EL25-49-000 · 2026-08-28 · Northern Virginia Electric Cooperative, Inc.

Motion for Leave to Answer and Answer of Northern Virginia Electric Cooperative, Inc. to the 08/18/2026 Answer et al. of Vistra Corp

Text extracted from the eLibrary original (SHA-256 898ce3a94fa81b65…). Download the original from the official source.

Contents · 3 sections
  1. I. MOTION FOR LEAVE TO ANSWER p. 3
  2. II. ANSWER p. 3
  3. III. CONCLUSION p. 4

Read topic-matched comments in EL25-49

Topics in the text: Filing procedure · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.
Read this passage

I. MOTION FOR LEAVE TO ANSWER

printed heading

MOTION FOR LEAVE TO ANSWER NOVEC respectfully requests leave to submit this Answer.
Read this passage

II. ANSWER

printed heading · Topic match: Filing procedure

Power Pool, Inc., 168 FERC ¶ 61,085, P 51 (2019) (“We accept [the] answers…because they have provided information that assisted us in our decision-making process.”), order on reh’g & clarification, 170 FERC ¶ 61,024 (2020); Morgan Stanley Capital Grp., Inc. v.
Read this passage Filed comments: Filing procedure

III. CONCLUSION

printed heading

CONCLUSION WHEREFORE, for the foregoing reasons, NOVEC respectfully requests that the Commission reject Vistra’s August 18 Answer and issue an order clarifying the June 18, 2026, Order as requested in NOVEC’s July 29 Motion for Clarification.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C. this 28th day of August, 2026. //s// Emma Kirby Emma Kirby Legal Administrative Assistant Washington Energy Law LLP 900 17th Street, N.W., Suite 500-A Washington, D.C. 20006 Tel: (202) 326-9313 Email: ekirby@washingtonenergylaw.com