulatory Commission in this proceeding.

Dated at Washington, D.C. this 28th day of August, 2026.

  //s// Emma Kirby

Emma Kirby
Legal Administrative Assistant
Washington Energy Law LLP
900 17th Street, N.W., Suite 500-A
Washington, D.C. 20006
Tel: (202) 326-9313
Email: ekirby@washingtonenergylaw.com